2017 FIVE‐YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM
pg. 1
2017 FIVE‐YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM 2016‐2017 THROUGH 2020‐2021
Recommended by the Transportation Advisory Committee February 28, 2017 Approved by the Board of Supervisors June 7, 2017 (Tentative)
DRAFT
2017 FIVE‐YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM
2016‐2017 THROUGH 2020‐2021
The Pinal County Board of Supervisors (Board) proudly presents the 2017 Five‐Year Transportation Improvement and Maintenance Program (TIMP) for Budget Years 2016‐2017 through 2020‐2021. The TIMP is Pinal County’s near‐term transportation plan that identifies potential funding and establishes a tentative schedule for planning, construction, and maintenance projects. It is fiscally constrained and updated annually with new projects added to the fifth year.
The Transportation Advisory Committee (TAC) is the Board appointed, ten member panel representing each of Pinal County’s five supervisor districts. The TAC is charged with prioritizing transportation projects for the TIMP and recommending the draft TIMP to the Board. On February 28, 2017, the TAC met in an open public meeting and recommended approval of the 2017 TIMP for Budget Years 2016‐2017 through 2020‐2021.
In recognition of their significant contributions, we would like to thank the TAC officers and members for their service to Pinal County.
First Row (L‐R): Paul Prechel, District 1; David Garcia, District 1; Vice‐Chair Maxine Brown, District 5; Jim Fabris, District 2; Second Row (L‐R): Tom Snider, District 4; Gordon Brown, District 2; Giao Pham, District 5; Chair Kevin Louis, District 3 Not pictured: Ted Hawkins, District 4 and Harold Vangilder, District 3
2017 FIVE‐YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM
2016‐2017 THROUGH 2020‐2021
The TAC conducts three public meetings during the months of September, November, and February in Florence and considers public comments in developing recommendations to the Board. We encourage you to attend the meetings and offer comments on the TIMP and future transportation projects.
Meetings are held on Tuesdays in the Ironwood Room (Northeast Multipurpose Room 101) of the Pinal County Administrative Complex (1891 Historic Courthouse) and begin at 2:30 p.m. as follows:
Agendas and minutes are posted in compliance with Arizona’s Open Meeting Law and can be found on Pinal County’s website: http://www.pinalcountyaz.gov/PublicWorks/TransportationPlanning/Pages/TACSchedule.aspx.
Funding for the TIMP is provided by revenues from the Pinal County Transportation Excise Tax, the half‐cent sales tax, approved by voters in 2005. The sole purpose of the tax is to fund construction, maintenance, and roadside development projects throughout the county. Shopping and buying your gasoline locally ensure that quality transportation projects are planned and implemented countywide. With your support, we can continue building and improving the county’s transportation system.
Pinal County Board of Supervisors
September 26, 2017 November 28, 2017 February 27, 2018
Vice‐Chairman Pete Rios, District 1; Mike Goodman, District 2; Chairman Stephen Miller, District 3; Anthony Smith, District 4; Todd House, District 5
2017 FIVE‐YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM
2016‐2017 THROUGH 2020‐2021
RESOLUTION NO.___________________________________
WHEREAS, Pinal County is empowered by Arizona Revised Statutes § 11‐251 and § 28‐6701, et seq. to layout, maintain, control, and manage public roads within the County; and,
WHEREAS, on April 21, 2010, the Pinal County Board of Supervisors (Board) approved bylaws for the Transportation Advisory Committee (TAC), a recommending body to the Board on countywide transportation planning, construction, and maintenance projects; and,
WHEREAS, pursuant to Article II of the bylaws, the TAC shall annually review, update, and recommend a five‐year transportation improvement and maintenance program to the Board; and,
WHEREAS, it is the recommendation of the TAC that the 2017 Pinal County Five‐Year Transportation Improvement and Maintenance Program for Budget Years 2016‐2017 through 2020‐2021 be approved.
THEREFORE, IT IS RESOLVED that the Pinal County Board of Supervisors approves the 2017 Five‐Year Transportation Improvement and Maintenance Program for Budget Years 2016‐2017 through 2020‐2021 and authorizes Public Works staff to proceed with pre‐construction, construction, and/or maintenance activities including expenditures for the programmed transportation projects.
IT IS FURTHER RESOLVED that this Resolution is effective upon approval and execution of this Resolution.
PASSED AND ADOPTED this __________ day of __________________________, 2017, by the PINAL COUNTY BOARD OF SUPERVISORS.
_________________________________________
Chairman of the Board
ATTEST:
____________________________________
Clerk of the Board
2017 FIVE‐YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM
2016‐2017 THROUGH 2020‐2021
GLOSSARY
Activity – Project work such as: pre‐construction/construction/new construction/reconstruction, drainage, dust palliative, pavement preservation or safety.
Construction – The building of roadway and/or related infrastructure improvements.
Drainage – The management of storm water to protect private and/or public infrastructure.
Dust Palliative – A surface treatment applied to unimproved roadways to control dust.
New Construction – The establishment of a roadway and/or related infrastructure improvements.
Pavement Preservation – A topical treatment that extends the service life of existing pavement surfaces.
Pre‐Construction – The project work conducted prior to construction of roadway and/or related infrastructure improvements such as: planning, environmental, design, and right‐of‐way acquisition.
Reconstruction – The rebuilding of roadway and/or related infrastructure improvements. Elements of new construction may be incorporated into the project.
Safety – The project work that eliminates or reduces the severity of roadway hazards. Examples include intersection realignment, guardrails, improved signage and/or pavement markings, traffic signals or related studies.
Status – The current state of the project such as: cancelled, closed, completed, pending, programmed, and underway
Cancelled – The project was terminated due to financial or other constraints such as unresolved right‐of‐way issues or changing priority.
Closed – The project was combined with another project (including allocated funding) to streamline activities or allocated funding for project was not used.
2017 FIVE‐YEAR TRANSPORTATION IMPROVEMENT & MAINTENANCE PROGRAM
2016‐2017 THROUGH 2020‐2021
GLOSSARY (continued)
Completed – The project was successfully finished/constructed and closed out.
Pending – The project is about to start or awaiting the completion of another activity.
Programmed – The project was approved/authorized and scheduled for a future budget year.
Underway – The project is in progress.
Unfunded – Funding has not been identified/allocated.
Budget Year 2016‐2017Transportation Improvement and Maintenance ProgramIMPROVEMENT
Project Location Activity PageDistrictStatus
PROJECT TYPETotal CostArea Engineer
Battaglia Drive Overfield Rd Intersection Construction/Reconstructi $350,000 14UnderwayAngeline To aFlorence‐Kelvin Highway Cochran Rd‐Donnelly Wash Construction $275,900 11CompletedAngeline To bGantzel Road (Pathway) Bella Vista Rd‐Poston Butte High School New Construction $500,000 22CompletedCeleste Garza aGermann Road Meridian Rd‐Ironwood Dr Pre‐Construction $244,124 22UnderwayCeleste Garza bHenness Road Val Vista Rd‐Waverly Dr New Construction $350,000 33UnderwayLindsey Randall aHunt Highway ‐ Phase IV Gary Rd‐Magma Rd Pre‐Construction $250,000 32CompletedCeleste Garza bMaricopa‐Casa Grande Highway Santa Cruz Wash Crossing New Construction $2,600,000 44CompletedJohn Kraft aMitchell Trail Heritage Rd‐Arizona Farms Rd Pre‐Construction $100,000 42UnderwayCeleste Garza bSafety Program Countywide Safety $915,600 57ProgrammedJohn Kraft a
Bronco Lane Valley View Dr south .1 mile Dust Palliative $30,000 55PendingCeleste Garza bCattle Tank Road Davis Ranch Rd‐Park Link Dr Dust Palliative $750,000 61, 4PendingAngeline To aCattle Tank Road Davis Ranch Rd‐Park Link Dr Pre‐Construction $90,000 61, 4UnderwayAngeline To bChristensen Road‐Bartlett Road Martin Rd‐5th St Dust Palliative $180,000 71CompletedCeleste Garza aEstancia Drive Davis Ranch Rd‐Hedgehog Tr Dust Palliative $100,000 74PendingAngeline To bHarmon Road Toltec Hwy‐Tweedy Rd Dust Palliative $360,000 81PendingAngeline To aHuisatch Road Garnet Rd‐Amarillo Valley Rd Dust Palliative $175,000 84PendingLindsey Randall bLa Barranca Road Sage St‐Hidden Valley Rd Dust Palliative $100,000 94CompletedLindsey Randall aLa Palma Road State Route 287‐.25 north of Kleck Rd Dust Palliative $150,000 91PendingLindsey Randall bMaverick Circle Mohican Rd west .1 mile Dust Palliative $30,000 105PendingCeleste Garza aPavement Preservation Program Countywide Pavement Preservation $84,400 107ProgrammedJoe Ortiz bPavement Preservation Program Countywide Pavement Preservation $915,600 117ProgrammedJoe Ortiz aRalston Road Wildcat Ln‐Dune Shadow Rd Dust Palliative $200,000 114CompletedLindsey Randall bRedington Road Veterans Memorial Blvd‐Pima County Line Dust Palliative $665,000 121UnderwayAngeline To aSixshooter Road Jacob Waltz St north .1 mile Dust Palliative $30,000 125PendingCeleste Garza bWildwood Road Warren Rd‐Amarillo Valley Rd Dust Palliative $400,000 134CompletedLindsey Randall a
$4,260,000SUBTOTAL MAINTENANCE
$9,845,624GRAND TOTAL 2016‐2017
District 7 = Multiple districts or countywide
Budget Year 2017‐2018Transportation Improvement and Maintenance ProgramIMPROVEMENT
Project Location Activity PageDistrictStatus
PROJECT TYPETotal CostArea Engineer
Curry Road State Route 287‐Storey Rd Construction $110,000 133ProgrammedLindsey Randall bMcCartney Road Interstate 10‐Evans Rd Reconstruction $3,500,000 141, 3UnderwayLindsey Randall aSafety Program Countywide Safety $500,000 147ProgrammedJohn Kraft bSunland Gin Road Battaglia Dr Intersection Safety $350,000 154ProgrammedAngeline To aTweedy Road State Route 287‐Storey Rd Construction $110,000 153ProgrammedLindsey Randall b
Cactus Road Kaniksu St (north)‐Frontier St Dust Palliative $20,000 165PendingCeleste Garza aDust Abatement Program Apache Junction area Dust Palliative $500,000 165PendingCeleste Garza bMcDavid Road Warren Rd‐Hidden Valley Rd Dust Palliative $110,000 174UnderwayLindsey Randall aMuleshoe Road Roundup St‐Shiprock St Dust Palliative $20,000 175PendingCeleste Garza bPavement Preservation Program Countywide Pavement Preservation $500,000 187ProgrammedJoe Ortiz aPeters Road Santa Cruz Wash‐Corrales Rd Dust Palliative $252,083 183ProgrammedLindsey Randall bWarren Road Farrell Rd‐McDavid Rd Dust Palliative $220,000 194PendingLindsey Randall a
$1,622,083SUBTOTAL MAINTENANCE
$6,192,083GRAND TOTAL 2017‐2018
District 7 = Multiple districts or countywide
Budget Year 2018‐2019Transportation Improvement and Maintenance ProgramIMPROVEMENT
Project Location Activity PageDistrictStatus
PROJECT TYPETotal CostArea Engineer
Arizona City Safety Study Multiple Intersections Pre‐Construction $100,000 194ProgrammedAngeline To bBaseline Avenue Mohican Rd‐East 980 feet Construction $55,417 205ProgrammedCeleste Garza aCactus Wren Street Mountain View Rd‐Val Vista Rd New Construction $61,700 205ProgrammedCeleste Garza bFlorence‐Kelvin Highway Donnelly Wash‐East 2 miles Construction $800,000 211ProgrammedAngeline To aGantzel Road Chandler Heights Rd Construction $325,000 212, 5ProgrammedCeleste Garza bGermann Road Meridian Rd‐Ironwood Dr New Construction $1,728,590 222ProgrammedCeleste Garza aHohokam Road Paisano Dr‐Quartzite Dr Construction $286,300 221ProgrammedCeleste Garza bLost Dutchman Road Sun Rd‐Prospectors Rd Construction $156,000 235ProgrammedCeleste Garza aSafety Program Countywide Safety $1,000,000 237ProgrammedJohn Kraft b
Arica Road Isom Rd‐Trekell Rd Dust Palliative $120,000 244ProgrammedJohn Kraft aBattaglia Drive Chuichu Rd‐Del Rio Rd Pavement Preservation $200,000 243, 4ProgrammedAngeline To bChuichu Road Battaglia Dr‐Interstate 8 Pavement Preservation $2,000,000 253ProgrammedJohn Kraft aDust Abatement Program Countywide Dust Palliative $1,000,000 257ProgrammedJoe Ortiz bFulcar Road Hidden Valley Rd‐Table Top Rd Dust Palliative $240,000 264ProgrammedJohn Kraft aSage Street Barnes Rd‐Miller Rd Dust Palliative $120,000 264ProgrammedJohn Kraft bSotol Road Warren Rd‐Hidden Valley Rd Dust Palliative $150,000 274ProgrammedJohn Kraft aStagecoach Pass Avenue Schnepf Rd‐Ghost Rider St Pre‐Construction $50,000 275UnderwayCeleste Garza b
$3,880,000SUBTOTAL MAINTENANCE
$8,393,007GRAND TOTAL 2018‐2019
District 7 = Multiple districts or countywide
Budget Year 2019‐2020Transportation Improvement and Maintenance ProgramIMPROVEMENT
Project Location Activity PageDistrictStatus
PROJECT TYPETotal CostArea Engineer
Florence‐Kelvin Highway Gardenshire Rd‐Apache Kid Rd Construction $700,000 281ProgrammedAngeline To aGantzel Road Queen Creek (Wash) Pre‐Construction $50,000 282, 5ProgrammedCeleste Garza bHash Knife Draw Road Schnepf Rd‐Sierra Vista Dr Construction $110,000 295ProgrammedCeleste Garza aJackpot Street Skyline Dr‐Rolling Ridge Rd Construction $82,500 295ProgrammedCeleste Garza bRoberts Road Felix Rd‐Joel Rd Construction $38,542 305ProgrammedCeleste Garza aRolling Ridge Road Schnepf Rd‐Sierra Vista Dr Construction $110,000 305ProgrammedCeleste Garza bSafety Program Countywide Safety $1,000,000 317ProgrammedJohn Kraft aSage Brush Avenue Schnepf Rd‐Sierra Vista Dr Construction $110,000 315ProgrammedCeleste Garza bStagecoach Pass Avenue Ghost Rider St‐Sierra Vista Dr Construction $28,333 325ProgrammedCeleste Garza aTombstone Street Skyline Dr‐Rolling Ridge Rd Construction $82,500 325ProgrammedCeleste Garza bVal Vista Road Warren Rd‐Hidden Valley Rd Construction $520,000 334ProgrammedJohn Kraft a
Comments Activity: Culvert for intersection and pavement replacementStatus: From Programmed to Underway. Design is underway (60% complete) with construction scheduled for Summer/Fall 2017.
Status Underway
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Activity: Asphalt rock dust palliativeBudget Year: Carryover of $275,900 from 2015‐2016 to 2016‐2017Status: From Pending to Completed. Construction on original project limits, from Adams Wy‐Cochran Rd, completed May 2015. Construction on one mile from Cochran Rd to Donnelly Wash completed Spring 2016.
Status Completed
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 6511204
3
1 b
Budget Year 2016‐2017 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520‐866‐6411 (telephone)520‐866‐6511 (fax)
Length in Miles
Gantzel Road (Pathway) Bella Vista Rd‐Poston Butte High School
Comments Activity: Pathway constructionBudget Year: Carryover of $500,000 from 2015‐2016 to 2016‐2017Status: From Underway to Completed. Construction is subtantially completed as of September 2016. Project constructed in conjunction with the Hunt Highway ‐ Phase III (Gary Rd ‐ Bella Vista Rd) and Gantzel Road ‐ Phase D1 projects.
Status Completed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Activity: Right‐of‐way acquisition, environmental, design for construction of two‐lane road, and plan review by the Arizona Department of TransportationCounty Cost: $13,866 reflects Pinal County's cost share matchStatus: Design underway and approximately 95% complete and pending review/management by Arizona Department of Transportation. Project was awarded Surface Transportation Program (federal) funds through Maricopa Association of Governments.
Status Underway
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 6621139
1
2 b
Budget Year 2016‐2017 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
Comments Status: Right‐of‐way has been obtained, in‐house design is underway, and construction is scheduled for Summer 2017. Design (at 60%) is anticipated to be completed February 2017.
Status Underway
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Activity: DesignStatus: From Underway to Completed. Design is 95% completed and is now bond funded. Final design submittal mid‐February 2017. Construction is anticipated June 2017.
Status Completed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
3
3 b
Budget Year 2016‐2017 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520‐866‐6411 (telephone)520‐866‐6511 (fax)
Length in Miles
Maricopa‐Casa Grande Highway Santa Cruz Wash Crossing
Comments Activity: Box culvert constructionCounty Cost: Increased from $2,300,000 to $2,600,000Budget Year: Carryover of $2,600,000 from 2015‐2016 to 2016‐2017Status: From Underway to Completed. Project completed Spring 2016.
Status Completed
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Activity: Right‐of‐way/design for new roadwayBudget Year: Carryover of $100,000 from 2015‐2016 to 2016‐2017Status: Right‐of‐way acquisition is underway but responses are not favorable at this time.
Status Underway
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
1
4 b
Budget Year 2016‐2017 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
Comments Activity: Asphalt rock dust palliativeStatus: Submitted final Environmental Assessment to the Bureau of Land Management. Right‐of‐way acquisition from the Arizona State Land Department is completed. Asphalt rock dust palliative is scheduled Spring 2017. Construction will be in phases starting with Davis Ranch Road to Amber Sunrise Drive.
Status Pending
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Activity: Environmental and right‐of‐way for Asphalt Rock Dust PalliativeStatus: Submitted final Environmental Assessment to the Bureau of Land Management. Right‐of‐way acquisition from the Arizona State Land Department is completed. Asphalt rock dust palliative is scheduled Spring 2017. Construction will be in phases starting with Davis Ranch Road to Amber Sunrise Drive.Project Numbers: 6511213 (environmental clearance), 6511214 (right‐of‐way acquisition)
Status Underway
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 6511213
5.5
6 b
Budget Year 2016‐2017 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
Comments Status: From Pending to Completed. Asphalt rock dust palliative completed August 2016. Comment: Project is a joint effort with the City of Coolidge.
Status Completed
Maintenance Area San Tan
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments County Cost: From $360,000 to $235,000Non County Cost: From $0 to $125,000Status: Cost share agreement with dairy owner pending approval by the Board of Supervisors 2/15/17. Construction scheduled for Summer 2017.
Status Pending
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Status: From Programmed to Pending. Asphalt rock dust palliative is scheduled Fall 2017.Project Manager: From John Kraft to Lindsey RandallEmail: From [email protected] to [email protected]
Status Pending
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
2.25
9 b
Budget Year 2016‐2017 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
Comments Activity: Direct funding to the Pavement Preservation ProgramCounty Cost: Additional allocation as recommended by the Transportation Advisory Committee (total direct funding $1,000,000.00)
Status Programmed
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
10 b
Budget Year 2016‐2017 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
Comments Activity: Asphalt rock dust palliativeStatus: Dust palliative on Redington Road from Veterans Memorial Blvd to River Rd completed September 2015. Environmental study completed on Redington Road from River Rd to Pinal‐Pima County boundary September 2016 with completion of asphalt rock dust palliative anticipated April 2017.
Status Underway
Maintenance Area Oracle
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Budget Year: Carryover of $400,000 from 2015‐2016 to 2016‐2017Status: From Underway to Completed. Asphalt rock dust palliative completed Spring 2016.
Status Completed
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
1
13 b
Budget Year 2017‐2018
Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
520‐866‐6411 (telephone)520‐866‐6511 (fax)
Budget Year 2016-2017
Length in Miles
McCartney Road Interstate 10‐Evans Rd
Reconstruction$3,500,000$0$3,500,000
ActivityCounty CostNon County Cost
IMPROVEMENT
District 1, 3Project Manager Lindsey Randall E‐mail [email protected]
Comments Activity: Installation of culverts at dip crossings. Budget Year: Carryover of $1,500,000 from 2016‐2017 to 2017‐2018County Cost: Increased from $2,000,000 to $3,500,000 to consolidate 2 programmed projects.Status: From Pending to Underway. Design is underway (90% completed) with construction anticipated Fall 2017.
Status Underway
Maintenance Area Casa Grande
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Activity: Area Engineer's discretionary project(s) to address fugitive dust (Particulate Matter 10) in Pinal County's Non‐Attainment area (T1N, R8E)Status: From Programmed to Pending. Asphalt rock dust palliatives scheduled Summer 2018
Status Pending
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
16 b
Budget Year 2017‐2018 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
Comments Project Manager: From John Kraft to Lindsey RandallEmail: From [email protected] to [email protected]: From Programmed to Underway. Project is underway and may be completed Budget Year 2016‐2017.
Status Underway
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Status: From Programmed to Pending. Dust palliative programmed for Summer 2018.Project Manager: From John Kraft to Lindsey RandallEmail: From [email protected] to [email protected]
Status Pending
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Location: Battaglia Drive from Sunland Gin Road to Overfield Road, Battaglia Drive from Chuichu Road to Del Rio Road, Lamb Road from Battaglia Drive to Milligan Road, Milligan Road from Sunland Gin Road Overfield Road, Overfield Road from Battaglia Drive to Milligan Road, and Sunland Gin Road from Battaglia Drive to Milligan Road
Status Programmed
Maintenance Area Arizona City
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
19 b
Budget Year 2018‐2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
Comments Activity: Construction of two‐lane roadBudget Year: Carryover from 2014‐2015 to 2018‐2019County Cost: $98,530 reflects Pinal County's cost share matchStatus: Design underway and approximately 95% complete. Project was awarded Surface Transportation Program (federal) funds through Maricopa Association of Governments.
Status Programmed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Activity: Area Engineers' discretionary project(s) to address fugitive dust (Particulate Matter 2.5 and 10) in Pinal County's Non‐Attainment areas
Status Programmed
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0
25 b
Budget Year 2018‐2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
Comments Project: Stagecoach Pass Av‐Ghost Rider Street to Stagecoach Pass AvenueActivity: In‐house design and right‐of‐way design. Budget Year: Carryover from 2014‐2015 to 2018‐2019Status: Design underway with construction anticipated in Budget Year 2019‐2020. Right‐of‐way acquisition underway but responses are not favorable.
Status Underway
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number
0.8
27 b
Budget Year 2018-2019 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
Comments Activity: Dust palliative includes 4.1 miles of the following roadways: Carefree Place, Reitz Ranch Road, Padilla Road, Clayton Road, and Lopez Road.
Status Programmed
Maintenance Area Hidden Valley
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 27124
4.1
34 b
Budget Year 2019‐2020 Public Works Department 31 N. Pinal Street, Building FP.O. Box 727Florence, AZ 85132
Comments Activity: Area Engineers' discretionary project(s) to address fugitive dust (Particulate Matter 2.5 and 10) in Pinal County's Non‐Attainment areas
Status Programmed
Maintenance Area Multiple
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Activity: Asphalt rock dust palliativeBudget Year: Carryover from 2015‐2016 to 2019‐2020Status: Right‐of‐way acquisitions are underway but responses are not favorable. Joint use agreement from crossing over the New Magma Irrigation is currently being processed
Status Programmed
Maintenance Area Apache Junction
Transportation Excise TaxFunding SourcePROJECT TYPE
Comments Status: Dust palliative is contigent on receiving right‐of‐way donations.Length: Dust palliative will extend to existing 5 miles of paved roadway.County Cost: $200,000 will be programmed annually for 4 years.
Status New Project
Maintenance Area Oracle
Transportation Excise TaxFunding SourcePROJECT TYPE
Total Cost
Project Number 191
8
47 a
Length in Miles
Rockcliffe Boulevard Oracle Ranch Rd (West)‐Alice St
Page & Map ID Project Location Activity Status District1a Battaglia Drive Overfield Rd Intersection Construction/Reconstruction Underway 41b Florence-Kelvin Highway *Cochran Rd-Donnelly Wash Construction Completed 12a Gantzel Road (Pathway) *Bella Vista Rd-Poston Butte High School New Construction Completed 22b Germann Road Meridian Rd-Ironwood Dr Pre-Construction Underway 23b Hunt Highway - Phase IV *Gary Rd-Magma Rd Pre-Construction Completed 24b Mitchell Trail Heritage Rd-Arizona Farms Rd Pre-Construction Underway 24a Maricopa-Casa Grande Highway *Santa Cruz Wash Crossing New Construction Completed 43a Henness Road Val Vista Rd-Waverly Dr New Construction Underway 35a Safety Program *Countywide Safety Programmed 7
Page & Map ID Project Location Activity Status District6a Cattle Tank Road Davis Ranch Rd-Park Link Dr Pre-Construction Underway 1, 46b Cattle Tank Road Davis Ranch Rd-Park Link Dr Dust Palliative Pending 1, 47b Estancia Drive Davis Ranch Rd-Hedgehog Tr Dust Palliative Pending 48a Harmon Road Toltec Hwy-Tweedy Rd Dust Palliative Pending 112a Redington Road Veterans Memorial Blvd-Pima County Line Dust Palliative Underway 15b Bronco Lane Valley View Dr south .1 mile Dust Palliative Pending 57a Christensen Road-Bartlett Road *Martin Rd-5th St Dust Palliative Completed 110a Maverick Circle Mohican Rd west .1 mile Dust Palliative Pending 512b Sixshooter Road Jacob Waltz St north .1 mile Dust Palliative Pending 58b Huisatch Road Garnet Rd-Amarillo Valley Rd Dust Palliative Pending 49a La Barranca Road Sage St-Hidden Valley Rd Dust Palliative Completed 49b La Palma Road State Route 287-.25 north of Kleck Rd Dust Palliative Pending 1
Transportation Improvement Projects Budget Year 2016 - 2017
Page & Map ID Project Location Activity Status District15a Sunland Gin Road Battaglia Dr Intersection Safety Programmed 413b Curry Road State Route 287-Storey Rd Construction Programmed 314a McCartney Road Interstate 10-Evans Rd Reconstruction Underway 1, 315b Tweedy Road State Route 287-Storey Rd Construction Programmed 314b Safety Program *Countywide Safety Programmed 7
Page & Map ID Project Location Activity Status District16a Cactus Road Kaniksu St (north)-Frontier St Dust Palliative Pending 516b Dust Abatement Program *Apache Junction area Dust Palliative Pending 517b Muleshoe Road Roundup St-Shiprock St Dust Palliative Pending 517a McDavid Road Warren Rd-Hidden Valley Rd Dust Palliative Underway 418b Peters Road Santa Cruz Wash-Corrales Rd Dust Palliative Programmed 319a Warren Road Farrell Rd-McDavid Rd Dust Palliative Pending 418a Pavement Preservation Program *Countywide Pavement Preservation Programmed 7
Transportation Maintenance Projects
Transportation Improvement Projects Budget Year 2017 - 2018
Page & Map ID Project Location Activity Status District19b Arizona City Safety Study Multiple Intersections Pre-Construction Programmed 421a Florence-Kelvin Highway Donnelly Wash-East 2 miles Construction Programmed 120a Baseline Avenue Mohican Rd-East 980 feet Construction Programmed 520b Cactus Wren Street Mountain View Rd-Val Vista Rd New Construction Programmed 521b Gantzel Road Chandler Heights Rd Construction Programmed 2, 522a Germann Road Meridian Rd-Ironwood Dr New Construction Programmed 222b Hohokam Road Paisano Dr-Quartzite Dr Construction Programmed 123a Lost Dutchman Road Sun Rd-Prospectors Rd Construction Programmed 523b Safety Program *Countywide Safety Programmed 7
Page & Map ID Project Location Activity Status District24b Battaglia Drive Chuichu Rd-Del Rio Rd Pavement Preservation Programmed 3, 427b Stagecoach Pass Avenue Schnepf Rd-Ghost Rider St Pre-Construction Underway 524a Arica Road Isom Rd-Trekell Rd Dust Palliative Programmed 425a Chuichu Road Battaglia Dr-Interstate 8 Pavement Preservation Programmed 326a Fulcar Road Hidden Valley Rd-Table Top Rd Dust Palliative Programmed 426b Sage Street Barnes Rd-Miller Rd Dust Palliative Programmed 427a Sotol Road Warren Rd-Hidden Valley Rd Dust Palliative Programmed 425b Dust Abatement Program *Countywide Dust Palliative Programmed 7
Transportation Maintenance Projects
Transportation Improvement Projects Budget Year 2018 - 2019
Page & Map ID Project Location Activity Status District28a Florence-Kelvin Highway Gardenshire Rd-Apache Kid Rd Construction Programmed 128b Gantzel Road Queen Creek (Wash) Pre-Construction Programmed 2, 529a Hash Knife Draw Road Schnepf Rd-Sierra Vista Dr Construction Programmed 529b Jackpot Street Skyline Dr-Rolling Ridge Rd Construction Programmed 530a Roberts Road Felix Rd-Joel Rd Construction Programmed 530b Rolling Ridge Road Schnepf Rd-Sierra Vista Dr Construction Programmed 531b Sage Brush Avenue Schnepf Rd-Sierra Vista Dr Construction Programmed 532a Stagecoach Pass Avenue Ghost Rider St-Sierra Vista Dr Construction Programmed 532b Tombstone Street Skyline Dr-Rolling Ridge Rd Construction Programmed 533a Val Vista Road Warren Rd-Hidden Valley Rd Construction Programmed 431a Safety Program *Countywide Safety Programmed 7
Page & Map ID Project Location Activity Status District34a Boyd Road Roosevelt St-End of road (Scenic St) Dust Palliative Programmed 535b Donnaloy Road Wilma Rd-Brenner Pass Rd Dust Palliative Programmed 235a Dolores Place-Shirley Road Olberg Rd-Avram Rd Dust Palliative Programmed 236b Marlow Road Jacob Waltz St-End of road Dust Palliative Programmed 537a Olberg Road Arizona Farms Rd-Brenner Pass Rd Dust Palliative Programmed 238a Plaza Drive Moon Vista St-Goldpoppy St Dust Palliative Programmed 538b Reed Road Bartlett Rd-At wash before Cactus Forest Rd Dust Palliative Programmed 139a Stagecoach Pass Avenue Schnepf Rd-Ghost Rider St Dust Palliative Programmed 533b Ashmore Street Passmore Rd-Baldwin Av Dust Palliative Programmed 3, 434b Carefree Place State Route 347-Pepper Pl Dust Palliative Programmed 439b Whirly Bird Road Amarillo Valley Rd-Ralston Rd Dust Palliative Programmed 436a Dust Abatement Program *Countywide Dust Palliative Programmed 737b Pavement Preservation Program *Countywide Pavement Preservation Programmed 7
Transportation Maintenance Projects
Transportation Improvement Projects Budget Year 2019 - 2020
Page & Map ID Project Location Activity Status District40a Bunkhouse Road Veteran's Memorial Blvd-San Manuel Lodge Reconstruction New Project 140b Cordones Road Catalina Hills Rd-Biosphere Rd Pre-Construction New Project 441a Hunt Highway (Old) Pioneer Path-Wildhorse Dr Construction New Project 241b Judd Road-Tourmaline Drive Gantzel Rd-Copper Basin Development Construction New Project 242a Kenworthy Road Germann Rd-Pima Rd Reconstruction New Project 242b Magma Road Hunt Hwy-Gary Rd Construction New Project 243a Mountain View Road Broadway Av Intersection Construction New Project 543b Ocotillo Road Meridian Rd-Ironwood Dr Construction New Project 2
Page & Map ID Project Location Activity Status District46a Mount Lemmon Road Campo Benito Rd-.5 miles south of AZ Zipline Dust Palliative New Project 147a River Road Redington Rd-Copper Creek Rd Dust Palliative New Project 147b Rockcliffe Boulevard Oracle Ranch Rd (West)-Alice St Dust Palliative New Project 144b Logan Boulevard Diffin Rd-Reed Rd Dust Palliative New Project 146b Rhea Road Brennar Pass Rd-Donnaloy Road Dust Palliative New Project 244a Bowlin Road Hidden Valley Rd-Stonebluff Rd Dust Palliative New Project 445a Louis Johnson Drive Amarillo Valley Rd-State Route 347 Dust Palliative New Project 445b Midway Road Beggs Rd-Marsh Rd Dust Palliative New Project 3, 448a Stonebluff Road Farrell Rd-Bowlin Rd Dust Palliative New Project 448b Tweedy Road Storey Rd-Randolph Rd Dust Palliative New Project 3
Transportation Maintenance Projects
Transportation Improvement Projects Budget Year 2020 - 2021
LegendEngineer Areas
Angeline To
Celeste Garza
Lindsey Randall
Area 1 Projects
Area 2 Projects
Area 3 Projects
Improvement and Maintenance ProjectsProject Time Frame : 2016-2021