    Mike GrabillMaintenance & TAR Programme Manager

    Nov, 2010TURNAROUND - CNRL 1

  • 8/12/2019 2010 TAR Presentation - Calculations

    2/49

    Resources - People

    Planning & Scheduling

    Safety Contract Strategy

    Information contained herein was taken from a study conducted by the

    Maintenance and Turnaround Group (2009-2010)

  • 8/12/2019 2010 TAR Presentation - Calculations

    3/49

    Nov, 2010TURNAROUND - CNRL 3

    Prior To Shutdown, When Does The Hiring Of

    Workers Begin?

    Recordable ncident RateLess Than 2 Weeks Before 0.48

    Two To Six Weeks Before 0.12

  • 8/12/2019 2010 TAR Presentation - Calculations

    4/49

    Nov, 2010TURNAROUND - CNRL 4

    Where Do Workers Come From?

    Recordable ncident RateAvailable Workers Not Familiar With The Work 1.26

    Transferred Workers Familiar With The Work 0.37

  • 8/12/2019 2010 TAR Presentation - Calculations

    5/49

    Nov, 2010TURNAROUND - CNRL 5

    Was Software Used To Schedule The TA?

    Recordable ncident RateNo 2.14

    Yes 0.22

  • 8/12/2019 2010 TAR Presentation - Calculations

    6/49

    Nov, 2010TURNAROUND - CNRL 6

    What Unit Of Time Was Used On Project Schedule?

    Recordable ncident RateDays 0.91

    Shifts 0.64

    Hours 0.35

  • 8/12/2019 2010 TAR Presentation - Calculations

    7/49Nov, 2010TURNAROUND - CNRL 7

    Combined: Worker Familiarity &

    Scheduling By The Hour

    Recordable ncident RateNot Familiar, Not Hours 1.15

    Familiar Or Scheduled By Hours 0.88

    Familiar & Scheduled By Hours 0.21

  • 8/12/2019 2010 TAR Presentation - Calculations

    8/49Nov, 2010TURNAROUND - CNRL 8

    Days Worked Each Week

    Recordable ncident Rate

    7 Days 0.96

    6 Days 0.56

  • 8/12/2019 2010 TAR Presentation - Calculations

    9/49Nov, 2010TURNAROUND - CNRL 9

    Typical Shutdown Duration

    Recordable ncident Rate

    4 To 6 Weeks 1.29

    Less Than 4 Weeks 0.61

  • 8/12/2019 2010 TAR Presentation - Calculations

    10/49Nov, 2010TURNAROUND - CNRL 10

    Combined:

    Shutdown Duration & Days Worked Each Week

    Recordable ncident RateAt Least 4 Weeks At 7 Days Per Week 1.34

    Less Than 4 Weeks & 6 Days Per Week 0.34

  • 8/12/2019 2010 TAR Presentation - Calculations

    11/49Nov, 2010TURNAROUND - CNRL 11

    Crew Size

    Recordable ncident RateOver 12 Workers 1.32

    7 Or Less 0.55

  • 8/12/2019 2010 TAR Presentation - Calculations

    12/49Nov, 2010TURNAROUND - CNRL 12

    Shutdowns, Turnarounds & Outages With Safety

    Incentive Contracts

    Recordable ncident Rate

    No Contractual Safety Incentive 1.03

    Fee-Impacted Safety Performance 0.61

  • 8/12/2019 2010 TAR Presentation - Calculations

    13/49Nov, 2010TURNAROUND - CNRL 13

  • 8/12/2019 2010 TAR Presentation - Calculations

    14/49

    Nov, 2010TURNAROUND - CNRL 14

    WORK SCOPE DEVELOPMENT IS ONE

    OF THE KEY ELEMENTS IN THE

    TURNAROUND PROCESS:

    Safety

    DurationExecution strategy

    Future Unit availability

    Turnaround frequency

  • 8/12/2019 2010 TAR Presentation - Calculations

    15/49

    Nov, 2010TURNAROUND - CNRL 15

    WORK SCOPE DEVELOPMENT IS

    THE PROCESS:

    Identifying mechanical jobs

    Process items

    Project work

  • 8/12/2019 2010 TAR Presentation - Calculations

    16/49

    Nov, 2010TURNAROUND - CNRL 16

    REASONS TO EXCLUDE WORK ITEMS :

    More effective and efficient to perform

    work outside of the turnaround

    Additional supervision and overhead cost

  • 8/12/2019 2010 TAR Presentation - Calculations

    17/49

    Nov, 2010TURNAROUND - CNRL 17

    REQUIREMENTS OF A JOB REQUEST:

    Have at least one sponsor

    Screened and challenged

    Support the business objective

    Approved by the unit turnaround team

  • 8/12/2019 2010 TAR Presentation - Calculations

    18/49

    Nov, 2010TURNAROUND - CNRL 18

    PRIMARY SOURCES OF WORK:

    Previous turnaround summary reports

    Work order backlogs

    Inspection Engineering

    Operations

    Regulatory inspections

    Process improvement projectsUnit shutdown and startup preparation

  • 8/12/2019 2010 TAR Presentation - Calculations

    19/49

    Nov, 2010TURNAROUND - CNRL 19

    MILESTONE CHART FOR SCOPE

    DEVELOPMENT:

    Identify sources of information

    Date needed and why

    Establish and communicate a freeze date

  • 8/12/2019 2010 TAR Presentation - Calculations

    20/49

    Nov, 2010TURNAROUND - CNRL 20

    ADDITIONAL WORK PROCEDURES:

    Job cost / Manpower impact

    Job duration/Impact on schedule

    Job category

    Management approval

  • 8/12/2019 2010 TAR Presentation - Calculations

    21/49

    Nov, 2010TURNAROUND - CNRL 21

    MAJOR SCOPE CHANGES

    INCREASE COST:

    Increase planning cost

    Engineering cost

    Material cost

    Manpower cost

  • 8/12/2019 2010 TAR Presentation - Calculations

    22/49

    Nov, 2010TURNAROUND - CNRL 22

    THE WORK SCOPE HAS THE LARGEST

    IMPACT ON TURNAROUND:

    Cost

    Unit down time

    Loss profit opportunity

  • 8/12/2019 2010 TAR Presentation - Calculations

    23/49

    Nov, 2010TURNAROUND - CNRL 23

    MAJOR KEYS FOR A SUCCESSFUL

    TURNAROUND:

    Good scope development

    Schedule

    Good extra work process

    Buy-in from all stakeholder groups

  • 8/12/2019 2010 TAR Presentation - Calculations

    24/49

    Nov, 2010TURNAROUND - CNRL 24

  • 8/12/2019 2010 TAR Presentation - Calculations

    25/49

    Long Range Planning

    Short Term Planning

    Planning and Scheduling during the Turnaround. Post Turnaround

    Nov, 2010TURNAROUND - CNRL 25

  • 8/12/2019 2010 TAR Presentation - Calculations

    26/49

    Coordination with upstream and downstream

    Materials Purchasing

    Industry economics

    Set Turnaround Budget (Based on historical spend

    and known work)

    Integrate Capital Projects

    Develop Key Performance Indicators

    Contracting Strategies

    Develop Work Scope Criteria and Responsibilities

    Nov, 2010TURNAROUND - CNRL 26

  • 8/12/2019 2010 TAR Presentation - Calculations

    27/49

    Risk rank Turnaround jobs Detailed work scopes and estimates

    Determine the length of the outage

    Detailed schedule including: Operations turnover of equipment

    Pre/Post Turnaround

    Turnaround Execution

    Detailed field logistics (Where to put trailers, laydown areas,

    etc.) Organization structure for Turnaround execution

    Nov, 2010TURNAROUND - CNRL 27

  • 8/12/2019 2010 TAR Presentation - Calculations

    28/49

    Planning Track and forecast cost

    Provide field support for job scope, contract issues and extras

    Scheduling

    Track Critical Path Track status of equipment

    Project completion date

    Nov, 2010TURNAROUND - CNRL 28

  • 8/12/2019 2010 TAR Presentation - Calculations

    29/49

    Modify tracking steps based on actual information

    Review methodology used to determine if the work could

    have been done more efficiently

    Check logistics plans and other peripheral components for

    needed modificationsHold critique meeting with all areas involved to determine

    areas for improvement

    Nov, 2010TURNAROUND - CNRL 29

  • 8/12/2019 2010 TAR Presentation - Calculations

    30/49

    Nov, 2010TURNAROUND - CNRL 30

  • 8/12/2019 2010 TAR Presentation - Calculations

    31/49

    Client

    Award Contract

    Contractor Several Weeks In Advance

    Nov, 2010TURNAROUND - CNRL 31

  • 8/12/2019 2010 TAR Presentation - Calculations

    32/49

    Clients Safety Procedure Contractor To HaveEnough Time To Know

    And Understand

    Nov, 2010TURNAROUND - CNRL 32

  • 8/12/2019 2010 TAR Presentation - Calculations

    33/49

    Clients Operations Contractor To InterfaceWith Operations

    Nov, 2010TURNAROUND - CNRL 33

  • 8/12/2019 2010 TAR Presentation - Calculations

    34/49

    Client To HaveDefinitive Scope

    ContractorsSupervision To Be

    Onboard In Advance

    Nov, 2010TURNAROUND - CNRL 34

  • 8/12/2019 2010 TAR Presentation - Calculations

    35/49

    Client

    Contractor To Perform All

    Of The Work

    Nov, 2010TURNAROUND - CNRL 35

  • 8/12/2019 2010 TAR Presentation - Calculations

    36/49

    Client To Establish Contractors View

    Nov, 2010TURNAROUND - CNRL 36

  • 8/12/2019 2010 TAR Presentation - Calculations

    37/49

    Nov, 2010TURNAROUND - CNRL 37

  • 8/12/2019 2010 TAR Presentation - Calculations

    38/49

    Nov, 2010TURNAROUND - CNRL 38

    1. Setting Contractor Milestones

    2. Setting Inspection Milestones

    3. Critical Path Management &

    Productivity

  • 8/12/2019 2010 TAR Presentation - Calculations

    39/49

    Nov, 2010TURNAROUND - CNRL 39

    1. Team to Learn Scope Early

    2. Verification of Onsite Materials

    3. Identification of Potential Conflicts

    4. Review of Rigging Plans and Safety

    Procedures

  • 8/12/2019 2010 TAR Presentation - Calculations

    40/49

    Nov, 2010TURNAROUND - CNRL 40

    Assuring Compliance

    1. Supervision to Review Written Policy

    2. Pre-Turnaround Permit Meeting with Supervision

    3. Pre-Job Walkthrough ( Foreman & Permit Issuer)

    4. Mutual Understanding

  • 8/12/2019 2010 TAR Presentation - Calculations

    41/49

    Nov, 2010TURNAROUND - CNRL 41

  • 8/12/2019 2010 TAR Presentation - Calculations

    42/49

    CONTRACTOR EMPLOYER

    RESPONSIBILITIES

    THE CONTRACT EMPLOYER SHALL ASSURE THATEACH CONTRACT EMPLOYEE IS TRAINED IN THE

    WORK PRACTICES NECESSARY TO SAFELY PERFORM

    HIS/HER JOB.

    Nov, 2010TURNAROUND - CNRL 42

  • 8/12/2019 2010 TAR Presentation - Calculations

    43/49

    EMPLOYER RESPONSIBILITIES

    THE EMPLOYER SHALL PERIODICALLY EVALUATE

    THE PERFORMANCE OF CONTRACT EMPLOYERS IN

    FULFILLING THEIR OBLIGATIONS.

    Nov, 2010TURNAROUND - CNRL 43

  • 8/12/2019 2010 TAR Presentation - Calculations

    44/49

    ENSURE THAT CRAFTSPERSONS ARESKILLED IN THIS REGION

    MEET PROCESS SAFETY MANAGEMENT

    Nov, 2010TURNAROUND - CNRL 44

  • 8/12/2019 2010 TAR Presentation - Calculations

    45/49

    SYSTEM NEEDS TO BE COMMON

    OWNERSCONTRACTORS

    CRAFTSPERSONS

    Nov, 2010TURNAROUND - CNRL 45

  • 8/12/2019 2010 TAR Presentation - Calculations

    46/49

    IMPLEMENT A STANDARD SKILL

    ASSESSMENT PROGRAM

    APPRENTICESHIP PROGRAM

    Nov, 2010TURNAROUND - CNRL 46

  • 8/12/2019 2010 TAR Presentation - Calculations

    47/49

    Nov, 2010TURNAROUND - CNRL 47

  • 8/12/2019 2010 TAR Presentation - Calculations

    48/49

    Q & A SUMMARYEMAILED LATER

    CRITIQUE FORM

    FILL OUT

    ADDITIONAL COMMENTS

    RETURN BEFORE LEAVING!

    Nov, 2010TURNAROUND - CNRL 48

  • 8/12/2019 2010 TAR Presentation - Calculations

    49/49

    SAFETY

    ENGINEERING CHG/SCOPE CREEP

    CONTRACTING STRATEGIES

    COST CONTROL DOCUMENT CONTROL

    OTHER TOPICS

    Q1 2011