WUXI GCS Workshop Common mistakes in planning and installing PV systems in Germany October 2011 Andreas Iliou Technical Customer Service Engineers Germany
23

20111010 gcs training wuxi common mistakes in planning and installation - v02

Jun 29, 2015

Download

Technology

The not so confidential planning and installation issues
made during Energy Audits
2011 onwards
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

WUXI GCS Workshop

Common mistakes in planning and installing PV systems in Germany

October 2011Andreas Iliou Technical Customer Service Engineers Germany

Page 2: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

Content

1. Common mistakes in planning a PV system

2. Common mistakes in installing a PV system

3. Consequences for Claim Management

2

Page 3: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

1. Common mistakes in planning a PV system

3

Page 4: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

a) Shadowing (can cause Bypass diode damages)

b) Temperature zones (performance issues)

c) Layout of the panels (vertical, horizontal) (performance issues with dirt)

d) Snow loads (glass breakage or frame damage)

e) EMC and surge protection (can cause surges and Bypass diode damages)

Planning mistakes 4

Page 5: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

Plan your solar plant w/o shadow (12PM on the shortest day of the year (Dec/21))!

a) Shadowing (1) 5

Page 6: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

Plan your solar plant w/o shadow (12PM on the shortest day of the year (Dec/21))!

a) Shadowing (2) 6

Page 7: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

Plan your solar plant w/o shadow (12PM on the shortest day of the year (Dec/21))!

a) Shadowing (3) 7

Page 8: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

Connect all panels together which are in one horizontal temperature zone!

b) Temperature Zones 8

Page 9: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

Optimize the string layout aiming for:

• matching string lengths for various strings (same string length for all strings)

• horizontal or vertical layout for a good mounting solution

• inclination should be >10°to effectively remove dirt (self cleaning effect)

• leave sufficient space between the panels for thermal expansion

c) Layout of the panels 9

Page 10: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

Check for a suitable mounting solution according to the snow load zone:

• for a higher snow load zone (Bavarian forest), a higher mechanical load must be chosen

• Installation Manual p. 9

• Modules should not be installed to narrow to roof-top limits

• mounting surface; >15m space between mounting structures

d) Snow Load and Wind load 10

Page 11: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

Always do not separate the plus pole and the minus pole on distance as it creates Electrical fields!

e) EMC and surge protection 11

Page 12: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

2. Common mistakes in installing a PV system

12

Page 13: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

a) Mounting systems (glass breakage)

b) Loose cables and connectors (connectors burnt)

c) Grounding and Earthing (equipotential)

d) Dirty panels

e) Inverter dimensioning (performance issues)

Installation mistakes 13

Page 14: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

a) Mounting systems 14

Page 15: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

b) Loose cables and connectors 15

Page 16: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

c) Grounding and Earthing 16

Page 17: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

d) Dirty panels 17

Page 18: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

e) Inverter dimensioning 18

• For Germany, a typical dimensioning is DC/AC: 110...115% depending on orientation, installation type, inverter, heat dissipation

• Always double-check with the inverter manufacturer sizing tool if the string length and the dimensioning is done properly!

Page 19: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

3. Consequences for Claim Management

19

Page 20: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

Planning & Installation mistakes 20

• Influences on Performance:

– dirty panels cause up to 10% losses

– wrong string connections (too short, too long) cause around 1...5% losses

– shadowing can cause up to 50% losses

– a wrong panel layout (with temperature zones) can cause around 1...10% losses

– loose connectors can cause up to 5% losses

Page 21: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

Planning & Installation mistakes 21

• Influences on Bypass diode:

– missing surge protection can cause Bypass diode damages

– permanent shading can cause Bypass diode damages

Page 22: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

Suntech confidential

Planning & Installation mistakes 22

• Further Influences:

– Glass breakage: too tight mounting solutions can cause glass breakage

– Hot Spots: permanent dirt on the panel has not been cleaned and can cause hot spots

– Isolation issues: inconsistent grounding in the field can cause isolation issues with the inverter and the panels

Page 23: 20111010 gcs training wuxi   common mistakes in planning and installation - v02

THANK YOU!

October 2011Andreas Iliou Technical Customer Service Engineers Germany