20 Years of Subsea Boosting Technology Development Pushing the Boundaries for Deepwater and Long Distance Tie-backs Arne B. Olsen
26

20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

Mar 27, 2018

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

20 Years of Subsea Boosting Technology DevelopmentPushing the Boundaries for Deepwater and Long Distance Tie-backs

Arne B. Olsen

Page 2: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

2

Content

20 Years of Subsea Boosting Technology Development

Historical view Technology map and development trends Boosting systems references Reliability Obvious potential vs. actual acceptances Latest contribution to subsea processing Closing remarks

Page 3: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

33

Pump Technology – Framo Engineering LegacyFirst Multiphase Pump Test Rig, 1987

20 Years of Subsea Boosting Technology Development

Page 4: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

44

Multiphase Pump Principle Selection

Various pump principles were evaluated and extensively tested in 1987-89 Positive displacement pump – Twin screw

and piston Dynamic pump – Helico-axial and CR

The Helico-axial principle was selected: Adequate pressure boosting capabilities Self regulating principle Can operate safely from 0-100% GVF

without re-circulation Simple and robust design (sand tolerant) Compact and low weight Easy to marinize

20 Years of Subsea Boosting Technology Development

Page 5: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

55

Original Vision for Subsea Multiphase Pumps

Extended satellite technology couldbring 80% of future prospects withinthe reach of existing infrastructure.

Extended satellite technology

50 km

20 Years of Subsea Boosting Technology Development

Page 6: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

66

Controlsystem

Barrier oilsystem

Qualifying Long Tie-back with Electrically Driven System

20 Years of Subsea Boosting Technology Development

Page 7: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

77

Pioneering Since Mid-90s

1983

• Legacy Framo Engineering established to develop products for the next decades

1984/5

• Screening boosting technologies

• First prototypes tested

1987

•Selected the Helico‐axial pump principle

1994

•Developed the electrical power and control system for subsea pumps

1997

•First commercial subsea electrical booster pump installed at Lufeng field

2000

•First true subsea multiphase pump installed at Topacio field

2001

•First subsea water injection pump installed at Troll

2006

•First subsea seawater injection system at Colomba E

2011

•Deepest, longest tie‐back and highest design pressure for Jack & St. Malo

2013

•Largest differential pressure system to Total’s GirRIproject (130 bar)

20 Years of Subsea Boosting Technology Development

Page 8: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

88

Single PhasePump

Multiphase PumpHybrid Pump

Multiphase Compressor

Multiphase Pump

A Tool for All Conditions

0

50

100

150

200

250

10% 20% 30% 40% 50% 60% 70% 80% 90% 100% GVF

DP[bar]

Hybrid PumpHybrid Pump

0

LIQUID

Multiphase CompressorMultiphase Compressor

Up to 10% gas content Up to 95% gas content (100% mechanical)

Up to 40% gas content(separator applications)

For wet gas applications from 0 to 100% gas content

GAS

Single-PhasePump

20 Years of Subsea Boosting Technology Development

Page 9: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

99

Water Depth Milestones

Page 10: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

1010

Shaft Power Evolution

Page 11: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

1111

Design Pressure Evolution

Page 12: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

1212

Diffe

renti

al Pr

essu

re <B

ar>

Barracuda, World’s First High Boost

Multiphase Pumps DP Evolution

Page 13: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

1313

Full-scale Test Facilities

20 Years of Subsea Boosting Technology Development

Page 14: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

1414

1994 First commercial subsea multiphase pump

650 kW pump270 m water depth9 km tie-back

Shell’s Draugen Field – North Sea

20 Years of Subsea Boosting Technology Development

Page 15: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

1515

1997 til 2011

First commercial subsea electrical pumpsProduction enabler

42 mill barrels of oil pumped

Statoil’s Lufeng Field – South China Sea

Page 16: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

1616

Topacio Satellite2-off MPP installed

Main pump has been in operation more than 50,000 hours since 2000

1 pump covers today’s required flow rates

Lifetime expectancy of up to 5 years (ref EM, Oct 2010)

ExxonMobil Topacio – Equatorial Guinea

Page 17: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

1717 20 Years of Subsea Boosting Technology Development

Chevron - Jack & St. Malo

Key data 60,000 bbld 3 MW shaft power 13,000 psi pressure

rating 4,000 psi boost 10% GVF design 7200 ft water depth

Page 18: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

1818

PCM

Total – GirRI Angola Installed Q4-2014

Scope 15 and 7 km tie-back (P80 and

P70) 1400 m water depth 130 bar differential pressure

Scope 15 and 7 km tie-back (P80

and P70) 1400 m water depth 130 bar differential pressure

Page 19: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

1919

Effect of Boosted Production

Production Rate

Pre

ssur

e

Increased production

20 Years of Subsea Boosting Technology Development

Page 20: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

2020

Extended Plateau ProductionEarly Natural Production

Free Flow to Surface + Boosting

-‘In-Well’ Lift

- Boosting

- Processing

Increased Recovery Over Field Lifetime

20 Years of Subsea Boosting Technology Development

Page 21: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

2121

Field Redevelopment - Example

20 Years of Subsea Boosting Technology Development

Page 22: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

2222

OneSubsea Pump System Reliability

Pump & System failures

Type A - Pump only

20 Years of Subsea Boosting Technology Development

Page 23: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

2323

0

1

2

3

4

5

1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

Compression

Separation

Re‐injection

Boosting

*Source: Morgan Stanley, “Big Subsea Opportunity: Deep Dive Revisited.” May 30, 2014.

Still a Slow Boosting Market…….

20 Years of Subsea Boosting Technology Development

Page 24: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

2424

Latest contribution to the oil and gas market First and only true wet gas compressor Boosting of unprocessed well streams,

from 0 to 100% liquid content No need for anti-surge control systems,

inter-stage coolers, or inlet scrubbers The OneSubsea Multiphase Compressor unit

is based on well-proven solutions from OneSubsea pump technology First commercial application is for

Statoil’s Gullfaks field

20 Years of Subsea Boosting Technology Development

Multiphase Compressor Latest Contribution to Subsea Processing

Page 25: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

2525

Unmatched Operation Experience

Page 26: 20 Years of Subsea Boosting Technology Developmentmcedd.com/wp-content/uploads/2014/04/02_Arne-B.-Olsen-OneSubse… · 3 Pump Technology – Framo Engineering Legacy First Multiphase

2626

Subsea pumping improves the economics by reducing backpressure on the reservoirs, thus increasing well flow rates and total recoverable reserves Subsea boosting improves flow assurance by

increasing velocity in pipelines, increasing temperature and stabilising production Our portfolio of proven, reliable systems has

successfully increased production rates from 30% to 100% for operators OneSubsea has been operating in the subsea

processing arena longer than any other company in the world, and records today more than 15 years MTTF of our pumps

20 Years of Subsea Boosting Technology Development

Concluding Remarks