Top Banner

of 12

2010 - Scl Bskyb v Eds - 8 March

Apr 07, 2018

Download

Documents

lucyiswired
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    1/12

  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    2/12

    BSkyB v EDS

    Presentation to SCL8 March 2010

    Jeremy Storey QC

  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    3/12

    Key Dates

    June 2000: EDS Presentation, Response to ITT, Bid

    July 2000: EDS selected, Work began

    9 August 2000: Letter of Intent signed (binding)

    30 November 2000: Prime Contract signed (Timeand Materials)

    16 July 2001: Letter of Agreement (compromise)

    31 July 2001: Contractual date for Live in One Hall

    6 March 2002: EDs removed as SI and Sky took over

    26 March 2002: Memorandum of Understanding(non-binding)

  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    4/12

    Summary of Claims

    Damages for deceit (alternatively negligentmisrepresentation) inducing Sky to select EDS andsubsequently enter into the Letter of Intent (August2000) and Prime Contract (November 2000)

    Damages for negligent misrepresentation inducingSky to enter into the Letter of Agreement (July 2001)

    Damages for Breach of Contract

  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    5/12

    Deceit The Representation Proved

    EDS represented:that they had carried out a properanalysis of the amount of elapsed time needed tocomplete the initial delivery and go live of thecontact centre.

    EDS represented: that they held the opinion that,and had reasonable grounds for holding the opinionthat, they could and would deliver the project withinthe timescales referred to in the Response and

    subsequently the Contract.

  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    6/12

    What the Judge Found EDSCaveats

    The ITT Response was based on what it knew at thetime

    The plan was high level and would be refined afterfurther analysis

    Project planning was on-going and timescales wereindicative

    Events between ITT Response and Contract madeprevious representations immaterial

  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    7/12

    What the Judge Found - Estimating

    Four stages of estimating:Scope: What work has to be done

    Effort: Calculation of resources needed to performthe work

    Resourcing: Number of resources required in theperiod

    Availability of Resources

    Ramsey J at # 699:there is surprisingly littledocumentation relating to the process by which

    EDS prepared its Response

  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    8/12

    What the Judge Found -Falsity

    Plans were produced to fit the 9 month timescaleSky desired

    No attempt was made to identify work required or tosort out the resourcing implications

    EDScosting spreadsheet showed 18 developersworking on the GUI for 320 days i.e. 5,760 man days

    The 9 month plan allowed 80 days for the work i.e.76 developers

    EDS admitted falsity (no proper analysis, no

    reasonable grounds)

  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    9/12

    What the Judge Found -DishonestyNot relevant:

    Consortium Partnersviews

    Previous experience on other projects

    Other bids: AA and PWC

    Relevant:Internal Risk Lists by the Project Manager

    Red Team Review -evidence of lack of resources

    Choppingthe Plan for presentation to Client in

    October:The Plan and resources will be artificiallymanipulated...

  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    10/12

    The Corporate Mind

    Who is the fraudster?

    Are they thedirecting mind and willof Corporation?

    The individual with the relevant knowledge need notmake the representation it is enough that he/sheknows that the representation is made.

  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    11/12

    Joe Galloway

    Mastermind for EDS Response

    MD of EDSCRM Practice (part of eSolutions)

    Reported to UK Head of eSolutions, Barry Yard (notcalled)

    Yard reported to EMEA Head of eSolutions, Steve

    Leonard

    eSolutions: 1 of EDS4 practice areas, providing

    consulting services in process and technologysolutions (implementation, integration and projectmanagement)

  • 8/6/2019 2010 - Scl Bskyb v Eds - 8 March

    12/12

    Themes and Conclusions

    No change to the law of deceit no need to panic!

    Having bid procedures is one thing; following them isanother

    Check employee CVs

    Review recruitment proceduresRe-train Sales Team

    Dont let Sales act independently of Business

    Documentation preservation (especially analysis oftime planning, sequencing, resourcing and cost)