1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization
73

1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Apr 01, 2015

Download

Documents

Efren Wisby
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

1.Status of Items Announced in Budget 10-11

2. Planning of N.G. conversion in NGP Divn.

3. Targeted works 2010-11.

Const. Organization

Page 2: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

DOUBLING• Item No. 116 ( XXIX) of Budget Speech• Durg – Rajnandgaon 3rd line ( 30.889 Km)

STATUS• Included in Pink Book - 2010-11.• Cost of project - `147.06 Crores. • Budget Grant - `10.00 Crores. for 2010-11 • Detailed estimate sanctioned by Rly.Bd in Oct. 10.• Tenders for geo-tech. exploration, earthwork and minor

bridges, opened on 4.11.10 & 11.11.2010

Status of Items Announced in Budget 10-11

Contd…

Page 3: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

New Gauge Conversion works• Item No 115 (i) Budget speech• Chhindwara -Nainpur – Mandla Fort (182.25 Km)

STATUS• Included in Pink Book - 2010 -11.• Cost of project - ` 556.54 Crores. • Budget Grant for 10 - 11: ` 1.00 Crores.• The detailed part estt. of NIR - MFR for ` 145.8 Cr.

sent to Railway Board in May-10 for sanction after conducting FLS departmentally.

• Tender for major bridges of NIR-MFR opened on 4.10.10.

Contd…

Page 4: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Gauge Conversion Project (Either completed or will be completed )

• Item No 113 (x) of Budget speech• Balaghat- Katangi (46.8Km) of Jabalpur - Gondia

• STATUS

• Included in Pink Book - 1996-97.

• Gondia - Balaghat including MOIL siding (42+7 Km) section commissioned in the year 2005

• Balaghat-Katangi[46.8] - Section completed & commissioned on 7.05.2010

Contd…

Page 5: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

New line Project• Item No 111 of Budget speech• Mandir Hasaud- Naya Raipur (20.00 Km)

sanctioned as material modification to Raipur – Titlagarh doubling of East Coast Railway

Status: • Included in Pink Book - 2010-11.• Cost of project - ` 77.32 Crores. • Budget Grant for 2010-11 - Nil• Budget demanded in R E -1.00 crore• Part estimate for ` 28 Lakhs. for preliminary

activities sanctioned by GM/SECR.• FLS is in progress.

Contd…

Page 6: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Updating of Socially Desirable Rail Connectivity Proposals

• Item No 102 of Budget speech (Sr. No.10)

• Barwadih- Chirimiri/Ambikapur [182 km]

• RET Survey report submitted on 17.05.03 for ` 406.86 Crs. with ROR (-) 4.85%. Project shelved by Rly. Bd. dated 28.07.03. Updating done as desired by Rly. Bd. and updated report submitted on 16.2.09. with ROR (-) 9.05%. Board again desired in May-10 for updating. Updated estimate under finance vetting..

• TDC - Dec. -2010

Contd…

Page 7: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Updating of proposals

Lohardaga-Korba (326 Km.) (via Dharmjaygarh & Pathalgaon)

• Item No 102 of Budget speech (Sl No. 63)• RET survey sanctioned in 1998. • Report Submitted to Rly. Board in 2003.• Cost ` 621.67 crores & ROR (+) 07.25 %.• Project shelved by Board in 2003. • Updated estimate with operating deptt. for

calculation of ROR. • TDC - Dec.-2010

Contd…

Page 8: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Updating of proposals Pendra Road –Korba/Gevra Rd. (121.7 Km.)

(via Pasan, Sundargarh & Deepika)

• Item No 102 of Budget speech (Sl. No. 82)

• PET survey sanctioned in 1996-97.

• Report submitted to Board in 2003.

• Cost ` 344.43 Crores & ROR (+)15.23%.

• Updated estimate under finance vetting.

• TDC - Dec-2010.

Contd…

Page 9: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Updating of proposals Raigarh - Mand Colliery to Bhupdeopur

(63 Km. with Fly over)

• Item No 102 of Budget speech (Sl. No. 88)

• PET survey sanctioned in 2008-09.

• Report submitted to Railway Board in July -2009 at the cost of ` 310.64 Crores & ROR (+) 29.58%

• Updated report submitted to Board in Aug. -10 at the cost of ` 344.20 crores and ROR (+) 26.33%

Contd…

Page 10: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Updating of proposals

Raipur – Jharsuguda (310 Km.)(via. Kharotapalan, Baloda Bazar, Bhatgaon & Sarangarh.)• Item No 102 of Budget speech (Sl. No. 89)

• RET survey sanctioned in 1999-2000

• Report submitted to Railway Board in Feb-2003.

• Cost ` 971.96 crores & ROR (-) 20%.

• Project was shelved by Board in Aug. -2003

• Updating of abstract estimate under progress & will be submitted to finance for vetting shortly.

• TDC - Jan -2011. Contd…

Page 11: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Updating of proposals

Ramtek – Gotegaon (275 Km.)(via Khawasa, Sioni & Dhuma)

• Item No 102 of Budget speech (Sl. No. 92) • RET survey sanctioned in 1995. • Report submitted to Railway Board in April 1999. • Cost `. 528.21 crores & ROR (-) 11.50%• Updated report submitted to Board in Mar. 2005.• Project was shelved by Board in Oct. 2005.• Updating in progress and will be submitted to

Board by Jan -2011.

Contd…

Page 12: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Updating of proposals

• Item No 118 (i) of Budget speech• Wadsa - Desaiganj - Gadchiroli - 49.5 Km

(Cost sharing)• RET survey sanctioned in Aug -1995.• Initial report submitted in July - 1998.• Updated report submitted in Aug - 2010.• Cost ` 232.40 crores & ROR without sharing

(-) 3.88% & with 50% cost sharing by State Govt. ROR (-) 0.40%

Page 13: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Planning of N. G. conversion in NGP division

Page 14: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Section Blocking Opening

(a) JBP - Sukrimangla (43.41km) Oct-2011 June-2012

(b) Sukrimangla-Nainpur (70.1 km)* Oct-2012 June-2013

* Subject to acquisition of forest land in Seoni Distt.

(c) Nainpur – Mandla Fort (42.2 Km.) Oct -2012 June -2013

Planning of N.G. conversion in NGP Divn.

Page 15: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Contd.

Section Blocking Opening

(d) Nainpur - Balaghat (75.4 Km.)* Dec -2012 Dec-2013

* Subject to acquisition of forest land in Balaghat Distt.

(e) NGP - Ramakona (86 Km.) Oct-2012 June-2013

(f) Ramakona - CWA (64 Km.) Jan -2013 Dec – 2013

(g) Nainpur - Seoni (76 Km.) Dec - 2013 Dec-2014

(h) Seoni - Chhindwara (64 Km.) Dec – 2014 Dec - 2015

Page 16: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Progress of Major ItemsJabalpur – Nainpur - Balaghat

Sr. No Items Scope Progress

1.Earth work

(Lakh Cum.)108 40%

2.Major Bridges (Nos.)

49 60%

3.Minor Bridges (Nos.)

313 54%

Page 17: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Progress of Major ItemsJabalpur - Sukarimangla

Sr. No Items Scope Progress

1.Earth work

(Lakh Cum.)14 66%

2.Major Bridges (Nos.)

15 65%

3.Minor Bridges (Nos.)

82 68%

Contd.

Page 18: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Progress of Major ItemsNagpur - Chhindwara

Sr. No

Items Scope Progress

1.Earth work

(Lakh Cum.)99.23

20% work completed. Agency available for 27 Lakh. Cum.

2.

Major Bridges (Nos.)

(a) Sub - Structure 27

Completed - 12

In progress - 12

Tender to be finalized - 3

(b) Super - Structure (Nos.)

87 steel girders

W/O placed on MMR/WS and trade. 42 girders received, launching of girders taken up.

Contd.

Page 19: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Sr. No

Items Scope Progress

3.Minor Bridges (Nos.)

254

36 - completed.

169 - Segments casted. Launching in mega block.

34 - In progress.

5 - To be closed.

10 - Tender to be finalized.

4. Tunnel 2 Tender under finalization.

Contd.

Page 20: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

(1) Operational Requirements

(i) Crew movement to & from Sukrimangla during Ist phase conversion from Oct -11

(ii) Running of BG DMU or normal ICF coaches on converted section of JBP – Sukrimangla from June - 12.

(iii) Feasibility of running of truncated NG services on CWA - NIR & NIR - BTC section after Oct-2012.

Options to be considered

(a) Close the NG section after Oct 12 till complete conversion, looking to the drastic reduction in passengers.

(b) Running of curtailed NG services after augmenting Mech. facilities need based at NIR by doing material modification of GC estimates.

Issues to be Finalized

Page 21: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

3. Additional infrastructure desired by Mech. Deptt. (to be decided judiciously in view of no provision in the estt.)

(A) At NIR(i) 115 M new washing cum inspection pit line.(ii) Extension of existing shed by 15 M with lighting

arrangement.(iii) Construction of rooms. (iv) 100 M line for keeping spare coaches.

Items (i) to (iv) will cost approx. ` 0.7 Crores.(iv) Accommodation for 35-40 maintenance staff.(vi) Development of diesel loco maintenance (` 2.98 Crores)

(B) At MIB - Development of diesel loco maintenance (`3.6 crores)

Page 22: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Targeted works 2010-11Name of work PH Prog. Remarks

Champa – Bye Pass 15 20% Delaying due to non-acquisition of land

Rebuilding of Bridge NO. 99

32 98% Commissioning delaying due to non shifting of HT by CSEB

ROB at Uslapur 30 82% Work in progress

ROB at Raigarh – Kotarlia

30 50% Work in progress

ROB at Raipur – Baloda Bazar

30 90% Work in progress

Page 23: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of work PH Prog. Remarks

ROB at KM 867/7-8 at Durg over DRZ line.

Deposit work

90%Work in progress.

USL – Development of Model Goods Shed.

16 100% Completed.

RSD - Raipur development of goods shed.

16 100% Completed.

Jharridih – Additional Dn loop.

16 100%Completed.

Himgir – Additional Up loop. 16 87%Work in progress.

Contd…

Page 24: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of work PH Prog Remarks

(a) KDTR – Remodeling for dealing with addl. traffic of JSPL siding.

(b) KDTR – Addl. Loop.

16

85%

95%

Work in progress

Work in progress

Bhilai – Relocation of ART/ARME train

16 96% Work in progress, GJ work being done by Div.

BRJN – Ext.of Dn island platform for 24/26 coaches.

16 98% Completed for 24 coach length.

Contd…

Page 25: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of work PH Prog. Remarks

Durg – Development of goods shed by providing common loop.

16 96%

Goods shed work completed. Signaling work to be taken up as per revision.

BSP – Renovation of pit line NO. 1 & 2 of coaching pit line.

42 55% Work in progress

Bhilai Peripheral Yard – Impro. in freight exam. Facility.

42100%

Completed.

Contd…

Page 26: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of work PH Prog. Remarks

Bhilai Elect. Loco Shed – Aug. of homing capacity from 150 to 175

42 100% Completed.

BSP – Replacement of W. A. on line No. 1 & Extension of PF No. – 4

42 100% Completed.

BSP – Replacement of W. A. on PF No. 3 & Extension of WA on PF No. - 2

42 50%Work in

progress.

Contd…

Page 27: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Description PB/OB/LB

Prog Remarks

BSP-142 units type-II

PB/242 100% Completed.

Raipur-96 type-II PB/245 36% Work in progress. 48 Qtrs. by Mar-11.

Raipur-11 type-V & 20 type-IV

PB/248 34% Work in progress. All type - V by Mar-11

Raigarh- 10 type-II, 15 type-III

LB/672 100% Completed.

PROGRESS OF QUARTERS

Page 28: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Description PB/OB/LB

Prog Remarks

BSP-Replacement of out house 50 units

LB/270 85%Work is in progress.

BSP-Replacement of type-I 50 units

LB/271 85%Work is in progress.

Contd.

Page 29: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

THANK YOU

Page 30: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.
Page 31: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.
Page 32: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.
Page 33: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.
Page 34: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.
Page 35: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.
Page 36: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

WORKS COMPLETED IN

2009 -10 & 2010 -11 (PB)

Sr. No.

Name of workSanc. Year

Completed Month

1. Jamga – Addl. Up loop. 07-08 July-09

2. IB – Addl. Dn loop. 07-08 Sep-09

3.Parmalkasa – Conversion of “C” class stn. into “B” class with 4 lines.

05-06 Oct-09

Page 37: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Sr. No.

Name of workSanc. Year

Completed Month

4. Salva - Conversion of “C” class stn. into “B” class with 4 lines.

06-07 Nov-09

5. Belpahar – Addl. Dn loop. 07-08 Dec-09

6. Uslapur – Development of model goods shed.

05-06 Apr-10

7. Raipur – Store depot. Development of goods shed.

08-09 June-10

8. Jharradih – Addl. Loop line. 05-06 Aug-10

9. Bhilai – Jamul cement siding Electrification including yard.

07-08 Feb-10

Contd.

Page 38: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Sr. No.

Name of workSanc. Year

Status

1. BSP : Extn. Of existing shunting neck by 180m at coaching depot.

04-05 Completed

2. BEF : Development of full rake handling point.

07-08 Completed

3. JRMG : Development of full rake handling point.

07-08 Completed

STATUS OF LAW BOOK WORKS

Page 39: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Sr. No

Name of workSanc. Year

Status

4. MXA: Provision of dispatch signal for line No. 5, 6 & 7 towards ore yard and for line No. 2, 3 & 4 towards DUG and DRG.

06-07 Completed

5. Surakachar : Electrification of Siding.

06-07 Completed

6. BRJN : Electrification of Orient Collieries siding.

06-07 Completed

Contd.

Page 40: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Sr. No.

Name of workSanc. Year

Status

7. Shifting of 04 Nos. of Cross – ovar at JRMG Railway Station.

08-09 Completed

8. RSD : Signaling facility for reception and dispatch for line No. 7

07-08 Clubbed with PI work.

TDC- Mar-11

Contd.

Page 41: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti.

Cost

TDC Prg.

Brajrajnagar – Extension of Dn island platform for 24/26 coaches.

07-08 2.40 Oct-10 98%

Remarks

ESP & IP approved. Slewing of main line and major OHE alterations completed. PF extension work completed except stone surfacing.

In. Crs.WORK IN PROGRESS

Page 42: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Himgir – Addl. Up loop 07-08 4.46 Nov-10 87%

Remarks

Existing relay room will be used. 100 % E/W, bridge work and ballast supply completed. FOB - 100 % & Linking 60%. OHE - 48 foundation out of 53 done & 28 mast erected, steel received. S & T progress - 80%. CRS sanction obtained.

Contd. In. Crs.

Page 43: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

1.Kirodimalnagar – Addl. Loop.

2.Kirodimalnagar – Remodeling for dealing with additional traffic of JSPL siding.

06-07

08-09

4.20

6.00

Nov-10

Nov-10

85%

60%

Remarks

Work is planned in two stages.

Stage -I – Up loop and one Dn loop work at KDTR.

Stage – II – 2nd Dn loop.

Connection for all 3 loops planned for simultaneous commissioning to avoid redundant works. CRS sanction awaited. E/W – 95%, Building & Bridge work – 100%, S & T – 95%, Track Linking in progress.

Contd. In Crs.

Page 44: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Bhilai – Relocation of ART/ARME train

08-09 5.41 Dec-10 96%

Completed work

Formation, track, extension of culvert.

Shed (40x12) 140 ton for crane.

S & T goomty (3mx3m) & Inspection pit.

Balance work in progress

Service building for C&W staff – Upto plinth level completed.

SIP & SWR to be revised after ESP alteration due to U/M LC in yard to be

manned & relocation of point.

CRS sanction for D cabin submitted on 20.09.10

Contd. In. Crs.

Page 45: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Bilaspur Yard - Raising of speed for Bye pass line & up through line.

07-08 3.10 Dec-10 24%

Work involves number of traffic and power block to carry

heavy slewing of track and relocation of 40 OHE masts.

Work needs to be reviewed in view of limited returns and

take off point for proposed Electrical Loco Shed on it.

Work has been kept in abeyance by COM.

Contd. In. Crs.

Page 46: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Durg – Development of goods shed by providing common loop & better unloading facilities.

08-09 7.00 Dec.-10 96%

Goods platform work nearly completed.

Placement/withdrawal of trains being done from BSP end.

Connectivity from NGP end should be done along with 3rd line bet.

Durg – Rajnandgaon to avoid repeated NI and yard modification.

Renovation of existing shed for labour rest room and merchant room

in progress.

Contd. In. Crs.

Page 47: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Dadhapara – Belha & Urkura – Mandhar (IBS on Up & Dn lines.)

07-08 1.88 Dec.-10 65%

Full quantity of cable procured. Electrical work completed. MDH-URK commissioned on 28.7.09.Tender awarded for Dadhapara - Belha section. Work in progress.

Contd. In. Crs.

Page 48: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Gevra Road – Run through facility.

08-09 6.52 Mar-11 5%

Remarks

Work proposed for dropping.

Contd. In. Crs.

Page 49: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Mandhar – New goods terminal.

08-09 3.18 NF -

Remarks

ESP Approved. Cost of work is exceeding the abstract estimate substantially. Detailed estimate is under revision.

Contd. In. Crs.

Page 50: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti.Cost

TDC Prog.

Rupond – Addl. Common loop to serve new goods shed.

08-09 3.46 Apr-11 -

Remarks

Scope of work revised. ESP approved. Estimate sanctioned. Civil tender finalised recently. OHE tender finalised. S & T tender opened on 05.02.10 and discharged. Fresh tender opened on 20.08.10 and under finalisation.

Contd. In. Crs.

Page 51: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

BSP Div. – IBS

(4 location)

08-09 6.00 Dec-10 20%

Detailed estimated sanctioned. Tender awarded & work under progress. SWR’s pending in division.

TDC

Dadhapara - Belha - Oct-10

Jairamnagar - Latia - Nov-10

Gatora - Jairamnagr - Nov-10

BSP - Gatora - Dec-10

Contd. In. Crs.

Page 52: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Bhupdeopur – Remodeling for dealing with new pvt. siding.

08-09 10.89 NF -

Remarks

Land acquisition required at JSG end land plan submitted. Revised ESP approved. Land acquisition proceedings stalled. Work to be truncated to avoid land acquisition and revised ESP prepared & under finalisation.

Contd. In. Crs.

Page 53: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Bhilai – Addl. Freight maintenance depot at coal empty yard with 3 examination lines & one shunting neck of full length.

08-09 19.71 Nov-11 28%

Contd. In. Crs.

S & T and OHE tender finalised. E/W in progress. One high tension tower in the alignment is yet to be dismantled by CSEB.

Page 54: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Bhilai – (Exchange yard) remodeling with 2 addl. loop line by extension of D/End.

09-10 5.95 Feb-12 -

Remarks:-

Scope of work finalised recently by the division. Detailed estimate sanctioned during July- 10. ESP under finalisation.

Contd. In. Crs.

Page 55: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Himgir – Addl. Dn. Loop. 09-10 5.00 NF -

Remarks:-

ESP approved. Work to be executed with 3rd line.

Contd. In. Crs.

Page 56: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Jamga – Yard remodeling. 09-10 4.55 NF -

Remarks:-

ESP approved. Work to be executed with 3rd line.

Contd. In. Crs.

Page 57: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

IB – Addl. Loop. 09-10 4.13 Dec-11 -

Remarks:-

Site details collected. ESP approved. Estimate vetted. Tender to be floated.

Contd. In. Crs.

Page 58: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Mudaria – Addl. Dn. Loop. 09-10 3.00 NF -

Remarks:-

Heavy cost over runs are noticed in S & T portion of the estimate. Scope of work reviewed and referred to Board.

Contd. In. Crs.

Page 59: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Name of Work Sanc. Year

Anti. Cost

TDC Prog.

Saragbundia – Conversion of goods shed siding into Up loop cum Dn reception line.

09-10 3.13 Oct-11 -

Remarks:-

ESP approved. Estimate under vetting.

In. Crs.

Page 60: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

JABALPUR – NAINPUR (113.5 km.) (Non – Electrified section)

This part of the project is falling in Seoni, Mandla & Jabalpur distt. of MP.

Total land acquisition is 344 hec. (Pvt. 261 + Govt. 50 + Forest land 33 hec.)

25 hect of Pvt./Govt. & 30 hect of forest land is balance for acquisition (Seoni district).

One important bridge over Narmada (18 x 30.5 m PSC box) completed.

Page 61: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

There are three major detours (Pindarai - Ghansore 20 km, Vinayaki - Shikara 9 km, and Bargi - Kachpura 20.7 km), two minor detours in Shikara – Sukari plus mini diversions at major bridge approaches. Total length of detour alignment is 62 km. Earth Work is progressing in 56 Km length .

Contd.

Item Scope Prog. Remarks

Earth work (Lakh. Cum.)

81 37.53Earth work in 6 km detour portion & in mega block is balance.

Blanketting (Lakh cum.)

7.7 1.54 About 60% qty. to be done in mega-block.

Page 62: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Item Scope Prog. Remarks

Major bridge (Nos.)

33

35%

Tender under finalized for 32bridges.Out of which -

Completed - 3 Br.

In Progress-21Br.

Minor bridge (Nos.)

194 56

Out of 115 bridges located in detour. 53 completed, 65 in progress. Out of 83 in same alignment pre-cast segment completed for 56 bridges & balanced 27 bridges in progress.

Ballast (Cum.)

244000 1413018000 cum taken in Nainpur–Pendarai section. For balance tender to be invited.

Page 63: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Gondia – Jabalpur gauge conversion incl. Balaghat – Katangi (275.20 Km.)

Year of sanction

Anticipated cost.

Exp. Upto Mar-10

2009-10Overall progressExp. Upto

Oct.-10

1996-97 1038.00 453.85 34.48 62%

Gondia – Balaghat section including MOIL siding (42+7 Km) already commissioned.

Balaghat–Katangi section 46.8 km completed. CRS after inspection on 23.02.2010. & section commissioned on 07.05.10

Page 64: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Track Linking – 125 Km. Indent placed for all P. way materials. 12000 Sleepers transported .

JBP-Gwarighat (20km) can be opened in June-2011. Thus abandoning NG alignment from JBP – Gwarighat (9.2 km).

TDC

Contd.

Section Blocking Opening

(a) JBP - Sukrimangla (43.41km) Oct-2011 June-2012

(b) Sukrimangla-Nainpur (70.1 km)* Oct-2012 June-2013

* Subject to acquisition of forest land in Seoni Distt.

(c) Nainpur – Mandla Fort (42.2 Km.) Oct -2012 June -2013

Page 65: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

BALAGHAT – NAINPUR (75.41 km. non – electrified section)

I- Section falling in distt. of Balaghat & Mandla in MP state.

II-Acquisition of land

Pvt. & Govt land (50.56 hect.) – nearly 100%.

Mandla distt- 100% (20.60 hect.)

Balaghat distt(75.47 hect) case pending with MOEF since Feb-09 .

Page 66: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Contd.Progress of Major Items as under.

Item Scope Prog. Remarks

Earth work (Lakh. Cum.)

19.0 (Pre.Block) + 9.50 ( in Block)

5.65 Balance Earth work to be done in mega block & in forest area.

Major Bridges (Nos.)

16 70%

3.5 completed.

10 under progress.

1 Bridge falling in forest area.

Page 67: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Item Scope Prog. Remarks

Minor Bridges (Nos.)

119 52%

Pre-cast Segments ready for 19 bridges. For 32 bridges tender finalised & 47 bridges on detour.

Ballast (Cum.) 141100 108000Contract finalised for full quantity. 20% ballast being taken in depot.

Track Linking (In Km.)

80 Km. (Incl. Loop

line)-

65% P. way material arranged.

Contd.

TDC - 30 months after possession of forest land i. e. Oct - 2012. Full 75 Km will be opened in one stretch.

Page 68: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

MANDALA FORT- NAINPUR - CHHINDWARA (182.25 Km. Non-Electrified)

The project is being tackled in two phases i. e. (i) Mandla Fort - Nainpur (42.25 Km.) (ii) Nainpur - Chhindwara (140 Km.)

Final location survey of Mandla Fort – Chhindwara completed. Part detailed estimate sent to Rly. Board in May-10.

Tender floated for Major Bridges on 04.10.10. TDC – Dec-2012

Year of sanction

Anticipated cost.

Exp. Upto Mar-10

2009-10Overall progressExp. Upto

Oct-10

2010-11 556.54 - 0 0%

Page 69: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

NAINPUR - CHHINDWARA (140 Km. Non-Electrified)

Contd..

Final location completed 50 Km. and balance is under progress.

Detailed estimate will be submitted to Rly. Board by April – 2011.

TDC

Section Blocking Opening

NIR - Seoni (76 Km.) Dec - 13 Dec -14

Seoni – Chhindwara (64 Km.) Dec - 14 Dec - 15

Page 70: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

CHHINDWARA – NAGPUR GC (149.52 Km. Non-Electrified)

The project is covering 53 Km. in Nagpur distt. of Maharastra & 96.52 km. in Chhindwara distt. of M.P.

Total land required 328 hec. (128 hec. forest & 200 hect. private/Govt. land. 80% in M. P. & 20% in Maharastra.

2nd stage clearance of MOEF for forest land received on 30.9.09. & trees cutting in progress.

Year of sanction

Anticipated cost.

Exp. Upto Mar-10

2009-10Overall progressExp. Upto

Oct-10

2005-06 585.93 123.23 15.06 23%

Page 71: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Item Scope Prog. Remarks

Earth work (Lakh. Cum.)

95.91 22.08

E/W in progress in six block sections covering 70 km. & including two major bridge approaches.

Major Bridge (Nos.)

27 42%

Sub structure of 12 bridges completed, 12 bridges in progress. Design of 3 bridges in prorgress. 43 fabricated spans received out of 87.

Contd.

Page 72: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

Item Scope Prog. Remarks

Minor bridge (Nos.)

254 (40 in detour)

-

18 in situ bridges completed. Segmental casting completed for 139 bridges. Out of 40 bridges in detour portion work is in progress on 3 Br. Tender opened for 16 bridges under finalisation.

Segmental 139

Cast in situ 40

Contd.

Tender for 2 tunnels of 750 m & 150 m long opened on 22.03.2010.

Tender for 3 viaducts are invited.

Page 73: 1.Status of Items Announced in Budget 10-11 2. Planning of N.G. conversion in NGP Divn. 3. Targeted works 2010-11. Const. Organization.

All indents for span of 12.2 m & 18.3 m placed on CEWS/Manmad. 30.5 m spans are being manufactured by agency. Indents for 45.73 m are being placed with modified 25 tonnes loading on CEWS/Manmad.

Ballast - Total requirement 3.36 lac. cum. Tender finalised for the stretch falling in Maharastra State of 0.84Lac cum and 0.85cum for MP.state and progressed 0.58 lac cum.

TDC

Section Blocking Opening

CWA - ULA (25 Km. Dec - 10 June -11

ULA – Saoner (80 Km.) June - 11 June -12

Saoner - NGP (44 Km.) Dec -12 June -13