Top Banner
1 120 th Avenue Connection Design-Build Project Informational Meeting STA 1281-011 – 120th Avenue Connection Design-Build Procurement
13

120 Avenue Connection Design-Build Project Informational ...

Dec 27, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 120 Avenue Connection Design-Build Project Informational ...

1

120th Avenue Connection

Design-Build Project

Informational Meeting

STA 1281-011 – 120th Avenue Connection Design-Build Procurement

Page 2: 120 Avenue Connection Design-Build Project Informational ...

2

Project Web Site

www.dot.state.co.us/120AvenueConnection/

or www.dot.state.co.us

Link under the “What’s New” Section, 120th Avenue

Connection Design-Build Project

Page 3: 120 Avenue Connection Design-Build Project Informational ...

3

Project Management Team

CDOTo Project Manager

o Project Design Lead

o Project Construction Lead

City and County of Broomfield

Federal Highway Administration

Jacobs Carter Burgess (Procurement Development and Support)

Page 4: 120 Avenue Connection Design-Build Project Informational ...

4

Project Partnerships

CDOT

City and County of Broomfield

FHWA

Page 5: 120 Avenue Connection Design-Build Project Informational ...

5

120th Avenue Connection

Extend 120th Avenue (SH128) from Wadsworth Parkway, across US 36, under BNSF Railroad, and connect to existing 120th Avenue at approximately Teller Street.

Page 6: 120 Avenue Connection Design-Build Project Informational ...

6

Phases of Improvements

Phase 1 (Design-Build - Minimum Basic Configuration)

Construct portions of 120th Avenue (0.7 mile) and

Wadsworth Boulevard (0.3 mile), a bridge carrying 120th Avenue over US 36, and a bridge carrying 120th

Avenue over Commerce Street.

Phase 3 (Design-Build - Additional Requested Elements)

Construct the local road system in the area between US

36 and Wadsworth Blvd.

Page 7: 120 Avenue Connection Design-Build Project Informational ...

7

Phases of Improvements

Phase 2 (Design-Bid-Build - Future Project)

Construct the remaining portions of 120th Avenue to

the east.

Page 8: 120 Avenue Connection Design-Build Project Informational ...

8

Phase 1 and 3 Project Elements

Page 9: 120 Avenue Connection Design-Build Project Informational ...

9

Design-Build Elements

Design Services

o Finalization of all design and preparation of

construction documents.

o Review by CDOT for completeness and

conformance with design requirements

Construction Services

o Construction of all project elements

o Quality Control only - Quality Acceptance and

Assurance by CDOT

Design-Build Contractor is responsible for the project meeting all applicable Federal, State, and Local requirements.

Page 10: 120 Avenue Connection Design-Build Project Informational ...

10

Prioritized Project Goals

1. Maximize improvements within the program budget.

2. Provide a quality product.

3. Minimize inconvenience to the traveling public and

affected residents and businesses.

4. Provide a visually-pleasing finished product.

5. Meet or beat the contract schedule.

Page 11: 120 Avenue Connection Design-Build Project Informational ...

11

Design-Build Process

1. Request For Qualifications

• Short-Listing (3-5 teams)

2. Request For Proposals (short-listed teams only)

• Stipend

Award Based on Best ValueTechnical Proposal

Cost Proposal

Page 12: 120 Avenue Connection Design-Build Project Informational ...

12

Project Procurement Schedule (* Estimated)

Issue Request for Letters of Interest (L.O.I.) April 10, 2008

L.O.I Informational Meeting April 24, 2008

Close Date for L.O.I (may extend) May 1, 2008

Request for Qualifications (RFQ) Phase 1.5 months*Issue RFQ, accept questions, issue addendumReceive and evaluate submittalsNotify short listed Submitters, debrief submitters

Request for Proposals (RFP) Phase 4-5 months*Issue Draft RFP for Industry Review Conduct contractor meetingsIssue Final RFP

Selection and Award Phase 1.5 months*Receive and evaluate proposalsRecommendation for awardContract Award

Page 13: 120 Avenue Connection Design-Build Project Informational ...

13

Comments or Questions