Detailed Project Report for Rail Based Mass Transit System in Varanasi Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS February, 2016 Page 13‐1 1 1 3 3 . . C C O O S S T T E E S S T T I I M M A A T T E E S S A A N N D D F F I I N N A A N N C C I I A A L L S S 13.1 CAPITAL COSTS 13.1.1 Coverage Cost estimate for Varanasi Metro corridors (Corridor‐I from BHEL to BHU and Corridor‐II from Benia Bagh) has been prepared covering civil, electrical, signaling and telecommunications works, rolling stock, environmental protection, rehabilitation, etc. at Jan’ 2016 price level. While preparing the capital cost estimates, various items have generally been grouped under three major heads on the basis of (i) Route km length of alignment, (ii) Number of units of that item and (iii) Item being an independent entity. All items related with alignment, construction, permanent way, Third Rail, Signaling & Telecommunication, whether in main lines or in maintenance depot, have been estimated at rate per Route km/km basis. Cost of station structures, other electrical services at these stations and Automatic Fare Collection (AFC) installations at all stations have been assessed in terms of each station as a unit. Similarly, for items like Rolling stock costs have been estimated in terms of number of units required for each item. In remaining items, viz. land, utility diversions, rehabilitation, etc. the costs have been assessed on the basis of each item, taken as an independent entity. In order to arrive at realistic cost of various items, costs have been assessed on the basis of recently awarded rates of Lucknow Metro, DPRs of DMRC Ph‐IV, Lucknow and other various Metros and suitable escalation factor has been applied to bring these costs to Jan’ 2016 price level. Basic cost is exclusive of various taxes and duties viz. custom duty, excise duty, Sale tax, VAT etc. and details of taxes and duties are worked out separately. Current rates of various taxes and duties have been taken into consideration and taxes / duties have been applied as per prevalent practice of DMRC. 13.1.2 Land Requirement a) Finalization of alignment, location of stations, entry / exits etc. has been done with the objective of keeping land requirement to the bare minimum. For this purpose, alignment, stations, depots, parking and Property Development (PD) have been planned in the State Government land unless and until it becomes unavoidable to plan these facilities in Central Government land or private land. Common Depot for both Corridor‐I & Corridor‐II has
60
Embed
13. COST ESTIMATES AND FINANCIALS · 2019-02-13 · works, rolling stock, environmental protection, rehabilitation, etc. at Jan’ 2016 price level. While preparing the capital cost
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐1
1133.. CCOOSSTT EESSTTIIMMAATTEESS AANNDD
FFIINNAANNCCIIAALLSS
13.1 CAPITAL COSTS
13.1.1 Coverage
Cost estimate for Varanasi Metro corridors (Corridor‐I from BHEL to BHU and Corridor‐II from
Benia Bagh) has been prepared covering civil, electrical, signaling and telecommunications
works, rolling stock, environmental protection, rehabilitation, etc. at Jan’ 2016 price level.
While preparing the capital cost estimates, various items have generally been grouped under
three major heads on the basis of (i) Route km length of alignment, (ii) Number of units of that
item and (iii) Item being an independent entity. All items related with alignment, construction,
permanent way, Third Rail, Signaling & Telecommunication, whether in main lines or in
maintenance depot, have been estimated at rate per Route km/km basis.
Cost of station structures, other electrical services at these stations and Automatic Fare
Collection (AFC) installations at all stations have been assessed in terms of each station as a
unit. Similarly, for items like Rolling stock costs have been estimated in terms of number of
units required for each item. In remaining items, viz. land, utility diversions, rehabilitation, etc.
the costs have been assessed on the basis of each item, taken as an independent entity.
In order to arrive at realistic cost of various items, costs have been assessed on the basis of
recently awarded rates of Lucknow Metro, DPRs of DMRC Ph‐IV, Lucknow and other various
Metros and suitable escalation factor has been applied to bring these costs to Jan’ 2016 price
level.
Basic cost is exclusive of various taxes and duties viz. custom duty, excise duty, Sale tax, VAT
etc. and details of taxes and duties are worked out separately. Current rates of various taxes
and duties have been taken into consideration and taxes / duties have been applied as per
prevalent practice of DMRC.
13.1.2 Land Requirement
a) Finalization of alignment, location of stations, entry / exits etc. has been done with the
objective of keeping land requirement to the bare minimum. For this purpose, alignment,
stations, depots, parking and Property Development (PD) have been planned in the State
Government land unless and until it becomes unavoidable to plan these facilities in Central
Government land or private land. Common Depot for both Corridor‐I & Corridor‐II has
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐2
been planned in the Non‐agricultural land of Ganeshpur area (Private land). As Varanasi city
is very congested, most part of both the corridors is planned underground and stations are
proposed in open land. The summary of land requirement for Corridor ‐ I & II is as under :‐
TABLE 13.1: LAND & STRUCTURES REQUIREMENT (IN HECTARES) FOR CORRIDOR‐I
Ownership Purpose Permanent
LandTemporary
LandStructures (Floor area)
Central Govt (Northern Railway)
Alignment, Station etc 0.07 0.40 0.05
State Govt
Alignment, Station etc 1 2.6 0.2633
Private
Alignment, Station etc 1.05 2.5 0.52
Depot (Ganeshpur) 13.2
0 0.5
Casting Yard 0 6 0
RSS 0.3 0 0
Total 14.55 8.5 1.02
TABLE 13.2: LAND & STRUCTURES REQUIREMENT (IN HECTARES) FOR CORRIDOR‐II
Ownership Purpose Permanent
LandTemporary
LandStructures (Floor area)
Central Govt Alignment, Station etc 0.14 0 0.0242
State Govt
Alignment, Station etc 0.8 2.1 0.105
RSS 0.3 0 0
Total 1.1 2.1 0.105
Private
Alignment, Station etc 0.13 0 0.18
Casting yard 0 4 0
Total 0.13 4 0.18
b) The land area for piers of elevated alignment, elevated stations falling over the existing
road and entry/exit falling on road / State Government land has not been accounted for in
the land requirement and costing as present land use is not getting affected by these
facilities. Land requirement for other metro utilities like ramp, off the road elevated
stations, depot, RSS, ancillary buildings etc. have been accounted as far as per details in
subsequent paras.
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐3
c) Rate of Central Govt. land (Northern Railway at Varanasi Cantt for Corridor‐1 and Post
office at Sarnath for Corridor‐2), required on permanent basis has been taken as Per Circle
rates ‐ 01st Aug'15, published by Collectorate, Varanasi. No solatium has been applied to the
basic land cost. Cost of Passenger Reservation System (PRS) at Varanasi Cantt. including
cost of structure, electrical and S&T items, terminals etc has been taken as Rs. 3.0 crores as
per discussion with CRIS.
d) Rate of Central Govt. land (Northern Railway at Varanasi Cantt), required on temporary
basis for 3 years construction period, has been taken @ 6% Per annum of Circle rates ‐ 01st
Aug'15, published by Collectorate, Varanasi. No solatium has been applied to the basic land
cost.
e) Rate of State Govt. Land required on permanent basis has been taken from DPR for
Lucknow Metro with updation. No solatium has been applied to the basic land cost. In case,
State Govt. is in a position to provide its land free of cost or at reduced rates, it will further
improve the financial statistics of the project.
f) Cost of structures for rehabilitation of squatters at Tulsi Manas Mandir has been taken as
Rs. 25 crore per Hectare. Rehabilitation of squatters is required as per norms of
International Funding Agencies.
g) Rate of Private land & non commercial structures has been taken from Circle rates ‐ 01st
Aug'15, published by Collectorate. Above this, 100% solatium has been applied as per
LARRA. No administrative cost is added towards land acquisition activities, as it is
understood that this activity shall be carried out by State Govt. from its own resources.
h) On lines with DPR for Kanpur MRTS, efforts have been made to provide parking for
maximum possible stations. To make the project financially viable, property development
has been proposed on suitable land pieces on preliminary stage. Moreover, in line with DPR
for Lucknow Metro, cost of land towards parking cum PD is not loaded to the cost estimates
and this cost will be borne by State Govt. separately. Details of land required for parking
cum PD is mentioned separately in relevant chapter.
i) As advised by LMRC, depreciated rates for State Govt. structures have been taken after
applying maximum allowable depreciation of 60%.
j) Rate of private commercial structures including land is calculated as 300 x specified
monthly rent, published by Collectorate Varanasi, August' 15. 100% Solatium has been
applied to basic cost of structures.
k) Annual cost of private land required on temporary basis (for construction of U/G stations at
University, RBS college etc.) is calculated as 6% of corresponding circle rate of that locality.
Construction period is taken as 3 years. No solatium has been applied to basic land cost.
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐4
l) The total cost of Land works out to be Rs. 438.47 Crores for Corridor‐I and Rs. 36.99 Crores
for Corridor‐II.
13.1.3 Items other than Land: Cost of items other than land is based upon LAR / DPR
rates as under:‐
TABLE 13.3: BASIS OF RATES
Item
No. Item Basis of Rates
2.0 Alignment and Formation
2.1 Underground section by
T.B.M excluding station
length
Avg. of Esc. Rates of DMRC Ph‐4 DPR May'14 & LMRC DPR
Estimated rates are based upon LMRC accepted rates SEP'15.
9.0 Environment, R & R incl. Hutments etc.
a Environmental Cost As per details given in Chapter 12
b R & R As per details given in Chapter 12
10.0 Misc. Utilities, road works, Topographic Surveys, Geotechnical Investigation, Barricading, Tree Cutting and replanting, other civil works such as signage's, Environmental protection and traffic management.
10.1 & 10.2
Civil works & Electrical works Estimated rates are based upon average of escalated rates of
DMRC Ph‐IV DPR May'14 & LMRC DPR May'13.
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐8
Item
No. Item Basis of Rates
11.0 Capital Expenditure on Security: Estimated rates are based upon average of escalated rates of
DMRC Ph‐IV DPR May'14 & LMRC DPR May'13. The expenditure is required to cover the civil and
Electrical items, equipments (X‐Ray machine, Metal detector etc.)
12.0 Staff Quarters and OCC Building: Estimated rates are based upon average of escalated rates of DMRC Ph‐IV DPR May'14 & LMRC DPR May'13. OCC building is included in cost estimate for corridor‐1 only and it will cover Corridor‐2 also. As such, no separate OCC building will be required for corridor‐2. Cost for Green Building concept has been taken as Rs. 7 Cr. for each corridor. This is based upon cost of Rs. 10 cr. taken for 23 Km Corridor of Kanpur MRTS.
13.0 Capital Expenditure on Inter modal integration including Footpath for pedestrians, Feeder Buses and Bicycles @2% of Total Cost excluding Land ‐ As per LMRC DPR, it is taken @ 2% of total cost excluding land.
13.1.4 Capital Cost Estimate
The abstract of capital cost estimate of Corridor‐1 & 2 is given in Table 13.4. Detailed capital
cost estimate for Corridor‐1 & 2 is given in Table 13.5 and 13.6 respectively.
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐9
TABLE 13.4: ABSTRACT OF COST ESTIMATE OF CORRIDOR‐1 & 2
S. No. Item
Corridor‐1 Corridor‐2
Amount (Rs. in Crore)
Amount (Rs. in Crore)
1 Land 438.47 36.99
2 Alignment and Formation 1950.92 960.11
3 Station Buildings incl. Civil works, EM works, ECS, TVS, Lift, escalators & Architectural Finishes etc
2409.98 1295.42
4 Depot including civil, EM, Machinery & plants, general works
218.31 0.00
5 P‐Way for main line, depot and depot connectivity 199.19 80.46
6 Traction & power supply 750V DC 439.43 181.08
7 Signalling and Telecom. Incl. AFC, Platform screen doors, CCHS etc.
392.74 195.24
8 Rolling Stock 684.18 325.80
9 R & R incl. Hutments etc. 8.99 2.95
10
Misc. Utilities, road works, Topographic Surveys, Geotechnical Investigation, Barricading, Tree Cutting and replanting, other civil works such as signage's, Environmental protection and traffic management
143.00 73.05
11 Capital Expenditure on Security including civil and EM works
5.61 2.97
12 Staff Quarters and OCC Building and green building concept (Cost of OCC building is included in corridor‐1 only)
92.83 21.63
13 Capital Expenditure on Inter modal integration including Footpath for pedestrians, Feeder Buses and Bicycles @2% of Total Cost excluding Land
130.90 62.77
14 Total of all items except Land 6676.08 3201.49
15
General Charges incl. Design charges, including Metro Bhawan, (Civil+EM works) @ 7% on all items except land. (Metro Bhawan is charged to coridor‐1 only and it will cater to both the corridors)
467.33 224.10
16 Total of all items including G. Charges 7143.41 3425.59
17 Contingencies @ 3 % on all items except land 214.30 102.77
Gross Total including Contingencies (excluding Land Cost) 7357.71 3528.36
Gross Total including Contingencies (including Land Cost) 7796.18 3565.35
Insurance 0.6% of Capital cost excluding land 40.06 19.21
Gross Total including Insurance, Contingencies and Land 7836.00 3585.00
Taxes & Duties 1157.00 555.00
Gross Total including Taxes & Duties 8993.00 4140.00
Note: For quantities of various items, detailed estimate may be referred.
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐10
TABLE 13.5: CAPITAL COST ESTIMATE CORRIDOR‐1
CORRIDOR ‐ 1: BHEL TO BHU
Total Length = 19.47 Km, From = (‐) 325m to 19025m, UG = 15.505 Km & ELEV = 3.845 Km
a Central Govt. Land ‐Permanent (without Solatium)
Ha 34.80 0.07 2.44
b Central Govt. Land ‐Temporary (@ 6% of circle rates PA for 3 years, without Solatium)
Ha 6.260 0.40 2.50
c Central Govt. Structures (PRS at Varansasi Cantt including structure, Electrical, S&T, Terminal etc)
Ha 3.00 LS 3.00
d State Govt. Land ‐Permanent (for Alignment, Depot, RSS, Ancillary Bldgs, Misc., without Solatium)
Ha 5.50 1.00 5.50
e State Govt. Land ‐Temporary Ha 1.32 2.60 3.43
f State Govt. Structures ‐Permanent(Depreciated cost after 60% depreciation)
Ha 7.01 0.2633 1.85
g Private Land ‐Permanent (for Depot including Solatium)
Ha 21.85 13.20 288.42
h Private Land ‐Permanent (for Alignment, RSS, Ancillary Bldgs, Misc., including Solatium)
Ha 48.40 1.35 65.34
i Private Land ‐Temporary (for underground station by cut & cover etc, Misc., @ 6% of circle rates PA for 3 years, including Solatium)
Ha 5.198 2.50 13.00
j Private Land ‐Temporary (for casting yard including Solatium)
Ha 5.198 6.00 31.19
k
Private Structure ‐ Permanent including Solatium as per LARRA (average rate has been worked out after applying relevant circle rates Aug' 2015 for residential and commercial structures)
Ha 20.40 1.02 20.81
l Cost of Structures for rehabtilation of squatters at Tulsi Manas Mandir
Ha 25.00 0.04 1.00
Sub Total (1) 438.47
2.0 Alignment and Formation
2.1 Underground section by T.B.M excluding station length
R. Km. 121.39 13.072 1586.81
2.2 Underground section by cut & cover for Ramp R. Km. 112.50 0.224 25.20
2.3 U/G section by NATM for alignment and access tunnel
R. Km. 142.15 1.349 191.76
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐11
S. No.
Item Unit Rate (Rs. in
Crore) Qty.
Amount (Rs. in Crore)
Without taxes
2.4 Elevated section excluding viaduct length in station
3.1 Underground Station (160 m length, 2 Level) incl. EM works, VAC etc. by Cut & Cover
a Underground Station‐ Structural Civil works Each 106.43 4.00 425.72
b Underground Station‐ EM works etc. Each 22.17 4.00 88.68
c Underground Station ‐ ECS & TVS etc Each 27.45 4.00 109.80
3.2 Underground Station (140 m or less length, 3 Level) incl. EM works, VAC etc. by Cut & Cover
a Underground Station‐ Structural Civil works Each 106.43 7.00 745.01
b Underground Station‐ EM works etc. Each 22.17 7.00 155.19
c Underground Station ‐ ECS & TVS etc Each 27.45 7.00 192.15
3.3 Underground Station (100 m or less length, 4 Level) incl. EM works, VAC etc. by Cut & Cover
a Underground Station‐ Structural Civil works Each 106.43 2.00 212.86
b Underground Station‐ EM works etc. Each 22.17 2.00 44.34
c Underground Station ‐ ECS & TVS etc Each 27.45 2.00 54.90
3.4 Underground Station (160 m length) incl. EM works, VAC etc. by NATM
a Underground Station‐ Structural Civil works Each 180.00 0.00 0.00
b Underground Station‐ EM works etc. Each 22.17 0.00 0.00
c Underground Station ‐ ECS & TVS etc Each 27.45 0.00 0.00
3.5 Underground Station‐ Architectural Finishes Each 9.61 13.00 124.93
3.6 Elevated Station Buildings (Type ‐I: 85mx19.2m)
a Elevated station ‐ Civil Works including Viaduct
Each 22.06 4.00 88.24
b Elevated station ‐ EM Works etc. Each 4.44 4.00 17.76
3.7 Elevated Station‐ Architectural Finishes Each 5.07 4.00 20.28
3.8 At‐grade Station Building
a At‐grade station ‐ Civil Works Each 16.26 0.00 0.00
b At‐grade station ‐ EM Works etc. Each 4.44 0.00 0.00
3.9 At‐grade Station‐ Architectural Finishes Each 5.07 0.00 0.00
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐12
S. No.
Item Unit Rate (Rs. in
Crore) Qty.
Amount (Rs. in Crore)
Without taxes
3.10 Lifts & Escalators (Elevated, At‐grade and UG stations)
a Lifts Each 0.38 53.00 20.14
b Escalators Each 0.78 141.00 109.98
Sub Total (3) 2409.98
4.0 Maintenance Depot
4.1 Civil works LS 109.49
4.2 EM works + Machinery & Plant + General Works
LS 108.82
Sub Total (4) 218.31
5.0 P‐Way
5.1 Ballastless track for elevated & underground Section
Route Km.
8.14 19.35 157.51
5.2 Ballasted track for Depot Track Km.
4.07 10.00 40.70
5.3 Ballastless track for entry to Depot Route Km.
8.14 0.12 0.98
Sub Total (5) 199.19
6.0 Traction & power supply (750V DC)
6.1 UG Section & Elevated including SCADA Route Km.
15.79 19.35 305.54
6.2 For Depot entry Route Km.
15.79 0.12 1.89
6.3 For Depot Track Km.
7.90 10.00 79.00
6.4 Differential cost of 132kV GIS LS 20.00
6.5 132kV cable/transmission line from GSS to RSS.
LS
33.00
Sub Total (6) 439.43
7.0 Signalling and Telecom.
7.1 Signalling R. Km. 8.78 19.35 169.89
7.2 Telecommunication Per
Station 4.64 17.00 78.88
7.3 Automatic fare collection Per
station 4.42 17.00 75.14
7.4 Central Clearing House System (CCHS) Each 18.00 1.00 18.00
7.5 Platform Screen Doors Per
Station 1.63 17.00 27.71
7.6 LED Screens for PD Per
Station 1.36 17.00 23.12
Sub Total (7) 392.74
8.0 Rolling Stock Each 10.86 63.00 684.18
Sub Total (8) 684.18
9.0 R & R incl. Hutments etc.
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐13
S. No.
Item Unit Rate (Rs. in
Crore) Qty.
Amount (Rs. in Crore)
Without taxes
9.1 Environmental Cost As per details given in Chapter
12
5.50
9.2 R & R
3.49
Sub Total (9) 8.99
10.0
Misc. Utilities, road works, Topographic Surveys, Geotechnical Investigation, Barricading, Tree Cutting and replanting, other civil works such as signage's, Environmental protection and traffic management
10.1 Civil works R. Km. 4.04 19.350 78.17
10.2 Electrical Works R. Km. 3.35 19.350 64.82
Sub Total (10) 143.00
11.0 Capital Expenditure on Security
11.1 Civil works Per
Station 0.270 17.00 4.59
11.2 EM works Per
Station 0.060 17.00 1.02
Sub Total (11) 5.61
12.0 Staff Quarters and OCC Building
12.1 Civil works R. Km. 1.190 19.350 23.03
12.2 EM works R. Km. 0.290 19.350 5.61
12.3 Cost of OCC Building ‐ Civil Works LS 45.55
12.4 Cost of OCC Building ‐ E&M Works LS 11.64
12.5 Cost for Green Building concept LS 7.00
Sub Total (12) 92.83
13.0
Capital Expenditure on Inter modal integration including Footpath for pedestrians, Feeder Buses and Bicycles @2% of Total Cost excluding Land
130.90
14.0 Total of all items except Land 6676.08
15.0 General Charges including Design charges, incl. Metro Bhawan Building (Civil+EM works) @ 7% on all items except land
467.33
16.0 Total of all items including G. Charges 7143.41
17.0 Contingencies @ 3 % on all items except land 214.30
18.0 Gross Total including Contingencies (excluding Land Cost) 7357.71
19.0 Gross Total including Contingencies (including Land Cost) = 7796.18
20.0 Insurance 0.6% of Capital cost excluding land 6233.83 Crore 40.06
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐14
S. No.
Item Unit Rate (Rs. in
Crore) Qty.
Amount (Rs. in Crore)
Without taxes
21.0 Gross Total including Insurance = 7836.23
Say 7836.00
Taxes & Duties 1157.00
Total Cost including Taxes & Duties 8993.00
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐15
TABLE 13.6: CAPITAL COST ESTIMATE CORRIDOR‐2
CORRIDOR ‐ 2: BENIA BAGH TO SARNATH
Total Length = 9.885 Km, From = (‐) 245m to 9395m, ELEV = 1.923 Km, Underground = 7.717 Km,
a Central Govt. Land ‐Permanent (without Solatium)
Ha 34.80 0.14 4.872
b Central Govt. Land ‐Temporary (@ 6% of circle rates PA for 3 years, without Solatium)
Ha 2.43 0.0000 0.00
c Central Govt. Structures‐ Permanent (PRS at Cantt Rly stn, Cost of structure, electrical, S&T, Terminals etc.,)
Ha 34.00 0.0242 0.82
d State Govt. Land ‐Permanent (for Alignment, Depot, RSS, Entry/Exits, Ancillary Bldgs, Misc., without Solatium)
Ha 5.50 1.100 6.05
e State Govt. Land ‐Temporary Ha 1.32 2.10 2.77
f State Govt. Structures ‐Permanent (Depreciated cost after 60% depreciation)
Ha 5.854 0.105 0.61
g Private Land ‐Permanent (for Alignment, RSS, Entry/Exits, Ancillary Bldgs, Misc., including Solatium)
Ha 30.965 0.130 4.03
h Private Land ‐Temporary (for underground station by cut & cover etc, Misc., @ 6% of circle rates PA for 3 years, including Solatium)
Ha 5.57 0.00 0.00
i
Private Structure ‐ Permanent including Solatium as per LARRA (average rate has been worked out after applying relevant circle rates Aug' 2015 for residential and commercial structures)
Ha 99.068 0.180 17.83
Sub Total (1) 36.989
2.0 Alignment and Formation
2.1 Underground section by T.B.M excluding station length
R. Km. 121.39 6.078 737.81
2.2 Underground section by cut & cover for Ramp R. Km. 112.50 0.402 45.23
2.3 U/G section by NATM for alignment and access tunnel
R. Km. 142.15 0.745 105.90
2.4 Elevated section excluding viaduct length in station
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐16
2.7 Entry to Depot R. Km. 40.37 0.00 0.00
Sub Total (2) 960.11
3.0 Station Buildings
3.1 Underground Station (160 m length, 2 Level) incl. EM works, VAC etc. by Cut & Cover
a Underground Station‐ Structural Civil works Each 106.43 1.00 106.43
b Underground Station‐ EM works etc. Each 22.17 1.00 22.17
c Underground Station ‐ ECS & TVS etc Each 27.45 1.00 27.45
3.2 Underground Station (140 m or less length, 3 Level) incl. EM works, VAC etc. by Cut & Cover
a Underground Station‐ Structural Civil works Each 106.43 5.00 532.15
b Underground Station‐ EM works etc. Each 22.17 5.00 110.85
c Underground Station ‐ ECS & TVS etc Each 27.45 5.00 137.25
3.3 Underground Station (100 m or less length, 4 Level) incl. EM works, VAC etc. by Cut & Cover
a Underground Station‐ Structural Civil works Each 106.43 1.00 106.43
b Underground Station‐ EM works etc. Each 22.17 1.00 22.17
c Underground Station ‐ ECS & TVS etc Each 27.45 1.00 27.45
3.4 Underground Station (180 m length) incl. EM works, VAC etc. by NATM
a Underground Station‐ Structural Civil works Each 180.00 0.00 0.00
b Underground Station‐ EM works etc. Each 22.17 0.00 0.00
c Underground Station ‐ ECS & TVS etc Each 27.45 0.00 0.00
3.5 Underground Station‐ Architectural Finishes Each 9.61 7.00 67.27
3.6 Elevated Station Buildings (Type ‐I: 85mx19.2m)
a Elevated station ‐ Civil Works including Viaduct Each 22.06 2.00 44.12
b Elevated station ‐ EM Works etc. Each 4.44 2.00 8.88
3.7 Elevated Station‐ Architectural Finishes Each 5.07 2.00 10.14
3.8 At‐grade Station Building
a At‐grade station ‐ Civil Works Each 16.26 0.00 0.00
b At‐grade station ‐ EM Works etc. Each 4.44 0.00 0.00
3.9 At‐grade Station‐ Architectural Finishes Each 5.07 0.00 0.00
3.10 Lifts & Escalators (Elevated, At‐grade and UG stations)
a Lifts Each 0.38 27.00 10.26
b Escalators Each 0.78 80.00 62.40
Sub Total (3) 1295.42
4.0 Maintenance Depot
4.1 Civil works including filling for low lying depot land
LS 0.00
4.2 EM works + Machinery & Plant + General Works
LS 0.00
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐17
Sub Total (4) 0.00
5.0 P‐Way
5.1 Ballastless track for elevated & underground Section
Route Km.
8.14 9.885 80.46
5.2 Ballasted track for Depot Track Km.
4.07 0.00 0.00
5.3 Ballastless track for entry to Depot Route Km.
8.14 0.00 0.00
Sub Total (5) 80.46
6.0 Traction & power supply (750V DC)
6.1 UG Section & Elevated including SCADA Route Km.
15.79 9.885 156.08
6.2 For Depot entry Route Km.
15.79 0.00 0.00
6.3 For Depot Track Km.
7.90 0.00 0.00
6.4 Differential cost of 132kV GIS LS 10.00
6.5 132kV cable from GSS to RSS. LS 15.00
Sub Total (6) 181.08
7.0 Signaling and Telecom.
7.1 Signaling R. Km. 8.78 9.885 86.79
7.2 Telecommunication Per
Station 4.64 9.00 41.76
7.3 Automatic fare collection Per
station 4.42 9.00 39.78
7.4 Central Clearing House System (CCHS) Each 18.00 0.00 0.00
7.5 Platform Screen Doors Per
Station 1.63 9.00 14.67
7.6 LED Screens for PD Per
Station 1.36 9.00 12.24
Sub Total (7) 195.24
8.0 Rolling Stock Each 10.86 30.00 325.80
Sub Total (8) 325.80
9.0 R & R incl. Hutments etc.
9.1 Environmental Cost As per details given in Chapter
12
2.28
9.2 R & R 0.67
Sub Total (9) 2.95
10.0
Misc. Utilities, road works, Topographic Surveys, Geotechnical Investigation, Barricading, Tree Cutting and replanting, other civil works such as signage's, Environmental protection and traffic management
10.1 Civil works R. Km. 4.04 9.885 39.94
10.2 Electrical Works R. Km. 3.35 9.885 33.11
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐18
Sub Total (10) 73.05
11.0 Capital Expenditure on Security
11.1 Civil works Per
Station 0.270 9.00 2.43
11.2 EM works Per
Station 0.060 9.00 0.54
Sub Total (11) 2.97
12.0 Staff Quarters and OCC Buiulding
12.1 Civil works R. Km. 1.190 9.885 11.76
12.2 EM works R. Km. 0.290 9.885 2.87
12.3 Cost of OCC Building ‐ Civil Works LS 0.00
12.4 Cost of OCC Building ‐ E&M Works LS 0.00
12.5 Cost for Green Building concept LS 7.00
Sub Total (12) 21.63
13.0
Capital Expenditure on Inter modal integration including Footpath for pedestrians, Feeder Buses and Bicycles @2% of Total Cost excluding Land
62.77
14.0 Total of all items except Land 3201.49
15.0 General Charges including Design charges, incl. Metro Bhawan Building (Civil+EM works) @ 7% on all items except land
224.10
16.0 Total of all items including G. Charges 3425.59
17.0 Contingencies @ 3 % on all items except land 102.77
18.0 Gross Total including Contingencies (excluding Land Cost) 3528.36
19.0 Gross Total including Contingencies (including Land Cost) = 3565.35
20.0 Insurance 0.6% of Capital cost excluding land 3201.49 Crore 19.21
21.0 Gross Total including Insurance = 3584.56
Say 3585.00
Taxes & Duties 555.00
Total Cost including Taxes & Duties 4140.00
13.1.5 Taxes and Duties
Basic cost is exclusive of various taxes and duties viz. custom duty, excise duty, VAT etc. and
details of taxes and duties are worked out separately. Current rates of various taxes and duties
have been taken into consideration and taxes / duties have been applied as per LMRC. Central
and state taxes and duties (customs, Excise and VAT) for Corridor ‐1 & 2 have been worked out
to Rs. 1157 Crores and Rs. 555 Crores respectively and are detailed in Table 13.7 and 13.8.
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐19
TABLE 13.7: DETAILS OF TAXES AND DUTIES CORRIDOR – 1
Customs Duty = 22.85%
Excise Duty = 12.50%
VAT = 12.50%
S. No.
Description
Total cost without Taxes &
duties (Cr.)
Taxes and duties Total
Taxes & Duties (Cr.)
Custom Duty (Cr.)
Excise Duty (Cr.)
VAT (Cr.)
1 Alignment & Formation
Underground 1803.77 123.67 110.48 62.15 296.29
Elevated, At‐grade & entry to Depot 147.15 12.88 7.24 20.12
2 Station Buildings
a) Underground station‐civil works 1508.52 103.42 92.40 51.97 247.79
b) Underground station‐EM works 775.18 53.15 57.65 32.43 143.23
c) Elevated station ‐ civil works 108.52 9.50 5.34 14.84
d) Elevated station‐EM works 17.76 0.81 1.51 0.85 3.17
e) At‐grade station ‐ civil works 0.00 0.00 0.00 0.00
f) At‐grade station‐EM works 0.00 0.00 0.00 0.00 0.00
3 Depot
Civil works 109.49 7.51 6.71 3.77 17.99
EM works 108.82 4.97 9.25 5.20 19.43
4 P‐Way 199.19 36.42 4.23 2.38 43.03
5 Traction & power supply
a) Traction and power supply 439.43 40.17 28.01 15.76 83.94
6 S and T Works
a) S & T 248.77 45.48 5.29 2.97 53.74
b) AFC, PSD, LED screens & CCHS 143.97 24.68 3.82 2.15 30.65
7 Rolling stock 684.18 137.59 6.67 3.75 148.02
8 R & R hutments 8.99 0.56 0.56
9 Misc.
Civil works 78.17 6.84 3.85 10.69
EM works 64.82 6.89 3.87 10.76
10 Security
Civil works 4.59 0.40 0.28 0.68
EM works 1.02 0.13 0.10 0.23
11 Staff Quarters & OCC Buildings
Civil works 68.58 6.00 0.44 6.44
EM works incl. green bldg. conept 24.25 3.03 2.18 5.21
Total 6545.18 577.86 371.69 207.25 1156.80
Total Taxes & Duties 1157
Detailed Project Report for Rail Based Mass Transit System in Varanasi
Final Report CHAPTER 13: COST ESTIMATES AND FINANCIALS
February, 2016 Page 13‐20
TABLE 13.8: DETAILS OF TAXES AND DUTIES CORRIDOR – 2
Customs Duty = 22.85%
Excise Duty = 12.50%
VAT = 12.50%
S. No.
Description
Total cost without Taxes &
duties (Cr.)
Taxes and duties Total
Taxes & Duties (Cr.)
Custom Duty (Cr.)
Excise Duty (Cr.)
VAT (Cr.)
1 Alignment & Formation
Underground 888.94 60.94 54.45 30.63 146.02
Elevated & entry to Depot 71.17 6.23 3.50 9.73
2 Station Buildings
a) Underground station‐civil works 812.28 55.69 49.75 27.99 133.43
b) Underground station‐EM works 420.00 28.79 31.24 17.57 77.60
c) Elevated station ‐ civil works 54.26 4.75 2.67 7.42
d) Elevated station‐EM works 8.88 0.41 0.75 0.42 1.59
3 Depot
Civil works 0.00 0.00 0.00 0.00 0.00
EM works 0.00 0.00 0.00 0.00 0.00
4 P‐Way 80.46 14.71 1.71 0.96 17.38
5 Traction & power supply
a) Traction and power supply 181.08 16.55 11.54 6.49 34.59