Top Banner

of 36

2.FBC Engg

Apr 05, 2018

Download

Documents

agrocel_bhv
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/2/2019 2.FBC Engg

    1/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Best Practices

    Learning and application

    In Engineering

  • 8/2/2019 2.FBC Engg

    2/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Product profile

    Bubbling Fluidized bed combustion (BFBC) boilers

    Circulating fluidized bed combustion (CFBC) boilers

    Heat recovery Steam Generator (HRSG)

    BFBCs for low grade coal as fuels

    CFBCs from 75 MW to 250 MW

    HRSGs for Frame 5 GT to Frame 9FA GT

    Product turnover 5 fold increase to Rs 1000 Cr. in a

    span of 4 years

    Introduction

  • 8/2/2019 2.FBC Engg

    3/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Current practiceAnalysis for improvement for

    Ease of manufacture

    Comfort for erection

    Better performance

    Implementation phase (initial)

    Continual improvement lead to

    Established product with best practices

    Approach towards improvement

  • 8/2/2019 2.FBC Engg

    4/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Collecting feed back from operational experience of units

    Learnings from site action requests and information

    obtained during the visit of engineering personnel

    Discussion with manufacturing group for ease of

    manufacturing and erection

    Discussion with erection group before finalisation ofarrangement engineering

    Methodology adopted towards improvement

  • 8/2/2019 2.FBC Engg

    5/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    SH Flow t/h 165

    SH Pressure kg/cm2 95

    SH Temperature Deg C 540

    77 Mw BFBC Power plant - Jindal

  • 8/2/2019 2.FBC Engg

    6/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    50 MW BFBC Power plant at ACC - Wadi

  • 8/2/2019 2.FBC Engg

    7/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    SH Flow t/h 75SH Pressure Kg/cm2 65

    SH Temperature Deg C 485

    BFBC Boiler at PT-IBR Indonesia 3 x 75 TPH

  • 8/2/2019 2.FBC Engg

    8/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    USAID Test Facility-1986

    (90 t/h Hot water)

    Combustion Test Rig-1979

    0.5 M X 0.5 m

    (4,00,000 kcal/h)

    FBC Test Facility - 1991

    (90 t/h Hot water)

    FBC Test Rigs at Trichy

  • 8/2/2019 2.FBC Engg

    9/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Municipal Solid WasteShivsankar Ind.,Bangalore

    SelCo, Hyderabad

    Kiln Char

    Sunflag Industries,BandaraWashery Rejects

    Tisco, Jamadobha

    Fuels Tested

  • 8/2/2019 2.FBC Engg

    10/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    High Ash coalBellampalli, AP

    Mill RejectsParli TPS

    Fuels Tested

  • 8/2/2019 2.FBC Engg

    11/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Rice HuskRice Mill, Tiruchi

    Rice StrawTiruchi

    Mustard Crop Residue

    Manipal Int., Gurgaon

    Biomass Fuels Tested

  • 8/2/2019 2.FBC Engg

    12/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Wood ChipsTiruchi

    Palm ShellsKerala Electricity Board,

    Biomass Fuels Tested

  • 8/2/2019 2.FBC Engg

    13/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    36

    2

    26

    29

    3

    1

    1

    46

    6

    7

    7

    9

    12

    15

    Westinghouse-W191

    MES-SB30

    MES-SB60GE/BHEL-Fr 3

    JBE-Fr 5

    ALST-MS5001

    GE/BHEL-Fr 5

    MHI-Fr6

    ALST-Fr 6

    GE/BHEL-Fr 6

    GE/BHEL-Fr 6FA

    GE/BHEL Fr 9E

    Siemens-V 94.2

    GE/BHEL-Fr9FA Fired HRSG Unfired HRSG

    3

    6

    2

    26

    29

    3

    1

    1

    4

    6

    6

    7

    79

    12

    15

    Westinghouse-W191

    MES-SB30

    MES-SB60

    GE/BHEL-Fr 3

    JBE-Fr 5

    ALST-MS5001

    GE/BHEL-Fr 5

    MHI-Fr6

    ALST-Fr 6

    GE/BHEL-Fr 6

    GE/BHEL-Fr 6FA

    GE/BHEL Fr 9E

    Siemens-V 94.2GE/BHEL-Fr9FA

    Fired HRSG Unfired HRSG

    Combined Cycle - 62Cogeneration

    Unfired - 9Supplementary Fired - 66Total - 137

    ALST-Alsthome Atlantique, France

    JBE-John Brown Engg, UK

    MHI-Mitsubishi Heavy Industries, Japan

    MES-Mitsui Engg & Shipbuilding, Japan

    HRSG Experience list

    Around 100 HRSGs are

    of HARP design

  • 8/2/2019 2.FBC Engg

    14/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Two Row Module

    Single Row Module

    HRSG Module design

    improvement

  • 8/2/2019 2.FBC Engg

    15/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Module manufacturing Vertical position

    For better weld quality

    &

  • 8/2/2019 2.FBC Engg

    16/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Facility created for largersize HRSG Module

    Fabrication vertical

    position welding

    HRSG Frame assembly

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    17/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Standardisation of HRSGs for 9FA GTs

    Inlet ductBeam

    Bottom brazing

    beam

    Internal Liner

    Inlet duct

    HP

    IPF

    CS

    IP LP

    Duct

    Top brazing beam

    Insulation

    Main boilerColumn

    Modules

    HP Drum

    IP Drum

    LP Drum

    HP/IP/LP Drums

    Module height

    Module width

    Heat transfer bundlesdisposition.

    Inlet duct configuration

    Ducting & Liner system

    Insulation system

    Structures

    Column location and spacing

    Floors and stairs

    Module support arrangementand hangers

    Major components standardised for all 9FA HRSGs

    Floor

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    18/36Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    CFBC Boiler Design Upgrade

    About 50 feedbacks from the operational experience from Surat Lignite(SLPP Phase 1) and BILT Graphics

    Learnings from 158 SARs from SLPP I and BILT Graphics incorporated

    Discussions with manufacturing and OP & C groups for using ofstandard tooling and materials

    Discussions with Erection Group Pre engineering and before

    commencement of erection

    For 125 MW category

    For 250 MW category

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    19/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Feedbacks from Operating Units

    Lignite Feeder Improvements

    Back Sifting of Bed Ash into PA Wind box Back pass Hanger Tube Erosion

    FBHE WW Failures - Wall Pitch reduced

    AH tube corrosion - Arrangement/Metallurgy

    Soot blower at Back pass entry

    Welded Flow Orifices for Spray lines

    PA and SA ducts NMEJ to MEJ

    Cyclone, Feeder Outlet MEJ to NMEJ

    Header Connections Changed to avoid Choking

    Indigenisation of Refractory, Air-nozzles, Drag Link Chain Feeder, Rotary

    Feeder, Vortex Finder

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    20/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Backpass Hanger tube Erosion at Entry

    o Due to nature of the Duct

    connections from the Cyclones

    to the common Backpass

    preferential gas flow pattern

    exists.

    o This induces high velocity zones

    leading to tube erosion asindicated in the enclosed

    transparencies.

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    21/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    FlueGas

    Half Shields

    Plan View Convection Backpass Hanger Tubes

    CFD Study made and sacrificial Half-shields introduced. Performance

    found to be good

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    22/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Superheater Header connection change to avoid chocking

    Existing Improved

    Similar changes in RH and Economiser Headers

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    23/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Discussion with Manufacturing Groups

    Suggestions Implemented in 125 MW CFBC boilers:

    No. ofWW panels reduced from 187 to 148

    In-conel attachments in coils replaced by SS Attachments for

    easy welding

    Combination of T12, T22 & T91 avoided in a single coil to havesingle HT cycle (wherever feasible)

    Close pitch drilling of headers eliminated

    ID controlled sleeves for coils attachments for easy insertion

    Short Radius bends eliminated (Wherever feasible)

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    24/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Combustor Panel Openings - improvements

    Ease of Panel Manufacture

    PresentFuture

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    25/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Evaporator circuit close pitch drillingExisting Improved

    Similar Improvements made in SH2A, SH2B, RH1, SH3, SH1, Eco, Seal Pot header

    connections

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    26/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Major issues

    Trial assembly of cyclones & match marking at works

    Pullout bends of FBHE front panels to be supplied in loose

    Erection weld of FBHE coils at about 250 to 300 mm fromwater wall panel

    Seal boxes, cyclone, inlet & outlet ducting of cyclone to be fully

    welded from inside for better accessibility

    Erection Feedbacks Incorporated

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    27/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Teething Issues faced and resolved in Giral Phase 1

    Leakages of hot ash: Improper seal weldingof pressure parts

    were identified and attended to. Procedure evolved and sent toSite to include Protocols for checkingduring erection in Giral II.

    Clinker formation at Start-up Burner:ImpingementofHFoilon

    burnerthroatcaused clinkers. Resolved bychanging burner tips

    with narrower spray angle. HFO was also contaminated withwater - damaged pump barrel, also caused improper combustion

    in the burner

    Lignite Rotary Air-lock Feeder trips: Frequent feeder trips due to

    clutchslipping and resetting of the torquevalue was analysed

    andimprovements incorporatedin the clutch assembly and

    operating satisfactorily

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    28/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Teething Issues faced and resolved Contd.

    Foreign material entry into the Lignite feeding system:Foreign

    materials like tubes of 2-2.5m longhave found entryinto the

    drag chain feedersand damaged theconveyorchain links.

    Material hang-up in cyclone: The material buildup in LHS

    cyclone was observed on two occassions. After analysis

    improvements in operation logics

    measurements like seal-pot inlet pressure and

    temperature

    air injection in cyclone at some critical locations where

    material hang up noticed were implemented and the unit

    has been in satisfactory operation.

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    29/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Limestone size finer:The fines content (

  • 8/2/2019 2.FBC Engg

    30/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Issues to be resolved (Customer) - contd.

    HFO contaminated with water:The Heavy fuel oil (HFO) used during start-up/load support is contaminated with water and led to improper combustion. The oil pump

    barrel got damaged due to water and was replaced. HFO is hence not used in bed lances for

    maintaining the load in case of a problem in the Lignite feeding system. Steps taken for reducing

    moisture content.

    Flue gas analysers :Measurement of CO2 and O2 in order to ensure safe and complete

    combustion and SO2 measurement to ensure adequate limestone feeding is yet to beestablished. So far it has been managed with our portable instrument. Presently the instrument

    has been calibrated by Vendor and will be observed during operation.

    Lignite Drag Chain conveyor trips:Damages of the chain links occurred due to entry offoreign materials. The damaged chain assemblies were stiff. Vendor specialist from UK came to

    site, analysed and informed that presence of stagnant wet lignite is the cause. Advised that

    lignite is to be drained in case of unit shut down and also lubrication of the chains periodically

    to avoid such occurrences. Replaced with new conveyor chain assembly. Failure of Pins noticed

    during recent operation, Taken up with Supplier for resolution. Meantime, existing chain

    assembly is being replaced with new material supplied for Unit II

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    31/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Non Integral FBHE Arrangement 125 MW CFBC design

    Integral design Non-integral design

    Reduced Shop Weld & Ease of Panel Manufacture

    Downcomers (9 nos)

    2 nos 457.2 x 40.0

    2 nos 355.6 x 30.0

    2 nos 141.3 x 16.0

    3 nos 219.1 x 22.2

    Risers (78 nos)

    48 nos 159.0 x 16.0

    12 nos 101.6 x 10.0

    18 nos 88.9 x 11.13

    Supply Pipes (64 nos)

    40nos168.3 x 14.27

    8 nos 141.6 x 16.0

    16 nos 88.9 x 11.13

    Downcomers (5 nos)

    3 nos 457.2 x 40.0

    2 nos 368.0 x 56.0

    Risers (58 nos)

    58 nos 159.0 x 16.0

    Supply Pipes (44 nos)

    44 nos 159 x16.0

    Use of Standardized

    Forged Drum Nozzle

    Multi-Cell CLH, Disc Spring & Multi Ball Bearing Supports Eliminated

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    32/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Convective Pass Arrangement Reduction in erection joints

    10000 x 6800 10871.6 x 6807.2

    Section Assy# SL ST

    FSH 53 96 203.2

    FRH 106 96 101.6

    LTSH 106 96 101.6

    Eco IV 106 96 101.6Eco III 106 96 101.6

    Eco II 106 96 101.6

    Eco I 106 96 101.6

    Hanger 3x53 203.2

    No of Joints 10112 (including FBHE)

    Section Assy# SL ST

    FSH 55 65/102 180FRH 56 65/96 180

    LTSH 110 76 90

    Eco IV 110 90 90

    Eco III 110 90 90

    Eco II 110 90 90

    Eco I 110 90 90

    Hanger 3x55 180

    No of Joints 13252 (including FBHE)

    Present Future

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    33/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Manufacture & Erection Friendly 125 MW CFB Design Erection

    joint reduction

    Description Integral design Non integral design Variation

    No.of WW headers 251 37 86

    No.of WW Panel DUs 297 114 62

    Multi cell CLH 36 Nil 100

    Convective pass panel bend 1992 Nil 100

    No.of joints in

    FBHE WW panel 4496 Nil 100

    Combustor 2384 2384 No Change

    HT coils 13252 10112 24

    Others 1027 1027 No Change

    Total 21159 13523 36

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    34/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    Manufacture & Erection Friendly 250 MW CFB Design

    Description Proposal

    design

    Contract

    design

    Future design

    ( Suggested)

    Variation

    Combustor panels 9800 5430 4756 12FBHE RH 1 2500 2160 2160 No Change

    Low temperature SH 3000 2880 1440 50

    Interstage SH 1 3000 2880 1440 50

    Interstage SH 2 3000 2880 1440 50

    Steam cooled wall 3300 2700 2560 5

    Hanger tubes 4800 3000 2400 20

    Final SH 3600 3360 1680 50

    Final RH 6000 5760 2880 50

    BP Evaporator 5500 5400 3600 33

    Economiser 2500 3360 2520 25

    Other links 2205 2028 2028 No Change

    Total 49205 41838 28904 31

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    35/36

    Bharat Heavy Electricals Limited Tiruchirappalli

    FBC & HRSG

    CFD modeling of ducting for optimisation and for ease of manufacturing.

    (Eg. HRSG inlet ducting, Cyclone outlet ducting)

    PDMS approach Implemented in Konimabo Nickel CFBC boiler design.

    Clashes detected during engineering stage itself.

    Modularisation approach To reduce number of erection activities. Care

    should be taken for mode of transport

    Periodic meeting with site personnel and units concerned apart from pre-

    engineering discussion

    Interface activities finalisation at 0 date Hyderabad & PEM/Delhi

    Importance of proper storage at site and identification of material for easy

    retrieval Documentation on lessons learned and documentation for future reference

    Enhancing customer awareness on process requirement

    Towards bench marking through best practices

    FBC & HRSG

  • 8/2/2019 2.FBC Engg

    36/36

    Thank you

    Improvement over improvement

    Continues with your co-operation ..