Top Banner

of 40

15. Tank Lifting Engineering

Apr 03, 2018

Download

Documents

Grave-da
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/28/2019 15. Tank Lifting Engineering

    1/40

    All accidence are preventable

  • 7/28/2019 15. Tank Lifting Engineering

    2/40

    Safe Methods & Procedures

    Tank Lifting

  • 7/28/2019 15. Tank Lifting Engineering

    3/40

    EEMUA Publication No. 159: 2003,3rd Edition Volume 2

    Appendix C: Typical Repair Solutions

    C.1.1 Application

    J acking is a very important technique for makingrepairs or modifications to tank foundations andbottoms.

    Tanks are jacked up by using hydraulic jacks or air-

    bags, which lift the tank 6 8ft above the foundation,and supported on timber stacks.

    The 6 8ft free height allows small earth-moving

    equipment to operate under the tank.

    C.1 Tank Jacking

  • 7/28/2019 15. Tank Lifting Engineering

    4/40

    More specifically, jacking is often used to:

    correct unacceptable foundation settlement

    install a high density polyethylene (HDPE)

    membrane under the entire tank together witha leak detection system or leak detection andmanagement system

    remove contaminated soil caused by bottom

    leakages, and restore the foundation

  • 7/28/2019 15. Tank Lifting Engineering

    5/40

    ensure safe replacement of the tank bottom if thefoundation is contaminated

    install a cathodic protection system under thetank bottom.

    inspect the tank bottom for underside corrosion; ifnecessary, the underside of the tank bottom

    can be blasted and coated after theinspection;

  • 7/28/2019 15. Tank Lifting Engineering

    6/40

    Hydraulic jacks.

    High capacity (up to 60 tons per jack) but heavy to

    move around.

    Lifting lugs need to be welded to the outside of the

    shell, or the jacks welded to the tank

    Large excavations are required to position the jacks

    directly under the shell.Such large excavations are undesirable.

    C.1.2 Types of Jacks

  • 7/28/2019 15. Tank Lifting Engineering

    7/40

    C.1.2 Types of Jacks

    Air-bags.

    High capacity (up to 74 tons per air-bag) easy tohandle and move around.

    Air-bags require a small excavation under the shell,about 2in high, to insert an empty bag.

    Usually, two excavations are required to lift part ofthe shell to allow the insertion of additional air bagsat adjacent locations.

  • 7/28/2019 15. Tank Lifting Engineering

    8/40

    C.1.7 General Requirements

    The general requirements for ensuring a safe andsuccessful jacking operation are:

    Selection of an experienced jacking contractor.

    J acking contractor to perform site survey includinglevel measurements.

  • 7/28/2019 15. Tank Lifting Engineering

    9/40

    J acking contractor to submit detailed methodincluding calculation of overturning stabilityunder wind conditions.

    Special attention should be given to tanks with

    corroded shell plates, i.e. more jacking pointsmay be required to reduce vertical bendingstresses.

    In addition, the contractor should demonstrate bymeans of calculations that the tank integrity

    (shell and roof structure) will be maintainedduring jacking.

  • 7/28/2019 15. Tank Lifting Engineering

    10/40

    Tank Lift Engineering

  • 7/28/2019 15. Tank Lifting Engineering

    11/40

    Tank lifting work is started after thorough

    professional engineering evaluations are performed.

    The evaluations are accomplished with veryconservative safety factors built in.

  • 7/28/2019 15. Tank Lifting Engineering

    12/40

    Air Bag Support Timbers

    SiesmicForces

    Allowable Air Bag Pressure

    Tank Lifting Engineering

    Wind UpliftWind Forces

    Tank Perimeter Supports Ground Bearing Pressure

    VerticalShellCompressionRadicalShell/FloorCompression

    Vertical Shell Compression Radial Shell/Floor Compression

    Calculations are in accordance with:

    Local codes and practices

    Knowledge of the tanks original construction

    A.P.I. tank construction standards and details

    Local wind conditions

  • 7/28/2019 15. Tank Lifting Engineering

    13/40

    Air Bag Support Timbers

    SiesmicForces

    Allowable Air Bag Pressure

    Tank Lifting Engineering

    Wind UpliftWind Forces

    Tank Perimeter Supports Ground Bearing Pressure

    VerticalShellCompressionRadicalShell/FloorCompression

    Vertical Shell Compression Radial Shell/Floor Compression

    Tank Stress

    Maximum air bag pressure

    Calculated floor sag

    Required number of perimeter supports

  • 7/28/2019 15. Tank Lifting Engineering

    14/40

    Air Bag Support Timbers

    SiesmicForces

    Allowable Air Bag Pressure

    Tank Lifting Engineering

    Wind UpliftWind Forces

    Tank Perimeter SupportsGround Bearing Pressure

    VerticalShellCompressionRadicalShell/FloorCompression

    Vertical Shell Compression Radial Shell/Floor Compression

    Foundation load

    Proven ground bearing pressure and shear strength

    Minimum number of tank supports

  • 7/28/2019 15. Tank Lifting Engineering

    15/40

    Air Bag Support Timbers

    SiesmicForces

    Allowable Air Bag Pressure

    Tank Lifting Engineering

    Wind UpliftWind Forces

    Tank Perimeter SupportsGround Bearing Pressure

    VerticalShellCompressionRadicalShell/FloorCompression

    Vertical Shell Compression Radial Shell/Floor Compression

    Wind Velocity

    Skidding Tank overturning

    Sty overturning

  • 7/28/2019 15. Tank Lifting Engineering

    16/40

    Procedure & Job Safety Analysis

    Client Safety Standards

    Client safety standards will be reviewed prior to the

    start of work and are to be followed.Additionally, all necessary work permits shall beobtained from client personnel prior to the start of

    work each day.

    Job Safety Analysis

    Prior to each phase of work, a job safety analysisshall be performed. See Individual Tank Specificdocuments.

  • 7/28/2019 15. Tank Lifting Engineering

    17/40

    Procedure & Job Safety Analysis

    Pre-lift

    Fill out Individual Tank Specific documents.

    The individual tank specific documents include site

    specific, heath, safety and environment requirements

    The sheets required for toolbox meetings and thesheets required for job safety analysis.

  • 7/28/2019 15. Tank Lifting Engineering

    18/40

    Job Tasks Potential Hazards Recommended Action or Procedure

    Inspect and mark out Fall Care when walking around Tank

    Cut and Weld Caught Welding leads, grinder, electric leadsare laid out safely. Use proper cutting

    / welding PPECrane Caught Inspect all rigging equipment prior to

    each use.

    Do not exceed the capacity of the

    equipment.Never lift loads over people

    Use tag lines to control all loads.

    Know the capacity of riggingequipment and weight of load that you

    are picking up.

    All hooks must have a safety latch.

    Use the right communications withcrane operator and rigger.

    Job Safety Analysis

  • 7/28/2019 15. Tank Lifting Engineering

    19/40

    Job Tasks Potential Hazards Recommended Action or Procedure

    Install timbers Caught & Fall Keep timbers stacked and storedwhen not using. Tripping hazard

    Be aware of pinch points, wear gloves

    Proper lifting techniques, bend theknees

    Install airbags andplates

    Hydraulic J acks

    Caught 2 men to move bags and steel plates

    Proper lifting techniques, bend the

    knees

    Airbag hosesHydraulic hoses

    Fall Keep hoses tidy tripping hazard

    Job Safety Analysis

  • 7/28/2019 15. Tank Lifting Engineering

    20/40

    Tool Box Meeting

    Topics:

    PPE Steel toe footwear

    Hard hats Eye protectionHand protection Fall protectionHearing protection Respiratory protection

    Discuss:

    Health & Safety issues

    Previous days work

    Work that we are hoping to achieve today

    Changes in working conditions

  • 7/28/2019 15. Tank Lifting Engineering

    21/40

    On the Job Safety; For Everyone; Everyday; All

    the time

    House keeping; Follow written procedures; ask forassistance, if needed

    Job Safety Analysis:

    ASSESS the risk;

    What could go wrong?

    What is the worst thing that could happen ifsomething does go wrong?

  • 7/28/2019 15. Tank Lifting Engineering

    22/40

    ANALYSE how to reduce the risk;

    Do I have the necessary Training and Knowledge todo this job safely?

    Do I have the proper Tools

    Do I have Personal Protective Equipment?

    Job Safety Analysis:

    ACT to ensure safe operation;Take necessary Action to ensure the job is donesafely

  • 7/28/2019 15. Tank Lifting Engineering

    23/40

    Do not proceed unless

    EVERYTHING IS SAFE

    Job Safety Analysis:

    If you THINK that it is SAFEDont do it

    Do it when you KNOW that it is SAFE

  • 7/28/2019 15. Tank Lifting Engineering

    24/40

    Air bag Technology

    Correction of the tank rim settlement

  • 7/28/2019 15. Tank Lifting Engineering

    25/40

    Repair/replacement of tank floor plates

    Restore/change the tank floor profile

    Reconstruct tank foundation

  • 7/28/2019 15. Tank Lifting Engineering

    26/40

    No welding required on tank

  • 7/28/2019 15. Tank Lifting Engineering

    27/40

    Air bags can be move to balance tank weight

  • 7/28/2019 15. Tank Lifting Engineering

    28/40

    Tank can be lifted completely external

  • 7/28/2019 15. Tank Lifting Engineering

    29/40

    100% under floor visual inspection

  • 7/28/2019 15. Tank Lifting Engineering

    30/40

    No limit in size

  • 7/28/2019 15. Tank Lifting Engineering

    31/40

    All internal fixtures can remain in place

  • 7/28/2019 15. Tank Lifting Engineering

    32/40

    Tank lifting equipment is portable

  • 7/28/2019 15. Tank Lifting Engineering

    33/40

    Tank can be lifted completely external

  • 7/28/2019 15. Tank Lifting Engineering

    34/40

    Tanks that have leaked can be safely lifted

  • 7/28/2019 15. Tank Lifting Engineering

    35/40

    Tank suction can be overcome by increasing

    the number of air bags

  • 7/28/2019 15. Tank Lifting Engineering

    36/40

    Tank can be moved and rotated

  • 7/28/2019 15. Tank Lifting Engineering

    37/40

    Laying new steel floor

  • 7/28/2019 15. Tank Lifting Engineering

    38/40

    Tank floor inspection made easier with

    plenty of light

  • 7/28/2019 15. Tank Lifting Engineering

    39/40

    An added benefit of tank lifting, is the ease atwhich a tank can be relocated once the tank is

    in the air. This can save the tank operators

    thousands of dollars and months of downtime.

  • 7/28/2019 15. Tank Lifting Engineering

    40/40

    Removing last airbag from under tank