[2017] 1 LNS 2042 Legal Network Series 1 DALAM MAHKAMAH RAYUAN MALAYSIA (BIDANG KUASA RAYUAN) [RAYUAN SIVIL NO: B-02(NCVC)(W)-154-01/2016] ANTARA SEDIABENA SDN BHD (No. Syarikat: 085679-H) ... PERAYU DAN CHINA COMSERVICE (HONG KONG) LIMITED ... RESPONDEN (disatukan dengan) DALAM MAHKAMAH RAYUAN MALAYSIA (BIDANG KUASA RAYUAN) [RAYUAN SIVIL NO: B-02(NCVC)(W)-152-01/2016] ANTARA CHINA COMSERVICE (HONG KONG) LIMITED ... PERAYU DAN SEDIABENA SDN BHD (No. Syarikat: 085679-H) ... RESPONDEN [Dalam Perkara Mahkamah Tinggi Malaya di Shah Alam (Bahagian Sivil) Guaman Sivil No: 22NCVC-254-05/2014 Antara China Comservice (Hong Kong) Limited ... Plaintif
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
[2017] 1 LNS 2042 Legal Network Series
1
DALAM MAHKAMAH RAYUAN MALAYSIA
(BIDANG KUASA RAYUAN)
[RAYUAN SIVIL NO: B-02(NCVC)(W)-154-01/2016]
ANTARA
SEDIABENA SDN BHD
(No. Syarikat: 085679-H) ... PERAYU
DAN
CHINA COMSERVICE (HONG KONG) LIMITED
... RESPONDEN
(disatukan dengan)
DALAM MAHKAMAH RAYUAN MALAYSIA
(BIDANG KUASA RAYUAN)
[RAYUAN SIVIL NO: B-02(NCVC)(W)-152-01/2016]
ANTARA
CHINA COMSERVICE (HONG KONG) LIMITED ... PERAYU
DAN
SEDIABENA SDN BHD
(No. Syarikat: 085679-H) ... RESPONDEN
[Dalam Perkara Mahkamah Tinggi Malaya di Shah Alam
(Bahagian Sivil)
Guaman Sivil No: 22NCVC-254-05/2014
Antara
China Comservice (Hong Kong) Limited ... Plaintif
[2017] 1 LNS 2042 Legal Network Series
2
Dan
Sediabena Sdn. Bhd.
(No Syarikat: 085679-H) ... Defendan]
CORAM:
NALLINI PATHMANATHAN, JCA
PRASAD SANDOSHAM ABRAHAM, JCA
ZABARIAH MOHD YUSOF, JCA
CONTRACT: Breach - Terms and conditions - Breach of obligations -
Failure to provide documents to enable verification of payment - Damages
- Whether there was breach of a fundamental term - Whether plaintiff was
entitled to withhold payment to defendant - Whether party who had suffered
from breach was entitled to claim for loss
TRUSTS: Trusts - Existence of - Express trust - Absence of express words
creating trust - Whether express trust may be created without using word
‘trust’ - Whether court will look at surrounding circumstances to determine
intention of a party to be trustee - Whether standard of proof of existence
of an express trust is very high - Whether intention to create a trust must
be expressed in clear language - Whether elements of fiduciary duties and
trust could be imported into contractual commercial contexts
[Appeals dismissed with no order as to costs.]
Case(s) referred to:
ESPL (M) Sdn Bhd v. Radio & General Engineering Sdn Bhd [2004] 4 CLJ
674 CA
Frame v. Smith [1987] 42 DLR 81 (refd)
[2017] 1 LNS 2042 Legal Network Series
3
Geh Cheng Hooi & Ors v. Equipment Dynamics Sdn Bhd [1991] 1 CLJ Rep
133 SC (refd)
Hospital Products Limited v. United States Surgical Cooperation [1984]
CLR 41 (refd)
MMC Oil & Gas Engineering Sdn Bhd v. Tan Bock Kwee & Sons Sdn Bhd
[2016] 4 CLJ 665 CA (refd)
Perman Sdn Bhd & Ors v. European Commodities Sdn Bhd & Anor [2005]
4 CLJ 750 CA (refd)
Poh Geok Sing v. HB Enterprise Sdn Bhd [2006] 1 CLJ 765 CA (refd)
Re Kayford Ltd [1975] 1 AER 604 (refd)
Steven Phoa Cheng Loon & Ors and other appeals [2003] 1 MLJ 567 (refd)
Legislation referred to:
Contracts Act 1950, s. 74
JUDGMENT
1. The claim by the Plaintiff against the Defendant, in the High Court,
is for, inter alia, the following reliefs:
a) a declaration that the Defendant had breached its express
obligations under the Strategic Alliance Agreement dated 23.12.2010
(SAA);
b) a declaration that the Defendant acted in breach of its implied
obligations under the SAA;
c) a declaration that the Defendant acted in breach of its fiduciary
duties and obligations as a trustee;
[2017] 1 LNS 2042 Legal Network Series
4
d) Damages, as consequential relief;
e) Costs.
2. The Defendant counterclaimed against the Plaintiff, inter alia, for a
declaration that the Plaintiff had breached the SAA, and sought an order or
compensation for the breach committed.
3. At the end of the trial, the learned trial Judge allowed the Plaintiff’s
claim in part, as follows:
“(1) it is declared that the Defendant acted in breach of its
expressed obligations under the Strategic Alliance
Agreement dated 23rd December 2010;
(2) damages are to be assessed and paid by the Defendant to the
Plaintiff;
(3) the Defendant shall pay to the Plaintiff interest on such
sums as awarded to the Plaintiff at the rate of 4% per
annum from the date of judgment until the date of full
settlement; and
(4) the Defendant shall pay to the Plaintiff costs of RM50,000.00.”
4. The claim of the Plaintiff that sought a declaration that the Defendant
acted in breach of its implied obligations under the SAA and a
declaration that the Defendant acted in breach of its fiduciary duties
and obligations in respect of its duties as a trustee were dismissed by
the learned trial Judge.
5. The counterclaim by the Defendant was also dismissed.
6. The Plaintiff appealed to the Court of Appeal against that part of the
decision of the learned trial Judge that disallowed the Plaintiff’s
claim. Whereas the Defendant appealed against the whole of the said
[2017] 1 LNS 2042 Legal Network Series
5
decision.
7. After hearing both parties and after perusing the Appeal Records, we
unanimously dismissed both Appeals with costs and affirmed the
decision of the learned trial Judge of the High Court.
8. Herein below are our grounds. Parties shall be referred to, as they
were in the High Court.
BACKGROUND:
9. On 15.2.2010, the Defendant and Dewarisan Holdings Sdn. Bhd.
(DHSB) entered into a “Smart Partner Project Agreement” (SPPA)
with Maxis Broadband Sdn. Bhd. (Maxis). Pursuant to this SPPA,
Maxis appointed the Defendant and DHSB for the supply, delivery,
construction, installation, testing, commissioning and
decommissioning and maintenance of network infrastructure and
facilities for Maxis for a period of 3 years (Works). Maxis has the
option to renew the SPPA for another 2 years.
10. The scope of work undertaken by the Defendant under the SPPA is
for the supply, delivery, construction, installation, testing,
commissioning and decommissioning of network infrastructure
(Defendant’s Works), whilst DHSB undertook the maintenance
portion of the works.
11. With regards to the Works including the Defendant’s Works, the
provisions of the SPPA (which are relevant to our present appeal),
are as follows:
(i) Clause 14 provides that such works as required by Maxis are
requisitioned by way of “Work Orders” in the form of Purchase
Orders or Departmental Release Orders (DROs);
(ii) Clauses 36 and 37 provide that, when such works have been
[2017] 1 LNS 2042 Legal Network Series
6
completed and accepted, Maxis will be invoiced by the
Defendant. Subsequently, Maxis will make payments of the
invoiced amount into a Nominated Joint Account (NJA) of
DHSB and the Defendant. From the NJA, the Defendant’s
portion will be paid to the Defendant.
12. The Plaintiff came into the picture when it entered into a SAA on
23.12.2010 with the Defendant for the Defendant’s Works under the
SPPA. These being the Work Orders issued by Maxis as of the date
of the SAA and defined thereto in the SAA as “On-Going Projects”
(2010 DROs).
13. Clause 2.1 of the SAA provides that the Defendant is to be the sole
and exclusive project manager for the Defendant’s Works under the
SPPA.
14. The SAA also provides that:
A. The Defendant shall, inter alia:
(i) allocate all work orders received from Maxis for
execution; (Clause 3.1 (a));
(ii) not issue any invoices for the Project Works without the
prior consent of the Plaintiff (Clause 3.1 (f));
(iii) provide the Plaintiff with all invoices issued to Maxis
and updates on all payments received from Maxis
(Clause 3.1 (f)).
B. The Plaintiff shall inter alia:
i) execute the works with due skill and care and in a
professional manner (Clause 3.2 (b));
ii) be responsible for all financing including operational
[2017] 1 LNS 2042 Legal Network Series
7
and capital expenses (Clause 3.2 (c));
iii) offer employment to all the Defendant’s employees as
may be determined by the Plaintiff (Clause 3.2 (d));
C. The Defendant warrants and represents that:
i) the aggregate contract value of the 2010 DROs is no
less than RM16,643,694.00 all of which is fully
recoverable from Maxis (Clause 4.1 (c));
ii) as at 23.12.2010 the works for the 2010 DROs duly
performed and carried out is no less than
RM8,321,847.00 all of which is fully recoverable from
Maxis (Clause 4.1 (d));
iii) all payments from Maxis can only be paid into the NJA
operated jointly by DHSB and the Defendant with the
Defendant’s portion thereafter credited into the
Defendant’s account by way of a standing instruction
issued jointly by DHSB and the Defendant (Clause 4.1
(e) and (f)).
D. Pursuant to the SAA, the Plaintiff was to implement the DROs
issued after the SAA was entered into, i.e. the post 2010
DROs, including financing all operational and capital
expenses incurred in that regard.
15. As for the 2010 DROs, it is not disputed that the implementation and
all operational and capital expenses incurred thereof, were the
responsibility of the Defendant. For these 2010 DROs, the Plaintiff
was to provide assistance to the Defendant with funding and that the
Defendant was required to complete the 2010 DROs. In this regard
the Plaintiff agreed to contribute no more than RM15,811,509.00 to
assist the Defendant in its commitment under the 2010 DROs, or On-
[2017] 1 LNS 2042 Legal Network Series
8
Going projects. The contribution was to be made in 3 Tranches which
as follows:
a) First Tranche - no more than RM8,321,847.00 to be paid on
24.12.2010;
b) 2nd Tranche - no more than RM5,825,293.00 to be paid when
the total amount of the invoices issued by the Defendant to
Maxis amounts to no less than RM12,482,771.00;
c) 3rd Tranche - no more than RM1,664,369.00 to be paid after
the Plaintiff has received RM16,643,694.00 from the On-
Going Projects (2010 DROs) paid by Maxis.
16. Upon payment of the 1st and the 2nd Tranches by the Plaintiff, the
Defendant was to complete the 2010 DROs within the time stipulated
and to invoice Maxis for the same.
17. Further, Clause 5.7 of the SAA provides that the Plaintiff is entitled
to RM16,643,694.00 from the 2010 DROs payable from 90% of all
payments received by the Defendant from Maxis for 2010 DROs,
with any excess amount going to the Defendant and any shortfall to
be paid by the Defendant to the Plaintiff.
18. Clause 6.1 (a) of the same, states that if the total payments received
from Maxis in relation to the Projects Works is less than RM200
million, the Plaintiff gets 90% of those total payments received.
Clause 6.1 (b) states that if the total payments received from Maxis
in relation to the Project Works is more than RM200 million, the
Plaintiff gets 95% of those total payments received.
The above is termed as the “Agreed Benefit Ratio”.
19. The Defendant agreed and undertook that all monies received by it
from Maxis would be paid into a “Dedicated Account”, which is the
[2017] 1 LNS 2042 Legal Network Series
9
Defendant’s dedicated current account. There was to be, after the
payment of the 1st and the 2nd Tranches, a Standing Instruction for
all monies in the Dedicated Account to be paid out to the Plaintiff
and Defendant according to the Agreed Benefit Ratio (Clause 6.1 (a)
and (b) of the SAA)).
20. It is not disputed that the Plaintiff had only paid the 1st Tranche to
the Defendant. The dispute is as to the 2nd Tranche which the Plaintiff
did not release to the Defendant. The Defendant contends that by
early August 2011, the total amount of invoices issued to Maxis
amounted to no less than RM12,482,771.00 and hence this triggered
the release of the 2nd Tranche payment, which the Defendant alleged
the Plaintiff failed to make.
21. However, the Plaintiff asserts that:
i) the total amount invoiced by the Defendant to Maxis and also
the payments received by the Defendant from Maxis could not
be verified by the Plaintiff;
ii) the Plaintiff was neither kept updated nor given copies of the
invoices issued out to Maxis;
iii) the Plaintiff was not kept informed of the payments received
from Maxis.
Premised on the above reasons, the Plaintiff could not release the 2nd
Tranche.
22. Parties attempted to resolve the dispute and find an amicable
solution. However, all attempts at resolution failed. The Plaintiff
alleged that despite its numerous requests for the invoices issued to
Maxis or evidence of payment to Maxis, it fell to deaf ears.
23. Subsequently, at a meeting on 25.7.2012, the Plaintiff gave notice to
[2017] 1 LNS 2042 Legal Network Series
10
the Defendant that it is withdrawing from the SAA (refer to page
563-564 of ACB Volume 2). It is not disputed that the Plaintiff had
completely withdrawn itself from the SAA between June/July 2012.
The Plaintiff pleaded that on or around 28.7.2012 the SAA was
terminated.
24. The Plaintiff initiated a suit in the High Court seeking a declaration
that the Defendant had acted in breach of its obligations under the
SAA and also in breach of its fiduciary duties and obligations as
trustee. This is the subject of the Appeal before us.
25. The main complaint of the Plaintiff is reflected in paragraph 11 of
the Statement of Claim. The Plaintiff claims that notwithstanding
that it had performed its obligations, including advancing the First
Tranche of RM8,321,847.00 and incurring a further sum of RM13
million plus towards operational and capital expenditure for the
Project Works, the Defendant committed various breaches of its
obligations under the SAA and/or its fiduciary/trustee duties and
obligations. The particulars of the breaches are:
(i) the Defendant attempted to put all of its employees on the
Plaintiff’s payroll regardless of whether they were deployed
for the Project Works;
(ii) From and around October 2011, the Defendant failed to obtain
the Plaintiff’s consent before invoices were issued to Maxis;
(iii) the Defendant failed to keep the Plaintiff informed and updated
on the invoices issued to Maxis;
(iv) the Defendant failed to keep the Plaintiff informed and updated
on the payments received from Maxis;
(v) the Defendant failed to account to the Plaintiff and keep the
Plaintiff informed and updated of all and any monies
[2017] 1 LNS 2042 Legal Network Series
11
transferred to the Dedicated Account;
(vi) the Defendant failed to account and pay to the Plaintiff the
Plaintiff’s share of the payments and monies received from
Maxis in the Agreed Benefit Ratio or at all;
(vii) the Defendant failed to issue the requisite Standing Instruction
to authorize immediate payments out of the Dedicated Account
to the Plaintiff according to the Agreed Benefit Ratio.
26. The Plaintiff alleged that, by reason of the said breaches by the
Defendant, the Plaintiff was put to suffer loss and damage. The
particulars of loss and damage claimed by the plaintiff are as follows:
a) RM16,643,694.00 being the sum the Plaintiff is entitled to
(Clause 5.7 of the SAA));
b) RM8,321,847.00 being the 1st Tranche of funding advanced by
the Plaintiff;
c) RM13,657,844.00 being the further sums incurred by the
Plaintiff towards the operational and capital expenditure for
the Project Works;
d) 90% of all sums received by the Defendant from Maxis by
which the Plaintiff is entitled to by Clause 6.1 (a) of the SAA;
and
e) RM1,388,217.52 being finance and other costs incurred by the
Plaintiff for the funding and expenditure as aforesaid.
27. Whereas, the counterclaim by the Defendant is as follows:
a) A declaration that the Plaintiff had breached the SAA;
b) An order for compensation of RM20,000.00 to be paid to the
[2017] 1 LNS 2042 Legal Network Series
12
Defendant by the Plaintiff for the breach committed by the
Plaintiff;
c) A declaration that the Plaintiff has no right over the monies in
the Dedicated Account in Maybank;
d) An Order for payment of RM14,353,611.88 being the
operational costs incurred by the Defendant from 24.12.2010
until 31.5.2012 (and still accruing);
e) An Order for payment of RM5,504,613.50 for advances made
by the defendant for expenses incurred for the Plaintiff;
f) An Order for payment of RM1,062,288.98 being the loss of
income suffered by the defendant for the On-going Works;
g) An Order for payment of RM386,914.54 for the reduced
claims;
h) A declaration that the Plaintiff is not entitled to 15%
shareholding in the Defendant’s company that has been
charged to the Plaintiff according to the Share Charge
Agreement dated 23.12.2010;
i) An Order to compel the Plaintiff to sign the Form of Transfer
of Securities in favour of Mr. Chew Wai Choy for the 15%
shares 7 days from the date of this Order;
j) In the alternative for an order that the amount of
RM16,643,694.00 being the amount of the shares be
considered as a set off if the Plaintiff’s claim is successful;
k) Loss and damages to be assessed; and
l) Costs and interest.
[2017] 1 LNS 2042 Legal Network Series
13
Issues:
28. The main issues to be determined were as follows:
i) Whether the Plaintiff/Defendant had breached the SAA;
ii) Whether the Defendant is a trustee on the monies paid by
Maxis in the Dedicated Account. If so, whether the Defendant
had acted in breach of its implied/fiduciary duties and
obligations under its trustee’s duties under the SAA.
The Decision of the High Court:
29. The primary issue before the Court was who was in breach of the
SAA. The contention of the Plaintiff was that it was the Defendant
who did not keep the Plaintiff informed of the invoicing to, and
payments received from, Maxis.
30. On the other hand, the Defendant maintained that it was the Plaintiff
who failed to advance the 2nd Tranche payment of RM5,825,283.00.
The Defendant contended that the undisputed evidence showed that
the Plaintiff abandoned works and failed to comply with its
obligations under the SAA and accordingly, it was the Plaintiff who
had committed a repudiatory breach of the SAA.
31. The trial proceeded on liability. The learned trial Judge found that
the Defendant was the one who had breached its obligations under
Clause 3.1 of the SAA. It was her finding that the Defendant had
failed to provide the Plaintiff with copies of Maxis’s invoices to
allow the Plaintiff to verify that the total amount of invoices issued
by the Defendant to Maxis had reached the threshold sum of
RM12,482,771.00 under Clause 5.2 of the SAA. Consistent with her
findings, she also found that:
a) the Defendant could only issue invoices with the prior consent
[2017] 1 LNS 2042 Legal Network Series
14
of the Plaintiff; and
b) the Defendant did not obtain the prior consent of the Plaintiff
before issuing invoices.
32. The first Tranche of RM8,321,847.00 was already paid. It is only the
2nd Tranche which was withheld by the Plaintiff. It was only payable
when the total invoice for the 2010 DROs was “no less than
RM12,482.00”. The Plaintiff was unable to verify the financial
progress of the Project nor the trigger point for the release of the 2nd
Tranche. Hence, the learned trial Judge found that the Plaintiff was
therefore entitled to withhold the 2nd Tranche.
33. The learned trial Judge also found that the breach by the Defendant
of such obligations constituted a breach of a fundamental term of the
agreement. However, she disallowed the Plaintiff’s
“fiduciary/trustee duties claim” premised, essentially on the fact that
the 2nd Tranche payment had yet to take place.
FINDINGS:
Whether the Plaintiff/Defendant had breached the SAA:
34. The learned trial Judge found that the Defendant failed to comply
with Clauses 3.1 (e) and (f) and was therefore in breach of a
fundamental term and hence was entitled to withhold the 2nd Tranche
payment to the Defendant and ultimately to terminate the SAA on
28.7.2012. The learned trial Judge preferred the evidence of the
Plaintiff whom she viewed as “more credible” in support of their
contention, as compared to the witnesses of the Defendant who were
“evasive and blowing hot and cold in responding to questions in
relation to the failure in providing the invoices in question as in so
much it had portrayed untruthfulness on their part and also lack
transparency as the parties to the agreement”.
[2017] 1 LNS 2042 Legal Network Series
15
35. It is trite law that findings of the credibility of witnesses by the trier
of the court of first instance, who has audio visual advantage, is
rarely disturbed by an appellate court, unless it can be shown that the
trier of fact is plainly wrong in arriving at its conclusions and
decision.
(refer to Steven Phoa Cheng Loon & Ors and other appeals [2003] 1
MLJ 567; MMC Oil & Gas Engineering Sdn Bhd v. Tan Bock Kwee
& Sons Sdn Bhd [2016] 2 MLJ 428). Was the learned trial Judge
wrong in her findings?
36. A perusal of the provisions of the SAA discloses the following.
Clause 3.1 (e) and (f) of the SAA provides for the general obligations
of the Defendant:
“3.1 The general Obligations of SSB
Subject to the terms and conditions herein contained, SSB
shall:
(e) not issue any invoices with respect to the Project Works
without the prior consent of CCSHK and where such
consent has been obtained, to do so in the form and
manner to be determined by CCSHK;
(f) subject to Clause 3.1 (e), to provide CCSHK with all
invoices issued to MBSB and an update on all payments
received therefrom;”
37. According to the SAA, the 2nd Tranche was only payable when the
total amount of invoices issued by the Defendant to Maxis for the
2010 DROs are not less than RM12,482,771.00.
38. The logical question to ask would be, how would the Plaintiff be able
to verify that the amount of the invoices issued by the Defendant to
[2017] 1 LNS 2042 Legal Network Series
16
Maxis for the 2010 DROs are not less than RM12,482,771.00.
39. Clauses 3.1 (e) and (f) appear to be the mechanism for the Plaintiff
to keep track of the payments made by Maxis to the Defendant. This,
consequently would have an effect on the funding obligations (the
Tranche payments) on the part of the Plaintiff for the Defendant’s
2010 DROs entitlement pursuant to the SAA. By this, the Plaintiff
would be able to monitor the contractual payments made by Maxis
by reference to the payments updates provided by the Defendant.
40. From the evidence, it is not in dispute that the Plaintiff’s consent to
the Defendant’s invoicing for the Project Works was by a
representative of the Plaintiff who would sign the invoices for
onward transmission to Maxis. From the testimony of the Plaintiff’s
representative, SP 3 (Li Wen) the Plaintiff was only given few
invoices to sign and it was never anywhere close to what ought to
have been invoiced to Maxis given the number of DROs received
from Maxis (refer to Tab 22 of the RCB Q & A No 10).
41. As a result, the Plaintiff queried repeatedly, as evidenced by the e-
mails dated 15.3.2011 and 21.4.2011, requesting that the Defendant
send to the Plaintiff the invoices before the issuance to Maxis for the
Plaintiff’s signing and records.
42. The Plaintiff had insisted that they be given an account of the actual
amount invoiced to and payment received from Maxis before the 2nd
Tranche could be released. Instead the Plaintiff was only given
listings of what the Defendant alleged to be invoices and payments.
43. The Defendant’s witness, Encik Zahar (SD 1) sought to justify the
failure to obtain the signature of the Plaintiff’s representative before
delivering it to Maxis, by alleging that this was due to the
unavailability of the Plaintiff’s representative. However, in the same
breath, he admitted that it was easy to call the Plaintiff for the
[2017] 1 LNS 2042 Legal Network Series
17
signature. It is the Plaintiff’s case that its representatives were
available at all material times and there is no evidence to suggest
otherwise. The Defendant continued to issue invoices to Maxis
without the Plaintiff’s consent, in total disregard of the provision of
Clause 3.1 (e) of the SAA. Hence, the learned trial Judge correctly
made the finding that the Defendant had breached Clause 3.1 of the
SAA. (Refer to para 34 of her grounds).
44. Evidence further showed that the Plaintiff continued to make further
requests from the Defendant for the invoices that were issued to
Maxis, as can be seen from the following documents:
a) e-mail on 21.4.2011 (Tab 4 page 31 of the RCB);
b) e-mail on 6.10.2011 (Tab 10 page 95 of RCB);
c) e-mail dated 28.6.2012 (Tab 14 at page 111 of RCB);
d) letter dated 13.7.2012 (Tab 15 at page 112-113 of RCB);
e) letter dated 6.8.2012 ( Tab 16 at page 114-115 of RCB);
f) letter dated 10.10.2012 (Tab 17 at page 116-118 of RCB);
g) letter dated 17.10.2012 (Tab 18 at pages 120-121 of RCB).
Therefore, the submissions by the Defendant that there was no
evidence to support the finding of the learned trial Judge that there
were repeated requests for the verification of the invoices was
misplaced.
45. The Defendant could, at the very least, have provided true copies of
the invoices issued to Maxis, to the Plaintiff. That would have been
sufficient to enable the Plaintiff to keep track of the amounts
invoiced. This is provided in Clause 3.1 (f) of the SAA.
[2017] 1 LNS 2042 Legal Network Series
18
46. Even SD 1 admitted that as at October 2011, the Plaintiff was still
asking for the justification of the total bill that the Defendant had
billed Maxis and total receivables based on the invoice or value.
However, the Plaintiff’s request was not acceded to, by the
Defendant, save and except for 9 or so invoices which were signed
by the Plaintiff’s representative.
47. The Defendant contended that it had provided to the Plaintiff, via e-
mail on 26.4.2011, scanned copies of letters which were sent to
Maxis by the Defendant purportedly enclosing the invoices issued.
However, a perusal of such e-mailed letters show that the invoices
were never enclosed. Clearly, the letters alone would not reflect the
actual amount or value of the invoices which were sent to Maxis.
Without the actual invoices, the Plaintiff would not be able to verify
the amount billed to Maxis by the Defendant. In any event, from the
e-mailed letters, the invoices were only for the period before
26.4.2011.
What happened to the invoices after that date? These invoices were
never provided to the Plaintiff.
48. The Defendant also asserted that it had provided a compilation of
invoices to the Plaintiff’s representative, Webb Wei (SP 4) on
30.7.2011. This was evidenced from the letter of the Defendant dated
22.8.2011 (Refer to tab 7 page 86 of the RCB). However, the Plaintiff
denied ever receiving such a letter and averred that it did not have
record of it. In any event, we agree with the submission of the
Plaintiff that it is unsafe to accept as conclusive that the delivery of
such letter had been made to the Plaintiff, because:
a) The letter did not state anywhere that a “compilation of
invoices” was enclosed. At best it states a “compile (d) invoice
summary” was given to Webb Wei (SP 4) on 30.7.2011;
[2017] 1 LNS 2042 Legal Network Series
19
b) The Defendant was not certain when exactly this alleged
“compile (d) invoice summary” was handed to the Plaintiff.
The Defendant’s witness, SD 2 who is the Managing Director
was evasive when cross examined on this, contradicting the
contents of his own letter. (refer to Tab 25 at page 166-168 of
RCB);
c) What is more damaging is that on the day, 30.7.2011, which
was the day the letter says the alleged “compile (d) invoice
summary” was purportedly handed to the Plaintiff, Webb Wei
(SP 4), it was not disputed that Webb Wei was not in Malaysia.
Hence the letter dated 22.8.2011 relied upon by the Defendant does
not help its case at all. In addition, a compiled summary of invoices
which is a summary obviously prepared by the Defendant, is
insufficient for purposes of verification of the actual amount
invoiced to Maxis.
49. Clause 3.1 (f) of the SAA places further obligations on the Defendant
to provide the Plaintiff with updates on all payments received from
Maxis, with the Plaintiff and the Defendant receiving the Agreed
Ratio Benefit of either 90:10 or 95:5.
50. It is agreed that all monies paid by Maxis which parties are entitled
to, are to be ultimately transferred into the Dedicated Account. Hence
it follows that such evidence of monies received from Maxis would
be reflected in the bank statements of the Dedicated Accounts itself.
51. However, until the conclusion of the trial, the bank statements of the
Dedicated Account had not been given to the Plaintiff, despite
numerous requests being made to the Defendant, be it oral or written.
This was the evidence that was produced at trial:
a) SP 3 e-mailed the Defendant on 24.8.2011 requesting that all
[2017] 1 LNS 2042 Legal Network Series
20
“project account receipts” are to be e-mailed to him to enable
the Plaintiff to verify the payments received from Maxis, with
such information to be on a fortnightly basis. SP 3 was
referring to the bank statements in the Dedicated Account.
b) However, what the Defendant did was to e-mail a summary of
what the Defendant said were payments received from Maxis
in an excel spreadsheet which was prepared by the Defendant,
as was conceded by SD 1 (Zahar). Surely this spreadsheet was
prepared based on the primary documents i.e. bank statements.
52. After the e-mail dated 24.8.2011, SP 3 approached the Defendant
through its representative, Mr. Deva who was in charge of the
Defendant’s finances. Mr. Deva was informed that the spreadsheet
was insufficient and that the actual bank statements were required
for the Plaintiff to verify the payments received from Maxis. Again
there was no response from the Defendant. Instead the Defendant
continued to send more summaries of the payment received from
Maxis in excel spreadsheets.
The Defendant denied that such a request was ever made to Mr. Deva.
However, Mr. Deva of the Defendant was never called to testify and
no reason given for such failure. The burden was on the Defendant
to call Mr. Deva, as it was the Defendant who asserted that no such
request was ever made to Mr. Deva of the Defendant. As Mr. Deva
was not called, the denial was a bare one.
53. As such, the failure of the Defendant to provide the necessary
documents to enable the Plaintiff to verify the payments received
from Maxis amounts to a breach of Clause 3.1 (f) of the SAA as was
the finding of the learned trial Judge in her grounds at page 204 para
57 at tab 27 RCB. It cannot therefore be said that the learned trial
Judge erred in arriving at her conclusion.
[2017] 1 LNS 2042 Legal Network Series
21
The 2nd Tranche Payment:
54. According to the SAA, the Plaintiff is to release this 2nd Tranche to
the Defendant when the total amount of invoices issued by the
Defendant to Maxis for the 2010 DROs is no less than
RM12,482,771.00.
55. The learned trial Judge found that the “the evidence shows that the
refusal by the plaintiff to release the 2nd Tranche is because the total
amount invoiced by the defendant to Maxis and also the payment
received by the defendant from Maxis could not be verified by the
plaintiff. The plaintiff was never kept informed of the payment nor
given copies of invoices issued to Maxis”. The Defendant submitted
that this finding of the learned trial Judge was wrong.
56. However, we are not with the Defendant in this respect. As had been
shown in the preceding paragraphs, the Defendant was the one which
had failed to provide the Plaintiff with the invoices to Maxis and the
updated payments received from Maxis. Without the Plaintiff being
able to verify the actual amount from the invoices to Maxis and the
updated payments received from Maxis, how could the Plaintiff
determine the trigger point for the release of the 2nd Tranche, as it
would only trigger at no less than RM12,482,771.00? The learned
trial Judge correctly observed that the built-in mechanism housed in
Clause 3.1 of the SAA provides the agreed method for the Plaintiff
to independently verify and monitor the amount invoiced to/and paid
by Maxis.
57. The Defendant submitted that BG Lim (the alleged agent of the
Plaintiff - which was never proven) would be able to give
confirmation and verification that the collections from Maxis had
reached the threshold of about RM14 million as at November 2011.
This can be seen from his e-mail of 23.11.2011. Later, this amount
was revised upwards to RM15 million in his e-mail of 20.12.2011.
[2017] 1 LNS 2042 Legal Network Series
22
However, a perusal of the e-mail dated 23.11.2011 does not show
that BG Lim had confirmed nor verified the collections from Maxis.
The e-mail shows that it was a mere summary of the discussion in
the meeting between the parties on 23.11.2011 (refer to ACB-2 at
page 446-447). Similarly, the e-mail of 20.12.2011 was also a
summary of the discussion between BG Lim, SP 1 and SD 2 on
20.12.2011 (refer to ACB-2 at page 447). Moreover, the issue
whether such collections were verified by the Plaintiff or BG Lim at
the meeting on 23.11.2011 and/or 20.12.2011 was never the case of
the Defendant and never put to any of the witnesses. Therefore the
Defendant’s argument that the collections from Maxis have reached
the threshold of RM14 million is baseless.
58. The Defendant also submitted that the court should invoke an adverse
inference against the Plaintiff for failure to call this BG Lim to court
as a witness. We are of the view that if at all an adverse inference is
to be made, it should be invoked against the Defendant, as it was the
Defendant who asserted that the invoices have reached the threshold.
In any event, BG Lim is not a material witness, given that the
evidence in relation to the invoice and evidence in relation to BG
Lim has all been reduced to writing (which are in part B and hence
not disputed).
59. Finally, as no determination could be made as to the amount of the
invoices, the Plaintiff is entitled to withhold the release of the 2nd
Tranche of RM5,825,847.00. The Defendant is the author of this
predicament. The Plaintiff has no basis to release the 2nd Tranche
payment. This was the finding of the learned trial Judge, which we
agreed to be correct.
Whether the breach by the Defendant constitutes a breach of a
fundamental term of the SAA:
60. The learned trial Judge after considering the evidence arrived at a
[2017] 1 LNS 2042 Legal Network Series
23
finding that the conduct of the Defendant constituted a breach of
Clause 3.1 (e) of the SAA. The learned trial Judge found that the
act of providing the invoices is fundamental to the SAA, which
justified the Plaintiff taking the steps of not releasing the 2nd
Tranche and terminating the SAA on 28.7.2012. Hence her finding
that the termination of the SAA was valid. The Defendant submitted
that the learned trial Judge did not explain in her grounds as to how
she came to the conclusion that the various obligations under Clause
3.1 of the SAA (which is an omnibus clause entitled “the General
Obligations of SSB”) constituted a “fundamental condition”. The
Defendant asserted that the SAA does not expressly classify any of
the obligations under Clause 3.1 as conditions. It was also not the
pleaded case of Plaintiff that Clause 3.1 was in the nature of
conditions. The Defendant submitted that any breach of Clause 3.1
(f) could not, in law, constitute a ground for termination. This,
according to the Defendant, was the error committed by the learned
trial Judge.
We, however, are in total agreement with the finding of the learned
trial Judge in this regard. In construing a clause of the SAA, regard
must be given to the words used in their factual and commercial
context. The clauses of the SAA must be viewed and assessed in
light of the overall purpose of the SAA. Clauses 3.1 (e) and (f) are
essential and go to the root of the entire SAA, without which the
ultimate purposes of the SAA are impossible to achieve. It is clear
that without the invoices, the Plaintiff could not verify the amount
billed to Maxis, which in turn affected the 2nd Tranche payment.
The Plaintiff had raised its concerns on the problem of collection
for the Defendant’s repayment for the 1st Tranche
(RM8,321,847.00) at the meeting on 25.7.2012 (refer to page 563
of ACB Volume 2), which caused difficulty to the Plaintiff to
continue the Project after these losses. Therefore, one cannot deny
[2017] 1 LNS 2042 Legal Network Series
24
the importance of these clauses, which are fundamental to the SAA,
a breach of which, by the Defendant, entitles the Plaintiff to
terminate the SAA.
61. It was argued by the Defendant in its submission that there was no
clear notice of the Plaintiff’s termination of the SAA. However, a
perusal of the minutes of meeting dated 25.7.2012 clearly show that
the Plaintiff did give a notice to the Defendant that the Plaintiff
would withdraw from the SAA and reasons were given for the
withdrawal (refer to page 563 and 564 of ACB Volume 2). Ultimately
the Plaintiff completely withdrew from the SAA between June/July
2012. This was never disputed at trial in the High Court.
Consequential relief to the Plaintiff as a result of the breach by the
Defendant:
62. The learned trial Judge further found that the Plaintiff had not
breached the SAA by withholding the 2nd Tranche as claimed by the
Defendant. The Plaintiff had already committed and contributed a
sum of RM8,321,847.00 in the 1st Tranche but had yet to receive any
returns whilst the Defendant had gained financial benefit derived
from Maxis Smart Partner Project. It therefore follows that the
Defendant’s counterclaim must fail as it is premised upon the
Plaintiff terminating the SAA. The Plaintiff is entitled to
compensation for any loss or damage which arose from the breach by
the Defendant. By virtue of section 74 of the Contracts Act 1950, the
Plaintiff who was the party who had suffered from the breach is
entitled to claim for whatever loss that it suffered as a result thereof.
63. We are of the view that the learned trial Judge had made the correct
findings in this respect and we find no reason to disturb the same.
Whether the Defendant is a trustee of the monies paid by Maxis in the
Dedicated Account. If so, whether the Defendant had acted in breach
[2017] 1 LNS 2042 Legal Network Series
25
of its fiduciary duties and obligations under its trustee’s duties under
the SAA
64. The learned trial Judge refused this claim on the basis that, inter alia,
the 2nd Tranche had yet to take place and that the claim for an account
and inquiry requested would only be relevant when the payment of
the 2nd Tranche was made. The Plaintiff submitted that the learned
trial Judge fell into error in law and fact, in that having determined
that the Plaintiff’s inability to release the 2nd Tranche was due to the
conduct of the Defendant when it failed to provide the Plaintiff with
the invoices issued to Maxis and the payments made by Maxis, she
disallowed the Plaintiff’s breach of fiduciary/trustee duties claim.
65. The Plaintiff submitted that nowhere in the SAA does it state that the
Plaintiff’s entitlement to the monies in the Dedicated Account is
dependent upon payment of the 2nd Tranche and/or securing the
replacement Bank Guarantee Facility. To say that it is, is reading into
the SAA terms which are plainly not there, which the law disallows.
Thus, the Plaintiff submitted that its entitlement is in no way
qualified or made conditional upon the payment of the 2nd Tranche
and/or any other condition.
66. The Plaintiff submitted that the learned trial Judge did not reject the
existence of a trust in the present Appeal. The Defendant submitted
that there was certainty of the subject matter of the trust as far as the
present appeal is concerned. The Defendant submitted that the
cumulative effect of Clauses 5.7, 6.1 and 6.2 disclose:
a) An intention to create a trust; the agreement sets out that the
Defendant agrees to receive and hold all payments and monies
from Maxis on trust for inter alia the Plaintiff in the Dedicated
Account;
b) there was certainty of object; it being clear that it is the
[2017] 1 LNS 2042 Legal Network Series
26
payments of Maxis to which the Plaintiff was entitled to in
accordance with the ratio in the SAA, and thus the Plaintiff is
a beneficiary of it; and
c) there was certainty of subject matter; it being clear that the
trust attaches itself to all the monies received by the Defendant
from Maxis pursuant to the SPPA dated 15.2.2010 which will
then be transferred and credited into the Dedicated Account.
For clarity and convenience, Clauses 5.7, 6.1 and 6.2 are set out
below:
Clause 5.7 of the SAA provides as follows:-
“For the avoidance of doubt, [the Plaintiff] is entitled to
receive RM16,643,694.00 from the On-Going Projects and
shall be paid from 90% of all payments and proceeds
accruing and received by [the Defendant] under the On-
Going Projects to be distributed in accordance with the
Agreed Benefit Ratio under the dedicated account...”
Clause 6.1 of the SAA provides as follows:-
“6.1. Agreed Benefit Ratio
Subject to the terms and conditions herein, the parties
agree and acknowledge that contractual payments for
the Project Works shall be apportioned in the
following manner:
(a) so long as the cumulative aggregate contractual
payments for the Project Works (which does not
include the contractual values of the On-Going
Projects) received is less than
RM200,000,000.00 and such sums are or will be
[2017] 1 LNS 2042 Legal Network Series
27
credited into the Dedicated Account, the parties
shall apportion the same as follows:
(i) 90% to [the Plaintiff]; and
(ii) 10% to [the Defendant].
(b) in the event, the cumulative aggregate
contractual payments for the Project Works
(which does not include the contractual value of
the On-Going Projects) received is more than
RM200,000,00.00 and such sums are or will be
credited into the Dedicated Account, the
apportionment for the next gross contractual
payment received for the Project Works shall be
apportioned in the following manner:
(i) 95% to [the Plaintiff] and;
(ii) 5% to [the Defendant].
The Parties agree and acknowledge that the respective
apportionment under Clause 6.1 above shall be carried out by
way of SI under the Dedicated Account.”
Clause 6.2 of the SAA provides as follows:-
“Dedicated Account
(a) [The Defendant] has already established and is operating
a dedicated current account in Malayan Banking Berhad
(Company No: 3813-K) at the branch in Tapah, Perak.
(b) [The Defendant] agrees and undertakes to transfer the
SSB Portion from the Nominated Joint Account into the
Dedicated Account. [The Defendant] agrees and
[2017] 1 LNS 2042 Legal Network Series
28
acknowledges that [the Defendant] shall ensure that all
monies to be received from [Maxis] under the [SPPA]
will be credited only into the Dedicated Account.
(c) With respect to the Dedicated Account, the parties shall
upon the First Tranche and Second Tranche being paid
in accordance with Clause 5.2, issue to Malayan
Banking Berhad a SI to be effectively immediately
authorising all payments credited to this Dedicated
Account to be immediately remitted to [the Plaintiff]
and [the Defendant] in the Agreed Benefit Ratio. The
parties agree and acknowledge that no changes to the
Dedicated Account or any instruction to the bank shall
be made without the prior written consent of [the
Plaintiff].
(d) Upon the First Tranche and Second Tranche being paid
in accordance with Clause 5.2 and the replacement bank
guarantee facility being made available in accordance
with Clause 5.6, the parties agree that all the cheque
and/or operating signatories to the Dedicated Account
shall be nominated and appointed by [the Plaintiff].
(e) [The Defendant] and [the Plaintiff] agree and undertake
that no payments, transfers, remittance or withdrawals
shall be made from the Dedicated Account unless it is
done under the SI with payments only to [the Plaintiff]
and [the Defendant] in accordance with their respective
Agreed Benefit Ratio.”
67. The Plaintiff submitted that, given that the Defendant is a trustee of
the monies in the Dedicated Account and the Plaintiff is a beneficiary
thereof, the Defendant thus owes fiduciary duties to the Plaintiff. It
was also submitted that, even if there is no trust, the Plaintiff owes
[2017] 1 LNS 2042 Legal Network Series
29
fiduciary duties as the relationship between the Plaintiff and the
Defendant is one that possesses the 3 general characteristics of a
fiduciary obligation as set out in Frame v. Smith [1987] 42 DLR 81
ie,:
“Relationships in which a fiduciary obligation have been
imposed seem to possess three general characteristics:
(1) the fiduciary has scope for the exercise of some
discretion or power;
(2) the fiduciary can unilaterally exercise that power or
discretion so as to affect the beneficiary’s legal or
practical interests;
(3) the beneficiary is peculiarly vulnerable to, or at the
mercy of, the fiduciary holding the discretion or power.”
Thus the Plaintiff contended that the Defendant has breached its
express and/or implied obligations under the SAA and its fiduciary
duties and obligations and/or its express and/or implied duties as
trustees when:
a) it failed to obtain consent from the Plaintiff before invoices
were issued to Maxis;
b) it failed to keep the Plaintiff informed and updated on the
invoices issued to Maxis and to keep the Plaintiff updated on
the payments received from Maxis;
c) it failed to account to the Plaintiff and keep the Plaintiff
informed and updated of all monies transferred to the
Dedicated Account;
d) it failed to account and pay to the Plaintiff the Plaintiff’s share
of the payments and monies received from Maxis in the Agreed
[2017] 1 LNS 2042 Legal Network Series
30
Benefit Ratio or at all; and
e) it failed to issue the requisite Standing Instruction to authorize
immediate payments out of the Dedicated Account to the
Plaintiff according to the Agreed benefit Ratio.
68. The argument advanced by the Plaintiff was premised on express
trust where the 3 certainties were referred to. In the course of the
Plaintiff’s argument to support the proposition of the existence of a
trust, the cases of ESPL (M) Sdn Bhd v. Radio & General
Engineering Sdn Bhd [2005] 2 MLJ 422 and Re Kayford Ltd [1975]
1 AER 604 were referred to us. We noted that, in those cases, there
was evidence of an express intention to create a trust. For example,
in ESPL (M) Sdn Bhd v. Radio & General Engineering Sdn Bhd
[2005] 2 MLJ 422 the word “trust” was used. None of those cases
imposed conditions that had to be fulfilled before the beneficiary’s
interest crystallized.
69. It is noted that an express trust may be created without using the
words “trust”. In the absence of express words creating such an
express trust, the Court will look at the surrounding circumstances to
determine whether the party intended to constitute itself a trustee, as
illustrated by this Court in ESPL (M) Sdn Bhd v. Radio & General
Engineering Sdn Bhd (supra) where there was a clear and an express
Clause 27.1 in the sub contract which stated “....Sub-Contractor will
receive the payment made by the Contractor and will hold the right
to receive such payments as a trust fund to be applied first to the
payment of labourers, suppliers, Sub-sub-Contractors and others
responsible for the Works justifying such payments....”. In that case
the said clause together with the contemporaneous correspondence
and the surrounding circumstances showed that the plaintiff clearly
“intended to constitute itself a trustee for the defendant”.
70. Similarly, Re Kayford Ltd [1975] 1 AER 604 is another authority that
[2017] 1 LNS 2042 Legal Network Series
31
illustrates the proposition that the intention of the parties is to be
gathered from the totality of the circumstances of the case, including
the words written or spoken and the conduct of parties, in the
determination of the existence of a trust. Megarry J held that
although no imperative words were used in any of the documents, it
was clear that the intention was that “there should be a trust”. He
said as follows:
“Now there are clearly some loose ends in the case. Mr. Kay,
advised to establish a “customers’ trust Deposit Account”,
seems to have thought that it did not matter what the account
was called so long as there was a separate account; and so the
dormant deposit account suggested by the bank manager was
used. The bank statement for this account is before me, and on
the first page, for which the title is simply “Deposit Account
Kayford Limited”, nearly 26 Pound is credited. The second and
third pages have the words “Customer Trust Deposit Account”
added after the previous title of the account; and Mr. Joel’s
payment was made after these words had been added. Mr. Kay
also left matters resting on a telephone conversation with the
bank manager until he wrote his letter of 12 December to the
bank. That letter reads: “We confirm our instructions regarding
the opening of the deposit account for customers deposits for
new orders”; and he then makes some mention of other
accounts with the bank. The letter goes on; Please ensure the
re-opened deposit account is titled “Customer Trust Deposit
Account”. Then he gives the reference number and asks for
confirmation that this has been done. Nevertheless, despite the
loose ends, when I take as a whole the affidavits of Mr.
Wainwright, Mr. Kay and Mr Hall (the bank manager) I feel no
doubt that the intention was that there should be a trust. There
are no difficulties. The property concerned is pure personality,
[2017] 1 LNS 2042 Legal Network Series
32
and so- called “three certainties” of a trust. The subject matter
to be held on trust is clear, and so are the beneficial interests
therein, as well as the beneficiaries. As for the requisite
certainty of words, it is well settled that a trust can be created
without using the words “trust” or “confidence” or the like; the
question is whether in substance a sufficient intention to create
a trust has been manifested.”
71. Gunn Chit Tuan SCJ in Geh Cheng Hooi & Ors v. Equipment
Dynamics [1991] 1 MLJ 293 applied Re Kayford Ltd (supra) where
he said:
“Although we would agree with the view that a trust should not
normally be imported into a commercial relationship, yet we
would hold that in cases such as those involved in these appeals
the court could and should consider the facts to determine
whether a fiduciary relationship existed. We therefore agreed
with Mr. Wong that in the present cases we must consider the
circumstances concerning the relationship between the parties.
We were satisfied and agreed with the learned judge that in the
circumstances of these cases a trust can be implied even where
the agreements themselves do not contain an express clause
that the proceeds of sale should be held on trust as it is clearly
manifested in the agreements and the correspondence
concerned that it was the intention of the parties that the
Emporium or its outlets as licensors should, after deduction of
the fees and commissions agreed to be paid to them, make over
to the concessionaires or consignors all payments by third
party customers (emphasis added).”
72. As far as the present appeal is concerned, there is nothing in the
testimonies of the witnesses to show that the true intention of the
parties was to create a trust, as this issue was never addressed by the
[2017] 1 LNS 2042 Legal Network Series
33
witnesses of the Plaintiff nor suggested via cross-examination of the
Defendant’s witnesses.
73. The Plaintiff sought to rely on the cumulative effect of Clauses 5.7,
6.1 and 6.2 of the SAA to show that there was a trust. However, we
failed to see how such provisions of the SAA can be interpreted to
create a trust. The entire structure of the SAA was such that, the
Plaintiff would only earn the right to repay themselves from the
Dedicated Account once the Plaintiff has paid the 1st Tranche and
the 2nd Tranche. It is not in dispute that the 1st Tranche was paid,
but not the 2nd Tranche.
If one is to read Clause 5.6 of the same, which provides that if the
Plaintiff failed to replace the bank guarantee facility of the
Defendant by 15.1.2011, then the Defendant shall be entitled to
utilize the funds in the Dedicated Account for that purpose. Such a
provision cannot be compatible with the existence of a trust as
contended by the Plaintiff.
74. This Court in Perman Sdn Bhd v. European Commodities Sdn Bhd
& Anor [2005] 4 CLJ 750) has held that the standard of proof of the
existence of an express trust in given circumstances is very high.
The rationale in law is that, no person’s property should be burdened
with the interest of another in the absence of the clearest of proof.
The law requires an intention to create a trust to be expressed in
clear language.
75. The relationship between the Plaintiff and the Defendant is strictly
governed by the SAA. There are no clear stipulations in the SAA as
to creation of a trust. What is clear, is the dispute in relation to the
alleged breaches by the parties of the provisions of the SAA. The
cause of action is breach of a commercial contract i.e. the SAA
which was entered between 2 business entities. A further
examination of the relevant provisions of the SAA discloses the
[2017] 1 LNS 2042 Legal Network Series
34
following:
a) Clause 6.2 (c) provides that after paying the 1st Tranche and
the 2nd Tranche, a Standing Instruction will be issued to
Maybank to authorize the remittance of the monies in the
Dedicated Account upon the Agreed Benefit Ratio;
b) It is from this Dedicated Account that the Plaintiff was to seek
repayment of the advances it was to make to the Defendant in
the form of the 1st Tranche and the 2nd Tranche, together with
the notional top up, to the extent of RM16,643,694.00. Hence
the right to seek repayment will only accrue upon payment of
the 2nd Tranche; and
c) Clause 5.7 provides that, if for whatever reason, the proceeds
of the On-Going Projects should be insufficient to repay the
Plaintiff, the Defendant was not to make any payment to cover
the shortfall from its own coffers. Instead, the shortfall was
to be covered from the profits derived from any future
collaboration between the Plaintiff and the Defendant.
The abovementioned provisions of the SAA militate against the
existence of a trust.
76. In addition, it is trite law that we do not import elements of fiduciary
duties and trust into contractual commercial contexts. In the case of
Hospital Products Limited v. United States Surgical Cooperation
[1984] CLR 41, Maison J summarized the contractual and fiduciary
relationship between contracting parties, where he held at page 97:
“That contractual and fiduciary relationships may co-exist
between the same parties has never been doubted. Indeed, the
existence of a basic contractual relationship has in many
situations provided a foundation for the erection of a fiduciary
[2017] 1 LNS 2042 Legal Network Series
35
relationship. In these situations it is the contractual foundation
which is all important because it is the contract that regulates
the basic rights and liabilities of the parties. The fiduciary
relationship, if it is to exist at all, must accommodate itself to
the terms of the contract so that it is consistent with, and
conforms to them. The fiduciary relationship cannot be
superimposed upon the contract in such a way as to alter the
operation which the contract was intended to have according to
its true construction.”
77. Hence, upon a true construction of the SAA, it is clear that the
repayment of the advances made by the Plaintiff (in the form of the
1st and the 2nd Tranches together with RM16,634,694.00) from the
Dedicated Account was after the 1st and the 2nd Tranches were paid.
An express/implied trust cannot be inferred to have been created in
these situations. The entitlement of the Plaintiff to the repayment
from the Dedicated Account did not crystallize, unlike the facts in
ESPL (M) Sdn Bhd v. Radio & General Engineering Sdn Bhd
(supra), Re Kayford (supra), Geh Cheng Hooi & Ors v. Equipment
Dynamics (supra). Ultimately, our present Appeal is a case of breach
of contract.
78. Therefore, we found that the learned trial Judge had not erred when
she dismissed the claim of the Plaintiff that the Defendant acted in
breach of its implied obligations under the SAA or that the
Defendant acted in breach of its fiduciary duties and obligations
under its trustees’ duties.
The purported departure by the Plaintiff from its pleadings:
79. The Defendant argued that the Plaintiff had departed from its pleaded
case when it argued that it was not able to verify the invoices issued
by Maxis. The Defendant submitted that the learned trial Judge‘s
finding that the Defendant had not provided the actual invoices and
[2017] 1 LNS 2042 Legal Network Series
36
payments, is at variance with the Plaintiff’s pleaded case. However,
this argument by the Defendant is without merit as the Plaintiff has
pleaded these material facts at:
i) para 7 (d) (iv) in the Statement of Claim which reads:
“(d) The Defendant shall.... (iv) provide the Plaintiff with
all invoices issued to maxis and updates on all
payments received from maxis (Clause 3.1 (f))”
ii) para 11 (c ) and (d) of the Statement of Claim which read:
“(c) The Defendant failed, in particular from in and
around October 2011, to keep the Plaintiff informed
and updated on the invoices issued to Maxis.”
(d) The Defendant failed, in particular from in and
around October 2011, to keep the Plaintiff informed
and updated on the payments received from Maxis.”
80. Subsequently, the Plaintiff adduced evidence at trial to support these
material facts, i.e. that such information or update on the invoices
must surely be that which is reasonably and objectively verifiable,
given that these two parties here are commercial business entities
entering into an agreement for the first time. It has been established
through evidence that there have been no invoices to Maxis,
provided to the Plaintiff for verification, which is an obligation
stipulated under the SAA. The invoices are the best evidence for the
said purpose, not the summaries or listings as provided by the
Defendant. Evidence from the Defendant’s witnesses who said that
they have provided the invoices to the Plaintiff are inadequate to
verify the actual amount of the invoices billed to Maxis. Similarly,
as to payments which the Defendant received from Maxis, the best
evidence would be the bank statements of the Dedicated Account.
[2017] 1 LNS 2042 Legal Network Series
37
81. Hence, we found that the Plaintiff’s case was in accordance to its
pleaded case and the argument that the Plaintiff had departed from
the same holds no water.
The Counterclaim by the Defendant:
82. The Defendant argued that as the Plaintiff had purportedly breached
the SAA, the Plaintiff cannot take advantage of its own wrong. The
Defendant referred us to the case of Poh Geok Sing v. HB Enterprise
Sdn Bhd [2006] 1 CLJ 765 in support of its proposition that a contract
breaker, being responsible for the breach of an agreement, “cannot
seek to recover any benefit he may have conferred upon the innocent
party where he is himself guilty of a breach of the contract. Were it
otherwise, a contract breaker will be in a position to take advantage
of his own wrong”.
83. However, the facts in Poh Geok Sing (supra) are distinguishable
from the facts in the Appeal before us for the following reasons:
(a) Firstly, the Plaintiff in the present Appeal is not the contract
breaker. We have found that it was the Defendant which
breached the SAA when it failed to comply with Clause 3.1 (e)
and (f) of the SAA, as there cannot be a determination on the
amount which had been invoiced to Maxis, thus making it
impossible for parties to determine that the payment for the 2nd
Tranche has been triggered. Hence, the Plaintiff could not be
faulted for withholding the 2nd Tranche payment to the
Defendant. The Plaintiff is not in breach of the SAA for
withholding of the 2nd Tranche.
(b) Secondly, in Poh Geok Sing (supra), there was a clear
termination of the contract by the defendant therein, which the
court held to be justified and lawful, and hence the defendant
therein was entitled to claim for damages. In our present
[2017] 1 LNS 2042 Legal Network Series
38
Appeal, the Defendant never terminated the SAA. If at all, in
fact it affirmed the SAA.
(c) In addition, in Poh Gek Sing (supra), the case involved a “lump
sum contract” where the contract requires the completion of an
entire project before payment becomes due, which is not the
situation in our present Appeal. Nowhere in the SAA was it
stated that the Plaintiff is to complete the Project Works before
it is entitled to receive payments. The SAA provides that the
Plaintiff is entitled to receive:
i) RM16,643,694.00 from 90% of the 2010 DROs;
ii) 90%/95% of the proceeds from the post 2010 DROs;
as and when these monies are paid into the Dedicated Account
by Maxis. This happened whenever Maxis issued a DROs, the
Plaintiff/Defendant will complete the DROs and the
Defendant will then invoice Maxis who will then make
payment.
(d) In Poh Gek Sing (supra), it was also found that the defendant
therein had not conferred any benefit upon the plaintiff therein
pursuant to the contract. It was held that the structures built by
the plaintiff were in fact a burden. This Court held in Poh Gek
Sing (supra) that in the absence of such finding of benefit, the
plaintiff was not entitled to claim for the benefits bestowed
upon the defendant therein. In the present Appeal, the Plaintiff
has carried out the works as issued out from the DROs in 2011,
and in the process expended a sum of RM13,657,844.00 in
capital and operational expenses. On the other hand, the
Defendant had in fact received payments from Maxis, and has
thus received benefits.
[2017] 1 LNS 2042 Legal Network Series
39
84. Consequently, the declaration sought by the Defendant in the
counterclaim was rightly dismissed by the learned trial Judge.
Conclusion:
85. We therefore dismissed both the appeals with no order as to costs.
The decision of the learned High Court Judge is affirmed.
(ZABARIAH MOHD YUSOF)
Judge
Court of Appeal
Putrajaya
Dated: 31 OCTOBER 2017
Counsel:
Appeal B-02(NCVC)(W)-152-01/2016
For the appellant - Conrad Young, K Thavanesan, Tan Shang Neng; M/s
Sreeneevasan Young
For the respondent - Michael Chow & TP Teh; M/s Michael Chow
Appeal B-02 (NCVC)(W)-154-01/2016
For the respondent - Conrad Young, K Thavanesan, Tan Shang Neng; M/s
Sreeneevasan Young
For the appellant - Michael Chow & TP Teh; M/s Michael Chow