2010 Census 2010 Census Field Data Collection Field Data Collection Automation (FDCA) Automation (FDCA) Industry Day August 27, 2004 Census Bureau Auditorium
Dec 21, 2015
2010 Census2010 Census
Field Data Collection Automation Field Data Collection Automation (FDCA)(FDCA)
Industry DayAugust 27, 2004
Census Bureau Auditorium
2
AgendaAgenda
1:00 WelcomeMike Palensky, Chief, Acquisition Division
1:05 Safety While in the Census Bureau – Carolyn Cumberland, Safety Manager, Human Resources
Division1:10 Field Data Collection: Vision
Preston Jay Waite, Associate Director for Decennial Census1:40 Field Data Collection: Automation
Barbara LoPresti, Chief, Technologies Management Office2:10 FDCA: Acquisition Approach
Michael Palensky, Chief, Acquisition Division2:30 Question & Answer Forum3:00 Conclusion – Mike Palensky
3
AgendaAgenda
1:00 WelcomeMike Palensky, Chief, Acquisition Division
1:05 Safety While in the Census Bureau – Carolyn Cumberland, Safety Manager, Human Resources
Division1:10 Field Data Collection: Vision
Preston Jay Waite, Associate Director for Decennial Census1:40 Field Data Collection: Automation
Barbara LoPresti, Chief, Technologies Management Office2:10 FDCA: Acquisition Approach
Michael Palensky, Chief, Acquisition Division2:30 Question & Answer Forum3:00 Conclusion – Mike Palensky
4
AgendaAgenda
1:00 WelcomeMike Palensky, Chief, Acquisition Division
1:05 Safety While in the Census Bureau – Carolyn Cumberland, Safety Manager, Human Resources
Division1:10 Field Data Collection: Vision
Preston Jay Waite, Associate Director for Decennial Census1:40 Field Data Collection: Automation
Barbara LoPresti, Chief, Technologies Management Office2:10 FDCA: Acquisition Approach
Michael Palensky, Chief, Acquisition Division2:30 Question & Answer Forum3:00 Conclusion – Mike Palensky
5
Field Data Collection: Vision
2010 Census
Preston Jay WaitePreston Jay Waite
Associate Director for Decennial CensusAssociate Director for Decennial Census
6
What It Took To Conduct What It Took To Conduct Census 2000Census 2000
Space (an estimated 5 million sq. ft. of rental space)
12 Regional Census Centers
520 Local Census Offices
Maps
Over 20 million maps
IT Systems
10 major systems and numerous secondary systems
Equipment
About 15,000 personal computers
About 1,300 servers
Over 16,000 telephone lines
Recruitment and HiringRecruited 3.5 million applicants
Hired 860,000 positions for data collection/data capture
7
Census 2000 a Great SuccessCensus 2000 a Great Success But There is Still Room for ImprovementBut There is Still Room for Improvement
We did phenomenal work in the field, but:
It was very expensive
We were drowning in paper, and
We conducted unnecessary field interviews for late mail return households
Our systems worked, but they were developed at high risk and without an established enterprise architecture
8
Lessons Learned from Census 2000Lessons Learned from Census 2000
If we want to save money in Census 2010, we must do so in the field
If we want to save money in the field, we must reduce workload, paper and people
If we want quality improvement, we must reduce operational risk in our IT systems and simplify enumerator work assignments
If we want to achieve our 2010 Census goals, operational testing of design infrastructure must continue in the decade
9
The 2010 Census Reengineering The 2010 Census Reengineering PlanPlan
Goals of the 2010 Census
Improve accuracy
Reduce risks
Contain costs
Provide more relevant data
10
Field Data CollectionField Data CollectionVision for 2010Vision for 2010
More efficient and accurate field data collection methods without sacrificing data quality
Use hand held computers (HHCs) with GPS technology for:
Determining accurate locations of housing units
Address and map updating activities
Nonresponse followup and other field data collection operations
Reduce paper data capture
Reduce NRFU workload by updating enumerator work assignments daily based on late mail returns
11
Field Data CollectionField Data CollectionPotential BenefitsPotential Benefits
Increased quality of data – GPS and embedded quality assurance
Reduction in costs for field data capture
Reduction in NRFU interviews – by providing daily updates on late mail returns
Reduced real estate costs – less space required for our 500+ temporary offices
12
Field Data CollectionField Data CollectionThe Challenges The Challenges
Reliability of technology – we only have one shot at this – it has to work
Temporary work force (average of 8 weeks)
Size of workforce limits experience level we can requireLimited time to trainDevices and software must be easy to use
QualityCan’t let technology get in the way of conducting a quality interviewHas to produce consistent results
Security - Census data must be protected under Title 13
13
Field Data CollectionField Data CollectionCosts Costs
HHCs for 500,000+ Enumerators at peak
Assume each unit of HHC will cost $300 - sound feasible?
The FDCA Contract will be One Component of Our Total Estimated Cost for Field Data Collection Automation Program
Total cost for all FDCA efforts (including HQ staff, all Field Systems, and infrastructures) - approximately $845 million
Hardware Operating Systems
GPS modules and map applications
Security
Deployment/integration
14
Where We Are NowWhere We Are Now
2004 Census Test operations are nearly complete
Preliminary data on HHCs indicate feasibility
HHC evaluations will be completed by early next year
15
AgendaAgenda
1:00 WelcomeMike Palensky, Chief, Acquisition Division
1:05 Safety While in the Census Bureau – Carolyn Cumberland, Safety Manager, Human Resources
Division1:10 Field Data Collection: Vision
Preston Jay Waite, Associate Director for Decennial Census1:40 Field Data Collection: Automation
Barbara LoPresti, Chief, Technologies Management Office2:10 FDCA: Acquisition Approach
Michael Palensky, Chief, Acquisition Division2:30 Question & Answer Forum3:00 Conclusion – Mike Palensky
16
Field Data Collection Field Data Collection Automation:Automation:
Program Scope for theProgram Scope for the 2010 Census2010 Census
Barbara M. LoPrestiBarbara M. LoPresti Chief, Technologies Management OfficeChief, Technologies Management Office
17
Presentation OverviewPresentation Overview
Scope of the Field Data Collection Automation (FDCA) Program
Field Data Collection Environment
FDCA Technical Challenges
18
FDCA Program Elements
Automation Support Services
Field Systems Integration and Services ManagementDevelopment, Integration, Test, Deployment, Quality Assurance,
Project Management
Data Collection andAdministrative Applications
Field Operations ControlData Collection InstrumentsAdministrative Applications
Telecom ServicesData, VoiceFixed, Mobile
Back Office ServicesEmailFile SharesDirectoriesWeb Hosts
Operations SupportDeploymentTrainingAsset ManagementSystem AdministrationHelp DeskMaintenanceDisposition
SecurityTitle 13Security Operations
Field Office Automation Equipment
PCs, Printers, PlottersLANsOffice Automation SoftwareTelephonesOther Equipment
Mobile Computing Equipment
Laptops, tablet PCs, GPS, HHCs
19
FDCA Program Elements
Automation Support Services
Field Systems Integration and Services ManagementDevelopment, Integration, Test, Deployment, Quality Assurance,
Project Management
Data Collection andAdministrative Applications
Field Operations ControlData Collection InstrumentsAdministrative Applications
Telecom ServicesData, VoiceFixed, Mobile
Back Office ServicesEmailFile SharesDirectoriesWeb Hosts
Operations SupportDeploymentTrainingAsset ManagementSystem AdministrationHelp DeskMaintenanceDisposition
SecurityTitle 13Security Operations
Field Office Automation Equipment
PCs, Printers, PlottersLANsOffice Automation SoftwareTelephonesOther Equipment
Mobile Computing Equipment
Laptops, tablet PCs, GPS, HHCs
20
FDCA Program Elements
Automation Support Services
Field Systems Integration and Services ManagementDevelopment, Integration, Test, Deployment, Quality Assurance,
Project Management
Data Collection andAdministrative Applications
Field Operations ControlData Collection InstrumentsAdministrative Applications
Telecom ServicesData, VoiceFixed, Mobile
Back Office ServicesEmailFile SharesDirectoriesWeb Hosts
Operations SupportDeploymentTrainingAsset ManagementSystem AdministrationHelp DeskMaintenanceDisposition
SecurityTitle 13Security Operations
Field Office Automation Equipment
PCs, Printers, PlottersLANsOffice Automation SoftwareTelephonesOther Equipment
Mobile Computing Equipment
Laptops, tablet PCs, GPS, HHCs
21
FDCA Program Elements
Automation Support Services
Field Systems Integration and Services ManagementDevelopment, Integration, Test, Deployment, Quality Assurance,
Project Management
Data Collection andAdministrative Applications
Field Operations ControlData Collection InstrumentsAdministrative Applications
Telecom ServicesData, VoiceFixed, Mobile
Back Office ServicesEmailFile SharesDirectoriesWeb Hosts
Operations SupportDeploymentTrainingAsset ManagementSystem AdministrationHelp DeskMaintenanceDisposition
SecurityTitle 13Security Operations
Field Office Automation Equipment
PCs, Printers, PlottersLANsOffice Automation SoftwareTelephonesOther Equipment
Mobile Computing Equipment
Laptops, tablet PCs, GPS, HHCs
22
FDCA Program Elements
Automation Support Services
Field Systems Integration and Services ManagementDevelopment, Integration, Test, Deployment, Quality Assurance,
Project Management
Data Collection andAdministrative Applications
Field Operations ControlData Collection InstrumentsAdministrative Applications
Telecom ServicesData, VoiceFixed, Mobile
Back Office ServicesEmailFile SharesDirectoriesWeb Hosts
Operations SupportDeploymentTrainingAsset ManagementSystem AdministrationHelp DeskMaintenanceDisposition
SecurityTitle 13Security Operations
Field Office Automation Equipment
PCs, Printers, PlottersLANsOffice Automation SoftwareTelephonesOther Equipment
Mobile Computing Equipment
Laptops, tablet PCs, GPS, HHCs
23
Address Canvass
Group Quarter Validation
Special Place Advance Visit
Military Advance Visit
Group Quarter Enumeration
Service Based Enumeration
Military Group Quarter Enumeration
Update/Leave
Update/Enumerate
Enumeration Hotels/Motels
Transient Night
NonResponse Followup
Coverage Followup
2010 Field Operations By 2010 Field Operations By Calendar Year QuarterCalendar Year Quarter
24
Field Operations - EnvironmentField Operations - Environment
No “startup” timeSolution must work from Day One
Staff fully productive at the end of training
Vary in Size/ScaleUrban/Rural/Mountain/Desert/Alaska/ Puerto Rico deployment
Solution must work everywhere, every time
High turnover (both office and field staff)Limited technical training
Solution must provide usability
25
FDCA - Technical ChallengesFDCA - Technical Challenges
ScalabilityEquipment deployments/dispositionsSoftware applicationsTelecommunicationsTechnical Support
RobustnessMeets requirements of numerous field operations24 hour/7 day accessibility at peakStable, proven technology – “Right the first time”Field worker equipment must function in variety of physical conditions
26
FDCA - Technical Challenges FDCA - Technical Challenges cont’dcont’d
Usability
All applications must be simple to use, intuitive
Consistent look and feel
Easy to train/support
Field worker equipment must be easily portable
Extensive reporting capability
Supportability
Standard configurations
Minimize time to resolution (minutes) and data loss
27
FDCA - Technical Challenges FDCA - Technical Challenges cont’dcont’d
Agility
Supports quick movement of equipment, software and data
Supports timely implementation of new operations or applications
Supports timely implementation of contingency plans
28
FDCA - Technical Challenges FDCA - Technical Challenges cont’dcont’d
Integration
Data collection applications (field operations control) and administrative applications (payroll, personnel)
Systems/applications with external systemsSocial Security Administration
HQ processing system
Seamless look and feel
29
FDCA - Technical Challenges FDCA - Technical Challenges cont’dcont’d
Security
Title 13 United States Code
Physical and data security meets all federal regulations, standards, policies
30
2010 Census Dress Rehearsal2010 Census Dress Rehearsal
Full and final operational test of 2010 Census design
Field operations begin Spring 2007
Requires timely delivery of Office equipment and systems connectivity (January 2007)
Administrative applications ( January 2007)Recruiting, personnel, payroll
Data collection equipment/systems/applications for Address Canvass (February 2007)
Short design/development window
31
Industry EngagementIndustry Engagement
We want ideas from Industry on how to solve the
Technical,
Logistical, and
Operational Challenges
32
AgendaAgenda
1:00 WelcomeMike Palensky, Chief, Acquisition Division
1:05 Safety While in the Census Bureau – Carolyn Cumberland, Safety Manager, Human Resources
Division1:10 Field Data Collection: Vision
Preston Jay Waite, Associate Director for Decennial Census1:40 Field Data Collection: Automation
Barbara LoPresti, Chief, Technologies Management Office2:10 FDCA: Acquisition Approach
Michael Palensky, Chief, Acquisition Division2:30 Question & Answer Forum3:00 Conclusion – Mike Palensky
33
FDCA Acquisition ApproachFDCA Acquisition Approach
Michael L. PalenskyMichael L. Palensky
Chief, Acquisition DivisionChief, Acquisition Division
FDCA Fiscal Year TimelineFDCA Fiscal Year Timeline – Industry Day – Industry Day
1/1/05
FDCARequest
forProposal
(Estimated)
FDCAContractAward
(Estimated)
LocalCensusOffices
Open forDress
RehearsalBegin
Operationsfor
DressRehearsal
Design, Develop, Integration, Test, Implement
2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
10/1/05
1st Quarter 2nd Quarter
10/1/06
FY 2006FY 2005 FY 2007
1/1/06 4/1/06 7/1/06 1/1/07 4/1/074/1/05 7/1/05
35
AgendaAgenda
1:00 WelcomeMike Palensky, Chief, Acquisition Division
1:05 Safety While in the Census Bureau – Carolyn Cumberland, Safety Manager, Human Resources
Division1:10 Field Data Collection: Vision
Preston Jay Waite, Associate Director for Decennial Census1:40 Field Data Collection: Automation
Barbara LoPresti, Chief, Technologies Management Office2:10 FDCA: Acquisition Approach
Michael Palensky, Chief, Acquisition Division
2:30 Question & Answer Forum
3:00 Conclusion – Mike Palensky
36
AgendaAgenda
2:30 Question & Answer Forum
Panelists:
Teresa Angueira, Chief, Decennial Management Division
Barbara LoPresti, Chief, Technologies Management Office
Mike Palensky, Chief, Acquisition Division
Janet Cummings, Assistant Chief for Decennial Management, Analysis, and Special Censuses, Field Division
Gail Leithauser, Assistant Chief for Geography and Data Collection, Field Division
Violeta Vazquez, Assistant Chief for Field Data Collection, Decennial Management Division
37
AgendaAgenda
1:00 WelcomeMike Palensky, Chief, Acquisition Division
1:05 Safety While in the Census Bureau – Carolyn Cumberland, Safety Manager, Human Resources
Division1:10 Field Data Collection: Vision
Preston Jay Waite, Associate Director for Decennial Census1:40 Field Data Collection: Automation
Barbara LoPresti, Chief, Technologies Management Office2:10 FDCA: Acquisition Approach
Michael Palensky, Chief, Acquisition Division2:30 Question & Answer Forum
3:00 Conclusion – Mike Palensky