7/30/2019 2011 Transforming the Tube
1/35
Transforming the Tube1 March 2011
Mike BrownManaging Director,
London Underground & London Rail
CILT
7/30/2019 2011 Transforming the Tube
2/35
London
World City: Culture; Finance; Trading Hub connecting Asia, Europe, US London helps the UK to prosper
London Underground Makes it Work Pivotal role in UKs transport system
7/30/2019 2011 Transforming the Tube
3/35
Customer satisfaction has grown...
CSS Quarterly results (%) 90/91-10/11
63
65
67
69
71
73
75
77
79
81
Chancery Laneincident & restoration
7/7 Bombings
Summer heat waves
7677
79 7980
8.17.8
6.66.4
5.85
6
7
8
9
10
11
12
13
68
70
72
74
76
78
80
2006/07 2007/08 2008/09 2009/10 2010/11YTD
ExcessJourney
Time(mins)
CustomerSatisfactionSurvey
7/30/2019 2011 Transforming the Tube
4/35
. . . and traffic growth has resumed . . . Employment is the key driver of
LU demand
But growing events traffic/ Withmore than a billion journeysmade each year, the Tube is keyfor the achievement of theTransport Strategy (anothermillion pass/day forecast by2020)
... over a billionjourneys a year
2010/11 forecast to be busiest year despite recession and
weekend closures to system
-8%-6%-4%-2%0%2%4%6%8%10%
40
50
60
70
80
90
100
07/08
P3
07/08
P5
07/08
P7
07/08
P9
07/08P
11
07/08P
13
08/09
P2
08/09
P4
08/09
P6
08/09
P8
08/09P
10
08/09P
12
09/10
P1
09/10
P3
09/10
P5
09/10
P7
09/10
P9
09/10P
11
09/10P
13
10/11
P2
Percentagechangeyear-on-
year
Pas
sengerJourneys(m)
PJs moving average 3 periods % change year-on-year
7/30/2019 2011 Transforming the Tube
5/35
2012 Olympic & Paralympic Games
7/30/2019 2011 Transforming the Tube
6/35
Our Heritage
.
.
.
7/30/2019 2011 Transforming the Tube
7/35
7
Oldest Underground system in the world More passengers then ever before
o 16% rise in seven years; 40% in 15 years
o Over90 million journeys made during the four weeksbefore Christmas a new record
Running more service than ever before
o 70 million train km a year, 27% increase over 15 years
Rebuilding every part of the network one of greatestengineering challenges in the world
Managing fallout of PPP collapse, reducing PPP-eradisruption
Bringing staffing structures up to date
Challenge
7/30/2019 2011 Transforming the Tube
8/35
8
Keeping London Moving
WhilstTransforming the Tube
7/30/2019 2011 Transforming the Tube
9/35
9
Transforming the Tube
7/30/2019 2011 Transforming the Tube
10/35
Ageing line side assets
7/30/2019 2011 Transforming the Tube
11/35
Legacy lever frames andrelay racks
7/30/2019 2011 Transforming the Tube
12/35
Current Signalling Asset Condition
Signalling dates to1935-40
Control roomupgrades 1950-1980
New components nowunavailable
System is fail safe But fails too often
Infrastructure wellbeyond economic life
1940s track circuit capacitor
7/30/2019 2011 Transforming the Tube
13/35
Trains: Current Asset Condition
Metropolitan Line 1960
Oldest UK passenger fleet
Intense maintenance regime
Circle/Hammersmith & City
Lines 1969
Trains are in an increasingly
poor stateAt six cars, limit the line capacity
and demand (on aged asset
base) is growing...
7/30/2019 2011 Transforming the Tube
14/35
Kilometres operated exclude strike days
Kilometres operated in periods 11-13 2010/11 are based on forecast.
LU Performance
7/30/2019 2011 Transforming the Tube
15/35
15
Customer satisfaction has increased from 76 points to80 points in five years (according to independent
customer satisfaction survey)
The impact that incidents have on customer journey
time has reduced by over 30% since 2007
Asset failures as the cause of incidents have declined
by 50% since 2003/04
Customer satisfaction and reliability
7/30/2019 2011 Transforming the Tube
16/35
Underlying investment needs stillpresent, long term planning still
required
Metronet now integrated with LU;Tube Lines acquired by TfL in
June 2010
Future Investment and the PPP/PFI story
Amey continues to provide
management and maintenanceservice for Jubilee, Northern &Piccadilly lines
PPP benefits of benchmarking andperformance management
retained
Management energies now centredon efficient delivery rather than
PPP contract regime
7/30/2019 2011 Transforming the Tube
17/35
7/30/2019 2011 Transforming the Tube
18/35
LU Investment Programme to 17/18(including Tube Lines capital)
7/30/2019 2011 Transforming the Tube
19/35
19
1969:Worlds first Automatic RailwayNow:600,000 passengers/day
New 47 x 8 Car 09TS Fleet with onboard
signalling (supplied by Bombardier and
Invensys)43 Trains (Peak) 31 Trains (Off-Peak)First automatic upgrade in worldPower, depot and many other enablingworks
Now 24 trains (new) in service
Victoria Line Upgrade Jubilee Line Upgrade
21%i
ncreasein
capacity
33%i
ncreasein
capacity
Thales S40
movingblock
AutomaticSignalingSystem
63 trains7th car
Power, depotand manyotherenablingworks
7/30/2019 2011 Transforming the Tube
20/35
20
New Signalling
Now 24 trains (new) in service
Northern Line Upgrade
20%i
ncreasein
capacity
Original Tube Lines programme included 65weekend closures and 16 months of early
evening shut-downs. Cancelled
programme on acquisition new approach
will significantly reduce disruption;
programme to be published shortly following
conclusion of contractual discussions.
http://en.wikipedia.org/wiki/File:1995ts_at_Finchley_Central.jpghttp://en.wikipedia.org/wiki/File:1995ts_at_Finchley_Central.jpghttp://en.wikipedia.org/wiki/File:1995ts_at_Finchley_Central.jpghttp://upload.wikimedia.org/wikipedia/commons/1/15/Northern_Line.pnghttp://en.wikipedia.org/wiki/File:1995ts_at_Finchley_Central.jpg7/30/2019 2011 Transforming the Tube
21/35
Automating the most complexmetro in the world
21
0
1
2
3
4
5
6
7
8
9
10
ComparativeCom
plexity
Most complex Metro in the world
850,000 passengers daily26% of LU total
Makes up 40% of LU network
Huge increase in capacityMet 27% / Dist 24% / C&H 65%
32tph in central section (27 now) Contract award in soon. Two bidders left
1395 cars: 15% more than now
Air-conditioned trains, LUs first
On order and being delivered
Major depot, power, platformlengthening works
Paddington-Farringdon isworlds oldest underground
railway (1863) Much of upgrade cost is
actually renewal: Trains up to 50 years old (A
Stock) Signalling some parts from
1920s
S S k i i
7/30/2019 2011 Transforming the Tube
22/35
S-Stock now in passenger service
(Bombardier supplied)
22
7/30/2019 2011 Transforming the Tube
23/35
Stations
23
270 stations, most over 100 yearsold
Bottlenecks Especially after line upgrades
Kings Cross St Pancras complexthought to be worlds largest land
transport interchange
Victoria
Major Congestion Relief schemes
Some complete; more underway
Critical for Crossrail at several
locations Large population of new assets
Tunnels, L&E, HVAC, comms
Kings Cross St Pancras newNorthern Ticket Hall (completed)
Victoria - North ticket hall entranceBressenden Place (2017-18)
Tottenham Court Road (2015-17)
7/30/2019 2011 Transforming the Tube
24/35
Future standard deep tube train EVO
7/30/2019 2011 Transforming the Tube
25/35
Sustainable deep tube renewalsLine Upgrade Option Costs
bn PVEnergykWh/
Pax km
BCR Air-conditioning andPassenger Facilities
Notes
ConventionalVictoria; Jubilee;
Northern (1) 1.21 0.42 1.03Air-con very difficult
due to space and
power constraints
1-2-2-1 doors
Conventional train needs
traction power upgrade, tunnel
cooling
EVO (no final decisionsyet taken on
deployment)
Bakerloo; Piccadilly;
Northern (II); Central
0.89 0.26 1.33
Some of saved powerused for air-con; fewer
bogies means more
underframe space. All
double doors, lower floor,
intercar gangways
EVO train design with reducedTraction Power infrastructure,
no tunnel cooling, lower whole
life energy and opex costs for
broadly equivalent customer
benefits
7/30/2019 2011 Transforming the Tube
26/35
Efficienciesand
Benchmarking
7/30/2019 2011 Transforming the Tube
27/35
The next decade . . .
Good result in Comprehensive Spending
Review.
Were in Commercial Public Sector Of our money, around half is farebox and half DfT grant
Have to recognise fiscal reality savings must be made
But must find a way to continue the transformationand avoid another cycle of deep decline Clear correlation between London transport infrastructure and service
improvements and economic growth
Strategy: do more for less Significant productivity improvements in capital and operational
expenditure.
Economically and environmentally sustainable future deep tube
upgrades
7/30/2019 2011 Transforming the Tube
28/35
Clear approvals & acceptance
procedures
More efficient delivery, through:
NewLU
ContractApproach
Standards simplification
Rule book flexibility (already done
for Radio)LU responsible for risks it is best
placed to manage
Better Management of SupplyChain
7/30/2019 2011 Transforming the Tube
29/35
Benchmarking
Two aspects cost and approach Costusing benchmarking to drive cost and challenge why,
why, why e.g. resignalling cost/track km, track cost/km, stationcost /per square metre.
Approach learning from the best and implementing on LondonUnderground e.g. resignalling with minimal closures,visualisation techniques, integrated programme teams
The four new areas of work that will incorporate this: Track
Sub Surface Upgrade
Station Capacity
London Rail
7/30/2019 2011 Transforming the Tube
30/35
30
London Overground
Orbital overground rail network
East London phase 1 completed
North London signalling upgrade/capacityimprovements
New fleet
LOROL best train operator last month
7/30/2019 2011 Transforming the Tube
31/35
31
Incremental growth/extension
Stratford International
3 car trains
Olympic challenges
Dockland Light Railway
7/30/2019 2011 Transforming the Tube
32/35
32
Trams
New trams required
Performance improvement
Safety improvement
7/30/2019 2011 Transforming the Tube
33/35
Summary
Upgrades driven by asset condition AND demand
Key to London and UK economy
Delivery record (milestones, budget scope) so farvery good across trains, infrastructure andsignalling but Jubilee line
Must increase and improve pace of delivery and
embed further capital and operating efficiencies
7/30/2019 2011 Transforming the Tube
34/35
Transforming theTube for London
7/30/2019 2011 Transforming the Tube
35/35