24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES Presented By: James Bryan, P.E. Trag Bailey
25

24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Sep 09, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

24” FORCE MAIN BYHDD FOR DALLASWATER UTILITIES

Presented By:James Bryan, P.E.Trag Bailey

Page 2: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Agenda

•Project Overview•Why HDD?•Traffic Control•Construction Footprint•HDD Layout•Construction Photos•Summary

Page 3: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Project Overview

•Location•Scope

• 9 MGD Lift Station• 15,000 LF 24” HDPE

Force Main• 5,000 LF by HDD

•Total Project Cost• $5.5 Million

Page 4: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Project Overview

Page 5: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Why HDD?

•Belt Line Road Corridor•Adjacent Development•Railroad•Traffic•School•Existing Utilities•Visibility

Page 6: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Traffic Control

•Belt Line Road Section• 4-lane Divided• 6-lane Divided

•Maintain minimum two lanes each direction•Rolling lane closures•Phased traffic control plans•Strung pipe out in sections to keep mediansopen

•CTB protection for drill rig overnight; cones forremaining traffic control

Page 7: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Construction Footprint

•Water Tanker Truck•Mud Recycling Trailer•Job/Tool Trailer•Drilling Rig•Excavator•Flatbed Truck•Work Trucks

Page 8: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Project Overview

BELT LINE ROADDART RAILROAD FA

IRW

AYD

R.

TRA CONNECTION

HDD #1

HDD #2

HDD #3

HDD #4

NORTH

BARBARA BUSHMIDDLE SCHOOL

Page 9: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Project Overview

BELT LINE ROAD

DART RAILROAD

HDD #1

HDD #2

ENTRYEXIT

1140 FEET

NORTH

Page 10: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Project Overview

NORTH

BELT LINE ROAD

DART RAILROAD

HDD #2

HDD #3

ENTRY EXIT

890 FEET

HDD #1

Page 11: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Project Overview

NORTH

BELT LINE ROAD

DART RAILROAD

HDD #3ENTRY EXIT

1150 FEET

HDD #2 HDD #4

Page 12: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Project Overview

NORTH

BELT LINE ROAD

DART RAILROAD

HDD #4

ENTRY

EXIT

1060 FEET

FAIR

WAY

DRI

VE

HDD #3

Page 13: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Project Overview

Page 14: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Construction Footprint

•Water Tanker Truck•Mud Recycling Trailer•Job/Tool Trailer•Drilling Rig•Excavator•Flatbed Truck

Page 15: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Photos

Page 16: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Photos

Page 17: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Photos

Page 18: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Photos

Page 19: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Photos

Page 20: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Photos

Page 21: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Photos

Page 22: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Photos

Page 23: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Photos

Page 24: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Summary

•Schedule• 1 month per drill• 4 months total in Belt Line Road corridor

•Coordination success•Minimal disruption and no complaints!•Lessons Learned

• Depth variation/ideal radius• Utility clearance• Drill rig anchoring

Page 25: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE

Thank You! Any Questions?

James Bryan, P.E.Kimley-Horn and Associates, [email protected](972) 776-1752

Trag BaileyChisholm [email protected](214) 244-2722