6/19/2014 1 Aaron L. Stover, PE, SE Michael Baker Jr., Inc. Milton Madison Bridge Slide Kentucky Society of Professional Engineers May 23 rd , 2014 – Lexington KY Project Partners Milton, KY Madison, IN The Challenge Existing Bridge 80+ year old bridge Structurally Deficient Functionally Obsolete Sufficiency Rating of 6.5 Remaining life <10 years Constructible Affordable Replacement Bridge
21
Embed
2014 KSPE Milton Madison Bridge Slide · Microsoft PowerPoint - 2014 KSPE Milton Madison Bridge Slide.pptx Author: astover Created Date: 6/19/2014 9:47:59 AM ...
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
6/19/2014
1
Aaron L. Stover, PE, SEMichael Baker Jr., Inc.
Milton Madison Bridge Slide
Kentucky Society of Professional EngineersMay 23rd, 2014 – Lexington KY
Project Partners
Milton, KY
Madison, IN
The Challenge
Existing Bridge
80+ year old bridge
Structurally Deficient
Functionally Obsolete
Sufficiency Rating of 6.5
Remaining life <10 years
Constructible Affordable Replacement Bridge
6/19/2014
2
Presentation Outline
Project Overview
Maintenance of Traffic
Temporary Piers
Truss Restraints
Bearings and Slide Harnesses
Dislodged Bearing
Span D Slide
Truss Slide
Open to Traffic
4
Markland Dam
Project Site
I-275
I-65
Cincinnati
Louisville
LocationOne of two Ohio River bridges between Cincinnati and Louisville
I-65 Bridge - 46 milesMarkland Dam - 26 milesI-275 Bridge – 65 miles
Project Location Map
5
Superstructure Replacement
Milton Approach Re‐construction
STR 1 Replace KY Approaches
STR 2 Truss Replacement
Pier Strengthening And Scour Mitigation
Superstructure Replacement
6
Milton, KY
Madison, IN
• STR 3 – Replace IN Approaches
• STR 4 – Pedestrian Access
No Right-of-Way required
1 2 3
4
6/19/2014
3
Pier Strengthening
7
1. Drill holes into ex. caisson
2. Grout Rebar into Caisson
3. Add Stem Reinforcement
4. 2’ thick encapsulation
5. Pier Cap Reinforcement
6. Cast new Pier cap
7. Scour Countermeasure
SECTION A-A
A A
12’-0”LANE
8’-0”SHOULDER
5’-0” 12’-0”LANE
8’-0”SHOULDER
8
Typical Section
Existing Bridge is 20 ft curb to curb
5 ft pedestrian walkway
Selected Alternative
9
Existing Bridge
Proposed Bridge
6/19/2014
4
12 Month Closure
Design – Build Letting Summary
September 22, 2010
Five Contractors submitted bids
Formula for Effective Bid Price
lowest effective bid wins
[A + B – Adjustment]
A = construction cost
B = closure days x $25,000/day.
Adjustment = $3.75 million for early opening
11
Design – Build Letting Summary
September 22, 2010
Five Contractors submitted bids
Formula for Effective Bid Price
lowest effective bid wins
[A + B – Adjustment]
A = construction cost ($102‐$127 million)
B = closure days x $25,000/day. (365 days max)
Adjustment = $3.75 million for early opening(Sept 2012 or May 2013)
12
$103.7 M
10 Days
Sept 2012
6/19/2014
5
Maintenance of Traffic
13
Existing Existing Bridge
New Bridge
during 1Tie In Ramps
during 1st Closure
Slide Truss during Closure
Slide Truss during 2nd Closure
Maintenance of Traffic
14
Sliding
15
Pulling Strands
Bearing Pulling Bracket
6/19/2014
6
Temporary Towers
16
Sliding Girders
17
Sliding Girder Pedestal
18
6/19/2014
7
Sliding Girder and Pedestal
Slide 19
KY Approach Span D
Slide 20
Rebuild Common Pier
Rebuild Common Pier
N
Span DSpan D
Span D Sliding Girder Support
Slide 21
6/19/2014
8
Preparing Pier Caps
Slide 22
Pier 2 Sliding Plates for Both Slides
Span D SS Slide PL
GR 36 PL
Stainless Steel Sliding Surface
Slide 24
6/19/2014
9
Polishing Sliding Plates
Slide 25
Restraint Configuration
Slide 26
H H H H H
H
H
LongitudinalRestraint (TYP)
LongitudinalRestraint (TYP)
TransverseRestraint (TYP)
TransverseRestraint (TYP)
Restraints during Slide
Lateral Restraint was provided by pulling system
Pier 4 Bearings were restrained longitudinally
Unguided Bearing (TYP)
Unguided Bearing (TYP)
Transverse Restraints
Slide 27
TransverseRestraint
TransverseRestraint
Stowed for Transit
6/19/2014
10
Longitudinal Restraint for Slide
Slide 28
Installed At Pier 4Guided Angles
Installed At Pier 4
Pier 4 Bearing Harness
Disc Bearings
Slide 29
Sole PL
Permanent Slide PL
Bearing PL
Disc Bearing
SS Sliding Surface
Base PL
Erection Slide PL
Sliding Surface
Bearing Pulling Harnesses
Slide 30
6/19/2014
11
Bearing Pulling Harness
Slide 31
Lead Bearing
Trailing Bearing
Pulling Strands
Clamping Rods
Pulling Rod from Lead Bearing
Push PL
Push PL
Lead Bearing Harness
Slide 32
Push PL
Pulling Rods to Trailing BearingPulling Rods to Trailing Bearing
StrandsRestraint PL
Push PL
Trailing Bearing Harness
Slide 33
Pulling Rods From Lead Bearing
Pulling Rods From Lead Bearing
Upper Sliding Surface
Upper Sliding Surface
Pulls Bearing during the slide
Locks Upper Slide PL wrt. Upper Bearing PL
Permits Lower sliding surface movement
Lower Sliding Surface
Lower Sliding Surface
6/19/2014
12
Then, a Problem
Slide 34
Dislodged Bearing
Slide 35
10” Drop
Dislodged Bearing
Slide 36
6/19/2014
13
Upper Lateral Bracing
Slide 37
Slippage at Upper Chord Bracing
Slide 38
Analysis of Drop
Slide 39
Analysis of Drop
6/19/2014 39
6/19/2014
14
Jacking to Replace Bearing
Slide 40
Additional Lateral Restraint
Slide 41
Additional Longitudinal Restraint
Slide 42
Pier 2 and 6
Stuffers Installed
Prevent bearing from moving during slide
6/19/2014
15
Harness Vertical Support
Slide 43
Added Pipe Sliders to keep Harnesses AlignedAdded Pipe Sliders to
keep Harnesses Aligned
Span D Slide Process
44
Jack Completed Bridge
Remove Permanent Bearings
Attach Strands
Slide Bridge / Jack Bridge
Reinstall Bearings
Elastomeric Bearing Elastomeric Bearing
Pier 2 PedestalPier 2 Pedestal
Jack AssemblyJack Assembly
Sliding GirderSliding Girder
Span D DiaphragmSpan D DiaphragmSliding Bearing Sliding Bearing