Top Banner
This training was prepared by the U.S. Department of Agriculture (USDA) team of Otto Gonzalez-USDA Foreign Agricultural Service (Team Leader), Jon Fripp (Civil Engineer) and Chris Hoag (Wetland Plant Ecologist)-USDA Natural Resources Conservation Service (Civil Engineers). Fripp and Hoag were the primary authors of this material. The U.S. AID provided funding support for the USDA team. 8 Introduction to Check Dams
35

13 Check Dams 2006

Dec 06, 2015

Download

Documents

Vishal Mishra

check dams
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 13 Check Dams 2006

This training was prepared by the U.S. Department of Agriculture (USDA) team of Otto Gonzalez-USDA Foreign Agricultural Service (Team Leader), Jon Fripp (Civil Engineer) and Chris Hoag (Wetland Plant Ecologist)-USDA Natural Resources Conservation Service (Civil Engineers). Fripp and Hoag were the primary authors of this material. The U.S. AID provided funding support for the USDA team.

8

Introduction to Check Dams

Page 2: 13 Check Dams 2006

Check Dams•Usually Used in Collection Zone•Can Also be used in Transport Zone

Page 3: 13 Check Dams 2006

These are structures

• Use caution

• Understand the processes at work in the system

• Know the components of a check dam

!

Page 4: 13 Check Dams 2006

What happens in if all the vegetation is removed from a watershed?

Understand the processes at work in the system

Answer:More erosion of surface

Page 5: 13 Check Dams 2006

So what happens if you have more water running down the watershed collection zone?

Answer: Erosion. Gullies will form and grow. The channel will get hungry and eat its boundary.

Page 6: 13 Check Dams 2006

The stream or gulley will start by attacking the bottom of the channel first.

Page 7: 13 Check Dams 2006

The channel will get deeper

Section

Page 8: 13 Check Dams 2006
Page 9: 13 Check Dams 2006

The channel will keep getting deeper until the sides start to fall in

Section

Page 10: 13 Check Dams 2006

Then it starts to get wider

Now it is really starting to get bad

Page 11: 13 Check Dams 2006

This is process is called the channel stages

Stage 1

Section

Stage 3

Stage 2

Assessment Tool: Channel StagesGood for collection and transport zone

Page 12: 13 Check Dams 2006

STAGE 1

Test Time

Page 13: 13 Check Dams 2006

Headcut

STAGE 2

Channel downcutting creates straighter, steeper gully.

Page 14: 13 Check Dams 2006

wideningSTAGE 3

Channel widening, cut banks on both sides.

Page 15: 13 Check Dams 2006

It is best to stop this process early in Stage 2

Page 16: 13 Check Dams 2006

To stop it: use a check dam

Profile

Stage 2

Page 17: 13 Check Dams 2006

Profile

A check dam will keep the channel from getting too deep

Page 18: 13 Check Dams 2006

Check DamsLots of different types

Lots of different materials

Page 19: 13 Check Dams 2006

A Check Dam must• Have a Control Section

• Have a Energy Dissipation Section

• Be Keyed into Channel Bottom

• Be Keyed into Channel Bank

• Be appropriately spaced

Components of a check dam

This introduction is going to cover the basicsYou may want to get more detailed training

Page 20: 13 Check Dams 2006

Control Section: Keeps the water in the channel

Bank Key: Keeps water from eroding around check dam

Page 21: 13 Check Dams 2006

•Control Section should have the same area as a stable section of the stream or gully.

Page 22: 13 Check Dams 2006

Energy dissipation section should be two times the structure height

Maximum height should be less than 1.5 m

H

2H

Page 23: 13 Check Dams 2006

Key into channel bottom for a minimum of 60 cm

Key into channel bank for a minimum of 1 m

Top of check dam should be at least 30 cm below top of channel

section

1 m

60 cm

Page 24: 13 Check Dams 2006

Energy Dissipation Section: Absorbs energy as water flows over top.

Key into Channel Bottom: Keeps water from eroding under check dam

May need a filter with log check dams

Profile

Same rules for all types of check dams

Page 25: 13 Check Dams 2006

Profile

The check dams work as a team

Downstream erosion might undermine the upstream check dam

Page 26: 13 Check Dams 2006

Space so that the slope can be level between the check dams and the upstream one will not be undermined.

Profile

Page 27: 13 Check Dams 2006

Test Time

Question: What is wrong with this check dam

Answer: bank key and adjacent protection

Page 28: 13 Check Dams 2006

Question: What is wrong with this check dam?

Answer: no control section. Made worse by bad bank key

Page 29: 13 Check Dams 2006

Question: What is wrong with this check dam?

Answer: bank key in

Page 30: 13 Check Dams 2006

Answer: everything, bad spacing, no control section, no bed or bank key in, no energy dissipation

Question: What is wrong with this check dam?

Page 31: 13 Check Dams 2006

Question: What is wrong with this check dam? Answer: nothing major

Page 32: 13 Check Dams 2006

Question: What is wrong with this check dam?

Answer: nothing major

Page 33: 13 Check Dams 2006

Question: What is wrong with these check dams?

Answer: nothing major

Page 34: 13 Check Dams 2006

You need an engineer to help with the design if:

• The river has high velocities

• The river is large

• The erosion is significant

• The river system is unstable

• There is something very important on the bank

• The project will cost a lot of money

• Laws state you must have an engineer

Page 35: 13 Check Dams 2006

The End