Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces Conclusions 22/06/2007 18-1 18. CONCLUSIONS AND RECOMMENDATIONS The Environmental Impact Assessment (EIA) process for the proposed establishment of a Pumped Storage Scheme (PSS) in the Steelpoort area has been undertaken in accordance with the EIA Regulations published in Government Notice No R385, R386 and R387 of 2006 in terms of Section 24 (5) of the National Environmental Management Act - NEMA (Act No 107 of 1998). The essence of any EIA process is aimed at ensuring informed decision-making and environmental accountability, and to assist in achieving environmentally sound and sustainable development. In terms of NEMA (No 107 of 1998), the commitment to sustainable development is evident in the provision that “development must be socially, environmentally and economically sustainable…and requires the consideration of all relevant factors…”. NEMA also imposes a duty of care, which places a positive obligation on any person who has caused, is causing, or is likely to cause damage to the environment to take reasonable steps to prevent such damage. In terms of NEMA’s preventative principle, potentially negative impacts on the environment and on people’s environmental rights (in terms of the Constitution of the Republic of South Africa, Act 108 of 1996) should be anticipated and prevented, and where they cannot be altogether prevented, they must be minimised and remedied in terms of “reasonable measures”. In assessing the environmental feasibility of the proposed project, the requirements of all relevant legislation has been considered including inter alia those of: • National Environmental Management Act (No 107 of 1998); • Environment Conservation Act (No 73 of 1989); • National Water Act (No 36 of 1998); • National Heritage Resources Act (No 25 of 1999); • The Minerals and Petroleum Resources Development Act (No. 28 of 2002); • Atmospheric Pollution Prevention Act (No 45 of 1965); • National Environmental Management: Air Quality Act 39 of 2004; • Mine Safety Act (No 29 0f 1996) • Occupational Health and Safety Act (No 85 of 93); • White Paper on Energy Policy, GN 3007, 17/12/1998; • White Paper on Integrated Pollution and Waste Management for South Africa (January 2000); and • National Waste Management Strategy documents (October 1999). This relevant legislation has informed the identification and development of appropriate management and mitigation measures that should be implemented in order to minimise potentially significant impacts associated with the project.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-1
18. CONCLUSIONS AND RECOMMENDATIONS
The Environmental Impact Assessment (EIA) process for the proposed
establishment of a Pumped Storage Scheme (PSS) in the Steelpoort area has
been undertaken in accordance with the EIA Regulations published in Government
Notice No R385, R386 and R387 of 2006 in terms of Section 24 (5) of the
National Environmental Management Act - NEMA (Act No 107 of 1998).
The essence of any EIA process is aimed at ensuring informed decision-making
and environmental accountability, and to assist in achieving environmentally
sound and sustainable development. In terms of NEMA (No 107 of 1998), the
commitment to sustainable development is evident in the provision that
“development must be socially, environmentally and economically
sustainable…and requires the consideration of all relevant factors…”. NEMA also
imposes a duty of care, which places a positive obligation on any person who has
caused, is causing, or is likely to cause damage to the environment to take
reasonable steps to prevent such damage. In terms of NEMA’s preventative
principle, potentially negative impacts on the environment and on people’s
environmental rights (in terms of the Constitution of the Republic of South Africa,
Act 108 of 1996) should be anticipated and prevented, and where they cannot be
altogether prevented, they must be minimised and remedied in terms of
“reasonable measures”.
In assessing the environmental feasibility of the proposed project, the
requirements of all relevant legislation has been considered including inter alia
those of:
• National Environmental Management Act (No 107 of 1998);
• Environment Conservation Act (No 73 of 1989);
• National Water Act (No 36 of 1998);
• National Heritage Resources Act (No 25 of 1999);
• The Minerals and Petroleum Resources Development Act (No. 28 of 2002);
• Atmospheric Pollution Prevention Act (No 45 of 1965);
• National Environmental Management: Air Quality Act 39 of 2004;
• Mine Safety Act (No 29 0f 1996)
• Occupational Health and Safety Act (No 85 of 93);
• White Paper on Energy Policy, GN 3007, 17/12/1998;
• White Paper on Integrated Pollution and Waste Management for South
Africa (January 2000); and
• National Waste Management Strategy documents (October 1999).
This relevant legislation has informed the identification and development of
appropriate management and mitigation measures that should be implemented in
order to minimise potentially significant impacts associated with the project.
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-2
The conclusions of this EIA are the result of comprehensive studies and specialist
assessments. These studies were based on issues identified through the EIA
process and the parallel process of public participation. The public consultation
process has been rigorous and extensive, and every effort has been made to
include representatives of all stakeholders within the process.
18.1 Evaluation of the Proposed Project
The preceding chapters of this report provide a detailed assessment of the predicted
environmental impacts on specific components of the social and biophysical
environment as a result of the proposed project. This chapter concludes the EIA
report by providing a holistic evaluation of the most important environmental
impacts identified through the process. In so doing, it draws on the information
gathered as part of the EIA process and the knowledge gained by the environmental
consultants during the course of the EIA and presents an informed opinion about the
proposed project.
In order to meet the objectives as set out in the South African Energy Policy as
well as to meet developmental and socio-economic objectives in South Africa, the
country needs to optimally use the available energy resources. Eskom is required
to respond to the growing electricity demand of approximately 3 - 5% per annum.
This growing demand is placing increasing pressure on Eskom’s existing power
generating capacity. In order to ensure that potential future electricity demands
are met, Eskom is investigating a variety of options including conventional
pulverised fuel power plants, pumped storage schemes, gas-fired power plants,
nuclear plants, greenfield fluidised bed combustion technologies, renewable
energy technologies (mainly wind and solar projects), and import options within
the Southern African region.
Eskom’s “project funnel”, which shows the range of supply options being
considered by Eskom to meet the increasing demand for electricity in the country,
currently consists of 34 projects ranging from research projects to new-build
projects. Research projects include a demonstration solar power project,
underground coal gasification and the pebble bed modular reactor (PBMR). In
additions, three ‘mothballed’ stations, including the Camden, Komati and
Grootvlei power stations, are currently being returned-to-service.
In order to meet future peak capacity demands, Eskom proposes constructing a
pumped storage scheme (PSS) in the Steelpoort area.
A PSS utilises surplus electricity generating capacity on the Eskom system during
off-peak hours to pump water from the lower to the upper reservoir and releases
this water again during peak load hours to generate electricity. A PSS thus
relieves the need for other more expensive peaking plant such as gas fired
turbines to meet peak loads and also relieves the need of two running coal fired
plants as load following or peaking plants. Coal fired power stations are best
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-3
suited to base load and are optimally run at constant loads. The use of PSS for
peaking power therefore allows coal fired generating units to operate more
efficiently, increases the expected life of these units and to provide a method of
“storing” energy for later release it when it is required.
The proposed PSS will consist of two reservoirs (an upper and a lower reservoir),
interconnected by an underground tunnel system (waterways) with pump turbine
units located in an underground powerhouse complex with an installed capacity of
approximately 1520 MW. In addition to this, the scheme will also have access and
site roads (temporary and permanent), two construction villages, two
communication masts that will each be a maximum of approximately 45m high
(one at the upper reservoir and the other at the lower reservoir).The heights were
assessed in the Visual Impact Assessment and the correct positioning of the
masts will reduce the required height substantially.
The Environmental Scoping Study investigated 3 sites identified as potentially
feasible for the establishment of the proposed PSS. Through numerous specialist
environmental studies (both social and biophysical) the following site was
nominated during the scoping phase for further investigation within the EIA phase
of the project. The scoping report was accepted by the Department of
Environmental Affairs and Tourism:
• Site A3 (between farms Luipershoek 149 JS and Keerom 151 JS)
The potentially significant environmental impacts associated with the proposed
project as discussed in the EIA include:
• Potential impacts on geology, soils and agricultural potential as a result of the
proposed project;
• Potential impacts on geohydrology and surface water drainage;
• Potential impacts on wetlands;
• Potential impacts on flora, fauna and ecology;
• Potential impacts on archaeological and heritage resources;
• Potential visual impacts associated with the proposed project;
• Potential noise impacts;
• Potential social impacts;
• Potential traffic impacts; and
• Potential tourism impacts associated with the proposed project.
On initial investigations associated with the Scoping phase, no fatal flaws were
identified since the impacts were deemed mitigatable to acceptable levels.
Due to the outcomes of the Environmental Scoping Study, additional
investigations were required with regards to associated infrastructure. The EIA
also evaluated the two access road alternatives, two construction villages, and
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-4
the construction of two communication masts. The specialist studies undertaken,
made recommendations which are included within the discussions below.
18.2 Final Conclusions of the Specialist Studies
18.2.1 Geology
The feasibility stage geotechnical investigations have revealed the following:
• Poorer foundation conditions at both the upper and lower reservoir than
originally anticipated, however, this will not inhibit the construction process.
• In general, construction materials for the dam walls are all available within
the dam basin. Clay material for the lower dam core is available in close
proximity.
• Generally very good rock conditions exist for the underground works.
• The various rock types grade almost imperceptibly into one another with the
boundaries not readily apparent.
• Major faults/shear zones should not be discounted in the underground works
in the area of the pressure tunnel although the Steelpoort Fault is some
distance away and should not impact on the preferred site. Some minor
zones of highly fractured rock, which may well be associated with water
inflows, should be expected, again these can be adequately mitigated.
• A distinctive “zebra-striped” band of very strong to extremely strong rock
(mixed anorthosite-rich and magnetite-rich diorite) appears to occur in the
upper levels of the machine and transformer halls. This band is expected to
occur over a fairly extensive length in the pressure tunnel. The band does
not appear to form a discontinuity with the adjacent very strong rock diorite,
i.e. no obvious plane of weakness appears to occur between the rock types.
• Portal and trench excavations will require shallow angle cut slopes or fairly
robust support measures.
Further investigations will be required in order to supply sufficient information
and data for detailed design to proceed. However, no fatal flaws were discovered
in the initial geotechnical investigation that would restrict the development from
taking place.
18.2.2 Soils and Agricultural Potential
The upper and lower reservoir sites consist mostly of shallow soils. Closer to the
streams, a zone of deeper, alluvial soils occurs. Some deeper, but more
structured soils occur to the east of the lower reservoir site.
No areas with high agricultural potential occur within the upper and lower
reservoir sites. Furthermore, since all the roads are already existing routes, the
overall impacts on soils and agricultural potential is low.
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-5
Developments occurring near the zone of deeper, alluvial soil should be treated
with caution. If such developments are temporary (as in the case of the
construction villages), the land should be rehabilitated and returned to its original
condition as far a possible.
18.2.3 Geohydrology
The study area is underlain by rock formations of the Bushveld Igneous Complex
and from a geohydrological point of view it is classified as minor-aquifer system.
Therefore no large scale groundwater abstraction occurs within the study area.
• A north-east and north-west striking fault converge over the study area.
These geological structures can enhance the groundwater potential in the
area by increasing the permeability and transmissivity of the host rock.
Secondary processes, such as faulting and fracturing, can create
secondary fractured rock aquifers. Should these structures be water
bearing, short term groundwater related impacts are foreseen during the
construction phase of the tunnel, as dewatering will be required.
• Static groundwater levels measured in piezometers at the lower reservoir
site indicated highly weathered zones with possibly enhanced aquifer
parameters. Aquifer recharge may be enhanced as a result of secondary
processes (weathered zones) intersecting in these borehole sites.
• The degree of fluctuation in the groundwater levels along the lower
reservoir site relates to the weathering depth of diorite, as the water table
occurs at the contact between the weathered and unweathered rock.
Artificial aquifer recharge that may result from seepage will improve the
sustainability of groundwater, which is currently classified as poor based
on their poor aquifer parameters. Seepage below and around the dam wall
grouting curtain will allow for base-flow to the tributaries down-gradient of
the lower reservoir site. This will assist in complying with the catchments
ecological reserve requirements.
• Dewatering in order to enable construction of certain components of the
underground pumped storage facilities is only seen as a temporary
negative impact, which will cease during the operational phase.
• Static groundwater levels in the boreholes at the upper reservoir site
remained constant within boreholes. This indicates limited recharge and
transmissivity and conductivity associated with weathering
zones/fractures.
• Intercepting water bearing fractures during the construction phase of the
pumped storage facility is considered as a short-term negative impact.
Grouting of these structures will prevent long-term impacts. There are no
groundwater uses in the expected zone of influence that will be caused by
dewatering.
• Unless prevented, seepage from pollution sources (fuel, sewage and
waste) is considered the only long term negative impact.
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-6
• The proposed sewage is a closed system with treatment plants therefore
there is likely to be no impact on groundwater.
• The correct construction and management of the infrastructure will ensure
that the overall risk to the groundwater resources is tolerable and thus the
project can be supported from a geohydrological perspective.
18.2.4 Surface Water and Drainage
The study area is situated in the headwater to middle reaches of a tributary of the
Steelpoort River, where most of the river flow is generated by direct precipitation.
The study has found that there are no fatal flaws or any intolerable impacts,
which will result from the proposed project, with regards to the surface water
aspects. Through careful mitigation, correct management strategies, and auditing
procedures, during the construction and operation phases, the envisaged
potential impacts should be low (mitigation measures are included in Table 18.2).
The impacts are, however, envisaged to be localised.
Negative impacts resulting from the secondary construction activities (including
but not limited to; burrowing, housing, sewage, and water abstraction), can all
successfully be mitigated to low impacts of a temporary nature, and can
successfully be rehabilitated to a state, according to the objective of the
Environmental Management Plan, for the specific area.
It can thus be concluded that the proposed project is feasible should the
suggested management options be implemented.
18.2.5 Wetlands
No wetlands occur within the footprint of the proposed scheme (except for a small
area in the vicinity of the lower construction village), the scheme will not cause a
loss of physical wetland habitat and the project can be supported from a wetland
perspective.
A number of wetlands are located adjacent to the upper reservoir, and a 50m
buffer has been demarcated around these wetlands. It is of crucial importance
that no development or other impacts should be allowed within this zone; this
would include traversing of the area by vehicles or the establishment of any
ancillary infrastructure such as stockpile areas.
18.2.6 Biodiversity
The nature of the proposed development makes the complete mitigation of likely
impacts extremely difficult; the exclusion of high sensitivity areas will in effect
sterilise the entire project and is therefore not considered a viable option.
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-7
Impacts resulting from the development will result in transformation of large
tracts of natural and sensitive environment and will be permanent. These impacts
are therefore significant and cannot be mitigated effectively. However, impacts
will mostly be localised and site specific and can therefore be contained within a
relative small area and there were no red data species found within the
construction footprint. Constant environmental monitoring will play a significant
role in the timely identification of potential significant effects resulting from
construction activities while periodic bio-monitoring will highlight effects such as
species changes and infestation by invasive species.
It is, therefore, the conclusion of the biodiversity assessment that, with the
successful implementation of environmental and bio-monitoring programmes, the
resultant loss in biodiversity attributes and habitat is acceptable and within
reason and therefore the project can be supported.
18.2.7 Archaeological and Heritage Resources
A number of sites dating to the Late Iron Age, Early Historic Period were identified
that would be impacted on by the proposed development. The identified sites do
not present much of a problem, as current legislation allows for mitigation
measures to be implemented. However, impacts on sites can be lessened by:
• Rerouting/relocating of access routes, construction yards, etc.
• Formalising sites by fencing them off
Based on what was found and its evaluation, it is recommended that the
proposed development can continue, with implementation of the following
recommendations:
• That the mitigation measures for each identified site are implemented before
development takes place.
• Sites 14 and 15 that will be impacted by the construction yard can be avoided
by moving the yard further south. This can be determined by taking the
coordinates as centre point and extending a buffer zone of 30 metres from
these points. This would be sufficient to avoid the heritage sites.
• Site 3 dating back to the Late Iron Age should be documented and test
excavations done.
• Sites 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 17 in the lower reservoir area date to
the Late Iron Age and early historic period. All of these sites should be
documented and test excavated.
• The developer should therefore keep in mind that archaeological sites might
be exposed during construction activities. If anything is noticed, work in that
area should be stopped and the occurrence should immediately be reported
to a museum or regional SAHRA office, specifically one at which an
archaeologist is available. The archaeologist should then investigate and
evaluate the finds.
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-8
18.2.8 Visual/Aesthetic
The construction of a feature as huge and extensive as the Pumped Storage
Scheme introduces a highly contrasting feature into the environment. The
character of the study area in general reflects a high degree of natural veld, with
human activities related to rural settlements. The escarpment-like topography of
the area renders it a very high visual quality which will be impacted upon by the
proposed development.
The visual impact of the proposed development will be adverse, the significance
of which varies from very high to medium, as indicated by the Visual Impact
Index. As indicated in Figure 14.16, these impacts are localised and mostly
associated with proximity to the site. However, the overall impact after mitigation
measures are implemented is a medium negative significance.
The area is sparsely populated with critical visual receptor points localised at
villages, farmsteads and on roads. At these points, the adverse impact will be
significant. Cognisance must be taken of lighting as an important visual impact
with an annoyance element linked to it. It is recommended that design specific
mitigation measures be drawn up as soon as details of lighting design become
available. With regard to construction, care are must be taken to maintain
temporary structures and building yards at an aesthetic acceptable level.
In conclusion, visual impacts associated with the project are unavoidable, but the
specialist has investigated these impacts and believes the proposed project does
not hold a fatal flaw that would restrict the development from taking place.
18.2.9 Noise
The following may be concluded from the noise assessment:
• The baseline noise data from a similar facility (Drakensberg PSS) was
available and the assumptions made are considered adequate to give a
meaningful analysis of the noise impact situation.
• The area of potentially serious noise impact around the planned PSS in the
Steelpoort area once the PSS is operational will be fairly small. It is
predicted that any impacts will be contained an area within a distance of
about 300m of the edge of the PSS works. There will be no noise impacts
at Sehlakwane Village from the operations at the upper reservoir site.
• With the natural growth in traffic (with the development of the Veremo Mine),
noise levels alongside the main roads will continue to increase and the already
degraded noise climate within the area of influence of these roads will worsen.
The additional noise from the PSS site generated traffic will be insignificant.
Based on the above conclusions, the project is thus supported from a noise
perspective.
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-9
18.2.10 Social
The pre-construction phase has a number of positive impacts that should be
enhanced as this would lay the foundation for the rest of the project. Negative
impacts are mostly found during the construction/decommissioning phases of the
project. This is mainly due to the nature of the activities that take place during
these phases. Most of the negative impacts can be mitigated successfully.
The operational phase is also characterised by a number of positive impacts,
which could be further enhanced if managed effectively. These impacts mostly
relate to sustainable development in the affected community by means of
employment opportunities (directly and indirectly) as well as infrastructure
development.
Both the social and land use themes have a number of negative impacts.
However, all of these impacts can be mitigated successfully if effectively
managed. Economic impacts as a result of the project are all positive in nature,
which is mainly due to the economic investment and development that will take
place in the community as a result of the project. The project can therefore be
supported from a social perspective.
18.2.11 Traffic
• The effect on pavement loading by construction vehicles and subsequent
acceleration of any rehabilitation programme could be mitigated by initiating
negotiations regarding the possible contribution by Eskom to the pavement
rehabilitation programme with the relevant provincial authorities.
• The traffic impact of the envisaged construction traffic on key intersections is
not significant.
• The effect of locating 2500 workers on site at the lower reservoir will reduce
the number of buses to and from the site to zero. This change, therefore, has
the beneficial effect of reducing the traffic impact of transporting the workers
to a very small amount in both peak hour and during the day. The
transportation of food and supplies for the workforce, although higher, is
considered to be low in magnitude and in frequency.
• There is presently sufficient spare capacity at all key intersections (an
increase of approximately 15%) to accommodate peak period traffic increase
during the operational phase.
18.2.12 Tourism
The tourism industry in the Steelpoort area is still in its infancy, but is growing.
The industry has, in the past, been dependant on the mining industry for its
sustainability. There is ‘little to no’ tourism in the Mathula/Sehlakwane area, but
it does form part of the Cultural Heritage Route.
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-10
The proposed development of the PSS is expected to have negative impacts
relating to loss of sense of place during the construction phase and to a lesser
extent during the operational phase. The construction phase is likely to exert the
greatest negative impact on the existing game reserves in the area through the
construction camp and the construction traffic. This is mainly due to the large size
of the construction camp which will house 2500 workers at the lower reservoir.
However, the overall impact will be a positive one both during construction and
operation as a result of the increased business tourism that is expected to be
generated by the proposed development.
18.3 Access Roads
The specialist studies investigated two road alternatives for the permanent access
roads to the proposed site. Both alternatives follow existing routes, and all
specialist studies found that as the roads followed existing routes there would be no
additional impacts on biophysical and social environment, however from a social
perspective Road alternative - Option 1 was deemed as the most viable option,
seeing as this alternative requires the lowest cost to upgrade as most of the road
sections within this alternative are already paved, hence development of this road is
more economical. This route will also have the lowest impact on all environmental
features within the study area. The upgrading of the Tonteldoos Road in Road
alternative - Option 2 is not seen as a major impact, however, the existing road
alternatives in Road alternative - Option 1 are more favourable.
As far as maintenance of roads to be used by Eskom is concerned, it is therefore
recommended that Eskom and/or its appointed contractor(s) meet with the
Provincial Road Agency beforehand to discuss implications and accountability of
road maintenance.
18.4 Recommendations for Appropriate Mitigation Measures
From the findings of the specialist studies undertaken, the following mitigation
measures are proposed to be implemented in order to minimise any potentially
significant impacts. Table 18.1 below displays a summary of aspects, the rating of
impacts and the associated mitigation measures in the construction phase
investigated in the EIA. Table 18.2 below displays a summary of aspects, the
rating of impacts and the associated mitigation measures in the operational phase
investigated in the EIA.
A summary of issues, the rating of impacts and the associated mitigation
measures in the construction and operational phases investigated in the EIA, will
follow, the rating criteria are included in Table 18.1 the rating of 8- for example
indicates a medium negative impact 12+ is a high positive impact.
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-11
Table 18.1 Criteria for the rating of classified impacts environmental impacts
Significance
• Low impact (4-7
points)
• Medium impact (7-10
points)
• High impact (10-13
points)
• Very high impact (13-
16 points)
The significance of impacts is rated as follows.
• A low impact has no permanent impact of significance.
Mitigatory measures are feasible and are readily
inistituted as part of a standing design, construction or
operating procedure
• Mitigation is possible with additional design and
construction inputs
• The design of the site may be affected. Mitigation and
possible remediation are needed during the
construction and/or operational phases. The effects of
the impact may affect the broader environment
• Permanent and important impacts. The design of the
site may be affected. Intensive remediation os needed
during construction and/or operational phases. Any
activity which results in a “very high impact” is likely to
be a fatal flaw.
Status
• Positive (+)
• Negative (-)
• Neutral
Denotes the perceived effect of the impact on the affected
area.
• Beneficial impact.
• Deleterious or adverse impact.
• Impact is neither beneficial nor adverse.
• It is important to note that the status of an impact is
assigned based on the status quo – i.e. should the
project not proceed. Therefore not all negative impacts
are equally significant.
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-12
Table 18.2 Summary of issues, the rating of impacts and the associated mitigation measures in the construction phase investigated in the
EIA.
Issue Impact
Rating
Mitigation Measures Impact Rating after
Mitigation
Geology
Geology 7- • No mitigation measures were recommended at this stage of
these investigations.
• Mitigation measures will be recommended during additional
detailed geotechnical investigations in the design phase of the
project.
-
Soils and Agricultural Potential
Loss of soil resource 9- • No mitigation measures are possible, since the soils will be
covered by the construction of the dams
-
Loss of agricultural potential 7- • Due to the low existing agricultural potential in the area.
Mitigation measures are not required.
-
Geohydrology
Borehole loss 6- • Compensation for boreholes loss by providing alternative water
source.
• Re-drilling boreholes to substitute loss.
10+
Dewatering of surge shaft
decant
4- • Drill 700m deep borehole at the proposed shaft position to
establish presence of water bearing fracture zones.
• Dewater inflowing groundwater during the construction phase.
• Apply water in construction process, minimising the demand
from more expensive sources.
• Grouting side walls will prevent groundwater inflow during
construction phase.
After mitigation no
impact is foreseen.
Dewatering of machine and
transformer halls
4- • Dewatering during the construction phase.
• Apply water in the construction process, minimising the
demand for more expensive sources.
• Grouting side walls will prevent long-term impacts after
construction.
After mitigation no
impact is foreseen.
Dewatering of pressure
tunnel
6- • Dewatering during the construction phase.
• Apply water in the construction process, minimising the
After mitigation no
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-13
demand for more expensive sources.
• Grouting side walls will prevent long-term impacts after
construction.
impact is foreseen.
Dewatering of tailrace,
access and emergency
tunnels
5- • Dewatering during the construction phase.
• Apply water in the construction process, minimising the
demand for more expensive sources.
• Grouting side walls will prevent long-term impacts after
construction.
After mitigation no
impact is foreseen.
Groundwater quality
associated with waste water
treatment
8- • Exclude soak-aways and wastewater irrigation as methods of
disposal.
• Assess underlying geological structures prior to positioning. of
all evaporation/maturation ponds, if any.
• In case of wastewater works as treatment method, ensure
correctly sized, designed and constructed facility.
• Construct all waste water dams to minimise seepage, i.e. lined
dams.
• Design ponds (if any) in such a manner to ensure sufficient
capacity and prevent overflow / spillage.
• Install monitoring boreholes to monitor groundwater quality.
7-
Groundwater quality
associated with seepage from
waste disposal
10- • Area to be managed to prevent ponding of poor quality water.
• Install a drainage system below the disposal facility.
• Poor quality water to be diverted to lined recovery dams.
• Line waste disposal facility to prevent leachate from entering
the groundwater.
• Dispose of solid waste at an alternative licensed disposal
facility.
• Install groundwater monitoring boreholes to monitor
groundwater quality down-gradient of disposal facility.
• Prevent further groundwater use until after remediation period.
7-
Groundwater quality
associated with fuel/oil
spillages
9- • Contain oil and fuel in bunded areas.
• Ensure clean-up protocols are in place and followed when
required.
• Install oil traps and separators.
• Keep accurate oil/fuel records (purchased, disposal, and
recycled).
4-
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-14
• Install monitoring boreholes to monitor groundwater quality.
• Remediate spillages.
• Prevent further groundwater use until after remediation period.
Groundwater losses due to
borrow pit areas
9- • Excavations to remain above static groundwater level to
prevent evaporative losses as a result of groundwater decant.
6-
OVERALL ASSESSMENT 7- • With the appropriate mitigation measures, the potential
impacts on geohydrology will remain low.
6-
Surface Water and Drainage
Ecological instream flow
requirements
12- • Design outlet works, for ecological releases.
• Establish, implement and monitor the ecological reserve.
• Flow measurement of releases.
• Set management objectives for the ecological reserve.
9-
River diversions 8- • Should be engineer-designed to allow for the free movement of
runoff water.
• Should be engineer-designed to prevent degradation of water
courses such as the forming of erosion.
• Should be designed to mitigate biological loss and habitat.
7-
Stream/drainage line
crossings
8- • Adequate drainage systems at river crossings to prevent
damming up and backwater at upstream sides.
• Sufficient drainage systems should be designed as not to choke
watercourse.
• Erosion protection at approaches and drainage systems, to
prevent sediment entering water bodies and to prevent
erosion.
• Protection downstream to prevent scour and to keep flow
velocities down.
• Adequate discharge capacities in the event of flooding.
5-
Permanent stream crossings 10- • Regular inspections at river crossings (EMP).
• Regular maintenance.
• Adequate discharge capacities in the event of flooding.
5-
Spillway erosion 6- • Spillway and stilling basin to be designed according to
acceptable engineering Standards.
6-
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-15
• Regular monitoring of possible forming of erosion or
degradation of watercourses (EMP).
Borrow areas 9- • Borrow areas should be placed outside the 1:100 year flood
line. Where this is not possible, flood protection measures
should be implemented and maintained in cases where borrow
areas are within the 1:100 year flood line.
• Area should be made free draining after construction and
landscaped to follow the natural topography.
6-
Risk of flooding of the
Steelpoort River
12- • Downstream slope, toe, outlet works, spillway, needs to be
designed according to relevant engineering standards.
• Construct dam structure outside relevant flood events.
• Emergency response and preparedness plans need to be
developed for the dam.
• Hydrological data and relevant flood evaluations should be
addressed during the 5-yearly dam safety inspections.
10-
Reservoir breach 12- • Engineer design and construction supervision according to the
guidelines of the South African Committee on Large Dams, and
relevant engineering standards.
• Adequate operation and maintenance.
• Regular dam safety inspections.
• Early warning systems.
• Emergency Response and Preparedness plans.
• - Review of dam design by Authorities or specialists to bring
down the probability of occurrence.
10-
Sewage impacts
8- • Adequate water treatment plant.
• Surface Water Quality Monitoring.
• Flow metering/measuring.
• Safe Disposal of sewage sludge.
6-
Taking of surface water for
the construction camp
7- • Obtaining water from existing water users.
• Installing flow metering / measuring devices to stay within
allocation.
7-
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-16
• Reusing / Recycling of water.
• Maintain systems to reduce leaks.
• Training of workers on water conservation and demand
management.
Service and wash bays 8- • Designated areas for service bay and workshop.
• Adequate bunded and storage areas.
• Safe disposal of oils, grease and soaps off site.
• Environmental clean up procedures in the event of spillage.
• - Separation of clean and dirty water catchments and the
containment of dirty water.
5-
Flooding of the construction
site by surface water bodies
7- • Locality of construction sites should be above 1:100 year flood
lines.
• Adequate engineered designed flood protection measures.
• Maintenance of flood protection measures.
5-
Sewage return flows from
permanent buildings
10- • Community training and awareness.
• Water treatment options.
• Removal or re-routing of contaminant sources.
• - Set environmental objective of the water quality.
7-
OVERALL ASSESSMENT 9- • The medium negative impact can be reduced to a low negative
impact with appropriate mitigation.
7-
Wetlands
Impact on wetlands adjacent
to the upper reservoir site
6- • Ensure that wetlands and associated buffers are not affected
by any construction activities.
4-
Biodiversity
Increase in habitat diversity
and biodiversity
12- • Implementation of bio-monitoring programmes.
• Adaptive management & conservation strategies. • Rehabilitation and control programmes.
9-
Destruction of threatened
species and habitat
11- • Site specific surveys prior to development.
• Removal and translocation of sensitive flora species.
• Use of plants in landscaping.
7-
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-17
• Confine impacts to development area.
• Implementation of site specific rehabilitation programmes.
Destruction of sensitive
habitat types and areas of
high biodiversity
11- • Confine impacts to development area.
• Include sensitive areas as conservation areas.
• Limit movement of vehicles and personnel through areas of
sensitivity.
• Implementation of site specific rehabilitation programmes.
• Implementation of bio-monitoring programme.
7-
Destruction of pristine habitat
types
11- • Confine impacts to development area.
• Implementation of site specific rehabilitation programmes.
• Limit movement of vehicles and personnel through areas of
sensitivity.
• Implementation of bio-monitoring programme.
6-
Surrounding natural habitat
and species
9- • Confine impacts to development area.
• Limit movement of vehicles and personnel through areas of
sensitivity and within receiving environment.
• Awareness programmes for construction and operational
personnel.
• Implementation of site specific rehabilitation programmes.
• Implementation of bio-monitoring programme.
6-
Road infrastructure on
biodiversity
9- • Proper contour sloping.
• Erosion control.
• Perpendicular crossing of rivers and streams.
• Confining construction activities and infrastructure to low
impact areas.
• Avoiding unnecessary peripheral impacts.
6-
OVERALL ASSESSMENT 10- • The high negative impact will be reduced to a low negative
impact after the implementation of mitigation measures.
7-
Heritage
Heritage 12- • Excavation and mapping of sites.
• Shifting of development/infrastructure to avoid sites (sites 14 and 15 that will be impacted by the construction yard can be
avoided by moving the yard further south. This can be
determined by taking the coordinates as centre point and
extending a buffer zone of 30 metres from these points. That
11-
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-18
would be sufficient to avoid the heritage sites.
• Formalising sites by fencing them in.
Visual/Aesthetic
Visual Quality 10.8- • Rehabilitation of construction camps.
• Landscaping of sites, especially lower dam.
• Enhance lower dam as a water feature.
8.8-
Visibility 8.6- • No mitigation measures are proposed, since it is unlikely that the topography of the area will change
8.6-
Observer Proximity 7- • Prevent residential development within 2 km from the sites 7-
Viewer Incidence and
Perception
9.6- • Promote the site as a tourist attraction to positively influence viewer perception.
7-
Visual Absorption Capacity 13- • Ensure that construction material will not contrast with the environment in respect of texture and colour.
• Shield administrative buildings and access roads with appropriate landscaping techniques
10-
Lighting 14- • The use of mast lighting should be avoided. • All light sources should be directed downwards, and away from the mountain side.
• Light sources should be shielded where appropriate.
12-
Final visual impact index 10.6- • All mitigation measures implemented as proposed above. 8-
Noise
Noise 9- • Local residents are to be notified of any potentially noisy field
survey works or other works during the planning and design
phase and these activities are to be undertaken at reasonable
times of the day. These works should not take place at night
or on weekends.
• Construction site yards, concrete batching plants, asphalt
batching plants, construction worker camps (accommodation)
and other noisy fixed facilities should be located well away
from noise sensitive areas adjacent to the development site.
• All construction vehicles and equipment are to be kept in good
repair.
• Construction activities, and particularly the noisy ones, are to
7-
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-19
be contained to reasonable hours during the day and early
evening.
• With regard to unavoidable very noisy construction activities in
the vicinity of noise sensitive areas, the contractor should liaise
with local residents on how best to minimise impact.
• The effect of blasting on the local nesting raptor population, if
relevant, is to be monitored.
• In general operations should meet the noise standard
requirements of the Occupational Health and Safety Act (Act
No 85 of 1993).
• Construction staff working in areas where the 8-hour ambient
noise levels exceed 75dBA should wear ear protection
equipment.
Social
Intra-conflict
Inter-conflict
7-
8-
• Intra-conflict
� Weekly forum meetings between contractors and
construction workers to address any issues and/or concerns
pro-actively.
� Consider the use of a uniformed salary structure whilst
construction workers are on site.
• Inter-conflict:
� Ensure that a transparent recruitment process takes place
prior to construction.
� Consider making use of the local trade unions, if available,
to enhance the recruitment process.
7-
Increased social problems 14- • An aggressive STI and HIV/AIDS awareness campaign should
be launched, which is not only directed at construction workers
but also at the community as a whole.
• Access at the construction site should be controlled to prevent
sex workers from either visiting and/or loiter at the construction village.
• Construction workers should be clearly identifiable.
• Local women should be empowered.
• The construction village should be located some distance away
12-
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-20
from the local community.
Noise pollution 8- • Construction activities should be restricted to daytime hours
between 07:00 and 19:00.
• Adjacent property owners should be consulted and notified of
any activities that could lead to excessive noise levels, e.g.
blasting, as well as night time construction activities.
• The construction village at the lower dam site should be
located away from the local community to ensure that noise
levels at the village do not affect them during the night.
6-
Dust pollution 8- • Dust pollution could be restricted by the tarring of the access
roads.
• If access roads are not tarred, it should be watered down
regularly to compact the soil and restrict dust pollution to an
extent.
• Residents should be consulted prior to activities that could
cause large amounts of dust pollution.
7-
Increased demand on
municipal services
9- • Contractors should consult with the EMLM prior to construction
to assess the availability of municipal services such as water
and electricity to ensure that these services would be available
and if not, to determine what steps could be implemented to
lessen the burden on the EMLM during the time of
construction.
8-
Damage to roads 7- • Road rehabilitation should take place prior to and once
construction is completed.
• Construction traffic should only make use of an approved
route.
• General road rules should be enforced.
6-
Construction villages 10- • The location of the large construction village should be
determined in consultation with the EMLM in view of the fact
that it would potentially be a permanent structure. It is
therefore vital that the location is appropriate and in line with
the EMLM development plans.
8-
Development of local road
networks
12+ • Potential speeding in the vicinity of the school on the R8/R10
should be controlled.
• Traffic signs should warn motorists of the presence of
12+
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-21
pedestrians and school children along the road.
Direct employment
opportunities
9+ • The positive impact can be enhanced through a transparent
recruitment process.
• Employ a rotary job allocation scheme to enable all unskilled
labour to have an equal opportunity of employment.
9+
Indirect employment
opportunities
8+ • Indirect job opportunities should be offered to the local
community, e.g. by employing local domestic workers.
8+
Local economic investment 10+ • Construction workers should be encouraged to make use of the
local facilities.
10+
OVERALL ASSESSMENT 6- • The benefits outweigh the negative impacts of the project. 6+
Traffic and Transport
Transport of components 8- • Number of trips kept to a minimum.
• Use approved route.
• Transport outside peak hours on busy sections.
8-
Construction traffic 9- • Road rehabilitation after construction. 9-
OVERALL ASSESSMENT 8.5- • The effect on pavement loading by construction vehicles and
subsequent acceleration of any rehabilitation programme could
be mitigated by initiating negotiations regarding the possible
contribution by Eskom to the pavement rehabilitation
programme with the relevant provincial authorities.
• The medium negative impact determined using the matrix
rating system should be given a lower weighting when
compared to other environmental factors as the proposed PSS
benefits far outweigh the considered impact of
transport/traffic.
8.5-
Tourism
Sense of place 11- • Location of construction camp away from tourism areas.
• Containment of construction camps to predetermined areas
away from tourism areas.
9-
Land use 9- • Location of construction camp away from tourism areas.
• Containment of construction camps to predetermined areas
away from tourism areas.
7-
Tourism growth and
sustainability
8+ • Containment of construction camp and construction
vehicles to as small as area as possible.
14+
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-22
• Use of existing tourism facilities by construction
management staff.
• Marketing of tourism facilities identified near the
development during the construction phase.
OVERALL ASSESSMENT 6+ • The positive impacts associated with the projects outweigh
the negative impacts.
12+
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-23
Table 18.3 Summary of issues, the rating of impacts and the associated mitigation measures in the operational phase investigated in the
EIA.
Issue Impact
Rating
Mitigation Measures Impact Rating after
Mitigation
Geohydrology
Upper reservoir seepage 5- • During the operational phase, seepage through the dam wall
will contribute towards down-gradient base-flow requirements
(springs along mountain slope). Locate possible seepage paths
for remedial grouting by installation of piezometers
downstream of grout curtain, will reduce excessive seepage
(<400m3/d).
• Install groundwater monitoring boreholes down-gradient of the
dam wall to monitor quality and water levels.
8+
Lower reservoir seepage 7- • Less seepage due to fluctuations in water level. Locate possible seepage paths for remedial grouting by installation of
piezometers downstream of grout curtain.
• Install groundwater monitoring boreholes down gradient of the
dam wall to monitor quality and water levels.
7+
Artificial groundwater
recharge
4- • Apply source in construction, oppose to obtaining it from a
more expensive/located source elsewhere.
• Backfill existing geotechnical boreholes in dam basin with a
mixture of bentonite and cement trimmed and filled from the
bottom, to prevent excessive losses through recharge.
• Line reservoirs with clay bases to minimise seepage losses.
8+
OVERALL ASSESSMENT 5- • The recommended mitigation measures would reduce the
overall impact to a medium positive impact.
8+
Surface Water and Drainage
Evaporation 10- • Keep surface areas of reservoirs to a minimum.
• Provide floating covers or buoys for upper reservoir to keep
open water areas to a minimum.
8-
Existing irrigation water
users
7- • Compensation Releases.
• Designing of suitable outlet works.
5-
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-24
OVERALL ASSESSMENT 8.5- • The recommended mitigation measures would reduce the
overall impact to a low negative impact.
6.5-
Wetlands
Streamflow regulation -
functioning of wetlands in the
catchment
9- • Release of a Q70 (i.e. the flow within the tributary that is
exceeded more than 90% of the time) flow from the reservoir
as a compensation flow. This would mimic the baseflow that
typically occurs in the tributary during low flow periods.
4-
Noise
Noise 8- • The design of the PSS in the Steelpoort area should
incorporate all the necessary acoustic design aspects required,
in order for the overall generated noise level from the new
installation not to exceed a maximum equivalent continuous
rating level as specified for industrial districts in SANS 10103.
• Notwithstanding this provision, the design is also to take into
account the maximum allowable equivalent continuous day and
night rating levels of the potentially impacted sites outside the
proposed PSS site.
• The latest technology incorporating maximum noise mitigating
measures for the PSS components should be designed into the
system.
• The design process should consider, inter alia, the following
9aspects:
- The position and orientation of buildings on the site. The
position of the surface facilities that generate the loudest
noise should be located far as possible from the noise
sensitive sites on adjacent farms.
- The enclosure of noisy plants in buildings where possible
and practical.
- The design of the buildings to minimise the transmission of noise from the inside to the outdoors.
- The insulation of particularly noisy plant and equipment.
7-
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-25
Social
Health and safety 9/ • Water should be tested regularly by scientifically accepted
standards for any form of bacteria.
• If any bacteria are found, the community should be notified
and the problem should be rectified.
7/
Safety hazards of water 9- • The area should be fenced and access should be controlled by
means of a security access point.
• The community should be educated on the operation of the
scheme and the dangers involved with rapid moving water,
e.g. at open days or through school excursions to the scheme.
• An emergency plan should be developed outlining standard
operating procedures if a person should fall into one of the
dams.
7-
Employment opportunities 9+ • Enhance the positive impact by employing local community
members if the skills are available in the community.
• Consider on-the-job training for local community members who
show the necessary capabilities and potential to become skilled
in the operation.
9+
Housing developments in
Roossenekal
9+ • Housing developments should be co-ordinated with the EMLM.
• Make use of local contractors and labour for the construction of
these houses.
9+
Maintenance of access roads 11+ • The regular maintenance of the roads should form part of the
EMP.
• Local labour should be used where possible in the maintenance
of roads.
11+
Indirect job opportunities 10+ • Enhance the positive impact by encouraging installation
employees to make use of and employ local community
members in their households.
10+
Sustainable local economic
development
11+ • Enhance the positive impact by encouraging installation
employees to make use of and employ local community
members in their households.
11+
OVERALL ASSESSMENT 10+ • The recommended mitigation measures maintain a high
positive impact.
10+
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-26
Traffic
Operational traffic 8- • Travel between sites is minimised (electronic control).
• Only 40 staff at Valley Control Centre.
8-
Tourism
Sense of place 7- • Location of construction camp away from tourism areas.
• Containment of construction camps to predetermined areas
away from tourism areas.
6-
Land use 8- • Location of development so as to limit negative impacts on
existing tourism operations.
• Establishment of a tourism Visitor centre and a nature reserve
around the proposed development.
13+
Tourism growth and
sustainability
10+ • Marketing of tourism facilities identified near the development
during the construction phase.
• Use of existing tourism establishments for maintenance management staff
• Location of development so as to limit negative impacts on
existing tourism operations.
• Establishment of a tourist visitor’s centre and a nature reserve
around the proposed development.
12+
Final Environmental Impact Assessment Report for the Proposed Pumped Storage Power Generation Facility in the Steelpoort area, Limpopo and Mpumalanga Provinces
Conclusions 22/06/2007 18-27
18.5 Conclusion
The findings of the specialist studies undertaken within this EIA provide an
assessment of both the benefits and potential negative impacts anticipated as a
result of the proposed project. The findings conclude that there are no
environmental fatal flaws that could prevent the proposed project from
proceeding, provided that the recommended mitigation and management
measures are implemented. Thus, from all the studies undertaken to investigate
environmental impacts of the proposed pumped-storage scheme, it is
recommended that the proposed project be approved. This is the view and
recommendation of the Environmental Assessment Practitioner based on the
studies conducted within this Environmental Impact Assessment.
18.6 Recommendations
In order to achieve appropriate environmental management standards and
ensure that the findings of the environmental studies are implemented through
practical measures, the recommendations from this EIA must be included within
an EMP. This EMP should form part of the contract with the contractors appointed
to construct and maintain the proposed plant and associated infrastructure. The
EMP would be used to ensure compliance with environmental specifications and
management measures. The implementation of this EMP for all life cycle phases
(i.e. construction, operation and de-commissioning) of the proposed project is
considered to be key in achieving the appropriate environmental management
standards as detailed for this project.
It is also recommended that the process of communication and consultation with
the community representatives is maintained after the closure of this EIA process,
and, in particular, during the construction phase associated with the proposed