Total No. of Questions - 101 [Total Nc. cf Pr-intcd pagcs - g MBA_IIl5 216522 M.B.A. (Management Science in Decision Making ) ( New Course ) Time Allowed: 3 Hours Maximum Marks: 70 l{ote: Attempt Jive questions in ail serecting one question Ji"orn each Unit. Each question cayries 14 marlcs. TINIT _ I l. A manufacturer makes a product, of'which the principal ingredient is a chemicar X. At the moment, the manui.acturer spends Rs.l000 per year on supplv of X, but there is a possibility that the price may soon increase to four times its present figure because of a worrdwide shortage of the chemical. There is another chemical y, which the manufacturer could use in conjunction with the third chemical Z in order to give the same effect as chemical X. chemicar y & Z would together cost the manufacturer Rs.3000 per year, but their prices are unlikely to rise. what action should the manufacturer take: (a) Apply the Maximin and Minimax criteria for decision making and give two sets of solutions. couRsE NO.203
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Total No. of Questions - 101 [Total Nc. cf Pr-intcd pagcs - g
MBA_IIl5
216522
M.B.A.
(Management Science
in Decision Making )
( New Course )Time Allowed: 3 Hours Maximum Marks: 70
l{ote: Attempt Jive questions in ail serecting one question Ji"orneach Unit. Each question cayries 14 marlcs.
TINIT _ Il. A manufacturer makes a product, of'which the principal
ingredient is a chemicar X. At the moment, the manui.acturer
spends Rs.l000 per year on supplv of X, but there is a
possibility that the price may soon increase to four times itspresent figure because of a worrdwide shortage of thechemical. There is another chemical y, which the
manufacturer could use in conjunction with the third chemical
Z in order to give the same effect as chemical X. chemicar y& Z would together cost the manufacturer Rs.3000 per year,
but their prices are unlikely to rise. what action should the
manufacturer take:
(a) Apply the Maximin and Minimax criteria for decision
making and give two sets of solutions.
couRsE NO.203
z.
(2)
(b) If the coefhcient of optimisn is 0'4' find the course of
action that minimizes the cost'
A businessman has trvo independent investment portfolios A
and B available to him, but he lacks the capital to underlake
both of them simultaneously' He can choose A first and then
stop, or if A is not successful' then take B or vice-versa' The
probabiliry of success of A is 0'6' while for B is 0'4' Both the
investment schemes tequire an initial capital outlay of
Rs.10,000 and both return nothing if the venture is
unsuccessfui. Successful completion of z\ u'ill retum
Rs.20,000 (over cost) and successflil completion of B will
retum Rs'24,000 (over cost)' Draw a decision tree and
determine the best strategY'
UNIT - II
3. Using the penalty (Big-M) method solve the following LP
problem:Maximize'Z: xl * 2x2+ 3 x3 - xa
Subject to constraints
x1 + 2 xz+3 x,r = 15
2x1 -x2t5x;=20x1*2Xz*x:*x+:10where X1, X2' x3, Xa Z 0
Ii
(3)
The XYZ company has the option of producing two productsduring period of srack activity. For the next period, productionhas been schedured so that the miting machine is free for r0hours and skilled rabour wiil have g hours of time available.
For the above Lp problem:
(a) Write dowathe dual form
(b) obtain the optimar sorution for the primar form.
UNIT _ IIIA company has three factories (Fr, Fz & F: ) which supply tcthree warehouses ( W1,W2 & W: ). Weekly factory capacitiesare 200' 160 and g0 trnits respectivery. weekry warehouserequirements are 1g0, r20 and 150 units respectivery. The unitshrpprng costs (in rupees) are as given below:
Product Machine timePer unit
Skilled labourfime ner rr.r't
Prnfit contributionpcr unit
5---.--.---.==_-----J,
A 4 2B 2 2
wl w2 w3
Fl
F'2
F3
I6
l426
20
I24
l)
I8
I6
(4)Obtain air
ii) Initial soluticn for the given ffanspoflation problern
' using Vogel's Approxinia:!+n Method: and
(ii) Optimal solutlcn hr the given trailspcftation
probic:n using MODI method.
A small airlines company, owning five planes operaie-q on all
ihe seven days of the week. Flights between ihe three cities A,
B and c a*cording to the schedule is given in the table belor,v.
The layover cosi psr stop is roughly proportional to the sqllare
of the layovcr time.:
FlightNo From I Departure timeI (in hours)
To i Arrival time
| ( in hours)
1
2
J
4
5
6
I
8
9
10
A
A
A
A
A
B
B
B
C
C
09:00
10:00
15:00
20:00
22:00
04:00
11:00
15:00
07:00
15:00
B
B
B(-
C
A
l2:00
13:00
18:00
Midnight
02:00
07:00
14:00
18:00
I 1:00
19:00
A
A
A
A
!
I
I
i
I
I
I
I
7.
(s)
Find how the pian';*s should be assigned to the rlights so as to
rniniinize the tctal la3'over cost? \l.hile solving for the above
problem assurne the foll*wing conditions:
(a) A plane cannot make more than two trips ( to and fro);
(b) A plane flying from a particular destination mirst be back
within 24 hours fcr the next scheduled trip from the
destination.
LINIT - IVThe following is the table showing details of a project:
The indirect cost is Rs.400 per day
(a) Draw the network diagram and identify the critical path;
(b) What are the normal project duration & associated cost;
ActivitlImmediatePredecessor
Normal CrasTime(in davs)
Cost(in Rs,'0001
Time{in davs
-T;st(in Rs.'000i
A
B
C
D
E
F
G
B
B
B
E
A,D,C
t0
8
5
6
8
5
t2
20
1s
8
11
9
5
3
7
6
4
4
5
4
8
30
2A
l4
15
15
8
4
8.
(6)
(c) Crash the relevant activities systematically and determine
the optimum project cornpletion time and cost.
'lhe data for a PERT network is displayed in the table below:
Time Estimates (in days)
Activity Sequence Optimistic Most likely Pessimistic
l-2I -3l-4t- J
2-53-43-64-65-6
(a) Draw the network
Path.
666612242s8
l1 l4
15 24
369 15
410diagram and determine the critical
23
45
9
27
16
(b) What is the expected duration of completion of the entire
project?
(c) What is the probability that the project duration will
exceed 60 days?
(d)
(e)
(7 )
What is the chance of completing the project between 45
days and 54 days?
It becomes known later that the three time estimates for
the activity 4 - 6 have to be revised to 14, 20 and.32 for
Optimistic, Most Likely and Pessimistic time estimates
respectively. What impact does this have on the project
duration? What will be the probability that the project
can now be completed before 46 days? For the above
PERT problem the additional data.given is as fallsws:
z 0.40 4.25 A.50 0.75 1.0A t.S0 I.6T
(zsz) a.s00 0.599 0.692'0.778 0.84r 0.9s3 0.9s3
UNIT _ V
In a small town, there are only two stores, ABC & XyZ, that
handle sundry goods. The total number of customers is equally
divided between the two, because price and quality of goods
sold are equal. Both the stores have good reputation in the
community, and they render equally good customer service.
Assume that a gain of customers by ABC is a loss to XyZ and
vice-versa. Both the stores plan to run annual pre-Deepawali
sales during the first week of November. The sales are
9.
l'6.'
advertised through a local newspaper, radio and television
rnedia. With the aid of the advertising firm, store ABC
consffucted the game matrix as given below (the figures in the
matrix represent a gainor loss customers.
Strategt of ABC Nauspaper Radio Television
Newspaper
Radio
Television
30 40
01590 20 s0
10.
Determine the optimal strategies and the worth of such
strategies for both ABC and XYZ stores. ,
A bakery keeps stock of popular brand of cake. The daily
demand based on past experience is"liven below:
Daily Demand 0 15 25 35 45 50
Probability 0.01 0.15 0.2a 0.50 a.n 0.02
Consider the foliowing sequence of random numbers:
48,78, Ag, 51,56, 77, 15, 14, 68and09.
(a) Using the sequence, simulate the demand for the
next 10 days.
(b) Find the stock situation if the owner of the bakery
decides to make 35 cakes everyday. Also estimate the
daily average demand for the cakes on the basis of the