Top Banner

of 17

2. RISK Criteria Establishment Guideline

Feb 28, 2018

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/25/2019 2. RISK Criteria Establishment Guideline

    1/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEI-GN-QS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    RISK CRITERIA ESTABLISHMENT

    GUIDELINES

    APPROVAL SHEET

    Name Title Date Signature

    Rev Date Description Prep. Review App

    Kangean Energy Indonesia

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    2/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 2 of 17

    Kangean Energy Indonesia

    TABULATION OF REVISED PAGES

    SHEET REVISIONS SHEET REVISIONS

    A B C 0 A B C 0

    1 51

    2 52

    3 53

    4 54

    5 55

    6 56

    7 578 58

    9 59

    10 60

    11 61

    12 62

    13 63

    14 64

    15 65

    16 66

    17 67

    18 68

    19 6920 70

    21 71

    22 72

    23 73

    24 74

    25 75

    26 76

    27 77

    28 78

    29 79

    30 80

    31 81

    32 82

    33 83

    34 84

    35 85

    36 86

    37 87

    38 88

    39 89

    40 90

    41 ATTACHMENT APPENDIX

    42 1 A

    43 2 B

    44 3 C

    45 4 D

    46 5 E

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    3/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 3 of 17

    Kangean Energy Indonesia

    TABLE OF CONTENTS

    1.

    Introduction .............................................................................................................................. 6

    2.

    Objective .................................................................................................................................. 6

    3.

    References ................................................................................................................................ 7

    4.

    Definitions ................................................................................................................................ 7

    5.

    Characteristics of Successful Risk Management Approaches ................................................. 8

    6.

    Risk Reporting Matrix ............................................................................................................ 11

    7.

    Risk Management Process ...................................................... Error! Bookmark not defined.

    8.

    Risk assessment ...................................................................... Error! Bookmark not defined.

    9.

    Comparison of risk assessment techniques ............................ Error! Bookmark not defined.

    10.

    Related Procedures ................................................................................................................. 17

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    4/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 4 of 17

    Kangean Energy Indonesia

    FIGURE LIST

    Figure 1 Risk Reporting Matrix ......................................................................................................... 11

    Figure 2 Level of Likelihood Criteria ................................................................................................ 12

    Figure 3 Level and Type of Consequence Criteria ............................................................................. 13

    Figure 4 Risk Analysis and Reporting Classification ........................................................................ 14

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    5/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 5 of 17

    Kangean Energy Indonesia

    No table of figures entries found.

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    6/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 6 of 17

    Kangean Energy Indonesia

    1. Introduction

    Kangean Energy Indonesia (KEI) Risk management Program involves establishing an

    appropriate infrastructure and culture and applying a logical and systematic method of

    establishing the context, identifying, analysing, evaluating, treating, monitoring against

    criteria established by theKEIand communicating risks associated with any activity, function

    or process in a way that will enable organizations to minimize losses and maximize gains.

    To be most effective, risk management should become part of an organization's culture. It

    should be embedded into the organization's philosophy, practices and business processes and

    criteria relating with those practical KEI risk criteria rather than be viewed or practiced as a

    separate activity. When this is achieved, everyone in the organization becomes involved in the

    management of risk.

    This Guidelines specifies the criteria of the risk management monitoring, but it is not the

    purpose of this Standard to enforce uniformity of risk management systems. It is generic and

    independent of Kangean Energy Indonesia Workplace Health and Safety Area. The design and

    implementation of the risk management criteria will be influenced by the varying needs of an

    organization, its particular objectives, its products and services, and the processes and specific

    practices employed.

    2. Objective

    2.1

    The objective of a well-managed risk management program is to provide a repeatable

    process for balancing cost, schedule, and performance goals within program funding,

    especially on programs with designs that approach or exceed the state-of-the-art or have

    tightly constrained or optimistic cost, schedule, and performance goals.

    2.2

    Without effective risk criteria the program may find itself doing crisis management, a

    resource-intensive process that is typically constrained by a restricted set of available

    options.

    2.3

    Successful risk management depends on the knowledge gleaned from assessments of all

    aspects of the program coupled with appropriate criteria to mitigation applied to the

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    7/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 7 of 17

    Kangean Energy Indonesia

    specific root causes and consequences.improved compliance with relevant risk criteria;

    and better corporate governance.

    3. References

    ISO/IEC 31000:2009 Risk Management - Principle and Guideline

    DNV-OSS-121 Performance Criteria Determined from Risk Assessment

    Methodology

    4. Definitions

    Consequences are the expected effects of an event occurring

    Frequency is the number of occurrences of an event per unit time. In risk

    assessment, it is usually expressed as the frequency per year

    Hazard is a source of potential harm or a situation with a potential to

    cause loss (any negative consequence).

    A criteria standard is a statement, which can be expressed, in qualitative or

    quantitative terms as appropriate, of the performance required

    of a safety-critical element in order to ensure the safety and

    integrity of the installation

    Risk acceptance criteria are standards by which the results of the risk assessment can be

    measured. The acceptance criteria represent the acceptable level

    of safety and integrity of the installation

    Safety-critical elements are parts of the installation, or plant, which are essential to

    maintain the safety and integrity of the installation

    Verification is examination, testing, audit or review to confirm that an

    activity, a product, or a service, is in accordance with specified

    requirements

    WBS Work Break down Structure, part of work elements which

    starting from upstream to downstream

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    8/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 8 of 17

    Kangean Energy Indonesia

    5. Characteristics of Successful Risk Management Approaches

    5.1Assess the root causes of program risks and develop strategies to manage these risks

    during each acquisition phase.

    5.2Identify as early as possible, and intensively manage those design parameters that

    critically affect capability, readiness, design cost, or LCC.

    5.3

    Establish the risk criteria suitable with existing conditions on site

    5.4Use technology demonstrations, modeling and simulation, and aggressive prototyping to

    reduce risks.

    5.5Include test and evaluation as part of the risk management process.

    5.5.1 Include industry participation in risk management. Offerors should have a risk

    approach as part of their proposals as suggested in this guide to identify root

    causes and develop plans to manage those risks and should include a draft Risk

    Management Plan (RMP).

    5.5.2 Additionally, the offerors should identify risks as they perceive them as part of

    the proposal. This not only helps the government identify risks early, but

    provides additional insight into the offerors level of understanding of the

    program requirements.

    5.5.3

    Use a proactive, structured risk assessment and analysis activity to identify and

    analyze root causes.

    5.6

    Use the results of prior event-based systems engineering technical reviews to analyzerisks potentially associated with the successful completion of an upcoming review.

    Reviews should include the status of identified risks.

    5.7

    Utilize risk assessment checklists (available for all event-based technical reviews) in

    preparation for and during the conduct of technical reviews

    6. Identification of Root Causes

    This is a practical way of addressing the large and diverse number of risks that often occur in

    acquisition programs. For example, a WBS level 4 or 5 element may be made up of several

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    9/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 9 of 17

    Kangean Energy Indonesia

    root causes associated with a specification or function, e.g., potential failure to meet turbine

    blade vibration requirements for an engine turbine design.

    Root causes are identified by examining each WBS product and process element in terms of

    the sources or areas of risk. Root causes are those potential events that evaluators (after

    examining scenarios, WBS, or processes) determine would adversely affect the program at

    any time in its life cycle.

    An approach for identifying and compiling a list of root causes is to:

    6.1List WBS product or process elements,

    6.2Examine each in terms of risk sources or areas,

    6.3

    Determine what could go wrong, and

    6.4

    Ask why multiple times until the source(s) is discovered

    6.5

    Typical risk sources include:

    6.5.1 Threat.The sensitivity of the program to uncertainty in the threat description,

    the degree to which the system design would have to change if the threat's

    parameters change, or the vulnerability of the program to foreign intelligence

    collection efforts (sensitivity to threat countermeasure).

    6.5.2 Requirements. The sensitivity of the program to uncertainty in the system

    description and requirements, excluding those caused by threat uncertainty.

    Requirements include operational needs, attributes, performance and readiness

    parameters (including KPPs), constraints, technology, design processes, and

    WBS elements.

    6.5.3 Technical Baseline. The ability of the system configuration to achieve the

    program's engineering objectives based on the available technology, design tools,

    design maturity, etc. Program uncertainties and the processes associated with the

    ilities (reliability, supportability, maintainability, etc.) must be considered. The

    system configuration is an agreed-to description (an approved and released

    document or a set of documents) of the attributes of a product, at a point in time,

    which serves as a basis for defining change.6.5.4 Test and Evaluation. The adequacy and capability of the test and evaluation

    program to assess attainment of significant performance specifications and

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    10/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 10 of 17

    Kangean Energy Indonesia

    determine whether the system is operationally effective, operationally suitable,

    and interoperable.

    6.5.5 Modeling and Simulation(M&S). The adequacy and capability of M&S to

    support all life-cycle phases of a program using verified, validated, and

    accredited models and simulations.

    6.5.6 Technology. The degree to which the technology proposed for the program has

    demonstrated sufficient maturity to be realistically capable of meeting all of the

    program's objectives.

    6.5.7 Logistics.The ability of the system configuration and associated documentation

    to achieve the program's logistics objectives based on the system design,

    maintenance concept, support system design, and availability of support data and

    resources.

    6.5.8 Production/Facilities. The ability of the system configuration to achieve the

    program's production objectives based on the system design, manufacturing

    processes chosen, and availability of manufacturing resources (repair resources in

    the sustainment phase).

    6.5.9 Concurrency. The sensitivity of the program to uncertainty resulting from the

    combining or overlapping of life-cycle phases or activities.

    6.5.10 Industrial Capabilities. The abilities, experience, resources, and knowledge of

    the contractors to design, develop, manufacture, and support the system.

    6.5.11 Cost. The ability of the system to achieve the program's life-cycle support

    objectives. This includes the effects of budget and affordability decisions and the

    effects of inherent errors in the cost estimating technique(s) used (given that the

    technical requirements were properly defined and taking into account known and

    unknown program information).

    6.5.12 Management. The degree to which program plans and strategies exist and are

    realistic and consistent. The governments acquisition and support team should

    be qualified and sufficiently staffed to manage the program.

    6.5.13

    Schedule. The sufficiency of the time allocated for performing the definedacquisition tasks. This factor includes the effects of programmatic schedule

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    11/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 11 of 17

    Kangean Energy Indonesia

    decisions, the inherent errors in schedule estimating, and external physical

    constraints.

    6.5.14 External Factors.The availability of government resources external to the

    program office that are required to support the program such as facilities,

    resources, personnel, government furnished equipment, etc.

    6.5.15 Budget.The sensitivity of the program to budget variations and reductions and

    the resultant program turbulence.

    6.5.16 Earned Value Management(EVM) System. The adequacy of the contractors

    EVM process and the realism of the integrated baseline for managing the

    program

    7. Risk Reporting Matrix

    Each undesirable event that might affect the success of the program (performance, schedule,

    and cost) should be identified and assessed as to the likelihood and consequence of occurrence.

    A standard format for evaluation and reporting of program risk assessment findings facilitates

    common understanding of program risks at all levels of management.

    7.1

    The Risk Reporting Matrix below is typically used to determine the level of risks identified

    within a program. The level of risk for each root cause is reported as low (green),

    moderate (yellow), or high (red).

    Figure 1 Risk Reporting Matrix

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    12/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 12 of 17

    Kangean Energy Indonesia

    7.2

    The level of likelihood of each root cause is established utilizing specified criteria (Figure

    1). For example, if the root cause has an estimated 50 percent probability of occurring, the

    corresponding likelihood is Level 3.

    Figure 2 Level of Likelihood Criteria

    7.3

    A single consequence scale is not appropriate for all programs, however. Continuing with

    the prior example of a root cause with a 50 percent probability of occurring, if that same

    root cause has no impact on performance or cost, but may likely result in a minor schedule

    slippage that wont impact akey milestone, then the corresponding consequence is a Level

    3 for this risk. For clarity it is also classified as a schedule risk since its root cause is

    schedule related.

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    13/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 13 of 17

    Kangean Energy Indonesia

    Figure 3 Level and Type of Consequence Criteria

    7.4

    The results for each risk are then plotted in the corresponding single square on the Risk

    Reporting Matrix. In this example, since the level of likelihood and consequence wereboth 3, the corresponding schedule risk is reported as yellow, as shown in Figure 4,

    using a recommended display method that includes the risk title (where (S) identifies this

    risk as a schedule risk), risk causal factor, and mitigation approach

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    14/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 14 of 17

    Kangean Energy Indonesia

    Figure 4 Risk Analysis and Reporting Classification

    8. Parameters Considerations

    8.1

    Performance (P) Considerations

    This risk has a performance consequence. These risks generally have associated schedule

    and cost impacts, but should be carried as a performance risk.

    Operational (e.g., Initial Capabilities Document (ICD), Capability Development

    Document (CDD), Capability Production Document (CPD), threats, suitability,

    effectiveness).

    Technical (e.g., Technology Readiness Levels, specifications, technical baselines,

    standards, materiel readiness )

    Management (e.g., organization, staffing levels, personnel qualifications/experience,

    funding, management processes, planning, documentation, logistics)

    8.2Schedule (S) Considerations

    The Risk Assessors should analyze impact of the risk to the IMS and the critical path(s),

    to include:

    Evaluating baseline schedule inputs (durations and network logic);

    Incorporating technical assessment and schedule uncertainty inputs to the program

    schedule model;

    Evaluating impacts to program schedule based on technical team assessment;

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    15/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 15 of 17

    Kangean Energy Indonesia

    Performing schedule analysis on the program IMS, incorporating the potential impact

    from all contract schedules and associated government activities;

    Quantifying schedule excursions reflecting the effects of cost risks, including resource

    constraints;

    Providing a government schedule assessment for cost analysis and fiscal year planning,

    reflecting the technical foundation, activity definition, and inputs from technical and cost

    areas; and

    Documenting the schedule basis and risk impacts for the risk assessment.

    Projecting an independent forecast of the planned completion dates for major milestones

    8.3Cost (C) Considerations

    with no performance or schedule impacts, the risk is a cost risk, and may impact estimates

    and assessments such as:

    Building on technical and schedule assessment results;

    Translating performance and schedule risks into life-cycle cost;

    Deriving life-cycle cost estimates by integrating technical assessment and schedule risk

    impacts on resources;

    Establishing budgetary requirements consistent with fiscal year planning;

    Determining if the adequacy and phasing of funding supports the technical and

    acquisition approaches;

    Providing program life-cycle cost excursions from near-term budget execution impacts

    and external budget changes and constraints; and

    Documenting the cost basis and risk impacts.

    8.4Assemble Scoring Models

    After evaluation criteria have been identified, a scoring model may be developed to

    incorporate all criteria to yield a single risk score. In general, scoring models use

    multiplicative or additive means to calculate risk. Very often, criteria are weighted

    based on the importance of a criteria to the overall risk. Several examples of scoring

    schemes are presented below8.4.1 Risk Matrix

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    16/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision Date

    Risk Criteria Guidelines Rev.A Page 16 of 17

    Kangean Energy Indonesia

    The Risk Matrix presented in Figure 1-4 is a simple scoring model that requires no

    calculation. The matrix provides an excellent visual model that is easy to understand. This

    matrix is effective in models where only two criteria are involved

    8.4.2 + / - Scoring Scheme

    The + / - scoring scheme provides a numerical range centered on zero for various criteria.

    The ranges are standardized to reflect that values on one side of zero always represent

    higher risk and values on the opposite side of zero represent lower risk. Scores assigned

    to each criterion are added together to yield overall risk. The table below shows a sample

    scoring model using the /- scoring scheme, as below

    Criteria Scoring Range Actual Score

    Potential for Harm -10 to +10 +5

    Level of Non-conformances -3 to +3 -2

    Ability to Detect Deviations -5 to +5 +3

    Adequacy of Staffing Levels -3 to +3 -1

    TOTAL SCORE (Range: -21 to +21) +5

    8.4.3 Weighted Scheme

    The weighted scoring scheme assigns a weighting to each criteria and uses a

    consistent numerical range for each criteria. The individual weighted scores

    are either averaged or added. Weighting may be defined as a percentage or as

    a value in a range. The table below shows a sample scoring model using the

    weighted scheme

    Criteria Actual Score Weight Weighted Score

    Potential for Harm 5 60% 3

    Level of Non-conformances 6 15% 0.9

    Ability to Detect Deviations 2 25% 0.5

    Adequacy of Staffing Levels 5 10% 0.5

    TOTAL SCORE (1 to 10) 4.9

  • 7/25/2019 2. RISK Criteria Establishment Guideline

    17/17

    Project

    GENERAL

    KANGEAN ENERGY INDONESIA

    Document Number

    KEIGNQS-PRC-XXXX

    Discipline

    PSM

    Doc. Type

    PROCEDURE

    Originator Revision DateKangean Energy Indonesia

    8.4.4 Filtering

    Filtering involves focusing the scope of risk management by selectively reducing risk

    control for low-risk systems and increasing risk control for high-risk systems. Effectively

    filtering systems requires a consensus definition of action thresholds. Using the example

    of auditing manufacturing sites, a simple set of action thresholds might look as follows.

    Overall Site Risk Score Action

    Greater than 7 Audit performed annually

    37, inclusive Audit performed once every two (2) years

    Less than 3 Internal Audit not needed

    9. Related Procedures

    The implementation of Risk Criteria Guidelines as per DNV-OSS-102 Standard will be used

    independently according to the following procedures,

    KEIGNQS-PRC-XXXX RISK Management Guidelines

    KEIGNQS-PRC-XXXX HAZID Guideline

    KEIGNQS-PRC-XXXX HAZOP Guideline

    KEIGNQS-PRC-XXXX LOPA Guideline

    KEIGNQS-PRC-XXXX SIL DETERMINATION Guideline

    KEIGNQS-PRC-XXXX SIL VERIFICATION Guideline

    KEIGNQS-PRC-XXXX FAULT TREE ANALYSIS Guideline

    KEIGNQS-PRC-XXXX EVENT TREE ANALYSIS Guideline

    KEIGNQS-PRC-XXXX CAUSE ANALYSIS Guideline

    KEIGNQS-PRC-XXXX CONSEQUENCE ANALYSIS Guideline

    KEIGNQS-PRC-XXXX BOW TIE ANALYSIS Guideline

    KEIGNQS-PRC-XXXX QUANTITIVE RISK ANALYSIS Guideline