Regional Connector Transit Project 1 st /Central Community Leadership Council monthly meeting Construction Update February 8, 2016
Regional Connector Transit Project 1st/Central Community Leadership Council monthly meeting
Construction Update February 8, 2016
Construction Update
> Ongoing construction activities
> Mangrove yard
> 1st/Central yard
> 1st/Alameda intersection work
> Construction schedule & Look-ahead
> 2nd St. grouting
> Central Ave. 20” water line
> 1st/Alameda pile and deck
> Excavation of 1st/Central Station
2
Ongoing Construction Activities
> Eastbound 1st St widening completed
> Street light improvements completed
3
Ongoing Construction Activities
> Mangrove yard— Gold Line track demolition & relocation
> 1st/Central yard & 1st/Alameda— Continuation of piling
4
2nd Street Grouting Potholing
> January 26 for two weeks; complete February 9
> 9 a.m.–3:30 p.m.; parking restricted
> One lane in each direction
5
Schedule & Sequence of Work
Activity Proposed Dates
> 2nd St. Grouting
> Between San Pedro and Central Ave.
> Motorist traffic: one lane in each direction
> Pedestrian access maintained
> Potholing is necessary to confirm utilities prior to activity
> Removal of two trees
> As early as March 11 for four months
> Jan. 26 for two weeks;
complete Feb. 9
> 20” water line work on Central Ave. between 1st St and 2nd St.
> Outreach on-going with the affected stakeholders
> One night water service interruption to tie in the water lines
> Southbound Central Ave. open; northbound directional closure > Local access and driveways will be maintained
> As early as Feb. 15 for two weeks
> Feb. 29—water service
interruption
> Pile & deck at 1st/Alameda
55 hour full weekend closure, piling & decking
> Alameda between Temple and 3rd St. > 1st St. between Alameda and Vignes
> Ongoing through Summer 2016
10
2nd Street Grouting – Street Parking Maintained East of the Mid-block Crosswalk
Existing Phase 1 -
North side
Phase 2 -
South side
Meter parking
38 spaces 17 spaces 20 spaces
Commercial
loading zone
4 – north side
1 – south side
2 – north side
1 – south side
2 – north side
1 – south side
12
Central Ave. Water Line Work
> February for approx. three weeks
> Southbound access open
> Northbound access restricted (nights only)
> Pedestrian access maintained
17
Utility, Pile & Deck at 1st/Alameda 55 Hour Weekend Closures
> Jan. 29–Feb. 1
> Feb. 5–7
> Local access maintained
19
Community Outreach
> Distributed construction notices since 1/25 meeting
> Utility investigation on 2nd St. between Central Ave. and San Pedro St.
> 55-hour weekend closure at 1st St./Alameda St.
> Construction activities behind K-rail at 1st St./Alameda St. intersection
> Mangrove Yard sound wall installation
> Start of station excavation at 1st St./Central Ave. yard
> Reached stakeholders through the following methods:
> E-blast to over 3,600 email addresses
> Door-to-door briefing
> Door-to-door distribution with in ½ mile radius
> Website
> Social Media posts to audience of 5,000
23
Community Outreach
> Individual briefings to approx. 50 businesses on the following activities:
> Temporary commercial loading zone on 2nd St
> Permeation grouting on 2nd St
> Ongoing coordination with stakeholders on upcoming 20’ water line relocation and tie-in on Central Ave. between 1st St. and 2nd St.
> One night—water service interruption to 14 businesses
> Assessing water needs and mitigations with individuals
24
Construction Mitigation Banners
> Bulleted copy.
> Bulleted copy.
`
Southeast Corner of 1st/Alameda
West Side of 1st/Alameda Intersection
Eastbound 1st St across from Buddhist Temple
East 1st/Central Intersection Crosswalk
Along Westbound 1st St Sidewalk 25
Contact Us
metro.net/RegionalConnector twitter.com/MetroConnector facebook.com/MetroRegionalConnector
213.922.7277
26