STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 13.04.13

1.Basement-II slab Completed2. Basement-I slab Completed

3.Ground Floor slab Flat No 01 & 02 Completed , Remaining Flats Bar Bending Work Completed

Page 2: 13 04-2013

STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 13.04.13

1.Basement-II Slab Completed.2.Basement-I Slab completed

3.Ground floor slab flat no 1,2 & 3,4 flats completed ,5th flat Shuttering work in progress4.First Floor slab flat no 01 & 02 completed

Page 3: 13 04-2013

STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 13.04.13

1.Basement II Slab Completed.2.Basement I slab Completed

Page 4: 13 04-2013

STATUS REPORT OF MY HOME ABHRA Tower-”D”As On 13.04.13

1.Basement II Slab Completed.2.Basement I Slab Completed

3.Ground Floor slab Completed

Page 5: 13 04-2013

STATUS REPORT OF MY HOME ABHRA Tower-”E”As On 13.04.13

1.Basement II Slab Completed2. Basement I Slab Completed

3.Ground Floor slab 1 and 2 flats shuttering completed

Page 6: 13 04-2013

STATUS REPORT OF MY HOME ABHRA “TOTAL SITE”As On 13.04.131.Total Site Basement II slab- Completed2.Total site Basement I Slab-Completed

3.Total Site Ground Floor slab Tower : A-1&2 flats Completed Tower : B-4 flats completed Tower D-5 flats completed