    API 570 CERT

    Slide 1

    PQR:FORM QW-483

    This presentation is to help you understand

    the variables on the PQR form QW-483

    As you review this presentation ,make sure

    you have a printed copy of your QW-483

    form .The idea is that as you look at eachslide, you look at the corresponding area on

    your QW-483 form

    PRESENTATION 3

  • 7/30/2019 1.B.4-3

    2/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 2

    This is the front of the form

    FORM QW-483

  • 7/30/2019 1.B.4-3

    3/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 3

    This is the back of the form

    FORM QW-483

  • 7/30/2019 1.B.4-3

    4/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 4

    PQR:FORM QW-483

    Red= Essential variables

    Green= Non-essential variables

    Yellow= Supplementary essential

    variables

    E

    S

    NE

    For this PQR form ,there are fewer differences in the classification of the

    variables between the SMAW,GTAW.GMAW and SAW processes than

    there were for the WPS form QW-482

    The text colour shows whether anentry on the form (for

    SMAW,GTAW,GMAW or SAW)

    is an essential,supplementary or

    non-essential variable

    Key

    NOTE

  • 7/30/2019 1.B.4-3

    5/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 5

    Start by looking at the top

    section of the QW-483 form

    The next slide shows this section in

    detail.Note the colour codes denoting

    the classification of variable

    PQR:FORM QW-483

    E

    SNE

  • 7/30/2019 1.B.4-3

    6/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 6

    QW-483 PQR (FRONT)Company Name_____________________________________________________________________

    Procedure Qualification Record No. _______________________________________Date__________

    WPS No___________________________________________________________________________

    Welding Process(es)_______________ESSENTIAL___________________Types (Manual, Automatic, Semi-Auto)

    JOINTS (QW-402)

    NON ESSENTIAL

    Groove Design of Test Coupon

    (For combination qualifications, the deposited weld metal thickness that shall be recorded for each filler metalor process used)

    E

    SNE

    PQR:FORM QW-483

  • 7/30/2019 1.B.4-3

    7/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 7

    BASE METALS (QW-403)Material spec._________________________

    Type or Grade ________________________

    P-No ____ESSENTIAL____________to P-No__ESSENTIAL___

    Thickness of test coupon ____ESSENTIAL____________

    Diameter of test coupon _________________

    Other_________________________________________________________________________________________________

    _____________

    FILLER METALS (QW-404)SFA Specification ______ NON ESSENTIAL _____________

    AWS Classification ______________________

    Filler metal F-No _____ESSENTIAL___________

    Weld Metal Analysis A-No ____ESSENTIAL___________

    Size of Filler Metal ______NON ESSENTIAL_______________

    Other ________________________________

    Weld Metal Thickness____ESSENTIAL________________

    E

    SNE

    PQR:FORM QW-483

  • 7/30/2019 1.B.4-3

    8/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 8

    POSITIONS (QW-405)

    Position of Groove ______NON ESSENTIAL______

    Welding Progression (Uphill, Downhill) _NON ESSENTIAL___Other _______________________________________

    PREHEAT (QW-406)

    Preheat Temp. _______ESSENTIAL______________

    Interpass Temp._____________________________

    Other _____________________________________

    POSTWELD HEAT TREATMENT (QW-407)

    Temperature___ESSENTIAL_____________________

    Time __________ESSENTIAL____________________

    Other ______________________________________

    ___________________________________________

    E

    SNE

    PQR:FORM QW-483

  • 7/30/2019 1.B.4-3

    9/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 9

    GAS (QW-408)

    Percent composition

    Gas(es) (Mixture) Flow Rate

    Shielding ____E____ ____E___ ____NE_____

    Trailing ___NE____ ____NE___ ___NE_____

    Backing ___NE___ ____NE____ ___NE_____

    ELECTRICAL CHARACTERISTICS (QW-409)

    Current ________NON ESSENTIAL____________

    Polarity_________NON ESSENTIAL____________

    Amps __NE____________Volts ____NE_________

    Tungsten Electrode Size _____NE__GTAW only__

    Other ____(Metal transfer mode- GMAW)________

    _____________________________________________

    For GMAW and GTAW only

    E

    SNE

    PQR:FORM QW-483

  • 7/30/2019 1.B.4-3

    10/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 10

    TECHNIQUE (QW-410)

    Travel Speed ______________________________

    String or Weave Bead ____NON ESSENTIAL_____

    Oscillation __NON ESSENTIAL (Not SMAW)_____

    Multiple or Single Pass (per side) ____NE__________

    Single or Multiple Electrodes ______NE___________

    Other ____________________________________

    __________________________________________

    _________________________________________

    E

    SNE

    PQR:FORM QW-483

  • 7/30/2019 1.B.4-3

    11/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 11

    PQR No. _______

    TENSILE TEST (QW-150)

    Type of

    Failure &

    Location

    Ultimate Unit

    Stress

    psi

    Ultimate

    Total

    load

    lb

    AreaThicknessWidthSpecimen No

    Types of test are given in figures QW-462.1(a) through to QW-462.1(e)

    Acceptance criteria is given in QW-153.1

    Minimum Specified Tensile values for base materials are given in table QW-422

    E

    SNE

    PQR:FORM QW-483 (BACK)

  • 7/30/2019 1.B.4-3

    12/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 12

    GUIDED- BEND TESTS (QW-160)

    ResultType and Figure No

    Types of bend will normally be transverse side, transverse root or transverse face bends.

    QW-462.2 contains details of side bends

    QW462.3(a) contains details of face bends and root bends

    QW-163 contains the acceptance criteria for bend tests

    Table QW-451.1 gives types and number of transverse bend tests required for base material thickness.

    MARK THESE SECTIONS WITH POST IT NOTES

    E

    SNE

    PQR:FORM QW-483 (BACK)

  • 7/30/2019 1.B.4-3

    13/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 13

    TOUGHNESS TESTS (QW-170)

    DropWeight

    Break (Y/N)

    Impact ValuesFt-lb% Shear MilsTest TempSpecimen

    Size

    Notch

    Location

    Specimen

    No

    Comments ___________________________________________________________________________________

    This section is for when notch toughness is required so can be ignored for the exam.

    E

    SNE

    PQR:FORM QW-483 (BACK)

  • 7/30/2019 1.B.4-3

    14/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 14

    FILLET WELD TEST (QW-180)

    Result Satisfactory? : Yes_____ No ______ Penetration into Parent Metal? : Yes____ No ______

    Macro Results ________________________________________________________________________

    OTHER TESTSType of Test __________________________________________________________________________

    Deposit Analysis ____________________________________________________________________________

    Other _____________________________________________________________________________________

    Prepare specimens to QW-181.1

    Macro examine in accordance with QW-183

    Ignore this area

    E

    SNE

    PQR:FORM QW-483 (BACK)

  • 7/30/2019 1.B.4-3

    15/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 15

    Welders Name _________________________________ Clock No. ______________ Stamp No.________

    Tests conducted by: ________________________________ Laboratory Test No. _____________________

    We certify that the statements in this record are correct and that the tests welds were prepared, welded, and tested

    in accordance with the requirements of Section IX of the ASME Code.

    Manufacturer _________________________________

    Date_____________________________________ By _________________________________

    (Detail of record of tests are illustrative only and may be modified to conform to the type and number of tests

    required by the Code.)

    Ensure these are all filled in.

    The PQR must contain the manufacturers name and be signed by the manufacturer to certify it is a truerecord of the variables and tests.

    The actual mechanical testing can be subcontracted (ie to a test house or laboratory)E

    S

    NE

    PQR:FORM QW-483 (BACK)

  • 7/30/2019 1.B.4-3

    16/16

    Matthews Engineering Training Ltd

    API 570 CERT

    Slide 16

    BEFORE PROCEEDING

    FURTHER

    Check now that you know what the classificationof the various variables are on the PQR for the 4

    main welding processes

    THERE WILL ALMOST CERTAINLY BE EXAM

    QUESTIONS ON THIS TOPIC

    GMAWSMAW GTAW SAW

    PQR

    FORM QW-483