Public Works and Transportation Committee April 27, 2011 2011-2016 Proposed Highway Improvement Program 1
Feb 24, 2016
1Public Works and Transportation Committee
April 27, 2011
2011-2016Proposed Highway
Improvement Program
2
Management philosophy sets system priorities:
1. Preservation2. Modernization3. Expansion
2011-2016 Five Year Highway Improvement Program
3
Developing a set of projects ARGUS Pavement Management Software
Keeping tabs on the system Asset Inventories
$1.6 billion to build
Priority One: Preservation
4
ARGUS Pavement Management System……
……Today is an introduction to ARGUS
Developing the Project Set
5
Make cost effective decisionsFor given 5 year budget levels:
Where repairs are needed
What repair strategies to use
When the repairs should be done
Pavement Management Goal
6
County highway databaseAutomated pavement testingRepair strategies with costsPavement aging predictionOptimization program
Pavement ManagementSystem Components:
7
Contains information on…
Surface type
Surface width
Section area
Traffic volumes
Percentage of trucks
County Highway Database
8
About 848 lane miles in system
County is divided into quadrants
One quadrant is tested each year
Entire county is covered in four years
Automated Pavement Testing
9
First: Laser Road Surface Tester (RST)
measures…
Cracking
Rutting
Ride quality
Automated Pavement Testing
10
Automated Pavement Testing
Second: Dynaflect deflection tester measures…
Strength and condition of pavement
Strength and condition of subgrade
11
Two Groups of Roadway Priorities:(starting with 2012-2016 program analysis)
Four lane roads - 53 milesTwo lane roads - 242 miles
Repair Strategies and Costs
12
Four resurfacing strategiesThree “3R” strategiesThree reconstruction strategiesAssociated per-square-yard costs
Repair Strategies and Costs
13
Pavement Aging Prediction Costs
14
Pavement Management System does…
Assess the present condition of the systemEstimate future road conditionsIdentify and rank road projectsMaximize the condition of the system
within the given budget
ARGUS Summary
15
Pavement Management System does not…
Replace professional judgmentProvide certain detailed project-specific
information
ARGUS Summary …
16
Started in 1986System condition has improved from a
rating of 68 to 78 (on 100 scale)
Area of backlog and failing pavement has
been reduced from 55% to 15%
LCDOT ARGUS results
17
The following charts to appear in Section 2 Preservation Projects
2011 – 2016Proposed Highway Improvement Program
18
2011 Traffic Volumes
19
Definitions of Pavement Condition
20
Current Pavement Condition = 78
21
2011 Pavement Conditions
22
ARGUS optimizes improvements
23
Multiple treatments evaluated
24
System Recommendations
25
System Preservation Projects 2012-2016
26
2012 ProjectsStreet Name From To Project Type
Buffalo Grove Road Pavement Change Lake Cook Road Reconstruction
Buffalo Grove Road At Sandalwood Road Resurfacing
Deerfield Parkway Busch Parkway Barclay Boulevard Resurfacing
Kenosha Road 9th Street IL Route 173 Resurfacing
Lewis Avenue Russell Road 9th Street Resurfacing
Lewis Avenue 9th Street North of 21st Street Resurfacing
Lewis Avenue Wadsworth Road Beach Road Resurfacing
Lewis Avenue Beach Road Everett Street Resurfacing
Lewis Avenue Everett Street York House Road Resurfacing
Petite Lake Road Fairfield Road IL Route 83 Reconstruction
Quentin Road Old McHenry Road IL Route 22 Resurfacing
27
2013 ProjectsStreet Name From To Project Type
Darrell Road IL Route 176 Riverwalk Lane Resurfacing
Delany Road 21st Street Wadsworth Road Resurfacing
Dilleys Road Wadsworth Road Stearns School Road Resurfacing
Dilleys Road Stearns School Road IL Route 132 Resurfacing
Greenwood Avenue Golf Road Sheridan Road Resurfacing
Monaville Road Cedar Lake Road IL Route 83 Resurfacing
Rollins Road Washington Avenue Wilson Road Resurfacing
Rollins Road Wilson Road Fairfield Road Resurfacing
Sunset Avenue IL Route 131 Golf Road Resurfacing
Wadsworth Road Dilleys Road CP Railroad Tracks Resurfacing
28
2014 ProjectsStreet Name From To Project Type
Center Street IL Route 83 US Route 45 Resurfacing
Fairfield Road Petite Lake Road IL Route 132 Reconstruction
Lewis Avenue Glen Flora Avenue IL Route 132 Reconstruction
Midlothian Road Winchester Road IL Route 176 Resurfacing
Pulaski Drive IL Route 131 Sheridan Road Resurfacing
29
Street Name From To Project Type
21st Street IL Route 131 Kenosha Road Resurfacing
9th Street Kenosha Road Lewis Avenue Resurfacing
Cedar Lake Road IL Route 134 IL Route 120 Reconstruction
Deep Lake Road Grass Lake Road Gelden Road Resurfacing
Deep Lake Road Gelden Road IL Route 132 Resurfacing
Kilbourne Road Wisconsin State Line Russell Road Resurfacing
Petite Lake Road IL Route 59 Fairfield Road Reconstruction
Russell Road Kilbourne Road IL Route 131 Resurfacing
Sand Lake Road IL Route 132 US Route 45 Resurfacing
Washington Street UP Railroad Bridge IL Route 131 Resurfacing
2015 Projects
30
Street Name From To Project Type
Deep Lake Road North Avenue IL Route 173 Resurfacing
Hunt Club Road IL Route 173 Wadsworth Road Resurfacing
Lewis Avenue Dugdale Road IL Route 137 Resurfacing
2016 Projects
31
Pavement and bike facilities, guardrailBridges and railroad crossingsSignals and signsDrainage and stormwater facilitiesMore…
Keeping Tabs on the System:Asset Inventories
32
Program resurfaces about 9 miles per year
33
Many roads initially built in the 1950s
34
Inventory: Lane Miles
35
Age of Highway Bridges
36
Age of Bridge Deck Surface
37
Age of Bike and Pedestrian Bridges
38
Bridges: Sufficiency Ratings
39
Stormwater Management Facilities
40
By the NumbersInventory: Non-Pavement Assets
14,226
Storm sewer structures
544 Culverts
183 Miles of storm sewer pipe
18,577
Feet of fencing
9,058 Feet of retaining wall
51 Miles of 4’ paved shoulder
18 Miles of guardrail
April 2011
41
Inventory: Signs
42
Inventory: Railroad Crossings
43
Inventory: Signal Controllers
44
Developing a set of projectsARGUS Pavement Management Software
Keeping tabs on the systemAsset Inventories
Next Program Presentation:Priority Two – System ModernizationPriority Three – System Expansion
Priority One: Preservation