S.No Month
KVAH
Units
supplied
KWH
Units
supplied
KVAH Units
recorded /
computed
KWH Units
recorded
AV-Power
FactorMax.Dem
and
Recorded
KVA
Opening
Balance
Energy
ChargesDemandchargesbilled
(InRs.)
ED Billed
(In Rs.)
Capacitor
Surcharge
Billed (In
Rs.)Surcharge
for
meteringonLT
side
Latepaym
ent
surcharge
biled
Total Amount
Billed
(In Rs.)
Total
Amount
due
(in Rs.)
Amo
receive
Rs
A B C D E=D/C F G H I J K L M N=H+I+J+K+L+M O=G+N P
1 Apr-11
2 May-11
3 Jun-11
4 Jul-11
5 Aug-11
6 Sep-11
7 Oct-11
8 Nov-11
9 Dec-11
10 Jan-12
11 Feb-12
12 Mar-12
1
2 1
3 2
4 3
5
1
Electric Division-IV, Khanyar Sub-Division:-
Category: LT Indust. CT Ratio: Supply Type:
Zaku
ENERGY ACCOUNT OF 25 KVA AND ABOVE INSTALLATIONS UNDER TRIPARITE MOU DURING THE YEAR 2011-12
Name of Installation:- M/S Snowbar Cotton Mills
Circle: EM & RE Circle-Ist, Srinagar
Capacitor Installed: Rating of Capacitor: F-1
Note:
Type: Metered / Flat Rate: Metered
Installation No: Meter Rated Current Meter Type: Zakura
KVAH and demand readings will be required for load more than 100KW only. Late payment surcharge of 1.5 % per month on energy, demand charges and
dividing
recorded KWH units with power factor = 0.85 Surcharge on HT consumers for having metering on LT.
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT Surcharge shall include following:
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWHCapacitor surcharge @ 10% for not installing capacitors on all loads more tha
except for domestic, street lighting and loads where KVAH billing done.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
Note:
Late payment penalty (surcharge) if any adjusted in opening balance, when payment has not been made within due date.
7/28/2019 25kVA Endingfor the Year 2011-12I
2/94
DiVisio
200/5 LT3Ph
29084 5 Amp. LTKWH Name of 33/11KV Sub-Station
Computer Code: 3407 N N.A Feeder NSanctioned Load: 47HP
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
KVAH Units
recorded /
computed
KWH Units
recorded
AV-Power
Factor
Max.
Demand
Recorded
KVA
Opening
Balance
Energy
Charges
Demand
charges billed
(In Rs. )
ED Billed
(In Rs.)
Capacitor
Surcharge
Billed(In
Rs.)
Surcharge
for
metering
on LT side
Late
payment
surchar
ge biled
Total Amount
Billed
(In Rs.)
Total
Amount
due
(in Rs.)
A B C D E=D/C F G H I J K L M N=H+I+J+K+L+M O=G+N
1 Apr-11 3012 2560 3012 2560 0.85 N.A 106976.64 6054.00 1225.00 1331.97 550.40 8611.00 115588.00
2 May-11 1647 1400 1647 1400 0.85 N.A 117321.83 3311.00 1225.00 728.42 301.00 5264.00 122586.00
3 Jun-11 1647 1400 1647 1400 0.85 124425.00 3311.00 1225.00 728.42 301.00 5264.00 129689.00
4 Jul-11 2024 1720 2024 1720 0.85 N.A 131635.00 4068.00 1225.00 894.00 369.00 6188.00 137823.00
5 Aug-11 1176 1000 1176 1000 0.85 N.A 139889.00 2365.00 1225.00 520.00 215.00 4110.30 144000.00
6 Sep-11 1129 960 1129 960 0.85 N.A 146160.00 2270.00 1225.00 499.00 206.00 3994.89 150155.00
7 Oct-11 659 560 659 560 0.85 N.A 152407.00 1521.00 1400.00 335.00 138.00 3256.00 155664.00
8 Nov-11 0 0 0 0 0.85 N.A 157998.00 0.00 1400.00 0.00 0.00 1400.00 159399.00
9 Dec-11 0 0 0 0 0.85 N.A 161789.00 0.00 1400.00 0.00 0.00 1400.00 163190.00
10 Jan-12 0 0 0 0 0.85 N.A 165637.00 0.00 1400.00 0.00 0.00 1400.00 167037.00
11 Feb-12 0 0 0 0 0.85 N.A 167037.00 0.00 1400.00 0.00 0.00 1400.00 168437.00
12 Mar-12 0 0 0 0 0.85 N.A 168437.00 0.00 1400.00 0.00 0.00 1400.00 169837.00
1
2 1
3 2
4 3
Asstt. Exe. Engineer Executive Enginee
Zakura Electric Division-IV, kh
ENERGY ACCOUNT OF 25 KVA AND ABOVE INSTALLATIONS UNDER TRIPARITE MOU DURING THE YEAR 2010-11 ENDING March, 201
Name of Installation:- M/S P.H Industries
Circle: EM & RE Circle-Ist, Srinagar Electric Division-IV, Khanyar Sub-Division:
Installation No: Meter Rated Current Meter Type: Zakura
Category: LT Indust. CT Ratio: Supply Type:
Capacitor Installed: Rating of Capacitor: F-1
Type: Metered / Flat Rate: Metered
KVAH and demand readings will be required for load more than 100KW only. Late payment surcharge of 1.5 % per month on energy, demand cha
dividing
recorded KWH units with power factor = 0 85 S h HT f h i t i LT
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT Surcharge shall include following:
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWHCapacitor surcharge @ 10% for not installing capacitors on all loads
except for domestic, street lighting and loads where KVAH billing do
7/28/2019 25kVA Endingfor the Year 2011-12I
3/94
Asstt. Exe. Engineer Executive Engineer
Zakura Electric Division-IV, khanyar
7/28/2019 25kVA Endingfor the Year 2011-12I
4/94
DiVisio
100/5 LT3Ph
8151/M 5 Amp. LTKWH Name of 33/11KV Sub-Sta
Computer Code: 3882 N N.A Feeder
Sanctioned Load: 60HP
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
KVAH Units
recorded /
computed
KWH Units
recorded
AV-Power
Factor
Max.
Demand
Recorded
KVA
Opening
Balance
Energy
Charges
Demand
charges billed
(In Rs. )
ED Billed
(In Rs.)
Capacitor
Surcharge
Billed(In
Rs.)
Surcharge
for
metering
on LT side
Late
payment
surchar
ge biled
Total Amount
Billed
(In Rs.)
Total
Amount
due
(in Rs.)
re
A B C D E=D/C F G H I J K L M N=H+I+J+K+L+M O=G+N
1 Apr-11 3153 2680 3153 2680 0.85 N.A 0.00 6338.00 1575.00 1394.00 576.20 9307.60 9308.00
2 May-11 1929 1640 1929 1640 0.85 N.A 9447.00 3878.00 1575.00 853.29 352.60 6306.89 15754.00
3 Jun-11 1835 1560 1835 1560 0.85 N.A 15990.00 3689.40 1575.00 811.67 335.40 6076.07 22067.00
4 Jul-11 1647 1400 1647 1400 0.85 N.A -3.39 3311.00 1575.00 728.00 301.00 5614.00 5611.00
5 Aug-11 565 480 565 480 0.85 N.A 0.00 1135.00 1575.00 249.74 103.20 2959.94 2960.00
6 Sep-11 282 240 282 240 0.85 N.A 0.00 567.00 1575.00 124.87 51.60 2267.00 2267.00
7 Oct-11 471 400 471 400 0.85 N.A 2301.00 1086.00 1800.00 239.00 98.00 3126.00 5427.00
8 Nov-11 518 440 518 440 0.85 N.A 1.77 1195.00 1800.00 263.00 109.00 3259.00 3260.00
9 Dec-11 376 320 376 320 0.85 N.A 0.25 869.00 1800.00 191.00 79.00 2860.00 2861.00
10 Jan-12 329 280 329 280 0.85 N.A 2903.00 760.00 1800.00 167.00 69.00 2728.00 5632.00
11 Feb-12 329 280 329 280 0.85 N.A 0.01 760.00 1800.00 167.00 69.00 2728.00 2728.00
12 Mar-12 471 400 471 400 0.85 N.A 0 1086.00 1800.00 239.00 98.00 3125.00 3125.00
12 1
3 2
4 3
ZENERGY ACCOUNT OF 25 KVA AND ABOVE INSTALLATIONS UNDER TRIPARITE MOU DURING THE YEAR 2010-11 ENDING March, 2011
Name of InstallationM/S Royal Enterprises
Circle: EM & RE Circle-Ist, Srinagar Electric Division-IV, Khanyar Sub-Division:-
Installation No: Meter Rated Curr Meter Type: Zakura
Category: LT Indust CT Ratio: Supply Type:
Capacitor Installe Rating of Capacitor: F-1
Type: Metered / Flat Rate: Metered
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
except for domestic, street lighting and loads where KVAH billing done.
KVAH and demand readings will be required for load more than 100KW only. Late payment surcharge of 1.5 % per month on energy, demand charge
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT Surcharge shall include following:
dividing
recorded KWH units with power factor = 0.85 Surcharge on HT consumers for hav ing metering on LT.
7/28/2019 25kVA Endingfor the Year 2011-12I
5/94
DiVisio
400/5 HT
1/SD 5 Amp. N.A Name of 33/11KV Sub-Station
Computer Code: 3944 N N.A Feeder N
Sanctioned Load: 35 HP
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
KVAH Units
recorded /
computed
KWH Units
recorded
AV-Power
Factor
Max.
Demand
Recorded
KVA
Opening
Balance
Energy
Charges
Demand
charges billed
(In Rs. )
ED Billed
(In Rs.)
Capacitor
Surcharge
Billed(In
Rs.)
Surcharge
for
metering
on LT side
Late
payment
surchar
ge biled
Total Amount
Billed
(In Rs.)
Tota
Amou
due
(in Rs
A B C D E=D/C F G H I J K L M N=H+I+J+K+L+M O=G+
1 Apr-11 0 0 0 0 0.85 N.A 387919.75 41316.00 0.00 9089.52 3756.00 50405.52 438325
2 May-11 0 0 0 0 0.85 N.A 444900.00 41316.00 0.00 9089.52 3756.00 50405.52 495306
3 Jun-11 0 0 0 0 0.85 502735.00 41316.00 0.00 9089.52 3756.00 50405.52 553141
4 Jul-11 3106 2640 3106 2640 0.85 N.A 561438.00 41316.00 0.00 9089.52 3756.00 50405.52 611843
5 Aug-11 1035 880 1035 880 0.85 N.A 621021.00 41316.00 0.00 9089.52 3756.00 50405.52 671426
6 Sep-11 1035 880 1035 880 0.85 N.A 671426.00 41316.00 0.00 9089.52 3756.00 50405.52 721831
7 Oct-11 5808 4937 5808 4937 0.85 N.A 302431.00 41708.00 2940.00 9175.00 3792.00 53823.00 356254
8 Nov-11 7786 6618 7786 6618 0.85 N.A 361598.00 51645.00 0.00 11362.00 4695.00 63006.00 424605
9 Dec-11 5948 5056 5948 5056 0.85 N.A 329474.00 51645.00 0.00 11362.00 4695.00 63006.00 392481
10 Jan-12 6468 5498 6468 5498 0.85 N.A 398368.00 23223.00 2940.00 5109.00 2111.00 31272.00 429641
11 Feb-12 3421 2908 3421 2908 0.85 N.A 429641.00 12283.00 2940.00 2702.00 1116.00 17925.00 447567
12 Mar-12 3421 2908 3421 2908 0.85 N.A 447567.00 12283.00 2940.00 2702.00 1116.00 17925.00 465493
1
2 1
3 2
4 3
Zakura Electric Division-IV, k
Circle: EM & RE Circle-Ist, Srinagar Electric Division-IV, Khanyar Sub-Divisio
ENERGY ACCOUNT OF 25 KVA AND ABOVE INSTALLATIONS UNDER TRIPARITE MOU DURING THE YEAR 2010-11 ENDING March, 20
Installation No: Meter Rated Current Meter Type: Zakura
Name of Installation:- Joint Director Animal Husbandary
Category: State/Central CT Ratio: Supply Type:
Capacitor Installed: Rating of Capacitor: F-1
Type: Metered / Flat Rate: Flat Rate
KVAH and demand readings will be required for load more than 100KW only. Late payment surcharge of 1.5 % per month on energy, demand c
In case trivector meter is not installed for load more than 100KW, please workout the KVAH units by
dividing Surcharge on HT consumers for having metering on LT
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT Surcharge shall include following:
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWHCapacitor surcharge @ 10% for not installing capacitors on all loa
except for domestic, street lighting and loads where KVAH billing
7/28/2019 25kVA Endingfor the Year 2011-12I
6/94
Asstt. Exe. Engineer Executive Engineer
Zakura Electric Division-IV, khanyar
7/28/2019 25kVA Endingfor the Year 2011-12I
7/94
DiVisio
N.A HT
80/SD N.A N.A Name of 33/11KV Sub-Station
Computer Code: 4386 N N.A Feeder N
Sanctioned Load: 170HP
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
KVAH Units
recorded /
computed
KWH Units
recorded
AV-Power
Factor
Max.
Demand
Recorded
KVA
Opening
Balance
Energy
Charges
Demand
charges billed
(In Rs. )
ED Billed
(In Rs.)
Capacitor
Surcharge
Billed(In
Rs.)
Surcharge
for
metering
on LT side
Late
payment
surchar
ge biled
Total Amount
Billed
(In Rs.)
Tota
Amou
due
(in Rs
A B C D E=D/C F G H I J K L M N=H+I+J+K+L+M O=G
1 Apr-11 0 0 0 0 0.85 N.A ######## 189200.00 0.00 41624.00 17200.00 230824.00 440234
2 May-11 0 0 0 0 0.85 N.A ######## 189200.00 0.00 41624.00 17200.00 230824.00 469920
3 Jun-11 0 0 0 0 0.85 N.A ######## 189200.00 0.00 41624.00 17200.00 230824.00 500051
4 Jul-11 0 0 0 0 0.85 N.A ######## 189200.00 0.00 41624.00 17200.00 230824.00 530634
5 Aug-11 0 0 0 0 0.85 N.A ######## 189200.00 0.00 41624.00 17200.00 230824.00 561676
6 Sep-11 0 0 0 0 0.85 N.A ######## 189200.00 0.00 41624.00 17200.00 230824.00 593184
7 Oct-11 0 0 0 0 0.85 N.A ######## 236500.00 0.00 52030.00 21500.00 288530.00 623934
8 Nov-11 0 0 0 0 0.85 N.A ######## 236500.00 0.00 52030.00 21500.00 288530.00 662146
9 Dec-11 0 0 0 0 0.85 N.A ######## 236500.00 0.00 52030.00 21500.00 288530.00 700932
10 Jan-12 0 0 0 0 0.85 N.A ######## 236500.00 0.00 52030.00 21500.00 288530.00 740299
11 Feb-12 0 0 0 0 0.85 N.A ######## 236500.00 0.00 52030.00 21500.00 288530.00 769152
12 Mar-12 0 0 0 0 0.85 N.A ######## 236500.00 0.00 52030.00 21500.00 288530.00 798005
1
2 1
3 2
4 3
ENERGY ACCOUNT OF 25 KVA AND ABOVE INSTALLATIONS UNDER TRIPARITE MOU DURING THE YEAR 2010-11 ENDING March, 20Name of Installation:- Ex. Engineer PHE Mechanical Irrigation
Circle: EM & RE Circle-Ist, Srinagar Electric Division-IV, Khanyar Sub-Divisio
Type: Metered / Flat Rate: Flat Rate
Installation No: Meter Rated Curren Meter Type: Zakura
Category: LT Water Works CT Ratio: Supply Type:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT Surcharge shall include following:
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWHCapacitor surcharge @ 10% for not installing capacitors on all loexcept for domestic, street lighting and loads where KVAH billing
Capacitor Installed: Rating of Capacitor: F-2
Note:
KVAH and demand readings will be required for load more than 100KW only. Late payment surcharge of 1.5 % per month on energy, demand
In case trivector meter is not installed for load more than 100KW, please workout the KVAH units by
dividing Surcharge on HT consumers for having metering on LT.
7/28/2019 25kVA Endingfor the Year 2011-12I
8/94
Asstt. Exe. Engineer Executive Engineer
Zakura Electric Division-IV, khanyar
7/28/2019 25kVA Endingfor the Year 2011-12I
9/94
DiVisio
200/5 HT
3163 5 Amp.
HT
trivector Name of 33/11KV Sub-Station
Computer Code: 4408 N N.A Feeder N F-4
Sanctioned Load: 173kW
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
KVAH Units
recorded /
computed
KWH Units
recorded
AV-Power
Factor
Max.
Demand
Recorded
KVA
Opening
Balance
Energy
Charges
Demand
charges billed
(In Rs. )
ED Billed
(In Rs.)
Capacitor
Surcharge
Billed(In
Rs.)
Surcharge
for
metering
on LT side
Late
payment
surchar
ge biled
Total Amount
Billed
(In Rs.)
Tot
Amo
du
(in R
A B C D E=D/C F G H I J K L M N=H+I+J+K+L+M O=G
1 Apr-11 16246 13809 16246 13809 0.85 N.A 0.00 87122.77 3460.00 0.00 7920.00 90583.00 90583
2 May-11 19580 16643 19580 16643 0.85 N.A 0.00 104997.75 3460.00 0.00 9545.25 108457.00 10845
3 Jun-11 17930 15241 17930 15241 0.85 N.A 0.00 96149.63 3460.00 0.00 8740.88 99609.63 99610
4 Jul-11 21640 18394 21640 18394 0.85 N.A 0.00 116044.00 3460.00 0.00 10549.00 119504.00 11950
5 Aug-11 21240 18054 21240 18054 0.85 N.A 0.00 113899.00 3460.00 0.00 10354.00 117359.00 11735
6 Sep-11 19420 16507 19420 16507 0.85 N.A 0.00 104139.75 3460.00 0.00 9467.00 107599.00 10760
7 Oct-11 20530 17451 20530 17451 0.85 N.A 0.25 129909.00 4152.00 0.00 11889.00 134060.00 13406
8 Nov-11 38660 32861 38660 32861 0.85 N.A 0.00 244631.00 4152.00 0.00 22239.00 248783.00 24878
9 Dec-11 31740 26979 31740 26979 0.85 N.A 0.00 200843.00 4152.00 0.00 18258.00 204994.00 20499
10 Jan-12 32020 27217 32020 27217 0.85 N.A 0.00 202614.00 4152.00 0.00 18419.00 206766.00 20676
11 Feb-12 32700 27795 32700 27795 0.85 N.A 0.00 206917.00 4152.00 0.00 18810.00 211069.00 21106
12 Mar-12 22540 19159 22540 19159 0.85 N.A 0.00 142627.00 4152.00 0.00 12966.00 146779.00 14677
1
2 1
3 2
Electric Division-IV, Khanyar Sub-Divisi
Category: State/Central CT Ratio: Supply Type:
ENERGY ACCOUNT OF 25 KVA AND ABOVE INSTALLATIONS UNDER TRIPARITE MOU DURING THE YEAR 2010-11 ENDING March, 2Name of Installation:- Baba Atomic Research Centre
Circle: EM & RE Circle-Ist, Srinagar
Capacitor Installed: Rating of Capacitor:
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Type: Metered / Flat Rate: Metered
Installation No: Meter Rated Current Meter Type: Habak
Surcharge shall include following:
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWHCapacitor surcharge @ 10% for not installing capacitors on all lo
except for domestic, street lighting and loads where KVAH billin
KVAH and demand readings will be required for load more than 100KW only. Late payment surcharge of 1.5 % per month on energy, demand
7/28/2019 25kVA Endingfor the Year 2011-12I
10/94
Zakura Electric Division-IV, khanyar
Asstt. Exe. Engineer Executive Engineer
7/28/2019 25kVA Endingfor the Year 2011-12I
11/94
7/28/2019 25kVA Endingfor the Year 2011-12I
12/94
7/28/2019 25kVA Endingfor the Year 2011-12I
13/94
7/28/2019 25kVA Endingfor the Year 2011-12I
14/94
7/28/2019 25kVA Endingfor the Year 2011-12I
15/94
7/28/2019 25kVA Endingfor the Year 2011-12I
16/94
7/28/2019 25kVA Endingfor the Year 2011-12I
17/94
7/28/2019 25kVA Endingfor the Year 2011-12I
18/94
7/28/2019 25kVA Endingfor the Year 2011-12I
19/94
7/28/2019 25kVA Endingfor the Year 2011-12I
20/94
1911/M 100/5 3/LT B.A.M.Khan
415 LT/KWH 3 F-1
45 HP N
KVAH
Units
recorded
KWH
Units
recorded AV-Power
Factor
Max.Dema
nd
RecordedKVA
OpeningB
alance
EnergyCharges
billed
(In Rs.) Capicator
Charges
Demandc
harges
billed(In
Rs.)
ED Billed
(In Rs.) Surchargeifany
billed(InRs.)
TotalAmount
Billed
(InRs.)
Amountre
ceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 1858.82 1580 1858.82 1580 0.85 NA 0.00 3736.00 0.00 1190.00 822.07 0.00 5748.07 4364.00 1384.0
2 May-11 2094.12 1780 2094.12 1780 0.85 NA 0.00 4209.70 0.00 1190.00 926.13 0.00 6325.83 5749.00 576.83
3 Jun-11 3129.41 2660 3129.41 2660 0.85 NA 0.00 6290.90 0.00 1190.00 1384.00 0.00 8864.90 6325.00 2539.9
4 Jul-11 3152.94 2680 3152.94 2680.00 0.85 NA 0.00 6338.00 0.00 1190.00 1394.40 0.00 8922.40 8865 57.40
5 Aug-11 2658.82 2260 2658.82 2260 0.85 NA 0 5344.00 485.00 1190.00 1175.00 1214.00 7709.00 8923.00 17846
6 Sep-11 2070.59 1760 2070.59 1760 0.85 NA 0 4162 0 1190.00 915.73 1214 7481.00 7711.00 0.00
7 Oct-11 2376.47 2020 2376.47 2020 0.85 NA 0 5488 0 1360.00 1207.43 0 8055.00 6268.00 8056.0
8 Nov-11 1741.18 1480 1741.18 1480 0.85 NA 0 4021 365 1360.00 884.66 0 6265.00 8056.00 0.00
9 Dec-11 2282.35 1940 2282.35 1940 0.85 NA 0 5270 0 1360.00 1159 0 7791.00 6265.00 7791.0
10 Jan-12 2141.18 1820 2141.18 1820 0.85 NA 0 4944 0 1360.00 1087 0 7392 7791 7393
11 Feb-12 494.118 420 494.118 420 0.85 NA 0 1738.88 0 1360.00 382.55 0 3481 7393 3481
12 Mar-12 1764.71 1500 1764.71 1500 0.85 NA 0 4075 0 1360.00 896 0 6332 3481 6332
Total
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Information from April 2011 to March 2012
Please attach circle-wise and Divisional wise Abstracts with each energy account.
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
SUB-DIVISION: Hawal
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Computer Code: Meter Rated Current: Meter Type: Feeder No:
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
ENERGY ACCOUNT OF 25 KVA AND ABOVE INSTALLATIONS UNDER TRIPARITE MoU FROM
M/S ZAMIR Fayaz (timbo traders)Installation No: CT Ratio: Supply Type: Name of 33/11KV Sub-Stations:
7/28/2019 25kVA Endingfor the Year 2011-12I
21/94
7/28/2019 25kVA Endingfor the Year 2011-12I
22/94
ACCOUN
1 M/ 11 400/5 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan388 LT/KWH 3Feeder No: F-1
53 HP N
KVAHUnits
recorded
KWHUnits
recorded AV-Pow
erFactor
Max.De
mand
Recorde
dKVA
Opening
Balance
Energy
Chargesbilled
(In Rs.) Capicator
Charges
Deman
dcharges
billed
(InRs.)
ED Billed
(In Rs.) Surcha
rgeifany
billed
(InRs.)
TotalAm
ount
Billed
(InRs.)
Amount
received
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Mar-11 0 0 0 0 0.00 NA 68355.66 0.00 0.00 1400.00 0.00 700.00 2100.00 0.00 70455.6
2 Apr-11 0 0 0 0 0.00 NA 72607.00 0.00 0.00 1400.00 0.00 700.00 2100.00 0.00 74707.0
3 May-11 0 0 0 0 0.00 NA 75117.00 0.00 0.00 1400.00 0.00 700.00 2100.00 0.00 77217.0
4 Jun-11 0 0 0 0 0.00 NA 77664.00 0.00 0.00 1400.00 0.00 700.00 2100.00 0.00 79764.0
5 Jul-11 0 0 0 0.00 0.85 NA 80250.00 0.00 0.00 1400.00 0.00 700.00 2100.00 0.00 82350.0
6 Aug-11 0 0 0 0 0.85 NA 82875.00 0.00 0.00 1400.00 0.00 700.00 2100.00 0.00 84975.0
7 Sep-11 0 0 0 0 0.85 NA 85539 0.00 0.00 1400 0.00 700 2100.00 0 87639.0
8 Oct-11 0 0 0 0 0.85 NA 88243 0.00 0.00 1600 0 700 2300.00 0 90543
9 Nov-11 0 0 0 0 0.85 NA 91191 0.00 0.00 1600 0 700 2300.00 0 93491
10 Dec-11 0 0 0 0 0.85 NA 94183 0 0 1600 0 700 1600 0 95783
11 Jan-12 0 0 0 0 0.85 NA 97220 0 0 1600 0 700 1600 0 98820
12 Feb-12 0 0 0 0 0.85 NA 100302 0 0 1600 0 700 1600 0 101902
13 Mar-12 0 0 0 0 0.85 NA 103431 0 0 1600 0 700 1600 0 105031
1
23
4
Executive Engineer
Electric Division-IV, khanyar
Please attach circle-wise and Divisional wise Abstracts with each energy account.
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWHKVAH and demand readings will be required for load more than 100KW only.
SUB-DIVISION: Hawal
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Computer Code: Meter Rated Current: Meter Type:
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
m/s modern joinery mill
Installation No: CT Ratio: Supply Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
23/94
ACCOUN
3049/M 100/5 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
393 LT/KWH 3Feeder No: F-1
37 HP N
KVAH
Units
recorded
KWH
Units
recorded AV-PowerFac
tor
Max.Demand
RecordedKVA
OpeningBala
nce
Energy
Charges
billed
(In Rs.) Capicator
Charges
Demandcharges
billed(InRs.)
ED Billed
(In Rs.) Surchargeif
any
billed(InRs.)
TotalAmount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Mar-11 2400 2040 2400 2040 0.85 NA 37298.74 7180.80 0.00 1960.00 1579.78 400.00 11120.58 0.00 48419.3
2 Apr-11 2423.53 2060 2423.53 2060 0.85 NA 49627.00 7251.20 0.00 1960.00 1595.26 2000.00 10806.46 10000.00 52433.4
3 May-11 1388.24 1180 1388.24 1180 0.85 NA 51190.00 4153.60 0.00 2100.00 913.79 0.00 7167.39 10000.00 48357.3
4 Jun-11 1435.29 1220 1435.29 1220 0.85 NA 44008.00 4294.40 0.00 2100.00 944.77 0.00 7339.17 15000.00 36347.1
5 Jul-11 1552.94 1320 1552.94 1320.00 0.85 NA 36892.00 4646.40 0.00 2100.00 1022.21 0.00 7768.61 15000 29660.6
6 Aug-11 1129.41 960 1129.41 960 0.85 NA 30106 3379.20 0.00 2100.00 743.42 2000.00 6222.62 15000.00 21328.6
7 Sep-11 1529.41 1300 1529.41 1300 0.85 NA 21874 4576.00 0.00 2100 1006.00 0 7682 15000 14775.0
8 Oct-11 1529.41 1300 1529.41 1300 0.85 NA 14775 5491.00 0.00 2520 1208 0 9219 15000.00 9129.0
9 Nov-11 1529.41 1300 1529.41 1300 0.85 NA 9129 5491.00 0.00 2520 1208 0 9219 15000.00 18349.0
10 Dec-11 2000 1700 2000 1700 0.85 NA 0 7180.8 0 2520 1579.78 0 11280 18349 11280
11 Jan-12 2141.18 1820 2141.18 1820 0.85 NA 0 7687 0 2520 1691 0 11898 11280 11899
12 Feb-12 2141.18 1820 2141.18 1820 0.85 NA 0 7687 0 2520 1691 0 11898 11899 11899
13 Mar-12 1670.59 1420 1670.59 1420 0.85 NA 0 5998 0 2520 7317 0 9837 11899 9838
1
2
3
4
Executive EngineerElectric Division-IV, khanyar
Please attach circle-wise and Divisional wise Abstracts with each energy account.
Note:Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
SUB-DIVISION: Hawal
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Computer Code: Meter Rated Current: Meter Type:
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
m/s national wood industries
Installation No: CT Ratio: Supply Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
24/94
ACCOUN
1 M / 44 100/5 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
310 LT/KWH 3Feeder No: F-1
31 HP N
KVAH
Units
recorded
KWH
Units
recorded AV-PowerFactor
Max.Dema
nd
RecordedKVA
OpeningB
alance
EnergyCharges
billed
(In Rs.) Capicator
Charges
Demandc
harges
billed(In
Rs.)
ED Billed
(In Rs.) Surchargeifany
billed(In
Rs.)
TotalAmount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
lance as on 11/2010 3091.0
1 Mar-11 1435.29 1220 1435.29 1220 0.85 NA #REF! 2885.30 0.00 840.00 634.77 0.00 4360.07 5399.00 #REF!
2 Apr-11 1176.47 1000 1176.47 1000 0.85 NA 4425.00 2365.00 0.00 840.00 520.30 0.00 3725.30 0.00 8150.3
3 May-11 1364.71 1160 1364.71 1160 0.85 NA 8272.00 2743.00 0.00 840.00 603.55 0.00 4186.55 0.00 12458.5
4 Jun-11 1411.76 1200 1411.76 1200 0.85 NA 12646.00 2838.00 0.00 840.00 624.36 0.00 4302.36 0.00 16948.3
5 Jul-11 1529.41 1300 1529.41 1300.00 0.85 NA 17203.00 3074.00 0.00 840.00 676.39 0.00 4590.39 0 21793.3
6 Aug-11 870.588 740 870.588 740 0.85 NA 22121 1750.00 0.00 840.00 385.00 0.00 2975.00 0.00 25096.0
7 Sep-11 1623.53 1380 1623.53 1380 0.85 NA 0 3263.00 0.00 840 718 0 4821.00 25096.00 4821.0
8 Oct-11 1411.76 1200 1411.76 1200 0.85 NA 0 3260.00 0.00 960 717 0 4937.00 4822.00 4937.0
9 Nov-11 1647.06 1400 1647.06 1400 0.85 NA 0 3803.00 0.00 960 836 0 5599.00 4938.00 5599.0
10 Dec-11 1529.41 1300 1529.41 1300 0.85 NA 5684.21 3532 0 960 777.06 0 5269.06 0 10953.2
11 Jan-12 988.235 840 988.235 840 0.85 NA 11117.67 840 0 960 502.1 0 3744 0 14862
12 Feb-12 1105.88 940 1105.88 940 0.85 NA 0 22553.98 0 960 561.88 0 4075.86 14862 4076
13 Mar-12 1811.76 1540 1811.76 1540 0.85 NA 0 4184 0 960 920 0 6064 4076 6265
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Please attach circle-wise and Divisional wise Abstracts with each energy account.
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
SUB-DIVISION: Hawal
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Computer Code: Meter Rated Current: Meter Type:
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
m/s national spicesInstallation No: CT Ratio: Supply Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
25/94
1079/M 100/5 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
1871 LT/KWH 3Feeder No: F-1
30 HP N
KVAH
Units
recorded
KWH
Units
recorded A
V-PowerFactor
M
ax.Demand
R
ecordedKVA
O
peningBalance
Energy
Charges
billed
(In Rs.) C
apicator
C
harges
Demandcharges
billed(InRs.)
ED Billed
(In Rs.)Surchargeifany
billed(InRs.)
T
otalAmount
B
illed
(InRs.)
A
mountreceived
(InRs.)
Arrears(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 1035.29 880 1035.29 880 0.85 NA 199917.00 2081.20 0.00 1575.00 457.56 0.00 4113.76 0.00 204030.
2 May-11 3952.94 3360 3952.94 3360 0.85 NA 207092.00 7946.40 0.00 1748.21 722.40 0.00 11269.00 0.00 218361.
3 Jun-11 2023.53 1720 2023.53 1720 0.85 NA 221637.00 4067.80 0.00 1575.00 894.92 0.00 6537.72 0.00 228174.
5 Jul-11 6541.18 5560 6541.18 5560.00 0.85 NA 231597.00 13149.40 0.00 1575.00 2892.27 0.00 17616.67 0.00 249213.
6 Aug-11 3576.47 3040 3576.47 3040 0.85 NA 252952 7189.00 1575.00 1581.71 0.00 10345.71 0.00 263297.
7 Sep-11 235.294 200 235.294 200 0.85 NA 267248 473 0 1575.00 104.6 0 2152.60 269400.
8 Oct-11 4988.24 4240 4988.24 4240 0.85 NA 273441 11520 0 1800.00 2534 0 15854.00 0.00 269401.
9 Nov-11 1694.12 1440 1694.12 1440 0.85 NA 293635 3912.48 0 1800.00 860 0 6572.48 0.00 300209.
10 Dec-11 470.588 400 470.588 400 0.85 NA 304712.03 1086.8 0 1800.00 239.1 0 3125 0 30783811 Jan-12 658.824 560 658.824 560 0.85 NA 282005 1521 0 1800.00 334.73 0 3656 30000 285662
12 Feb-12 941.176 800 941.176 800 0.85 NA 289946.69 2173.6 0 1800.00 478.19 0 4451 0 294398
13 Mar-12 517.647 440 517.647 440 0.85 NA 268814 1195 0 1800.00 263 0 3258 30000 272073
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Please attach circle-wise and Divisional wise Abstracts with each energy account.
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
SUB-DIVISION: Hawal
S.No Month
KVAH
Unitssupplied
KWH
Unitssupplied
Computer Code: Meter Rated Current: Meter Type:
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
Installation No: CT Ratio: Supply Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
26/94
ACCOUN
3439/M 150/5 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
15238 LT/KWH 3Feeder No: F-1
30 HP N
KVAH
Units
recorded
KWH
Units
recorded AV-PowerFactor
Max.Demand
RecordedKVA
OpeningBala
nce
Energy
Charges
billed
(In Rs.) Capicator
Charges
Demandcha
rges
billed(InRs.)
ED Billed
(In Rs.) Surchargeif
any
billed(InR
s.)
TotalAmount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 1164.71 990 1164.71 990 0.85 NA 5642.20 2341.35 0.00 805.00 515.00 0.00 3661.35 5721.00 3582.5
2 May-11 988.235 840 988.235 840 0.85 NA 3582.55 1986.00 0.00 805.00 437.05 0.00 3228.05 3662.00 3148.6
3 Jun-11 952.941 810 952.941 810 0.85 NA 3189.00 1915.65 0.00 805.00 421.44 0.00 3142.09 3228.00 3103.0
4 Jul-11 1305.88 1110 1305.88 1110.00 0.85 NA 3062.69 2625.15 0.00 805.00 577.53 0.00 4007.68 0.00 7070.3
5 Aug-11 705.882 600 705.882 600 0.85 NA 0 1419.00 0.00 805.00 312.00 0.00 2536.00 7197.00 -4661.0
6 Sep-11 847.059 720 847.059 720 0.85 NA 0 1702.00 0.00 805 374 0 2881.00 2536.00 345.00
7 Oct-11 952.941 810 952.941 810 0.85 NA 0 2200.00 0.00 920 484 0 3604.00 2883.00 721.00
8 Nov-11 741.176 630 741.176 630 0.85 NA 0 1711.00 0.00 920 376 0 3007.00 3605.00 -598.00
9 Dec-11 247.059 210 247.059 210 0.85 NA 0 570.57 0 920 125.53 0 1616.1 3008 1616
10 Jan-12 423.529 360 423.529 360 85 NA 0 978.14 0 920 215.19 0 2113.33 1616 2113
11 Feb-12 670.588 570 670.588 570 0.085 NA 0 1548 0 920 340.71 0 2808.71 2113 2810
12 Mar-12 811.765 690 811.765 690 0.085 NA 0 1874 0 920 412 0 3207 2810 3207
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
SUB-DIVISION: Hawal
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Computer Code: Meter Rated Current: Meter Type:
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
m/s shah steel industries
Installation No: CT Ratio: Supply Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
27/94
ACCOUN
20302/M 100/5 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
15245 LT/KWH 3Feeder No: F-1
31 HP N
KVAH
Units
recorded
KWH
Units
recorded AV-PowerFactor
Max.Demand
RecordedKVA
OpeningBala
nce
Energy
Charges
billed
(In Rs.) Capicator
Charges
Demandcha
rges
billed(InRs.)
ED Billed
(In Rs.) Surchargeif
any
billed(InR
s.)
TotalAmount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Mar-11 1294.12 1100 1294.12 1100 0.85 NA 40620.51 2601.00 0.00 840.00 572.33 500.00 4513.33 5000.00 40133.8
2 Apr-11 1435.29 1220 1435.29 1220 0.85 NA 35400.00 2885.30 0.00 840.00 634.77 500.00 4360.07 5000.00 34760.0
3 May-11 847.059 720 847.059 720 0.85 NA 35281.00 1702.80 0.00 840.00 374.00 500.00 3416.80 5000.00 33697.8
4 Jun-11 564.706 480 564.706 480 0.85 NA 33697.00 1135.00 0.00 840.00 249.74 500.00 2724.74 5000.00 31421.7
5 Jul-11 635.294 540 635.294 540.00 0.85 NA 31385.00 1277.00 0.00 840.00 280.96 500.00 2397.96 5000.00 28782.9
6 Aug-11 282.353 240 282.353 240 0.85 NA 29215 567.00 0.00 840.00 124.00 0.00 1531.00
7 Sep-11 541.176 460 541.176 460 0.85 NA 26209 1087.00 0.00 840 239 0 2167.00 5000.00 28377.0
8 Oct-11 258.824 220 258.824 220 0.85 NA 23727 597.00 0.00 960 131.5 500 1689.00 5000.00 25416.0
9 Nov-11 352.941 300 352.941 300 0.85 NA 20797 815.00 0.00 960 179.32 500 1954.00 5000.00 22752.0
10 Dec-11 352.941 300 352.941 300 0.85 NA 18018.38 815 0 960 179.32 0 1954 5000 19973
11 Jan-12 423.529 360 423.529 360 0.85 NA 15197 978.12 0 960 215.19 0 2153 5000 17351
12 Feb-12 776.471 660 776.471 660 0.85 NA 12350 1793.22 0 960 394.51 0 3147 5000 15498
13 Mar-12 894.118 760 894.118 760 0.85 NA 10730 2064 0 960 454 0 3479 5000 14210
1
2
3
4
Executive EngineerElectric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
m/s minoo metallic
Installation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
28/94
10811/M 400/5 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
15266 LT/KWH 3Feeder No: F-1
30 HP N
KVAH
Units
recorded
KWH
Units
recorded A
V-PowerFactor
M
ax.Demand
R
ecordedKVA
O
peningBalance
Energy
Charges
billed
(In Rs.) C
apicator
C
harges
Demandcharges
billed(InRs.)
ED Billed
(In Rs.)Surchargeifany
billed(InRs.)
T
otalAmount
B
illed
(InRs.)
A
mountreceived
(InRs.)
Arrears(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 5364.71 4560 5364.71 4560 0.85 NA 10912.48 9804.00 0.00 1260.00 2156.88 0.00 13220.88 10912.00 13221.3
2 May-11 2541.18 2160 2541.18 2160 0.85 NA 13221.36 4644.00 0.00 1260.00 1021.68 0.00 6925.68 13221.00 6926.0
3 Jun-11 2352.94 2000 2352.94 2000 0.85 NA 6926.04 4300.00 0.00 1260.00 946.00 0.00 6506.00 6926.00 6506.0
4 Jul-11 2729.41 2320 2729.41 2320.00 0.85 NA 6506.04 4988.00 0.00 1260.00 1097.36 0.00 7345.36 6506 7345.4
5 Aug-11 2164.71 1840 2164.71 1840 0.85 NA 0 3956.00 0.00 1260.00 870.32 0.00 6086.32 7345.00 -1258.6
6 Sep-11 2070.59 1760 2070.59 1760 0.85 NA 0 3784 0 1260 832 0 5876.00 6178 5876.0
7 Oct-11 1788.24 1520 1788.24 1520 0.85 NA 0 3754 0 1440 825.97 0 6019.97 5876 6021.0
8 Nov-11 1788.24 1520 1788.24 1520 0.85 NA 0 3754 0 1440 825.97 0 6019.97 6021 6021.0
9 Dec-11 5458.82 4640 5458.82 4640 0.85 NA 0 11460 0 1440 2521.38 0 15421.38 6020 1542210 Jan-12 6494.12 5520 6494.12 5520 0.85 NA 0 13634.4 0 1440 2999.57 0 18073.97 15422 18074
11 Feb-12 8000 6800 8000 6800 0.85 NA 0 16796 0 1440 3695.12 0 21931.12 18074 21931
12 Mar-12 4800 4080 4800 4080 0.85 NA 0 10077 0 1440 2217 0 13734.00 21931 13735
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Unitssupplied
KWH
Unitssupplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
Installation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
29/94
ACCOUN
1090/M 100/5 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
15269 LT/KWH 3Feeder No: F-1
50 HP N
KVAH
Units
recorded
KWH
Units
recorded AV-PowerFactor
Max.Demand
RecordedKVA
OpeningBalance
Energy
Charges
billed
(In Rs.) Capicator
Charges
Demandcharges
billed(InRs.)
ED Billed
(In Rs.) Surchargeifany
billed(InRs.)
TotalAmount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 1458.82 1240 1458.82 1240 0.85 NA 26693.00 2932.60 0.00 1330.00 645.17 300.00 5207.77 0.00 31900.7
2 May-11 1435.29 1220 1435.29 1220 0.85 NA 0.00 2885.30 0.00 1330.00 635.00 0.00 4850.30 0.00 4850.3
3 Jun-11 1200 1020 1200 1020 0.85 NA 0.00 2412.30 0.00 1330.00 530.71 0.00 4273.01 4850.00 -576.99
4 Jul-11 1364.71 1160 1364.71 1160 0.85 NA 4337.00 2743.00 0.00 1330.00 603.00 0.00 4676.00 0.00 9014.0
5 Aug-11 752.941 640 752.941 640.00 0.85 NA 9149.00 15613 0 1330.00 332.99 0.00 17275.99 0.00 26424.9
6 Sep-11 1152.94 980 1152.94 980 0.85 NA 4391 2317 0 1330.00 509.89 0.00 4156.89 8000.00 8549.0
7 Oct-11 1411.76 1200 1411.76 1200 0.85 NA 0 3260 0 1520 717 0 5497.00 8549.00 5497.0
8 Nov-11 1294.12 1100 1294.12 1100 0.85 NA 0 2988 0 1520 657.51 0 5165.51 5497.00 5167.0
9 Dec-11 1176.47 1000 1176.47 1000 0.85 NA 5244 2717 0 1520 597.74 0 4834.00 0.00 10079.0
10 Jan-12 1129.41 960 1129.41 960 0.85 NA 10229.63 2608.32 0 1520 573.83 0 4702 0 14932
11 Feb-12 1458.82 1240 1458.82 1240 0.85 NA 0 3369 0 1520 741 0 5630 14932 5630.2
12 Mar-12 823.529 700 823.529 700 0.85 NA 0 1901 0 1520 418 0 3840 5130 3841
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
m/s taj spices
Installation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
30/94
2126/M 200/5 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
294 LT/KWH 3Feeder No: F-1
60 HP N
KVAH
Units
recorded
KWH
Units
recorded AV-Power
Factor
Max.Demand
Recorded
KVA
OpeningB
alance
EnergyCharges
billed
(In Rs.) Capicator
Charges
Demandcharges
billed(InRs.)
ED Billed
(In Rs.) Surcharg
eifany
billed(InRs.)
TotalAmo
unt
Billed
(InRs.)
Amountre
ceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 47.0588 40 47.0588 40 0.85 NA 0.00 94.60 1575.00 20.81 0.00 1690.41 2383.00 -692.59
2 May-11 329.412 280 329.412 280 0.85 NA 0.00 662.20 1575.00 145.68 0.00 2382.88 1690.00 692.88
3 Jun-11 141.176 120 141.176 120 0.85 NA 0.00 283.80 1575.00 62.44 0.00 1921.24 2383.00 -461.76
4 Jul-11 188.235 160 188.235 160 0.85 NA 0.00 378.40 1575.00 83.25 0.00 2036.35 1921.00 2037.0
5 Aug-11 282.353 240 282.353 240.00 0.85 NA 0.00 567.00 1575.00 124.87 0.00 2266.87 2037.00 229.87
6 Sep-11 141.176 120 141.176 120 0.85 NA 2301.37 283.00 1575.00 62.44 0.00 1920.44 1921.00 4223.0
7 Oct-11 0 0 0 0 0.85 NA 0 0.00 1800 0.00 0.00 1800.00 4223 1800.0
8 Nov-11 0 0 0 0 0.85 NA 1826 0.00 1800 0.00 0.00 1800.00 1800 3627.0
9 Dec-11 47.0588 40 47.0588 40 0.85 NA 0 108.68 1800 23.91 0.00 1932.59 3627 1932.0
10 Jan-12 188.235 160 188.235 160 0.85 NA 0 434.72 1800 95.64 0 2330.36 1932 2331
11 Feb-12 188.235 160 188.235 160 0.85 NA 0 434.72 1800 95.64 0 2330.36 2331 2330
12 Mar-12 141.176 120 141.176 120 0.85 NA 2364 326 1800 71 0 2197 0 4563
1
2
3
4
133011
-116064
16947 13000 3947
Executive EngineerElectric Division-IV, khanyar
m/s k.p. iron product
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
m/s general electric industriesInstallation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
31/94
26 HP N
KVAH
Units
recorded
KWH
Units
recorded AV-PowerFactor
Max.Demand
RecordedKVA
OpeningBalance
Energy
Charges
billed
(In Rs.) Capicator
Charges
Demandcharges
billed(InRs.)
ED Billed
(In Rs.) Surchargeifany
billed(InRs.)
TotalAmount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 650.588 553 650.588 553 0.85 NA 135006.00 1307.00 0.00 700.00 287.73 1400.00 3694.73 0.00 138700.2 May-11 518.824 441 518.824 441 0.85 NA 139361.00 1042.96 0.00 700.00 229.45 1600.00 3572.41 0.00 142933.
3 Jun-11 669.412 569 669.412 569 0.85 NA 143454.00 1345.69 0.00 700.00 296.05 1800.00 4141.74 0.00 147595.
4 Jul-11 418.824 356 418.824 356.00 0.85 NA 147982.00 841.94 0.00 700.00 185.23 2000.00 3727.17 0.00 151709.
5 Aug-11 341.176 290 341.176 290 0.85 NA 151955 685.00 0.00 700.00 150.89 0.00 1535.89 0.00 153490.
6 Sep-11 332.941 283 332.941 283 0.85 NA 155794 669.29 0.00 700 147.24 0 1516.53 0.00 157310.
7 Oct-11 514.118 437 514.118 437 0.85 NA 159670.98 1187.00 0.00 800 261.21 2000 2248.00 0.00 161920.
8 Nov-11 395.294 336 395.294 336 0.85 NA 164348.33 912.91 0.00 800 200.8/4 2000.00 1913.75 0.00 166262.
9 Dec-11 204.706 174 204.706 174 0.85 NA 168756 472.76 0 800 104.01 3000 1376 0 170133
10 Jan-12 671.765 571 671.765 571 0.85 NA 172684 1551.41 0 800 341.31 2692.72 0 175377
11 Feb-12 804.706 684 804.706 684 0.85 NA 178008 1858.43 0 800 408.85 0 3067 0 18107512 Mar-12 321.176 273 321.176 273 0.85 NA 183791 741 0 800 163 0 1704 0 185496
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
7/28/2019 25kVA Endingfor the Year 2011-12I
32/94
18680/M 3/LT Name of 33/11KV Sub-Stations: Mpughal Masjid
17883 LT/KWH 3Feeder No: F-1
28 HP N
KVAH
Units
recorded
KWH
Units
recorded AV-Power
Factor
Max.Demand
Recorded
KVA
OpeningB
alance
EnergyCharges
billed
(In Rs.) Capicator
Charges
Demandcharges
billed(InRs.)
ED Billed
(In Rs.) Surcharg
eifany
billed(InRs.)
TotalAmo
unt
Billed
(InRs.)
Amountre
ceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 2460 2091 2460 2091 0.85 NA 0.00 4945.21 0.00 735.00 1087.95 0.00 6768.16 7715.00 -946.84
2 May-11 2570.59 2185 2570.59 2185 0.85 NA 0.00 5167.52 0.00 735.00 1136.86 0.00 7039.38 6768.00 271.38
3 Jun-11 2617.65 2225 2617.65 2225 0.85 NA 0.00 5262.13 0.00 735.00 1157.67 0.00 7154.80 7040.00 114.80
4 Jul-11 2251.76 1914 2251.76 1914.00 0.85 NA 0.00 4526.21 0.00 735.00 995.85 0.00 6257.06 7261 -1003.9
5 Aug-11 3060 2601 3060 2601 0.85 NA 6352 6151.00 0.00 735.00 1353.00 0.00 8239.00 0.00 14591.0
6 Sep-11 2252.94 1915 2252.94 1915 0.85 NA 218.55 4528.00 0.00 735.00 996.37 0.00 6259.37 14592 6479.0
7 Oct-11 2389.41 2031 2389.41 2031 0.85 NA 0 5518.23 0.00 840 1214.00 0.00 7572.23 6479 7572.0
8 Nov-11 1998.82 1699 1998.82 1699 0.85 NA 0 4616.00 0.00 840 1215.56 0.00 6471.00 7572 6472.0
9 Dec-11 2652.94 2255 2652.94 2255 0.85 NA 0 6126 0 840 1347.9 0 8314.74 6472 8315
10 Jan-12 3047.06 2590 3047.06 2590 0.85 NA 0 7037 0 840 1548.15 0 9425 8315 9425
11 Feb-12 3817.65 3245 3817.65 3245 0.85 NA 0 8816 0 840 11596 0 11596 9425 11596
12 Mar-12 3217.65 2735 3217.65 2735 0.85 NA 0 7431 0 840 1634 0 9905 11596 9906
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
m/s gee emm shawlsInstallation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
33/94
SD / 1 3/LT Name of 33/11KV Sub-Stations:
21203 Flat Rate Feeder No:
4115
KVA +
874.43
KW N
KVAH
Units
recorded
KWH
Units
recorded AV-PowerFactor
Max.Demand
RecordedKVA
OpeningBalance
Energy
Charges
billed
(In Rs.) Capicator
Charges
Demandcharges
billed(InRs.)
ED Billed
(In Rs.) Surchargeifany
billed(InRs.)
TotalAmount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
lance as on 11/2010 #######
1 Apr-11 607059 516000 607059 516000 0.85 NA 39799572.00 2696100.00 0.00 17500.00 ####### ######### 4391545.75 0.00 #######
2 May-11 547059 465000 547059 465000 0.85 NA 43752908.00 2429625.00 0.00 17500.00 ####### 0.00 2981642.00 0.00 #######
3 Jun-11 564706 480000 564706 480000 0.85 NA 47435568.00 2508000.00 0.00 17500.00 ####### 0.00 3077260.00 0.00 #######
4 Jul-11 705882 600000 705882 ####### 0.85 NA 41455352.00 3135000.00 0.00 17500.00 ####### 0.00 3842200.00 9670115 #######
5 Aug-11 764706 650000 764706 650000 0.85 NA 45977016.00 3396250.00 0.00 17500.00 ####### 0.00 4160925.00 0.00 #######
6 Sep-11 682353 580000 682353 580000 0.85 NA 508900008 3030500.00 0.00 17500.00 ####### 0.00 3714710.00 9848602.00 #######
7 Oct-11 623529 530000 623529 530000 0.85 NA 45427460 3267715.00 0.00 21000.00 ####### 0.00 4007612.31 0.00 #######
8 Nov-11 871765 741000 871765 741000 0.85 NA 49735076 4568635.00 0.00 21000.00 ####### 0.00 5594734.81 8892427.00 #######
9 Dec-11 725882 617000 725882 617000 0.85 NA 42377600 3804113.5 0 21000 836905 0 4662018.5 4585233 4703961
10 Jan-12 1290588 1097000 1290588 1097000 0.85 NA 41978872 6763553.5 0 21000 1487982 0 8272535.25 5766349 5025140
11 Feb-12 1211765 1030000 1211765 1030000 0.85 NA 51005180 6350465 0 21000 1397102 0 7768567.25 626374 5877374
12 Mar-12 904706 769000 904706 769000 0.85 NA 52929588 4741269 0 21000 1043079 0 5805348 2500000 5873493
1
2
3
4
Executive EngineerElectric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
director, s.k.i.m.s. souraInstallation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
34/94
SD / 2 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
16720 LT/KWH 3Feeder No: F-1
450 HP
KVAH
Units
recorded
KWH
Units
recorded AV-Power
Factor
Max.Demand
Recorded
KVA
OpeningB
alance
EnergyCharges
billed
(In Rs.) Capicator
Charges
Demandcharges
billed(InRs.)
ED Billed
(In Rs.) Surcharg
eifany
billed(InRs.)
TotalAmo
unt
Billed
(InRs.)
Amountre
ceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 0 0 0 0 0.00 NA 9406493.00 0.00 0.00 6720.00 0.00 101060.50 107780.50 0.00 9514273
2 May-11 0 0 0 0 0.00 NA 9554411.00 0.00 0.00 6720.00 0.00 101060.50 107780.50 0.00 9662191
3 Jun-11 0 0 0 0 0.00 NA 9704548.00 0.00 0.00 6720.00 0.00 101060.00 107780.00 0.00 9812328
4 Jul-11 0 0 0 0.00 0.00 NA 9856937.00 0.00 0.00 6720.00 0.00 101060.00 107780.00 0.00 9964717
5 Aug-11 0 0 0 0.00 0.00 NA 10011612.00 0.00 0.00 6720.00 0.00 101060.00 107780.00 0.00 #######
6 Sep-11 0 0 0 0 0 NA 10168607 0.00 0.00 6720 0.00 0.00 6720.00 0 #######
7 Oct-11 0 0 0 0 0 NA 10327957 0.00 0.00 8064 0.00 0.00 8064.00 0 #######
8 Nov-11 0 0 0 0 0 NA 10491061 0.00 0.00 8064 0.00 0.00 8064.00 0 #######
9 Dec-11 0 0 0 0 0 NA 10656612 0 0 8064 0 0 8064 0 #######
10 Jan-12 0 0 0 0 0 NA 10824646 0 0 8064 0 0 8064 0 1083271
11 Feb-12 0 0 0 0 0 NA 10995201 0 0 8064 0 0 8064 0 1100326
12 Mar-12 0 0 0 1 0 NA 11168314 0 0 8064 0 0 8064 0 1117637
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
manager, govt. spinning mill at nowshehraInstallation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
35/94
SD / 3 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
16719 LT/KWH 3Feeder No: F-1
33 KW
KVAH
Units
recorded
KWH
Units
recorded AV-PowerFa
ctor
Max.Demand
RecordedKV
A
OpeningBalance
Energy
Charges
billed
(In Rs.) Capicator
Charges
Demandcha
rges
billed(InR
s.)
ED Billed
(In Rs.) Surchargeifany
billed(InR
s.)
TotalAmount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 0 0 0 0 0.00 NA 2376507.00 0.00 0.00 660.00 0.00 10000.00 10660.00 0.00 2387167
2 May-11 0 0 0 0 0.00 NA 2412825.00 0.00 0.00 660.00 0.00 10000.00 10660.00 0.00 2423485
3 Jun-11 0 0 0 0 0.00 NA 2449687.00 0.00 0.00 660.00 0.00 10000.00 10660.00 0.00 2460347
4 Jul-11 0 0 0 0.00 0.00 NA 2487102.00 0.00 0.00 660.00 0.00 10000.00 10660.00 0 2497762
5 Aug-11 0 0 0 0 0.00 NA 2525079 0.00 0.00 660.00 0.00 10000.00 10660.00 0.00 25357396 Sep-11 0 0 0 0 0.00 NA 2563625 0.00 0.00 660 0.00 10000.00 660.00 0 2564285
7 Oct-11 0 0 0 0 0.00 NA 2602749.25 0.00 0.00 792 0.00 10000.00 792.00 0 2603541
8 Nov-11 0 0 0 0 0.00 NA 2642594.25 0.00 0.00 792 0.00 10000.00 792.00 0 2643386
9 Dec-11 0 0 0 0 0 NA 2683037 0 0 792 0 10000 792 0 268382
10 Jan-12 0 0 0 0 0 NA 2724086.5 0 0 792 0 0 792 0 272487
11 Feb-12 0 0 0 0 0 NA 2765751 0 0 792 0 0 792 0 276654
12 Mar-12 1 0 1 0 0 NA 2808042 0 0 792 0 0 792 0 280883
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
manager, govt. spinning mill for lighting
Installation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
36/94
13244 3/LT Name of 33/11KV Sub-Stations: Kathidarwaza
13733 Flat Rate Feeder No: F-3
400 HP
KVAHUnits
recorded
KWHUnits
recorded AV-PowerFactor
Max.D
emand
RecordedKVA
Openin
gBalance
Energy
Chargesbilled
(In Rs.) Capica
tor
Charges
Dema
ndcharges
bille
d(InRs.)
ED Billed
(In Rs.) Surch
argeifany
bille
d(InRs.)
TotalA
mount
Billed
(InRs.)
Amoun
treceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 9411.76 8000 9411.76 8000 0.85 NA 1800438.00 25520.00 0.00 59040.00 5614.00 50000.00 140174.00 0.00 1940612
2 May-11 80000 68000 80000 68000 0.85 NA 1918971.00 216920.00 0.00 59040.00 47722.40 50000.00 373682.40 0.00 2292653
3 Jun-11 51764.7 44000 51764.7 44000 0.85 NA 2246032.00 140360.00 0.00 59040.00 30879.00 50000.00 280279.00 0.00 2526311
4 Jul-11 47058.8 40000 47058.8 40000.00 0.85 NA 2513456.00 127600.00 0.00 44233.00 28072.00 50000.00 199905.00 0 2713361
5 Aug-11 4705.88 4000 4705.88 4000 0.85 NA 2674062 12760.00 0.00 59040.00 2807.20 50000.00 74607.20 0.00 #######
6 Sep-11 42941.2 36500 42941.2 36500 0.85 NA 2999480 116435.00 0.00 59040 25615.70 50000 691421.00 0 3200571
7 Oct-11 42941.2 36500 42941.2 36500 0.85 NA 2557158 145744.50 0.00 73800 32063.00 50000 251608.00 274512 28087668 Nov-11 42941.2 36500 42941.2 36500 0.85 NA 2650992.75 145744.50 0.00 73800 32063.79 50000 251608.00 0 2902601
9 Dec-11 42352.9 36000 42352.9 36000 0.85 NA 2789611 143748 0 55291.8 31624.6 50000 230664 156529 302027
10 Jan-12 42741.2 36330 42741.2 36330 0.85 NA 3065579.5 145065 0 73800 31914.5 50000 250780 0 331636
11 Feb-12 42682.4 36280 42682.4 36280 0.85 NA 3366105 144866 0 73800 31870 50000 250536 0 361664
12 Mar-12 458.824 390 458.824 390 0.85 NA 3670891 1557 0 73800 342 50000 75699 952482 374659
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
Installation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
Xen, phe water plant, bahrar
7/28/2019 25kVA Endingfor the Year 2011-12I
37/94
SD / 51 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
16723 HT/TVM 3 Feeder No: F-1
202 HP
KVAH
Units
recorded
KWH
Units
recorded AV-PowerFa
ctor
Max.Demand
RecordedKV
A
OpeningBalance
Energy
Charges
billed
(In Rs.) Capicator
Charges
Demandcharges
billed(InR
s.)
ED Billed
(In Rs.) Surchargeifany
billed(InR
s.)
TotalAmoun
t
Billed
(InRs.)
Amountrece
ived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 0 0 0 0 0.00 NA 34799946.00 0.00 19950.00 0.00 48000.00 67950.00 0.00 #######
2 May-11 0 0 0 0 0.00 NA 3552394.00 0.00 19950.00 0.00 49000.00 68950.00 0.00 3621344
3 Jun-11 0 0 0 0 0.00 NA 3625930.00 0.00 19950.00 0.00 50000.00 69950.00 0.00 3695880
4 Jul-11 0 0 0 0.00 0.00 NA 3600568.00 0.00 19950.00 0.00 0.00 19950.00 100000 3520518
5 Aug-11 0 0 0 0 0 NA 3674826 0.00 19950.00 0.00 55000.00 74950.00 0.00 37497766 Sep-11 0 0 0 0 0 NA 370197 0.00 19950 0.00 55000.00 19950.00 0 3710148
7 Oct-11 0 0 0 0 0 NA 3826700 0.00 22990 0.00 55000.00 22990.00 0 3849690
8 Nov-11 0 0 0 0 0 NA 3907435.25 0.00 22990 0.00 55000.00 22990.00 0 3930425
9 Dec-11 0 0 0 0 0 NA 3989381.75 0 22990 0 55000 22990 0 401237
10 Jan-12 0 0 0 0 0 NA 4072557.25 0 22990 0 0 22990 0 409554
11 Feb-12 0 0 0 0 0 NA 4156980 0 22990 0 0 22990 100000 417997
12 Mar-12 0 0 0 0 0 NA 414170 0 22990 0 0 22990 20000 416416
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
project coordinator, undp nallabal
Installation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
38/94
4196 3/LT Name of 33/11KV Sub-Stations: Bagwan Pora
13734 Flat Rate Feeder No: F-2
110 KW
KVAHUnits
recorded
KWHUnits
recorded AV-PowerFactor
Max.D
emand
RecordedKVA
OpeningBalance
Energy
Chargesbilled
(In Rs.) Capica
tor
Charges
Dema
ndcharges
bille
d(InRs.)
ED Billed
(In Rs.) Surch
argeifany
bille
d(InRs.)
TotalA
mount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 0 0 0 0 0.00 NA 5622348.00 130416.00 0.00 0.00 28691.52 800000.00 959107.52 0.00 6581455
2 May-11 0 0 0 0 0.00 NA 5868178.00 130416.00 0.00 0.00 28691.52 81000.00 240107.52 0.00 6108285
3 Jun-11 0 0 0 0 0.00 NA 6117695.00 130416.00 0.00 0.00 28691.52 82000.00 241107.52 0.00 6358802
4 Jul-11 0 0 0 0.00 0.00 NA 6370954.00 130416.00 0.00 0.00 28691.52 82000.00 241107.52 0 6612061
5 Aug-11 0 0 0 0 0 NA 6628031 130416.00 0.00 0.00 28691.52 82000.00 241107.52 500000.00 6869138
6 Sep-11 0 0 0 0 0 NA 6381427.5 130416.00 0.00 0 28691.52 82000 159107.52 0 6540535
7 Oct-11 0 0 0 0 0 NA 6638643 163020.00 0.00 0 35864.00 82000 198884.41 0 68375278 Nov-11 0 0 0 0 0 NA 6940090.5 163020.00 0.00 0 35864.00 82000 198884.41 0 7138975
9 Dec-11 0 0 0 0 0 NA 7246059.5 163020 0 0 35864 82000 198884.41 0 744494
10 Jan-12 0 0 0 0 0 NA 7556618 163020 0 0 35864 82000 198884.41 0 775550
11 Feb-12 0 0 0 0 0 NA 7871835 163020 0 0 35864 82000 198884.41 0 807072
12 Mar-12 0 0 0 0 0 NA 8191780 163020 0 0 35864 82000 198884 50000 839066
1
2
3
4
Executive Engineer
Electric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
ch. Medical officer, lepper hospital
Installation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
39/94
5072 600/5 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
21657 HT/TVM-3 Feeder No: F-6
100 KW N
KVAH
Units
recorded
KWH
Units
recorded AV-Po
werFactor
Max.D
emand
RecordedKVA
OpeningBalance
Energy
Charges
billed
(In Rs.) Capica
tor
Charges
Dema
ndcharges
bille
d(InRs.)
ED Billed
(In Rs.) Surchargeifany
billed(InRs.)
TotalA
mount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 29800 25330 29800 25330 0.85 NA 0.00 89161.60 0.00 7000.00 19615.00 0.00 115776.60 134415.00 -18638.4
2 May-11 32941.2 28000 32941.2 28000 0.85 NA 0.00 98560.00 0.00 7000.00 21683.00 0.00 127243.00 117514.00 9729.0
3 Jun-11 34117.6 29000 34117.6 29000 0.85 NA 0.00 102080.00 0.00 7000.00 22457.60 0.00 131537.60 127243.00 4294.6
4 Jul-11 35294.1 30000 35294.1 30000.00 0.85 NA 0.00 102080.00 0.00 7000.00 23232.00 0.00 132312.00 131538.00 774.00
5 Aug-11 31764.7 27000 31764.7 27000.00 0.85 NA 0.00 95040.00 0.00 7000.00 20908.00 0.00 122948.00 135832.00 -12884.0
6 Sep-11 31764.7 27000 31764.7 27000.00 0.85 NA 0 95040.00 0.00 7000 20908 0 122948.00 122949 122949.
7 Oct-11 28235.3 24000 28235.3 24000.00 0.85 NA 0 101376.00 0.00 8400 22302.7 0 132078.72 122949 132079.8 Nov-11 27058.8 23000 27058.8 23000.00 0.85 NA 132079 97152.00 0.00 8400 21373.4 0 126925.44 0 259004.
9 Dec-11 29411.8 25000 29411.8 25000 0.85 NA 0 105600 0 8400 23232 0 137232 259004 137232
10 Jan-12 28235.3 24000 28235.3 24000 85 NA 0 101376 0 8400 22302.7 0 132078.72 137232 132079
11 Feb-12 25882.4 22000 25882.4 22000 0.85 NA 0 92928 0 8400 20444 0 121772 132079 12772
12 Mar-12 23529.4 20000 23529.4 20000 0.85 NA 0 84480 0 8400 18585 0 111465 121772 11465
0
1
23
4
Executive Engineer
Electric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWHKVAH and demand readings will be required for load more than 100KW only.
Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
divisional engineer, ocb exchange devi angan
Installation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
40/94
SD / 102 200/5 3/LT Name of 33/11KV Sub-Stations:
21658 LT/KWH 3Feeder No:
45 KW N
KVAH
Units
recorded
KWH
Units
recorded AV-Po
werFactor
Max.D
emand
RecordedKVA
OpeningBalance
Energy
Charges
billed
(In Rs.) Capicator
Charges
Dema
ndcharges
bille
d(InRs.)
ED Billed
(In Rs.) Surchargeifany
billed(InRs.)
TotalA
mount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 4810.35 4088.8 4810.35 4089 0.85 NA 20614.47 14392.00 0.00 3150.00 3166.37 0.00 20708.37 20614.00 20708.8
2 May-11 4421.18 3758 4421.18 3758 0.85 NA 20708.84 13229.00 0.00 3150.00 2910.00 0.00 19289.00 21020.00 18977.8
3 Jun-11 4671.76 3971 4671.76 3971 0.85 NA 18977.84 13978.62 0.00 3150.00 3075.00 0.00 20203.62 19290.00 19891.4
4 Jul-11 3670.59 3120 3670.59 3120.00 0.85 NA 19891.46 10982.00 0.00 3150.00 2416.13 0.00 16548.13 20204 16235.5
5 Aug-11 2352.94 2000 2352.94 2000 0.85 NA 0 7040.00 0.00 3150.00 1548.00 3000.00 14738.00 16549.00 -1811.0
6 Sep-11 20792.9 17674 20792.9 17674 0.85 NA 0 62215.30 0.00 3150.00 13687.37 0.00 79052.67 11738.00 79053.0
7 Oct-11 8941.18 7600 8941.18 7600 0.85 NA 0 32102 0 3780 7062 0 42944 79053 42945.08 Nov-11 0 0 0 0 0.85 NA 643.76 0 0 3780 0 0 3780 42945.00 4424.0
9 Dec-11 5176.47 4400 5176.47 4400 0.85 NA 0 18585.6 0 3780 4088 0 26454.43 3780 26454
10 Jan-12 0 0 0 0 0.85 NA 0 0 0 3780 0 0 3780 26454 3781
11 Feb-12 800 680 800 680 0.85 NA 3781 2872 0 3780 631 0 7284 0 11065
12 Mar-12 1991.76 1693 1991.76 1693 0.85 NA 123 7152 0 3780 1573 0 12505 11064 12507
1
2
34
Executive Engineer
Electric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
rsu exchange soura, sde(frs) hariparbat at skims
Installation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
41/94
director crafts development institute dch, at b.a.m. khan.
29647 200/5 3/LT Name of 33/11KV Sub-Stations: Bagwan Pora
16721 LT/KWH 3Feeder No: F-1
22 KW N
KVAH
Units
recorded
KWH
Units
recorded AV-Po
werFactor
Max.D
emand
RecordedKVA
OpeningBalance
Energy
Charges
billed
(In Rs.) Capicator
Charges
Dema
ndcharges
bille
d(InRs.)
ED Billed
(In Rs.) Surchargeifany
billed(InRs.)
TotalA
mount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Mar-11 3341.18 2840 3341.18 2840 0.85 NA 16119.49 15229.50 680.00 3350.49 0.00 19259.99 16119.00 19260.4
2 Apr-11 4847.06 4120 4847.06 4120 0.85 NA 0.00 22093.00 680.00 4860.57 0.00 27633.57 19549.00 8084.5
3 May-11 1929.41 1640 1929.41 1640 0.85 NA 0.00 8794.50 680.00 1934.79 0.00 11409.29 28049.00 -16639.7
4 Jun-11 2729.41 2320 2729.41 2320 0.85 NA 0.00 12441.00 680.00 2737.00 0.00 15858.00 11409.00 4449.0
5 Jul-11 2305.88 1960 2305.88 1960.00 0.85 NA 0.00 10510.00 680.00 2312.31 0.00 13502.31 15858 -2355.6
6 Aug-11 2305.88 1960 2305.88 1960 0.85 NA 0 10510.00 680.00 2312.31 0.00 13502.31 13503.00 -0.69
7 Sep-11 1788.24 1520 1788.24 1520 0.85 NA 0 8151 680 1793.22 0 10624.22 13503.00 10624.08 Oct-11 2494.12 2120 2494.12 2120 0.85 NA 0 13414.83 816 2951.26 0 17182.09 10624.00 17182.0
9 Nov-11 3388.24 2880 3388.24 2880 0.85 NA 0 18223 816 4009.26 0 23048.26 17182.00 2304.0
10 Dec-11 2729.41 2320 2729.41 2320 0.85 NA 0 14680 816 3229.68 0 18726 23049 18726
11 Jan-12 4235.29 3600 4235.29 3600 0.85 NA 0 22779.9 816 5011..58 0 28607.48 18726 28608
12 Feb-12 5364.71 4560 5364.71 4560 0.85 NA 0 28854 816 6348 0 36018 28608 36018
13 Mar-12 4847.06 4120 4847.06 4120 0.85 NA 0 26070 816 5735 0 32621 36018 32622
1
2
34
Executive Engineer
Electric Division-IV, khanyar
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.Please attach circle-wise and Divisional wise Abstracts with each energy account.
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Sanctioned Load: Capacitor Installed: Y Rating of Capacitor:
SUB-DIVISION: Hawal
Installation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
42/94
director indian institute of crafts technology at b.a.m. khan.
29646 200/5 3/LT Name of 33/11KV Sub-Stations: B.A.M.Khan
16722 LT/KWH 3Feeder No: F-1
25 KW N
KVAH
Units
recorded
KWH
Units
recorded AV-Po
werFactor
Max.D
emand
RecordedKVA
OpeningBalance
Energy
Charges
billed
(In Rs.) Capicator
Charg
es
Dema
ndcharges
bille
d(InRs.)
ED Billed
(In Rs.) Surchargeifany
billed(InRs.)
TotalAmount
Billed
(InRs.)
Amountreceived
(InRs.)
Arrears
(A) (B) (C=B/A) (D) (E) (F) (G) (H) (E+F+G+H=I) (J) (K=I-J
1 Apr-11 3274.12 2783 3274.12 2783 0.85 NA 11086.00 14923.84 500.00 3283.24 500.00 19207.08 0.00 30293.0
2 May-11 1871.76 1591 1871.76 1591 0.85 NA 0.00 8531.00 500.00 1876.86 500.00 11407.86 29793.00 -18385.1
3 Jun-11 1871.76 1591 1871.76 1591 0.85 NA 0.00 8531.00 500.00 1876.98 500.00 11407.98 10909.00 498.98
4 Jul-11 2138.82 1818 2138.82 1818.00 0.85 NA 0.00 9749.03 500.00 2144.79 500.00 12893.82 14147 -1253.1
5 Aug-11 2375.29 2019 2375.29 2019 0.85 NA 0 10826.00 500.00 2381.00 500.00 14207.00 12394.00 1813.0
6 Sep-11 15507.1 13181 15507.1 13181 0.85 NA 0 7405.61 500 1629 9534.61 13709.00 9535.0
7 Oct-11 2081.18 1769 2081.18 1769 0.85 NA 0 11193 600 2462 14255.00 9535.00 9535.08 Nov-11 2520 2142 2520 2142 0.85 NA 0 13554 600 2981.89 17135.89 14256.00 17136.0
9 Dec-11 1631.76 1387 1631.76 1387 0.85 NA 0 8776.59 600 1930.85 11307.44 17136 11308
10 Jan-12 2827.06 2403 2827.06 2403 0.85 NA 169.25 15205 600 3345.23 19150.23 11308 19320
11 Feb-12 3301.18 2806 3301.18 2806 0.85 NA 0 17755 600 3906 22261 19320 22262
12 Mar-12 2100 1785 2100 1785 0.85 NA 20404 11295 600 2484 14379 22262 34784
1
2
34
Executive Engineer
Electric Division-IV, khanyar
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
KVAH and demand readings will be required for load more than 100KW only.
SUB-DIVISION: Hawal
S.No Month
KVAH
Units
supplied
KWH
Units
supplied
Sanctioned Load:
Please attach circle-wise and Divisional wise Abstracts with each energy account.
Capacitor Installed: Y Rating of Capacitor:
Installation No: CT Ratio: Supply Type:
Computer Code: Meter Rated Current: Meter Type:
7/28/2019 25kVA Endingfor the Year 2011-12I
43/94
7/28/2019 25kVA Endingfor the Year 2011-12I
44/94
7/28/2019 25kVA Endingfor the Year 2011-12I
45/94
7/28/2019 25kVA Endingfor the Year 2011-12I
46/94
7/28/2019 25kVA Endingfor the Year 2011-12I
47/94
7/28/2019 25kVA Endingfor the Year 2011-12I
48/94
7/28/2019 25kVA Endingfor the Year 2011-12I
49/94
7/28/2019 25kVA Endingfor the Year 2011-12I
50/94
7/28/2019 25kVA Endingfor the Year 2011-12I
51/94
7/28/2019 25kVA Endingfor the Year 2011-12I
52/94
7/28/2019 25kVA Endingfor the Year 2011-12I
53/94
7/28/2019 25kVA Endingfor the Year 2011-12I
54/94
7/28/2019 25kVA Endingfor the Year 2011-12I
55/94
7/28/2019 25kVA Endingfor the Year 2011-12I
56/94
7/28/2019 25kVA Endingfor the Year 2011-12I
57/94
7/28/2019 25kVA Endingfor the Year 2011-12I
58/94
7/28/2019 25kVA Endingfor the Year 2011-12I
59/94
7/28/2019 25kVA Endingfor the Year 2011-12I
60/94
7/28/2019 25kVA Endingfor the Year 2011-12I
61/94
7/28/2019 25kVA Endingfor the Year 2011-12I
62/94
7/28/2019 25kVA Endingfor the Year 2011-12I
63/94
7/28/2019 25kVA Endingfor the Year 2011-12I
64/94
7/28/2019 25kVA Endingfor the Year 2011-12I
65/94
DiVision:
ENERGY ACCOUNT OF 25 KVA AND ABOVE INSTALLATIONS UNDER TRIPARITE MoU DURING THE YEAR 2011-12Circle: EM & RE Circle-Ist Srinagar Sub-Division:- K
7/28/2019 25kVA Endingfor the Year 2011-12I
66/94
DiVision:
N.A LT3Ph
12735 N.A N.A Name of 33/11KV Sub-Stati
Computer Code: 6264 N Rating of Capacitor: N.A Feeder No: F-3
Sanctioned Load: 23 KW
S.N
o
Month
KVA
HUnits
s
upplied
KW
HUnits
s
upplied
KVA
HUnits
co
mputedKWH Units
computed
AV-PowerFactor
Max.Demand
RecordedKVA
Opening
Balance
Energy
ChargesDemand
charges
billed (In
Rs. )
ED
Billed
(In Rs.)
Capacitor
Surcharge
Billed(In
Rs.)
Surcharge
for
metering
on LTside
Latepay
ment
surcharge
billed Total Amount
Billed
(In Rs.)
TotalAmo
untdue
(inRs.)
A B C D E=D/C F G H I J K L M N=H+I+J+L+M O=G+N
1 Apr-11 NA NA NA 4233.12883 0.85 NA 3693250.0 27060.00 0.00 5953.20 2460.00 0.00 0.00 35473.20 3728723.2
2 May-11 NA NA NA 4233.12883 0.85 NA 3726263.0 27060.00 0.00 5953.20 2460.00 0.00 0.00 35473.20 3761736.2
3 Jun-11 NA NA NA 4233.12883 0.85 NA 3759276.0 27060.00 0.00 5953.20 2460.00 0.00 0.00 35473.20 3794749.2
4 Jul-11 NA NA NA 4233.12883 0.85 NA 3792289.0 27060.00 0.00 5953.20 2460.00 0.00 0.00 35473.20 3827762.2
5 Aug-11 NA NA NA 4233.12883 0.85 NA 3882682.0 27060.00 0.00 5953.20 2460.00 0.00 0.00 35473.20 3918155.2
6 Sep-11 NA NA NA 4233.12883 0.85 NA 3974431.0 27060.00 0.00 5953.20 2460.00 0.00 0.00 35473.20 4009904.2
7 Oct-11 NA NA NA 4233.12883 0.85 NA 4067556.0 33825.00 0.00 7441.50 3075.00 0.00 0.00 41266.50 4108822.5
8 Nov-11 NA NA NA 4233.12883 0.85 NA 4140455.0 33825.00 0.00 7441.50 7441.50 0.00 0.00 41266.50 4181721.5
9 Dec-11 NA NA NA 4233.12883 0.85 NA 4244447.5 33825.00 0.00 7441.50 7441.50 0.00 0.00 41266.50 4285714.0
10 Jan-12 NA NA NA 4233.12883 0.85 NA 4349999.5 33825.00 0.00 7441.50 3075.00 0.00 0.00 41266.50 4391266.0
11 Feb-12 NA NA NA 4233.12883 0.85 NA 4457135.0 33825.00 0.00 7441.50 3075.00 0.00 0.00 41266.50 4498401.5
12 Mar-12 NA NA NA 4233.12883 0.85 NA 4498401.0 33825.00 0.00 7441.50 3075.00 0.00 0.00 41266.50 4539667.5
1
2 1
3 2
4 3
Circle: EM & RE Circle-Ist, Srinagar Sub-Division:- K
Type: Metered / Flat Rate: Flat Rate
Installation No: Meter Rated Curr Meter Type: Khanyar
Name of Installatio Ex. Engineer City Roads
Category: State CT Ratio: Supply Type:
Surcharge shall include following:
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWHCapacitor surcharge @ 10% for not installing capacitors on all loads more than 5 K
except for domestic, street lighting and loads where KVAH billing done.
Surcharge on HT consumers for having metering on LT.
Capacitor Installe
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
KVAH and demand readings will be required for load more than 100KW only. Late payment surcharge of 1.5 % per month on energy, demand charges and / or
In case trivector meter is not installed for load more than 100KW, please workout the KVAH
units by dividing recorded KWH units with power factor = 0.85
DiVision: Sub-Division:-
ENERGY ACCOUNT OF 25 KVA AND ABOVE INSTALLATIONS UNDER TRIPARITE MoU DURING THE YEAR 2011-12KCircle: EM & RE Circle-Ist Srinagar
7/28/2019 25kVA Endingfor the Year 2011-12I
67/94
DiVision:
N.A LT3Ph
10805 N.A N.A Name of 33/11KV Sub-Stati
Computer Code: 6269 N N.A Feeder No: F-2
Sanctioned Load: 30 KW
S.N
o
Month
KVA
HUnits
s
upplied
KW
HUnits
s
upplied
KVA
HUnits
co
mputedKWH Units
computed
AV-
Power
Factor
Max.Demand
RecordedKVA
Opening
Balance
Energy
ChargesDemand
charges
billed (In
Rs. )
ED
Billed
(In Rs.)
Capacitor
Surcharge
Billed (In
Rs.)
Surchargefor
meteringonLTside
Latepay
ment
surchargebilled Total Amount
Billed
(In Rs.)
TotalAmo
untdue
(inRs.)
A B C D E=D/C F G H I J K L M N=H+I+J+L+M O=G+N
1 Apr-11 NA NA NA 4192.22914 N.A N.A 444080.0 33000.00 0.00 7260.00 3000.00 0.00 0.00 43260.00 487340.0
2 May-11 NA NA NA 4192.22914 N.A N.A 491607.0 33000.00 0.00 7260.00 3000.00 0.00 0.00 43260.00 534867.0
3 Jun-11 NA NA NA 4192.22914 N.A N.A 539843.0 33000.00 0.00 7260.00 3000.00 0.00 0.00 43260.00 583103.0
4 Jul-11 NA NA NA 4192.22914 N.A N.A 588805.0 33000.00 0.00 7260.00 3000.00 0.00 0.00 43260.00 632065.0
5 Aug-11 NA NA NA 4192.22914 N.A N.A 638501.0 33000.00 0.00 7260.00 3000.00 0.00 0.00 43260.00 681761.0
6 Sep-11 NA NA NA 4192.22914 N.A N.A 688942.0 33000.00 0.00 7260.00 3000.00 0.00 0.00 43260.00 732202.0
7 Oct-11 NA NA NA 4192.22914 N.A N.A 740140.0 41250.00 0.00 9075.00 3750.00 0.00 0.00 54075.00 794215.0
8 Nov-11 NA NA NA 4192.22914 N.A N.A 798573.0 41250.00 0.00 9075.00 3750.00 0.00 0.00 54075.00 852648.0
9 Dec-11 NA NA NA 4192.22914 N.A N.A 861688.0 41250.00 0.00 9075.00 3750.00 0.00 0.00 54075.00 915763.0
10 Jan-12 NA NA NA 4192.22914 N.A N.A 929498.0 41250.00 0.00 9075.00 3750.00 0.00 0.00 54075.00 983573.0
11 Feb-12 NA NA NA 4192.22914 N.A N.A 994521.0 41250.00 0.00 9075.00 3750.00 0.00 0.00 54075.00 1048596.0
12 Mar-12 NA NA NA 4192.22914 N.A N.A 1095171.0 41250.00 0.00 9075.00 3750.00 0.00 0.00 54075.00 1149246.0
1
2 1
32
4 3
5
Sub Division:
Type: Metered / Flat Rate:
Name of Installatio Maqdoom Sahib Shrine water pump
K
Category: state CT Ratio: Supply Type:
Circle: EM & RE Circle Ist, Srinagar
Surcharge on HT consumers for having metering on LT.
Capacitor Installe Rating of Capacit
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Flat Rate
Installation No: Meter Rated Curr Meter Type: Kathidarwaza
Surcharge shall include following:
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWHapac or surc arge or no ns a ng capac ors on a oa s more an
except for domestic, street lighting and loads where KVAH billing done.
Pl tt h i l i d Di i i l i Ab t t ith h t
KVAH and demand readings will be required for load more than 100 KW only. Late payment surcharge of 1.5 % per month on energy, demand charges and / or m
In case trivector meter is not installed for load more than 100KW, please workout the KVAH
units by dividing recorded KWH units with power factor = 0.85
DiVision: Sub-Division:-
ENERGY ACCOUNT OF 25 KVA AND ABOVE INSTALLATIONS UNDER TRIPARITE MoU DURING THE YEAR 2011-12KCircle: EM & RE Circle-Ist, Srinagar
7/28/2019 25kVA Endingfor the Year 2011-12I
68/94
N.A LT3Ph
8597 N.A N.A Name of 33/11KV Sub-Stati
Computer Code: 6440 N N.A Feeder No: F-2
Sanctioned Load: 20 KW
S.N
o
Month
KVA
HUnits
s
upplied
KW
HUnits
s
upplied
KVA
HUnits
co
mputedKWH Units
computed
AV-
Power
Factor
Max.De
mand
Recorde
dKVA
Opening
Balance
Energy
ChargesDemand
charges
billed (In
Rs. )
ED
Billed
(In Rs.)
Capacitor
Surcharge
Billed(In
Rs.)
Surcharge
for
metering
on LTside
Latepayment
surchargebilled
Total Amount
Billed
(In Rs.)
TotalAmo
untdue
(inR
s.)
A B C D E=D/C F G H I J K L M N=H+I+J+L+M O=G+N
1 Apr-11 NA NA NA 7265.51724 0.85 N.A 15652.00 12640.00 0.00 2781.00 0.00 0.00 0.00 15421.00 31073.0
2 May-11 NA NA NA 7265.51724 0.85 N.A 31539.10 12640.00 0.00 2781.00 0.00 0.00 0.00 15421.00 46960.1
3 Jun-11 NA NA NA 7265.51724 0.85 N.A 47664.50 12640.00 0.00 2781.00 0.00 0.00 0.00 15421.00 63085.5
4 Jul-11 NA NA NA 7265.51724 0.85 N.A 64031.78 12640.00 0.00 2781.00 0.00 0.00 0.00 15421.00 79452.8
5 Aug-11 NA NA NA 7265.51724 0.85 N.A 80644.57 12640.00 0.00 2781.00 0.00 0.00 0.00 15421.00 96065.6
6 Sep-11 NA NA NA 7265.51724 0.85 N.A 97506.55 12640.00 0.00 2781.00 0.00 0.00 0.00 15421.00 112927.6
7 Oct-11 NA NA NA 7265.51724 0.85 N.A 114619.98 14901.00 0.00 3278.22 0.00 0.00 0.00 18179.22 132799.2
8 Nov-11 NA NA NA 7265.51724 0.85 N.A 134791.78 14901.00 0.00 3278.22 0.00 0.00 0.00 18179.22 152971.0
9 Dec-11 NA NA NA 7265.51724 0.85 N.A 152971.00 14901.00 0.00 3278.22 0.00 0.00 0.00 18179.22 20474.0
10 Jan-12 NA NA NA 7265.51724 0.85 N.A 20780.00 14901.00 0.00 3278.22 0.00 0.00 0.00 18179.22 38959.2
11 Feb-12 NA NA NA 7265.51724 0.85 N.A 39544.00 14901.00 0.00 3278.22 0.00 0.00 0.00 18179.22 57723.2
12 Mar-12 NA NA NA 7265.51724 0.85 N.A 75902.00 14901.00 0.00 3278.22 0.00 0.00 0.00 18179.22 94081.2
1
2 1
3 2
4 3
5
, g
Supply Type: Type: Metered / Flat Rate: Flat Rate
Installation No: Meter Rated Curr Meter Type: Kathidarwaza
Capacitor Installe Rating of Capacit
Note:
Type of supply may be 33KV/11KV/3-ph. LT/1-ph. LT
Surcharge on HT consumers for having metering on LT.
Name of Installatio Maqdoom Sahib Shrine
Category: domestic CT Ratio:
Surcharge shall include following:
Type of metering may be HT Trivector/HT KWH/LT Trivector/LT KWH
except for domestic, street lighting and loads where KVAH billing done.
Please attach circle-wise and Divisional wise Abstracts with each energy account
KVAH and demand readings will be required for load more than 100KW only. Late payment surcharge of 1.5 % per month on energy, demand charges and / or m
In case trivector meter is not installed for load more than 100KW, please workout the KVAH
units by dividing recorded KWH units with power factor = 0.85