7/28/2019 15. Tank Lifting Engineering
1/40
All accidence are preventable
7/28/2019 15. Tank Lifting Engineering
2/40
Safe Methods & Procedures
Tank Lifting
7/28/2019 15. Tank Lifting Engineering
3/40
EEMUA Publication No. 159: 2003,3rd Edition Volume 2
Appendix C: Typical Repair Solutions
C.1.1 Application
J acking is a very important technique for makingrepairs or modifications to tank foundations andbottoms.
Tanks are jacked up by using hydraulic jacks or air-
bags, which lift the tank 6 8ft above the foundation,and supported on timber stacks.
The 6 8ft free height allows small earth-moving
equipment to operate under the tank.
C.1 Tank Jacking
7/28/2019 15. Tank Lifting Engineering
4/40
More specifically, jacking is often used to:
correct unacceptable foundation settlement
install a high density polyethylene (HDPE)
membrane under the entire tank together witha leak detection system or leak detection andmanagement system
remove contaminated soil caused by bottom
leakages, and restore the foundation
7/28/2019 15. Tank Lifting Engineering
5/40
ensure safe replacement of the tank bottom if thefoundation is contaminated
install a cathodic protection system under thetank bottom.
inspect the tank bottom for underside corrosion; ifnecessary, the underside of the tank bottom
can be blasted and coated after theinspection;
7/28/2019 15. Tank Lifting Engineering
6/40
Hydraulic jacks.
High capacity (up to 60 tons per jack) but heavy to
move around.
Lifting lugs need to be welded to the outside of the
shell, or the jacks welded to the tank
Large excavations are required to position the jacks
directly under the shell.Such large excavations are undesirable.
C.1.2 Types of Jacks
7/28/2019 15. Tank Lifting Engineering
7/40
C.1.2 Types of Jacks
Air-bags.
High capacity (up to 74 tons per air-bag) easy tohandle and move around.
Air-bags require a small excavation under the shell,about 2in high, to insert an empty bag.
Usually, two excavations are required to lift part ofthe shell to allow the insertion of additional air bagsat adjacent locations.
7/28/2019 15. Tank Lifting Engineering
8/40
C.1.7 General Requirements
The general requirements for ensuring a safe andsuccessful jacking operation are:
Selection of an experienced jacking contractor.
J acking contractor to perform site survey includinglevel measurements.
7/28/2019 15. Tank Lifting Engineering
9/40
J acking contractor to submit detailed methodincluding calculation of overturning stabilityunder wind conditions.
Special attention should be given to tanks with
corroded shell plates, i.e. more jacking pointsmay be required to reduce vertical bendingstresses.
In addition, the contractor should demonstrate bymeans of calculations that the tank integrity
(shell and roof structure) will be maintainedduring jacking.
7/28/2019 15. Tank Lifting Engineering
10/40
Tank Lift Engineering
7/28/2019 15. Tank Lifting Engineering
11/40
Tank lifting work is started after thorough
professional engineering evaluations are performed.
The evaluations are accomplished with veryconservative safety factors built in.
7/28/2019 15. Tank Lifting Engineering
12/40
Air Bag Support Timbers
SiesmicForces
Allowable Air Bag Pressure
Tank Lifting Engineering
Wind UpliftWind Forces
Tank Perimeter Supports Ground Bearing Pressure
VerticalShellCompressionRadicalShell/FloorCompression
Vertical Shell Compression Radial Shell/Floor Compression
Calculations are in accordance with:
Local codes and practices
Knowledge of the tanks original construction
A.P.I. tank construction standards and details
Local wind conditions
7/28/2019 15. Tank Lifting Engineering
13/40
Air Bag Support Timbers
SiesmicForces
Allowable Air Bag Pressure
Tank Lifting Engineering
Wind UpliftWind Forces
Tank Perimeter Supports Ground Bearing Pressure
VerticalShellCompressionRadicalShell/FloorCompression
Vertical Shell Compression Radial Shell/Floor Compression
Tank Stress
Maximum air bag pressure
Calculated floor sag
Required number of perimeter supports
7/28/2019 15. Tank Lifting Engineering
14/40
Air Bag Support Timbers
SiesmicForces
Allowable Air Bag Pressure
Tank Lifting Engineering
Wind UpliftWind Forces
Tank Perimeter SupportsGround Bearing Pressure
VerticalShellCompressionRadicalShell/FloorCompression
Vertical Shell Compression Radial Shell/Floor Compression
Foundation load
Proven ground bearing pressure and shear strength
Minimum number of tank supports
7/28/2019 15. Tank Lifting Engineering
15/40
Air Bag Support Timbers
SiesmicForces
Allowable Air Bag Pressure
Tank Lifting Engineering
Wind UpliftWind Forces
Tank Perimeter SupportsGround Bearing Pressure
VerticalShellCompressionRadicalShell/FloorCompression
Vertical Shell Compression Radial Shell/Floor Compression
Wind Velocity
Skidding Tank overturning
Sty overturning
7/28/2019 15. Tank Lifting Engineering
16/40
Procedure & Job Safety Analysis
Client Safety Standards
Client safety standards will be reviewed prior to the
start of work and are to be followed.Additionally, all necessary work permits shall beobtained from client personnel prior to the start of
work each day.
Job Safety Analysis
Prior to each phase of work, a job safety analysisshall be performed. See Individual Tank Specificdocuments.
7/28/2019 15. Tank Lifting Engineering
17/40
Procedure & Job Safety Analysis
Pre-lift
Fill out Individual Tank Specific documents.
The individual tank specific documents include site
specific, heath, safety and environment requirements
The sheets required for toolbox meetings and thesheets required for job safety analysis.
7/28/2019 15. Tank Lifting Engineering
18/40
Job Tasks Potential Hazards Recommended Action or Procedure
Inspect and mark out Fall Care when walking around Tank
Cut and Weld Caught Welding leads, grinder, electric leadsare laid out safely. Use proper cutting
/ welding PPECrane Caught Inspect all rigging equipment prior to
each use.
Do not exceed the capacity of the
equipment.Never lift loads over people
Use tag lines to control all loads.
Know the capacity of riggingequipment and weight of load that you
are picking up.
All hooks must have a safety latch.
Use the right communications withcrane operator and rigger.
Job Safety Analysis
7/28/2019 15. Tank Lifting Engineering
19/40
Job Tasks Potential Hazards Recommended Action or Procedure
Install timbers Caught & Fall Keep timbers stacked and storedwhen not using. Tripping hazard
Be aware of pinch points, wear gloves
Proper lifting techniques, bend theknees
Install airbags andplates
Hydraulic J acks
Caught 2 men to move bags and steel plates
Proper lifting techniques, bend the
knees
Airbag hosesHydraulic hoses
Fall Keep hoses tidy tripping hazard
Job Safety Analysis
7/28/2019 15. Tank Lifting Engineering
20/40
Tool Box Meeting
Topics:
PPE Steel toe footwear
Hard hats Eye protectionHand protection Fall protectionHearing protection Respiratory protection
Discuss:
Health & Safety issues
Previous days work
Work that we are hoping to achieve today
Changes in working conditions
7/28/2019 15. Tank Lifting Engineering
21/40
On the Job Safety; For Everyone; Everyday; All
the time
House keeping; Follow written procedures; ask forassistance, if needed
Job Safety Analysis:
ASSESS the risk;
What could go wrong?
What is the worst thing that could happen ifsomething does go wrong?
7/28/2019 15. Tank Lifting Engineering
22/40
ANALYSE how to reduce the risk;
Do I have the necessary Training and Knowledge todo this job safely?
Do I have the proper Tools
Do I have Personal Protective Equipment?
Job Safety Analysis:
ACT to ensure safe operation;Take necessary Action to ensure the job is donesafely
7/28/2019 15. Tank Lifting Engineering
23/40
Do not proceed unless
EVERYTHING IS SAFE
Job Safety Analysis:
If you THINK that it is SAFEDont do it
Do it when you KNOW that it is SAFE
7/28/2019 15. Tank Lifting Engineering
24/40
Air bag Technology
Correction of the tank rim settlement
7/28/2019 15. Tank Lifting Engineering
25/40
Repair/replacement of tank floor plates
Restore/change the tank floor profile
Reconstruct tank foundation
7/28/2019 15. Tank Lifting Engineering
26/40
No welding required on tank
7/28/2019 15. Tank Lifting Engineering
27/40
Air bags can be move to balance tank weight
7/28/2019 15. Tank Lifting Engineering
28/40
Tank can be lifted completely external
7/28/2019 15. Tank Lifting Engineering
29/40
100% under floor visual inspection
7/28/2019 15. Tank Lifting Engineering
30/40
No limit in size
7/28/2019 15. Tank Lifting Engineering
31/40
All internal fixtures can remain in place
7/28/2019 15. Tank Lifting Engineering
32/40
Tank lifting equipment is portable
7/28/2019 15. Tank Lifting Engineering
33/40
Tank can be lifted completely external
7/28/2019 15. Tank Lifting Engineering
34/40
Tanks that have leaked can be safely lifted
7/28/2019 15. Tank Lifting Engineering
35/40
Tank suction can be overcome by increasing
the number of air bags
7/28/2019 15. Tank Lifting Engineering
36/40
Tank can be moved and rotated
7/28/2019 15. Tank Lifting Engineering
37/40
Laying new steel floor
7/28/2019 15. Tank Lifting Engineering
38/40
Tank floor inspection made easier with
plenty of light
7/28/2019 15. Tank Lifting Engineering
39/40
An added benefit of tank lifting, is the ease atwhich a tank can be relocated once the tank is
in the air. This can save the tank operators
thousands of dollars and months of downtime.
7/28/2019 15. Tank Lifting Engineering
40/40
Removing last airbag from under tank