GTC 10 Year LTFM Demonstration of a 10 Year, Long Term Forecasting Model using Primavera Resource Loaded Projects Patrick O’Connell Project Control Group Lead Georgia Transmission Corporation [email protected]
28

205540 demonstration of a 10 year, long term project plan

Apr 14, 2017

Download

Business

p6academy
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFM

Demonstration of a 10 Year, Long Term Forecasting Model using Primavera Resource

Loaded Projects

Patrick O’ConnellProject Control Group LeadGeorgia Transmission [email protected]

Page 2: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFM

• There are more slides in this presentation with notes and procedures

• Not all will be discussed as we will go demo as much as we can

• Contact me if desired

Page 3: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFM

• GTC - owned by 39 Electric Membership Cooperatives (EMCs) in Georgia

• Build, operate and maintain Transmission Lines and Substations

• Not only for the EMC’s but also for the ITS• ITS – shared transmission system in Georgia with 4

members: GTC, GPC, MEAG and Dalton

Page 4: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFM

• Why this methodology?• The purpose of the LTFM

is to provide an aligned cost (EPIS & Cashflow) & man-hour forecasting tool

• Target audience• Finance• Functional Managers

Page 5: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMDefinitions

• EPIS – Electric Plant In Service• Depreciation begins• Affects members as we plan to recover cost for their stations

and lines• LTFM – Long Term Forecasting Model

• EPIS• Cashflow• Capacity planning / Workforce planning

• Cashflow vs EPIS• Paying the bills vs how we pay off paying the bills

Page 6: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMTools

• TPOP• Planning tool• Project attributes• “Real” projects based on customer need

• P6 v7• TPOP projects• “Ghost” projects

• Access• Query data from multiple data sources

• Excel• Input/output• Calculators• Charts

Page 7: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMTools

• Effect of “Ghost” projects

Page 8: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMP6

• Schedules created from standard templates• Resource loaded

• Expense codes for invoices and payments• Consistent across all projects• Project schedule has all cost – BAC, AC, ETC, EAC

• Roles assigned in template• Standard by project type / activity• Many departments and job titles

Page 9: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMTypes of Ghost Projects

• Nine types (well, 14 after considerations)• Complexity / Size

• New / Mod Subs and New / Mod T/Ls• Advanced Land Purchase

• Cost average across all for each type• All expense codes• All roles – input from team members• Last 5 years of project history used

• Provision for non standard (like a $30M SS or TL)• Excluded some as non repeating

• Also, reimbursable projects

Page 10: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMWhat are we doing?

• We have real data that goes out 2-3 years for some load growth projects and long term projects that extend for 5-6 year but we don’t plan at the project level, really that far out.

• We add Ghost projects to match a projection and from this we get EPIS by project types (accounting need) and workforce planning by job title.

Page 11: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMPredictor Tool (Excel Spreadsheet)

• Sources of Data• TPOP, Primavera and Formal Projection

• Calculator• Compares TPOP, Primavera and a prediction to

determine the number of projects to add or remove by project type

• Graph• Visual aid as the predictor is adjusted • It is bottom up estimating

Page 12: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFM

Page 13: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMMS Access Queries

• Count (number of projects by type)• TPOP EPIS• P6 EPIS• How many do we need to add (delete)

• Cost• TPOP EPIS• P6 EPIS• As projects are added the cost impacts are telling

Page 14: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMSpread Cost

• Each template spreads cost/MH based on activity duration and cost curves

• Cost Curves• Construction is back loaded• Land

• T/L – modified bell curve• S/S – last period

• Man-hours are linear

Page 15: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMCost by EPS Sheet

• Sanity Check• Visual check to see if an EPS node does not look “right”• Useful first step if the chart looks like it has a spike

Page 16: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMProject Cost by EPS Sheet

• Error Check• Step two if you think there might be a bad project• Easy to sort and group by the same format as the previous

• Example:• South looks like it has too much • Drill to South node• Spy projects and look for outlier(s)

Page 17: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMReports

• EPIS Charts• Workforce planning

Page 18: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMChart

Page 19: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMWorkforce Planning

• Departments• Interface charts

Page 20: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMWorkforce Planning

Page 21: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMRoles Tab

• List of roles with history• Class of project• Direct vs OH• Number of people supporting the role

• This is how you have charged your time NOT the place to estimate

Page 22: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMSelected Resources Tab

• Pruning• Who are good candidates to describe the role?• Selected are those who have worked full years,

consistently on projects• Exclude

• Started mid year• Part time• Re-tasked to other assignments

Page 23: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMRole History Tab

• Summarized data by role• Sanity check

Page 24: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMEPS Structure and Activity Counts

Page 25: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMLTFM EPS “Years”

• Note 2013 - 2014 have no data by choice• See how we are extending into the future to capture the

impact of front end activities on the target years

Page 26: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMLTFM Templates

Page 27: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMLTFM EPS “Years”

• Note 2013 - 2014 have no data by choice• See how we are extending into the future to capture the

impact of front end activities on the target years

Page 28: 205540 demonstration of a 10 year, long term project plan

GTC 10 Year LTFMOH Impact

• No OH shown• May be flat or steady but is (somewhat) independent of

capital growth• Ability to predict future year OH rates