Top Banner
WIPP Future Advancements and Operational Safety Rodney L. Whisenhunt, NWP Senior Project Manager, Capital Asset Projects
24

22 WIPP Future Advancements and Operational Safety

Jan 22, 2018

Download

Technology

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 22 WIPP Future Advancements and Operational Safety

WIPP Future Advancements and Operational Safety

Rodney L. Whisenhunt, NWPSenior Project Manager, Capital Asset Projects

Page 2: 22 WIPP Future Advancements and Operational Safety

Historic Ventilation Modes at WIPP●Normal Mode - 2 main 700 fans in unfiltered operation – up

to 480,000 cfm●Alternate Mode - 1 main 700 fan in unfiltered operation –

280,000 cfm●Filtration Mode - 1 860 fan in filtered operation – 60,000 cfm●Operating one or two 860 fans in unfiltered (by-pass) mode

(reduced and minimum flow)●Operating a main 700 fan in parallel with a unfiltered (by-

pass) 860 fan (maintenance)

Note: Airflows shown are nominal and at surface fan location

Page 3: 22 WIPP Future Advancements and Operational Safety

Ventilation Upgrades Post Radiologic Event

Page 4: 22 WIPP Future Advancements and Operational Safety

Current Filtered Ventilation System – Adding the Interim Ventilation System (IVS) fans

●IVS added two additional filter units●Two 960 fans with each fan having a 27,000 cfm

capacity●Flow increased to 114,000 cfm●Limited ability to provide ventilation to the

construction and north circuits●Does allow for limited emplacement operations

Page 5: 22 WIPP Future Advancements and Operational Safety

SVS Surface Fan Configuration

Page 6: 22 WIPP Future Advancements and Operational Safety

Filtered Ventilation System with Supplemental Ventilation System (SVS)

Fan in Operation●Exhaust flow is with UVS/IVS at 114,000 cfm at surface●SVS fan will pull air from the AIS and course the air to the

North and Construction Circuits●The Salt Handling Shaft will be on exhaust●Air to the disposal circuit is fixed at the UVS/IVS fan flow.

Air to the disposal circuit will be from the construction circuit

Page 7: 22 WIPP Future Advancements and Operational Safety

Long Term Ventilation Upgrades at WIPP

Page 8: 22 WIPP Future Advancements and Operational Safety

Long Range WIPP Planning

●WIPP was originally designed for 8 Panels with options for Panels 9 and 10.

●For planning purposes, NWP was directed by CBFO to extend the mission need to the year 2050.

●Other project direction was:●All exhaust air will be filtered from the disposal and

waste shaft station (NO unfiltered exhaust).●All underground activities, maintenance, waste

handling, mining, etc. will be performed in parallel.

Page 9: 22 WIPP Future Advancements and Operational Safety

Long Range Ventilation Goals at WIPP

●The use of the UVS/IVS/SVS systems will NOT be capable of meeting these long term goals at WIPP

●The original WIPP ventilation system will NOT be capable of meeting these mission statement needs.

●An upgrade to the surface exhaust and filter system is required

Page 10: 22 WIPP Future Advancements and Operational Safety

Long Range Ventilation Design Basis

●Assumed new panels would be constructed to the west of the existing repository.

●Panels would be identical to existing panels (room width and height, number of rooms, length of rooms, space between panels, and similar access airways)

●A repository life to the year 2050●From the receipt rate to 2050, the maximum

number of additional panels was estimated at 13

Page 11: 22 WIPP Future Advancements and Operational Safety

Long Range Ventilation Design Basis●Five main airways developed to the west. With

five airways, two will be for disposal intake.●Allows for ground control functions in one of the

intake mains without impacting waste handling operations.

●Mining will progress in a clockwise manner starting to the south nearest the existing repository mains●Minimizes mining to complete Panel 11 ●Reduces ventilation demand in early years

Page 12: 22 WIPP Future Advancements and Operational Safety

Long Range Ventilation Design

●Even without the radiation event in 2014, the Mission statement to emplace to 2050 would result in the need for:●New surface fans to accommodate distance to furthest panels●New shaft to replace aging Salt Handling Shaft and enhance

material handling capabilities●New shaft to separate construction air from disposal exhaust●New mining equipment (age of existing equipment would need

to be phased out)

Page 13: 22 WIPP Future Advancements and Operational Safety

WIPP Upgrade Projects

●Two new projects are considered to achieve the mission statement:●New surface fans with new filter system (sufficient for all

exhaust air as per DOE direction).●New shaft (to achieve long term goals at WIPP regarding

hoisting and separation of construction [mining] and waste handling operations)

Page 14: 22 WIPP Future Advancements and Operational Safety

Current New Filter Building (NFB) Design

●Principal underground ventilation design criteria for NFB●Maximum airflow of 540,000 cfm (at the fans)●Consider a salt reduction system to minimize salt

dust from reaching containment filters

Page 15: 22 WIPP Future Advancements and Operational Safety

Permanent Ventilation System Project StatusNew Filter Building General Layout

Page 16: 22 WIPP Future Advancements and Operational Safety

Salt Reduction Building

New Filter Building

New Standby Generators

Exhaust Stack

Fans

Exhaust Shaft

Page 17: 22 WIPP Future Advancements and Operational Safety

Exhaust Shaft (ES) Location

Page 18: 22 WIPP Future Advancements and Operational Safety

ES Project

●A new intake shaft results in all construction (mining) air to be routed to the AIS for exhausting to surface●Eliminates a significant dust source to Exhaust Shaft

filtration system and possibly eliminates the need for a salt reduction system on surface

●Greatly reduces any salt build up in duct work on Exhaust Shaft

Page 19: 22 WIPP Future Advancements and Operational Safety

Hoisting System in New Shaft

• The current project does not include a hoisting system

• A separate project is being considered to install a hoisting system in the new shaft.

Page 20: 22 WIPP Future Advancements and Operational Safety

New Shaft with Hoisting Capability

●The need for a hoisting system is based on the following criteria:● Increased salt handling operations● Increased personnel and materials handling operations

●The design would allow for salt skipping and personnel and material handling operations to occur simultaneously ●At least doubling current salt skipping operations●Large equipment can be hoisted via a large conveyance●Emergency egress is significantly enhanced

Page 21: 22 WIPP Future Advancements and Operational Safety

New Shaft with Hoisting Capability●Basis of new hoisting system design

●Need to replace existing Salt Handling Shaft (SHS)●The SHS has been in operation since the early 1980s and was

designed for a 25 year life (currently over 30 years old)●The current SHS is a small 10 ft. diameter shaft with

significant corrosion on internal shaft components. ●At some stage this shaft will need a major overhaul – which

will result in a cessation of salt skipping from the underground during shaft renovation.

●A complete shaft overhaul with updated controllers on the hoist system could take up to 12 months.

●This will impact mining to new panels to the west.

Page 22: 22 WIPP Future Advancements and Operational Safety

Loading pocket corrosion.

SHS liner and bunton corrosion

SHS bunton and wall connection corrosion

Page 23: 22 WIPP Future Advancements and Operational Safety

New Shaft with Hoisting Capability●The need for a hoisting system is based on the following

(continued):●The SHS has only an 8 ton skipping capacity for salt removal.

Bottlenecks were common with this limited skip capacity (storing salt in underground airways waiting to be skipped)

●The SHS has two functions, personnel and material conveyance and salt removal. The two functions CANNOToccur simultaneously.

● If the SHS is skipping salt, then all personnel and material handling is moved to the Waste Shaft – potentially limiting any waste handling operations.

Page 24: 22 WIPP Future Advancements and Operational Safety

Shaft Conveyances and Shaft Diameter●Twin skips – doubling salt hoisting capacity ●A 12 ft. x 18 ft. personnel and material

conveyance:● Increased productivity since personnel can be sent

underground more efficiently● Increased productivity in handling supplies, e.g. rock

bolts, mesh, equipment, diesel fuel, etc.● Can handle about 100 personnel in an emergency

(egress) and is closer to new panel development then the Waste Shaft or SHS – A Significant Safety Improvement

●A 12 ft. x 18 ft. personnel and material conveyance with two skips and up to 500,000 cfm results in a shaft diameter of 30 ft. (26 ft. finished)

Access to

Cage

Skip Skip

12 ft x 18 ft

Personnel

and Materials

Cage

Counterweight

15 ft13 ft

6 in

chco

ndui

t

Access to

Cage