8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
1/44
A Comparison of FPETool Predictions to ExperimentalA Comparison of FPETool Predictions to Experimental
Results: Comparison of Clean Agent and Sprinkler SystemResults: Comparison of Clean Agent and Sprinkler System
Performance on InPerformance on In--Cabinet Fires:Cabinet Fires:
Mark L. Robin and Eric F. Forssell
Hughes Associates, Inc.
and
Steven T. GinnGreat Lakes Chemical Corporation
Presented at:
2003 Halon Options Technical Working Conference
Sheraton Old TownAlbuquerque, New Mexico
May 13-15, 2003
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
2/44
IntroductionIntroduction
j Telco and EDP Facility Fire Protection
y Clean agents
y Automatic sprinklers
y Clean agent + Automatic sprinklery Best Protection?
y Objective
y Compare performance of clean agent and
automatic sprinkler systemsy Employ FPETool for design of test scenario
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
3/44
Automatic Sprinkler Systems:Automatic Sprinkler Systems:
j Design objective is fire controly Contain fire to room of origin
y Control ceiling temperature to avoid structural damage
y Fire extinguishment NOTprimary objective
j Fire size at system activation relatively highy Sprinkler systems employ thermal response
y Water not released until temperature at fusible link or glassbulb in excess of 135 oF
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
4/44
Automatic Sprinkler Systems:Automatic Sprinkler Systems:
Design ObjectivesDesign Objectives
- In general terms of property protection,
sprinkler systems are typically designed to
acheivefire co
ntrol...
- Fire control can be described as limiting the fire
size by decreasing the rate of heat release and
pre-wetting adjacent combustibles, while
maintaining ceiling gas temperatures so as to
avoid structural damage
NFPA Fire Protection Handbook, 19th Edition, p. 10-193.
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
5/44
Time
Heat
ReleaseRate
Fire ControlFire Control
sprinkler activation
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
6/44
Automatic Sprinkler Systems:Automatic Sprinkler Systems:
Standard Preaction SystemStandard Preaction System
j System piping charged with air under pressure
j System equipped with a supplemental detection
systemj Water held back by a preaction valve
y Operation of the supplemental detection system allows the
preaction valve to open, admitting water into the pipe
network (sprinkler still closed)
j Water discharged from pipe network when fire hasgenerated sufficient heat to activate one or more
sprinklers
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
7/44
Valve
Water supply
Controlpanel
Detector
Sprinkler head
Operation of detector trips valve
Water delivered when head T=T rating
Preaction SystemPreaction System
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
8/44
Clean Agent Suppression Systems:Clean Agent Suppression Systems:
Primary AdvantagesPrimary Advantages
j Ability to extinguish shielded, obstructed or three-
dimensional fires in complex geometries
y Clean agents are gases
y Uniform distribution throughout an enclosure
j Ability, through the use of detection, to extinguish
fires at a very early stage
y Extinguishment well before direct or indirect fire/smoke
damage occurs
j Cause no collateral damage due to agent discharge
y Are clean
y No residues
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
9/44
Heat
ReleaseRate
Time
Fire Control (Sprinklers)
Fire extinguishment(clean agent)
Clean Agent Systems:Clean Agent Systems:
Design Objective = Fire ExtinguishmentDesign Objective = Fire Extinguishment
Fire Control vs.
Fire Extinguishment
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
10/44
Time
HeatReleaseRate
sprinkler activation
clean agentsystem activation
detection
FIRE CONTROL
FIRE EXTINGUISHMENT
Clean Agent System vs. Sprinkler SystemClean Agent System vs. Sprinkler System
(Fire Extinguishment vs. Fire Control)(Fire Extinguishment vs. Fire Control)
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
11/44
Spri kler Systems Clea ge t System
Suppression agent Water Gas
Design Objective
Fire Control:
Confine fire
Control ceiling T
Fire Extinguishment
Design Objective Protect structure Protect contents of structure
Activation Sprinkler head T u 135 oF
Automatic activation following
detection (air sampling, smoke
detectors)
Fire size at activation Can be 100's of kW
Low as 0.1 kW with air
aspirating detection system
Total Flooding No. Water not three dimensional,will not fill entire enclosure Yes. Agent distributeduniformly throughout enclosure
Cleanliness
No. Water damage, smoke
damage
Yes. No residues to clean up
following extinguishment
Comparison of Sprinkler andComparison of Sprinkler and
Clean Agent SystemsClean Agent Systems
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
12/44
Comparison Testing of PreactionComparison Testing of Preaction
Sprinkler and FMSprinkler and FM--200200
SystemsSystemsj FM-200System
y Designed and installed in accordance with NFPA 2001
j Preaction Sprinkler Systemy Designed and installed in accordance with NFPA 13
j Detection/Alarm Systemsy Designed and installed in accordance with NFPA 72
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
13/44
Comparison Testing of PreactionComparison Testing of Preaction
Sprinkler and FMSprinkler and FM--200200
SystemsSystemsj Facility
y 32.8 x 32.8 x 12 foot enclosure
y 1.5 ft deep subfloor; suspended ceiling 2 ft belowdrywall ceiling
y 1/2 gypsum board over metal stud construction
y Enclosure access via two doors
y Eight polycarbonate windowsy Motorized damper system in ceiling for post-test
exhaust
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
14/44
Comparison Testing of PreactionComparison Testing of Preaction
Sprinkler and FMSprinkler and FM--200200
SystemsSystemsj FM-200Tests
y Subfloor covered in plastic to prevent leakage of agent into
subfloor
j Sprinkler Test
y Plastic formed into dike to contain water and facilitate
removal of water after testing
j All Tests
y Area 20 x 26 ft covered with floor tilesy Cabinet containing fire array and various articles of
furniture
y arranged on floor tiles
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
15/44
20 t
orth
32 t 10 in
26 t32 t 10 in
our ra er IBM abinet maller abinet
ile abinet
abinet ontaining uel rray Tables Windo
xhaust Vent (in eiling)
igure 1 hamber chematic.
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
16/44
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
17/44
Comparison Testing of PreactionComparison Testing of Preaction
Sprinkler and FMSprinkler and FM--200200
SystemsSystemsj Test Fire
y Eight sheets of 8 x 16 x 0.375 inch ABS
y
Vertically arranged in two rows of four sheetsy Mounted on all-thread rods in unistrut stand
y Fire array placed in a equipment cabinet
y Ignition: 3 mL heptane in 2 inch square pan
y Similar to plastic sheet fire test of UL 2166, UL
2127
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
18/44
1 Eight Sheets of
8 x 16 x 3/8 in
A S
76
16
16
1
7
21 38
2 in pan with
3 ml n-Heptane
Fuel ArrayFuel Array
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
19/44
0
50
100
150
200
250
300
350
400
450
500
0 100 200 300 400 500
Time, se conds
HeatR
elease,
kW
Heat Release Rate forInHeat Release Rate forIn--CabinetFireCabinetFire
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
20/44
Comparison of Preaction SprinklerComparison of Preaction Sprinkler
and FMand FM--200200SystemsSystems
Smoke Detection Systems (FM-200System)
j Fenwal AnaLASER II
y Air-sampling system, designed and installed by
distributor
y 1 inch PVC tubing main, 0.75 inch PVC branch lines
y Flow rate through system 0.0624 ft3/s
y 0.061% obscuration per foot alarm threshold
y Nine sampling holes, 11 ft spacings
y Exceeds NFPA 72 requirements
y Based on FM Loss Prevention Data Sheet 5-32 on
Electronic Data Processing Systems
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
21/44
Comparison of Preaction SprinklerComparison of Preaction Sprinkler
and FMand FM--200200
SystemsSystemsj Smoke Detection Systems (FM-200and
Sprinkler)
y
Simplex 4098 series True Alarm detectorsy Ionization and photoelectric
y Ionization: 1.3% obscuration/ft
y Photoelectric: 2.5% obscuration/ft
y Located at three air sampling points nearest fire
location
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
22/44
FMFM--200200Suppression SystemSuppression System
Designed in accordance with NFPA 2001
j 7% by volume FM-200
j Discharge time: 9.5 seconds
j Hygood Ltd cylinder
j Hygood Ltd 8-port aluminum nozzle
j orifice area 1.57 in2
j System design via Hygood Ltds design software
j 30 s delay employed from detection to system activation
j Maximum delay time allowed under recommendations of
FM Global Property Loss Prevention Sheet 5-14 on
Telecommunication Facilities
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
23/44
Preaction Sprinkler SystemPreaction Sprinkler System
Designed in accordance with NFPA 13
j Design and installation based on Ordinary Hazard
Class I
j
Nine sprinkler heads in main spacej Nine sprinkler heads above suspended ceiling
j 11 ft spacing for area coverage of 121 ft2
y Maximum spacing allowed under NFPA 13 is 15 ft
j
Recessed pendant standard response glass bulbsprinklers
y Temperature rating 155 oF
j Application density of 0.15 gpm/ft2 required
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
24/44
Preaction Sprinkler SystemPreaction Sprinkler System
Water supplyj NFPA 13 requires water supply to be adequate to supply all
sprinklers within the design area for a minimum of 60 minutes
18.2 gpm/head x 18 heads x 60 min = 19,600 gallons water
j Test facility unable to handle this quantity of water
j Water supply designed to supply the two sprinklers nearest
the fire location for a period of 30 minutes at the requireddesign flow rate of 18.2 gpm (application density 0.15 gpm/ft2)
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
25/44
Enclosure InstrumentationEnclosure Instrumentation
j Four thermocouple trees (Type K)
j Optical density
j O2
, CO, CO2
j FTIR: FM-200and HF concentrations
j Enclosure pressure
j Nozzle pressure
j
IR camera
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
26/44
Test ProcedureTest Procedurej Data acquisition commenced with ignition of heptane
below the ABS plastic array
j Room remained sealed during entire test
j FM-200 system system activated 30 s after AnaLASERII
smoke detection system went into alarm
j During preaction sprinkler system test, water supply
pump started prior to start of data acquisition
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
27/44
Input for FPETool SimulationsInput for FPETool Simulations
Input Parameter
inimum Oxygen Level
21oC
600oC
10.0
2.0
Heat Transfer Factor
Radiant fraction
ax energy loss internal
0.35
0.90
Sprinkler, NE location
Distance from center of fire (ft)
RTI (ft s)1/2
Activation temperature,oF
10.6
144
155
Sprinkler, N location
Distance from center of fire (ft)RTI (ft s) 1/2
Activation temperature,oF
11.3144
155
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
28/44
Input for FPETool SimulationsInput for FPETool Simulations
Input Parameter
Room dimensions
Ceiling height (ft)
Length (ft)
Width (ft)
8.0
32.8
32.8
Ceiling aterial
Thickness (in)Thermal conductivity (kW/mK)
Density (kg/m3)
Specific heat (KJ/kg K)
Glass fiber
0.50.00037
60
0.8
Ceiling aterial
Thickness (in)
Thermal conductivity (kW/mK)
Density (kg/m3)
Specific heat (KJ/kg K)
Gypsum board
0.5
0.00017
960
1.1
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
29/44
Heat Release Rate Required forHeat Release Rate Required for
Sprinkler ActivationSprinkler Activation
j Input
j Experimental HRR
j Location of firej Enclosure dimensions
j Location ofsprinkler heads
j Properties ofsprinkler heads
j Predict activation of NE sprinkler head at 249 seconds
j Ceiling jet temperature 249 oF
j Fire size approximately 210 kW
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
30/44
Smoke Detector Activation TimeSmoke Detector Activation Time
j Input
j Experimental HRR
j Location of fire
j
Enclosure dimensionsj Location ofsmoke detector
j FPETool: default activation temperature of 23 oF above initial T
j Predict activation of NE smoke detector at 95 seconds
j Ceiling jet temperature 93 oF
j Fire size approximately 15 kW
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
31/44
Results: FMResults: FM--200200SystemSystem
j AnaLASER II alarmed at 78 seconds from ignition
j FM-200system activated at 108 seconds from
ignition
j Fire extinguished at 125 seconds from ignition
j 7 seconds from end of system discharge
j Maximum ceiling T of 85 oF observed
j Fire damage
j slight scorching of inside of test cabinet
j Non-fire damagej several ceiling tiles displaced
j ceiling runner slightly bent
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
32/44
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
33/44
0
50
100
150
200
250
300
350
400
450
500
0 100 200 300 400 500
Time, seconds
Hea
tR
elease,
kW
detection
system activation
extinguishment
Extinguishment of In-Cabinet Fire byFM-200
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
34/44
Results: Preaction Sprinkler SystemResults: Preaction Sprinkler System
y Photoelectric detector in NE corner in full alarm
at 94 seconds from ignition
y Ionization detector in NE corner in full alarm at
112 seconds from ignition (FPETool: 95 s)
y Complete obscuration due to smoke at
approximately 240 seconds from ignition
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
35/44
Results: Preaction Sprinkler SystemResults: Preaction Sprinkler System
y Sprinkler head in NE corner actuated at 273
seconds from ignition (FPETool: 249 s)
y Sprinkler head in N corner actuated at 347
seconds from ignition
y Fire not extinguished by sprinkler system
y IR camera shows fire burning through entirety of test
y Fire contained to source cabinet
y Max ceiling temperature of 560 oF observed atthermocouple tree nearest fire
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
36/44
0
50
100
150
200
250
300
350
400
450
500
0 100 200 300 400 500
Time, seconds
Hea
tR
elease,
kW
detection
system activation
Control of In-Cabinet Fire with Preaction System
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
37/44
Ta le 3. Spri kler ctivatio Times
Sprinkler
Radial
distance
to fire,feet
easured
Activation
Time,seconds
Predicted
Activation
Time,seconds
easured
Ceiling Jet T
at bulb atactivation
oF
Predicted
Ceiling Jet T
at bulb atactivation,
oF
NE 10.6 278 249 288 249
N 11.3 352 253 276 250
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
38/44
Results: Preaction Sprinkler SystemResults: Preaction Sprinkler Systemy Fire Damage
y Test cabinet suffered extensive scorching
y Non-Fire Damage
y Black ring around entire enclosure
y Ceiling tiles discolored
y Soot particles scrubbed from smoke layer cover floor,
horizontal surfaces
y Walls discolored from smoke damagey Water damage to paper goods
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
39/44
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
40/44
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
41/44
Conclusions: System PerformanceConclusions: System Performance
y Preaction Sprinkler System
y Design objective attained: Fire was controlled
y System performed exactly as expected
y Fire contained to room of origin
y Ceiling temperatures managed such that structural
damage and/or collapse did not occur
y Structure saved
y FM-200 System
y Design objective attained: Fire extinguishedy System performed exactly as expected
y Contents of structure saved
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
42/44
ConclusionsConclusions
j Clean agent and preaction sprinkler systems vastly
different
y Fundamental design objective different: Control vs
Extinguishment
y Preaction systems best suited to protection of structurey Clean agent systems best suited to protection of contents of
structure
y Sprinkler systems alone inappropriate for protection of high
value assets
y Clean agents not ideally suited for structural protectiony FPETool useful for predicting performance of sprinkler system
and estimation of ceiling jet temperatures, smoke detector
activation and for test fire selection
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
43/44
j Applications involving expensive, sensitive assets
y Use of clean agents justified
y Clean agents offer unparalled peformance for very early
extinguishment of fires
j Maximum fire protection provided by use of a clean
agent system in combination with a sprinkler system
j Substantial additional risk reduction at high benefit/cost ratios
can be realized by protecting such assets with both a clean
agent system and a sprinkler system
ConclusionsConclusions
8/8/2019 2003 HOTWC Sprinkler Presentation Final (1)
44/44
AcknowledgementsAcknowledgements
Great LakesChemical Corporation
- Steve Ginn
HughesAssociates, Inc.
- Eric Forssell
- Jason Ouellette
- Matt Harrison
- Ralph Ouellette
- Art Hammett
- Jason Kennedy