1/17/2012 1 COST MANAGEMENT PRESENTED BY: HARSH JAIN PGDM SEM-1 SEC -µµC´ ROLL-5130
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 1/17
1/17/2012 1
COST MANAGEMENT
PRESENTED BY:
HARSH JAIN
PGDM SEM-1
SEC -µµC´ ROLL-5130
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 2/17
1/17/2012 2
Cost Management Cost Management includes:
Cost Estimation
Cost Budgeting
Cost Control
Estimation & Budgeting ± Main Tools & Techniques
Estimation Techniques Reserve Analysis ( Risk, Unknown, Cost of Quality)
Cost Baseline
Funding Requirements & Cash Flow
Cost Control.
Performance Measurement Analysis: Planned value, ActualCost, Cost Variance, Cost Performance Index, Estimate toComplete
Approved Change Requests
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 3/17
1/17/2012 3
Estimating Schedule Activity
Estimation Cost of the Resources Needed to complete the
activity
Includes variations to the cost estimate (Risk, Etc.)
Take into consideration Alternative Costing for the overall
project time period
Cost of extended design effort VS. additional maintenance costs
Cost estimates include ALL resources that will be charged to the
project including Inflation Forecast, Salary Increase,
Contingency cost.
ROM (Rough Order of Magnitude, E.G: ± 50/+100%) is allowed
in the first stages. Refinement is required at later stages ( E.G:
-10/+15%).
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 4/17
1/17/2012 4
Activity Estimating ± Inputs & Tools
Inputs External Factors: Marketplace Condition, External Cost
Information Databases
Organization Assets: Historical Information, EstimatingPolicies and Templates, Team Knowledge
Project Factors: Scope, WBS, Management Plan, SchedulePlan, Staffing Plan, Risk
Tools
Resource Cost Rates Parametric Estimates ( Function Points Etc.)
Vendor Bid Analysis
Project Management Software
Analogous estimate
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 5/17
1/17/2012 5
Activity Estimating ± Inputs & Tools
(Cont.) Reserve Analysis (Contingency Allowance)
Will Be Used at the Discretion of the Project Manager
Budgeting Project Unknowns
Risks Will Be budgeted according to their severity level andprobabilities
The budget will cover mitigation activities and workaroundsand will be implemented upon the project manager decision.
Cost of Quality (COQ) Costs added to the project in order to ensure conformance
with quality standards
Cost of Non Quality ± Failure Cost/Rework. Costs that willadded as a result of bugs and non-quality project activities
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 6/17
1/17/2012 6
Activity Estimating - Output
Activity Cost Estimating ± Most likely estimates of allthe activity resources
Estimate Details Basis for the estimate (how it was developed)
Assumptions made
Constraints
Possible range of the estimate ( 100000$ -10%/+15%)
Requested Changes ( If the estimate analysisrecommends a change)
CA ± Control Account (the corporate accountingnumber that will incur the cost of the activity)
Cost Management Plan (Update)
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 7/17
1/17/2012 7
Cost Baseline Aggregating the estimated costs of the individual
scheduled activities to establish a total COSTBASELINE for measuring and budgeting the project
Inputs: WBS, Activity Cost Estimate, ProjectSchedule, Resource Calendar, Contracts, Cost
Management Plan Tools & Techniques: Cost Aggregation, Reserve
Analysis, Parametric Estimating ( adjustment to theaggregate cost), Funding Limit Reconciliation (can
impact the schedule and overall cost)
Output: Cost Baseline, Expected Cash Flow, FundingRequirements (including Management Reserve),Requested Changes, Updated Cost ManagementPlan
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 8/17
1/17/2012 8
Cost control Assuring the Potential Cost Overrun do not exceed
the authorized funding PERIODICALLY and inTOTAL
Monitoring cost PERFORMANCE to detect andunderstand Variances from the Baseline
Detect Changes as they occur
Prevent unapproved changes
Ensuring Requested Changes are Agreed Upon
Report Changes to Stakeholders
Acting to bring expected overruns within acceptablelimits
Influencing factors that creates changes to the costbaseline
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 9/17
1/17/2012 9
Performance Measurements
Planned Value (PV) or Budget Cost of WorkSchedule (BCWS) ± baseline budget up to a givenpoint in time.
Earned Value of an Activity 0/100% technique ( The Recommended One): 0 if the
activity is not fully completed. Full Actual Cost if the activitywas completed.
50/50% technique: 50% of the planned cost if the activitystarted, 100% of the actual cost if it was completed
Milestone Technique: Actual Cost at the milestone date.
Earned Value (EV) or Budget Cost of WorkPerformed (BCWP) ± the sum of the baseline costs of the work performed up to a given point in time
Actual Cost (AC) or Actual Cost of Work Performed(ACWP) ± up to a given point in time
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 10/17
1/17/2012 10
Performance Indicators
Cost Variance ± The difference between actual andbudget cost spent up to a given point in time: EV ±
AC.
Schedule Variance ± The difference of the baseline
budget actually spend up to a given point of time andthe baseline budget that was originally planned up tothe same date: EV ± PV
CPI (Cost Performance\Overrun Indicator): EV/ ACEarned Value/ Actual Cost. CPI <1 indicates budget
overrun SPI (Schedule Performance\Overrun Indicator):
EV/PV Earned Value/Planned Value SPI<1 indicatesschedule overrun
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 11/17
1/17/2012 11
Example
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 12/17
1/17/2012 12
Forecasting
Making Predictions or Estimates of the Projectfuture Schedule or Cost based on the projectavailable information at the time of theForecasting.
Forecasting is USED TOGETHER withManual Forecasting of the remaining work.(which is considered to be more accurate)
Definitions:
BAC (Budget At Completion): Cost baseline at theend of the project
ETC (Estimate To Complete)
EAC (Estimate At Completion)
ADE ± Activity Duration Estimate
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 14/17
1/17/2012 14
Forecasting Techniques - Time
Recalculate Time of Future Activities Based on Typical Variance (History performance
of activity duration estimate is a good predictionfor the future performance) ADE(NEW) = ADE/SPI
Based On Atypical Variance ( History deviation of
planned performance is irrelevant for this activity) ADE(NEW)=ADE
Estimate Time To Completion will becalculated according to the project work
schedule and the critical path. If the variance is typical across the project we
can use a rough estimate : ADE = Plannedtime to completion/SPI
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 15/17
1/17/2012 15
Example
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 16/17
1/17/2012 16
Cost Control Workflow
Input: Cost Baseline, Funding Requirements,Performance Information and Reports, Approved
Change Requests, Project Management Plan
Tools & Techniques: Cost Change Control System,
Performance Measurement Analysis, Forecasting,Project Performance Review/Meeting, Variance
Management
Output: Cost Estimate Update, Cost Baseline
Update, Performance Measurements, Forecasted
Completion, Requested Changes, RecommendedCorrective Actions, Organization Process Assets
(lessons learned), Project Management Plan (update)
8/3/2019 26103858 Cost Management
http://slidepdf.com/reader/full/26103858-cost-management 17/17
1/17/201217
Approved Change Requests
Changes in the Scope of the System Requirements Requested By the Users and by
Project Management. May Change the Baseline Cost of the project as
well as the Planned Completion Date.
Requires Stakeholders Approval
Changes that do not affect the project Scope Usually Changed due to the project team requests
Changed in Design, Architecture, Delays, Etc.
Stakeholders will be notified if the changes aresignificant enough.