20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

Sep 20, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

N Y S E : A P C

W W W . A N A D A R K O . C O M

20A – Managing Subsea HPHT Equipment Risks

Gregory Walz

Page 2: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

2

• Anadarko’s 20A Project kicked off in 2014

• Design, verification, and validation 20ksi subsea equipment

Anadarko’s Unique Opportunity

Page 3: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

3

• Pressure controlling & containing equipment review process

BSEE Review Process

Page 4: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

4

Systems engineering approach

Whole Life Cycle Modes

Page 5: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

Load Identification & Bracketing

5

Page 6: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

System Design Flow

6

Page 7: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

Pressure Controlling or Pressure Containing Equipment

7

Page 8: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

Validation Testing Examples

8

Page 9: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

Integrated PRA Model

9

Page 10: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

10

Human contribution to the overall risk for the generic configuration

Probabilistic Risk Assessment (PRA) Overall Results

Page 11: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

Next Steps – Human Factors

11

Human Reliability Analysis Tool Predictions

Versus

Simulator Results

Page 12: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

12

• Anadarko and our suppliers have been performing an extensive development program for 20K subsea equipment since 2014

• Currently finishing all testing, 4Q18 / 1Q19

• Developing and submitting the I3P reports to BSEE 4Q18 / 2Q19

• Extensive technical rigor, documentation, and review is being performed to mitigate “Serial #1” risks

• Anadarko sees value in PRAs, working on how best to use the methodology

• Will continue to collaborate with BSEE and NASA on PRA modeling

Summary

Page 13: 20A Managing Subsea HPHT Equipment Risks · program for 20K subsea equipment since 2014 •Currently finishing all testing, 4Q18 / 1Q19 •Developing and submitting the I3P reports

A N A D A R K O P E T R O L E U M C O R P O R A T I O N

Thank you

13