Sr. Dr. Sarajul Fikri Mohamed Faculty of Built Environment MECHANICAL & ELECTRICAL WORKS MEASUREMENT (SBEQ3213) Week 11 : Air Conditioning Installations - Centralized
124

11-Air Conditioning Installations - Centralized

Dec 02, 2015

Download

Documents

sarathirv6

As per Malaysian SMM
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 11-Air Conditioning Installations - Centralized

Sr. Dr. Sarajul Fikri Mohamed

Faculty of Built Environment

MECHANICAL & ELECTRICAL WORKS MEASUREMENT (SBEQ3213)

Week 11 : Air Conditioning Installations - Centralized

Page 2: 11-Air Conditioning Installations - Centralized

Cold Water Installations PLUMBING WORKS

Electrical Installations

Fire Fighting System

MAIN COURSE COMPONENTS

Air Conditioning Installations

Unit/Split Package/Central

Single Phase Three Phase

ELECTRICAL WORKS

MECHANICAL WORKS

Soil & Waste Pipes/Sanitary Fittings

Underground Drainage

Page 3: 11-Air Conditioning Installations - Centralized

1. Air conditioning installations: main components of package & central system

2. SMM2 measurement rules for air conditioning installations

3. Taking off list for air conditioning installations

4. Heading and description.

5. Case study: WATER COOLED CHILLER SYSTEM

6. Studio work: AIR CONDITIONING SYSTEM: CENTRAL SYSTEM FOR CADANGAN MEMBINA DAN MENYIAPKAN KOMPLEKS PERNIAGAAN LARKIN MALL.

TABLE OF CONTENTS

Page 4: 11-Air Conditioning Installations - Centralized

© 2009 Sarajul Fikri Mohamed

MAIN COMPONENTS

Page 5: 11-Air Conditioning Installations - Centralized

PREAMBLES

EQUIPMENT: CONDENSING UNIT & FAN COIL UNIT ETC

DUCTING: SUPPLY DUCT & RETURN DUCT

DUCTING FITTING

INSULATION TO DUCTWORK/PIPE

DUCT WORK SUPPORT

PIPEWORK

EQUIPMENT/DIFFUSER/GRILLE/DAMPER

BUILDER’S WORK

ELECTRICAL SYSTEM

TESTING

AIR CONDITIONING SYSTEM

Page 6: 11-Air Conditioning Installations - Centralized

AIR CONDITIONING SYSTEM

UNIT SYSTEM PACKAGE SYSTEM CENTRAL SYSTEM

WINDOW UNIT

SPLIT UNIT

UNIT KEMAS SIAP PENYEJUKAN UDARA

UNIT KEMAS SIAP KESELURUHAN

UNIT KEMAS SIAP KESELURUHAN

UNIT KEMAS SIAP PENYEJUKAN UDARA

SISTEM AIR DISEJUKKAN

SISTEM LOGI PUSAT

AIR CONDITIONING SYSTEM

Page 7: 11-Air Conditioning Installations - Centralized

7

PACKAGE SYSTEM

Page 8: 11-Air Conditioning Installations - Centralized

8

COOLING TOWER Menara penyejuk

CENTRAL SYSTEM

Page 9: 11-Air Conditioning Installations - Centralized

9

COOLING TOWER CAPACITY

Page 10: 11-Air Conditioning Installations - Centralized

DUCTING SYSTEM

AIR HANDLING UNIT

Page 11: 11-Air Conditioning Installations - Centralized

A/C CHILLED WATER EXPANSION TANK

CHILLED WATER PUMP

AIR COOLED CHILLERS

Page 12: 11-Air Conditioning Installations - Centralized

12

Page 13: 11-Air Conditioning Installations - Centralized

13

Page 14: 11-Air Conditioning Installations - Centralized

COOLING TOWER AND CONCRETE PLINTH

RETURN AND SUPPLY REFRGERATION PIPE

Page 15: 11-Air Conditioning Installations - Centralized

15

WATER CHILLER UNIT

SUPPLY & RETURN CHILLED WATER PIPE

Page 16: 11-Air Conditioning Installations - Centralized

16

AIR HANDLING UNIT AND DIFFUSER

REGISTER AND DIFFUSER

Page 17: 11-Air Conditioning Installations - Centralized

17

COOLING TOWER

Page 18: 11-Air Conditioning Installations - Centralized

18

CAPACITY

COOLING TOWER

Page 19: 11-Air Conditioning Installations - Centralized

19

AIR HANDLING UNIT

Page 20: 11-Air Conditioning Installations - Centralized

20

AIR CHILLED SYSTEM

AIR HANDLING UNIT

Page 21: 11-Air Conditioning Installations - Centralized

21

DUCTWORK, DUCT FITTING AND

COMPONENTS

Page 22: 11-Air Conditioning Installations - Centralized

22

DUCTWORK COMPONENTS

Page 23: 11-Air Conditioning Installations - Centralized

23

ALL ROUND METAL DUCT WITH ROUND METAL BRANCH DUCTS

DUCTWORK TYPES

Page 24: 11-Air Conditioning Installations - Centralized

24

METAL TRUNK LINES WITH ROUND FIBERGLASS BRANCH DUCT

DUCTWORK TYPES

Page 25: 11-Air Conditioning Installations - Centralized

25

DUCTING INSTALLATIONS

Page 26: 11-Air Conditioning Installations - Centralized

26

Page 27: 11-Air Conditioning Installations - Centralized

27

Pre-insulated aluminium sandwich panels with an extra aluminium foil covering and internal closed-cell insulation

DUCTING INSULATION

Page 28: 11-Air Conditioning Installations - Centralized

28

MAIN DUCT

Page 29: 11-Air Conditioning Installations - Centralized

29

BRANCH DUCT

Page 30: 11-Air Conditioning Installations - Centralized

30

DUCT COMPONENT: ELBOW

Page 31: 11-Air Conditioning Installations - Centralized

31

INSPECTION HOLE

Page 32: 11-Air Conditioning Installations - Centralized

32

DIFFUSER

Page 33: 11-Air Conditioning Installations - Centralized

33

REGISTER

Page 34: 11-Air Conditioning Installations - Centralized

34

AIR DIFFUSER TYPES

Page 35: 11-Air Conditioning Installations - Centralized

35

FABRICATION METHOD

Page 36: 11-Air Conditioning Installations - Centralized

36

DUCTWORK SUPPORT

Page 37: 11-Air Conditioning Installations - Centralized

© 2009 Sarajul Fikri Mohamed

SMM2 MEASUREMENT RULES

Page 38: 11-Air Conditioning Installations - Centralized

38

AIR CONDITIONING AND VENTILATION SYSTEM MEASUREMENT RULES

SECTION Q PLUMBING AND MECHANICAL ENGINEERING INSTALLATIONS

Page 39: 11-Air Conditioning Installations - Centralized

39

DUCTWORK Q.14 DUCTING AND FITTING 1. Ducting (measured over all pipe fittings, short running lengths and

branches) shall be given in metres stating the type and the normal size. Joints in the running length shall be given in the description stating the method of jointing.

2. Lining ducting internally – meter – separately – stating the type and the thickness of the lining material and internal size of ducting.

3. Flexible ducting and extensible ducting (measured as fully extended)- described and enumerated.

MEASUREMENT RULES

Page 40: 11-Air Conditioning Installations - Centralized

40

DUCTWORK Q.14 DUCTING AND FITTING 4. Curved ducting - described and enumerated-stating mean radius.

Curved rectangular ducting stated whether shaped to curved on the wider or narrow side.

5. Duct fitting – in numbers – extra over the duct in which they occur.

Cutting and forming openings and jointing ducting to fitting – shall be deemed to be included. Fitting involving a change of direction of ducting- shall be described.

MEASUREMENT RULES

Page 41: 11-Air Conditioning Installations - Centralized

41

Elbow, Reducer And Branch

Shall be described and enumerated as extra over in which they occur. (Q.14.5)

6. Providing materials, heat, bolts, nuts, washers and everything else necessary for making joints in ducting shall be deemed to be included with the items. (Q.14.6)

MEASUREMENT RULES

Page 42: 11-Air Conditioning Installations - Centralized

42

DUCTWORK Q.15 SPECIAL CONNECTION, ETC 1. Special connection and special joints in ducting shall be enumerated

separately (except where given in the description of other enumerated item) stating size and kind of ducting concerned and method of jointing.

2. Classification :

a. Connection between ducting of differing materials. b. Connection between ducting and equipment stating the

nature of the equipment. c. Isolated joints which differ from those given in the

description of the ducting. d. Flexible connection between ducting and plant.

MEASUREMENT RULES

Page 43: 11-Air Conditioning Installations - Centralized

43

DUCTWORK Q.15 SPECIAL CONNECTION, ETC 3. Ducting turn and splitter shall be enumerated separately stating the

type and internal size of ducting.

4. Nozzle outlets, test holes and covers and access door shall be enumerated separately stating the size and method of jointing and material and thickness or gauge of the ducting and lining.

5. Cowls, terminals, intake louvers and like shall be enumerated separately stating the size and type, the size of ducting.

MEASUREMENT RULES

Page 44: 11-Air Conditioning Installations - Centralized

44

Q.16 DUCTWORK SUPPORTS

1. Components for supporting ductworks shall be enumerated- size and type of the components and size of ducting.

Stating the:-

– Size, type of the components

– Size of the ducting

Classification shall be as follows:-

– Components for supporting single runs of ducting

– Ditto multiple runs of ducting

– Combined components for supporting ducting and pipework.

MEASUREMENT RULES

Page 45: 11-Air Conditioning Installations - Centralized

45

Hanger

HANGER

Page 46: 11-Air Conditioning Installations - Centralized

46

Q.17 ALTERNATIVE METHOD OF MEASUREMENT

1. Clause Q. 18 provide alternative method of measurement.

MEASUREMENT RULES

Page 47: 11-Air Conditioning Installations - Centralized

47

Q.18 DUCTING AND DUCTING FITTING

1. Measured in metres (over all ducting fittings, short lengths and branches) stating the type and size.(Q.18.1)

2. Joints and method of the jointing shall be given in the description.

3. Flexible / extensible ducting shall be described and enumerated.(Q.18.3)

4. Curved ducting shall be so described and enumerated stating the mean radius.(Q.18.4)

MEASUREMENT RULES

Page 48: 11-Air Conditioning Installations - Centralized

48

EQUIPMENT AND ANCILLARIES

Q.19 GENERALLY

1. Unless otherwise stated, equipment such as boiler, generators, cylinder, pumps, cooling, air handling unit, fans, refrigerator equipment etc – in numbers – ( Q.19.1)

Condenser Unit And Fan Coil, etc.

– Measured in nos (Q.19.1)

2. Packaged item – shall be described in conjunction with a manufacturer’s detailed specification (Q.19.2)

MEASUREMENT RULES

Page 49: 11-Air Conditioning Installations - Centralized

49

EQUIPMENT AND ANCILLARIES

Q.19 GENERALLY

3. Any limiting dimensions on the size shall be given. (Q.19.3)

4. Electrical connection shall be given in accordance with section R .

(Q.19.4) Section R.

5. Platework, fuel hoppers and supporting steelwork -accordance Section P.

MEASUREMENT RULES

Page 50: 11-Air Conditioning Installations - Centralized

50

EQUIPMENT

FIRE DAMPER

Measured in nos. (Q.19.1)

The related specification shall be described

MEASUREMENT RULES

Page 51: 11-Air Conditioning Installations - Centralized

51

EQUIPMENT

AIR DIFFUSER & AIR GRILLE

Measured in nos.

Stating the type, size and method of fixing.

Described accordance with the details drawing and specification given.

MEASUREMENT RULES

Page 52: 11-Air Conditioning Installations - Centralized

52

AIR DIFFUSER

Page 53: 11-Air Conditioning Installations - Centralized

53

Page 54: 11-Air Conditioning Installations - Centralized

54

Page 55: 11-Air Conditioning Installations - Centralized

MEASUREMENT RULES

AIR CONDITIONING INSTALLATIONS

Page 56: 11-Air Conditioning Installations - Centralized

56

GENERALLY Q.1 INFORMATION AIR CONDITIONING SYSTEM AND INSTALLATION Generally Q.1. Information 1 Particulars of the following shall be given : a) Regulation, etc. b) Kind and quality of material. c) Gauge, thickness or substance of material. d) Any tests, etc.

MEASUREMENT RULES

Page 57: 11-Air Conditioning Installations - Centralized

57

Q.1.2 Assembling and jointing together the component parts of composite units and providing any necessary connecting flanges and jointing materials shall be deemed to be included with the items concerned. Where composite units are supplied by the Employer, particulars shall be given of the assembly work involved.

Q.1.3 Patterns, moulds, templets and the like shall be deemed to be included with the items.

MEASUREMENT RULES

Page 58: 11-Air Conditioning Installations - Centralized

58

WATER COOLED CHILLER UNIT

Install and complete the water cooled chiller unit (minimum capacity 186 tonne) c/w microprocessor system, concrete plinth (if necessary), vibration isolators and other assecories. (No)

CHILLED WATER PUMPSET

Horizontal split casing chilled water pumpset (minimum requirement 608 igpm, 120 ft) c/w motor, concrete plinth (if necessary), vibration isolators and other assecories. (No)

BILL OF QUANTITIES: EQUIPMENT

Page 59: 11-Air Conditioning Installations - Centralized

59

BILL OF QUANTITIES: EQUIPMENT

WATER EXPANSION TANK

200 gallons chilled water expansion tank c/w concrete plinth (if necessary) and other assecories. (No)

AIR HANDLING UNIT

Install and complete the 366 000 min btu/hr air handling unit c/w thermostat, evaporator blower unit, fan, motor, filters, concrete plinth (if necessary), vibration isolators and other assecories. (No)

Page 60: 11-Air Conditioning Installations - Centralized

60

Q.1.4 Priming and painting off-site and proprietary finishes or surface treatment applied as part of the production process shall be described stating whether applied before or after fabrication or assembly.

Q.1.5 Except where otherwise stated the method of fixing and the provision of nails, bolts, nuts, holes, screws, plugs, shot-fired pins and the like shall be given in the description of the work.

MEASUREMENT RULES

Page 61: 11-Air Conditioning Installations - Centralized

61

Q.1.6 The nature of the background to which work is to be fixed shall be given in the description. Any necessary drilling of the backgrounds shall be deemed to be included. Backgrounds shall be classified as follows :

a) Building-board which shall be deemed to include hardboard, compressed cement sheet, plasterboard, fibreboard and similar materials which do not grip woodscrews.

b) Etc

MEASUREMENT RULES

Page 62: 11-Air Conditioning Installations - Centralized

62

Q.1.6 The nature of the background ….

b) Timber which shall be deemed to include softwood, hardwood, blockboard, plywood and similar materials which will grip wood-screws when a lead-hole has been drilled.

c) Brickwork, concrete or stone work

d) Plain metal

e) Glass

MEASUREMENT RULES

Page 63: 11-Air Conditioning Installations - Centralized

63

Q.1.7. Temporary work shall be so described. Removing

temporary work and making good after shall be deemed to

be included with the item.

1.8. Connecting to existing services – shall be described

MEASUREMENT RULES

Page 64: 11-Air Conditioning Installations - Centralized

64

GENERALLY

Q.2. CLASSIFICATION OF WORK

Q.2.1 Work together with its metalwork, supports and the like (unless associated with more than one installation) shall be classified as follows and given under an appropriate heading :

t) Air handling installation, identifying whether ventilation supply, ventilation extract, ventilation with heating (air heated centrally), ventilation with heating (air heated locally),air conditioning (air heated centrally), air conditioning (air heated locally), or foul air extract.

MEASUREMENT RULES

Page 65: 11-Air Conditioning Installations - Centralized

65

Q.3. LOCATION OF WORK

Location of works :

a. Internally

b. Externally

c. In plant rooms

MEASUREMENT RULES

Page 66: 11-Air Conditioning Installations - Centralized

66

PIPE WORKS

Q.7 GENERALLY

1. Purpose-made pipes and purpose-made pipe fittings shall be described.

2. Pipes and pipe fittings which are wrapped, coated or lined by the manufacturer shall be so described stating the type of treatment.

3. Pipework required to be temporarily fixed in position, dismantled for chromium-plating or other special finishing and subsequently refixed shall be so described.

MEASUREMENT RULES

Page 67: 11-Air Conditioning Installations - Centralized

67

PIPEWORKS

a)Shall be supplied and installed:

- all necessary interconnecting pipeworks between item of

equipment

- all vents and exhausts

- all necessary pipe, valves, fittings, anchors, supports,

brackets, insulation etc

MEASUREMENT RULES

Page 68: 11-Air Conditioning Installations - Centralized

68

Q.8 PIPE AND FITTING

1. Pipes (measured over all pipe fittings, short running lengths

and branches) shall be given in metres stating the type and

the normal size. (Q.8.1)

Purpose-made pipe shall be so described and given

separately. Curved pipes shall be so described stating the

mean radius.

Joints in the running length shall be given in the description

stating the method of jointing.

MEASUREMENT RULES

Page 69: 11-Air Conditioning Installations - Centralized

69

Q.8 PIPE AND FITTING

2. Flexible pipes and extensible pipes (measured as fully

extended) shall each be so described. (Q.8.3)

3. Pipes laid or fixed in ducts, trenches and chases or

embedded in in-situ concrete or screeds shall each be so

described. (Q.8.4)

MEASUREMENT RULES

Page 70: 11-Air Conditioning Installations - Centralized

70

Q.9. SPECIAL CONNECTIONS, ETC.

1. Special connections and special joints in pipes shall each be

enumerated separately (except where given in the description

of another enumerated item) stating the nominal size and kind

of pipe concerned and the method of jointing. Classification

shall be as follows :

a) Connections between pipes of differing materials and

differing grades of the same material.

b) Connections between pipes and appliances or

equipment.

c) Connections to existing pipes.

MEASUREMENT RULES

Page 71: 11-Air Conditioning Installations - Centralized

71

Q.10. LABOURS

Labours on pipes (e.g. made bends, made springs, made

offsets, beaded ends, ornamental ends, etc.) shall be

deemed to be included with the pipes on which they occur.

MEASUREMENT RULES

Page 72: 11-Air Conditioning Installations - Centralized

72

Q.11 SUNDRIES

6. Pipe-sleeves through walls, floors ceilings shall be

enumerated stating the type, lengths, the nominal size

and kind of pipe passing through and the type of packing

required, and if to be supplied for fixing by other trades,

this shall be so described.

7. Wall, floor or ceiling plates shall be grouped together as

plates and enumerated stating the type and size.

MEASUREMENT RULES

Page 73: 11-Air Conditioning Installations - Centralized

73

Q.12 PIPEWORK SUPPORTS

1. Components or assemblies of components (e.g. clips,

saddles, pipe-hooks, holderbats, brackets, rollers, chairs

and hangers or black-plates and girder-lugs) used to fix

supports for more than one pipe shall be enumerated

separately stating the type and size of components.

Spring compensated components shall be so described

stating the loading and movement to be accommodated.

MEASUREMENT RULES

Page 74: 11-Air Conditioning Installations - Centralized

MEASUREMENT RULES

AIR CONDITIONING INSTALLATIONNS

Page 75: 11-Air Conditioning Installations - Centralized

75

DUCTWORK

Q.14 DUCTING AND FITTING

1. Ducting (measured over all pipe fittings, short running lengths and branches) shall be given in metres stating the type and the normal size. Joints in the running length shall be given in the description stating the method of jointing.

2. Lining ducting internally – meter – separately – stating the type and the thickness of the lining material and internal size of ducting.

3. Flexible ducting and extensible ducting (measured as fully extended)- described and enumerated.

MEASUREMENT RULES

Page 76: 11-Air Conditioning Installations - Centralized

76

DUCTWORK

Q.14 DUCTING AND FITTING

4. Curved ducting - described and enumerated-stating mean radius. Curved rectangular ducting stated whether shaped to curved on the wider or narrow side.

5. Duct fitting – in numbers – extra over the duct in which they occur. Cutting and forming openings and jointing ducting to fitting – shall be deemed to be included. Fitting involving a change of direction of ducting- shall be described.

MEASUREMENT RULES

Page 77: 11-Air Conditioning Installations - Centralized

77

ELBOW, REDUCER AND BRANCH

■ Shall be described and enumerated as extra over in which they occur. (Q.14.5)

6. Providing materials, heat, bolts, nuts, washers and everything else necessary for making joints in ducting shall be deemed to be included with the items. (Q.14.6)

MEASUREMENT RULES

Page 78: 11-Air Conditioning Installations - Centralized

78

DUCTWORK

Q.15 SPECIAL CONNECTION, ETC

1. Special connection and special joints in ducting shall be enumerated separately (except where given in the description of other enumerated item) stating size and kind of ducting concerned and method of jointing.

2. Classification :

a. Connection between ducting of differing materials.

b. Connection between ducting and equipment stating the nature of the equipment.

c. Isolated joints which differ from those given in the description of the ducting.

d. Flexible connection between ducting and plant.

MEASUREMENT RULES

Page 79: 11-Air Conditioning Installations - Centralized

79

DUCTWORK

Q.15 SPECIAL CONNECTION, ETC

3. Ducting turn and splitter shall be enumerated separately stating the type and internal size of ducting.

4. Nozzle outlets, test holes and covers and access door shall be enumerated separately stating the size and method of jointing and material and thickness or gauge of the ducting and lining.

5. Cowls, terminals, intake louvres and like shall be enumerated separately stating the size and type, the size of ducting.

MEASUREMENT RULES

Page 80: 11-Air Conditioning Installations - Centralized

80

BILL OF QUANTITIES: DUCTWORKS

Heading:

Galvanised iron duct as described with snaplock beam, pocket lock, grooved lock seam, pittsburgh lock and cross bracking for stiffening and including jointing and fixing for supply air

Description:

150mm x 150mm supply duct (M)

350mm x 300mm return duct (M)

Page 81: 11-Air Conditioning Installations - Centralized

81

BILL OF QUANTITIES: DUCTWORKS FITTING ELBOW

EXTRA over for 900mm x 350mm to 900mm x 350mm galvanised iron round elbow duct including cutting and forming opening and jointing ducting to fitting (NO)

REDUCER

EXTRA over for 450mm x 350mm to 350mm x 350mm galvanised iron round reducer including cutting and forming opening and jointing ducting to fitting (NO)

BRANCH

EXTRA over for 200mm x 250mm to 400mm x 450mm to 300mm x 500mm galvanised iron branch including cutting and forming opening and jointing ducting to fitting (NO)

Page 82: 11-Air Conditioning Installations - Centralized

82

Q.16 DUCTWORK SUPPORTS

1. Components for supporting ductworks shall be enumerated- size and type of the components and size of ducting.

■ Stating the:-

– Size,type of the components

– Size of the ducting

■ Classification shall be as follows:-

– Components for supporting single runs of ducting

– Ditto multiple runs of ducting

– Combined components for supporting ducting and pipework.

MEASUREMENT RULES

Page 83: 11-Air Conditioning Installations - Centralized

83

HANGER

Hanger

Page 84: 11-Air Conditioning Installations - Centralized

84

Q.17 ALTERNATIVE METHOD OF MEASUREMENT

1. Clause Q. 18 provide alternative method of measurement.

MEASUREMENT RULES

Page 85: 11-Air Conditioning Installations - Centralized

85

Q.18 DUCTING AND DUCTING FITTING

1. Measured in metres (over all ducting fittings,short lengths and branches) stating the type and size.(Q.18.1)

2. Joints and method of the jointing shall be given in the description.

3. Flexible / extensible ducting shall be described and enumerated.(Q.18.3)

4. Curved ducting shall be so described and enumerated stating the mean radius.(Q.18.4)

MEASUREMENT RULES

Page 86: 11-Air Conditioning Installations - Centralized

86

EQUIPMENT AND ANCILLARIES

Q.19 GENERALLY

1. Unless otherwise stated, equipment such as boiler, generators, cylinder, pumps, cooling, air handling unit, fans, refrigerator equipment etc – in numbers – ( Q.19.1)

Condenser Unit And Fan Coil, etc.

– Measured in nos (Q.19.1)

2. Packaged item – shall be described in conjunction with a manufacturer’s detailed specification (Q.19.2)

MEASUREMENT RULES

Page 87: 11-Air Conditioning Installations - Centralized

87

EQUIPMENT AND ANCILLARIES

Q.19 GENERALLY

3. Any limiting dimensions on the size shall be given. (Q.19.3)

4. Electrical connection shall be given in accordance with

section R . (Q.19.4) Section R.

5. Platework, fuel hoppers dan supporting steelwork -accordance Section P.

MEASUREMENT RULES

Page 88: 11-Air Conditioning Installations - Centralized

88

ELECTRICAL WORKS

Power cabling using 4 x 50mm sq. XLPE/PVC/CU c/w 150A TPN metalclad isolator and 150A TPN MCCB for 2 nos Air Cooled Chiller from ACP switchboard (at chiller plant room) (ITEM)

ELECTRICAL WORKS

Power cabling using 4 x 35mm sq. XLPE/PVC/CU c/w 100A TPN metalclad isolator and 100A TPN MCCB for 3 nos chiller water pump from ACP switchboard (at chiller plant room) (ITEM)

BILL OF QUANTITIES: ELECTRICAL WIRING

Page 89: 11-Air Conditioning Installations - Centralized

89

EQUIPMENT

FIRE DAMPER

■ Measured in nos. (Q.19.1)

■ The related specification shall be described

MEASUREMENT RULES

Page 90: 11-Air Conditioning Installations - Centralized

90

EQUIPMENT

AIR DIFFUSER & AIR GRILLE

■ Measured in nos.

■ Stating the type, size and method of fixing.

■ Described accordance with the details drawing and specification given.

MEASUREMENT RULES

Page 91: 11-Air Conditioning Installations - Centralized

91

DIFFUSER

Page 92: 11-Air Conditioning Installations - Centralized

TYPES OF DIFFUSER

Page 93: 11-Air Conditioning Installations - Centralized

93 DIFFUSER/COLLAR CONNECTION

Page 94: 11-Air Conditioning Installations - Centralized

94 REGISTER/COLLAR CONNECTION

Page 95: 11-Air Conditioning Installations - Centralized

95

BILL OF QUANTITIES: EQUIPMENTS DIFFUSER

600mm x 600mm anodized extruded aluminium supply air diffuser complete with blade damper.

200mm x 400mm 4 way square type air diffuser , fixed to suspended ceiling complete with all approved gasket

Page 96: 11-Air Conditioning Installations - Centralized

96

BILL OF QUANTITIES: EQUIPMENTS RETURN AIR GRILLES

600mm x600mm extruded aluminium return air grilles

DAMPER

Volume control damper complete with access opening.

Fusible link type fire damper (2 hour fire rated and approved by Jabatan Bomba) complete with access opening.

HANGER

Hanger, constructed of 2 nos 12mm mild steel rod, 60mm long centres, 25mm x 25mm x 5mm mild steel angels 80” long for 300 mm x 250 mm (m/s) supply duct / return duct (no)

Page 97: 11-Air Conditioning Installations - Centralized

97

EQUIPMENT AND ANCILLLARIES

Q.20 Anti-vibration and sound insulation

Anti-vibration mountings for plant shall be enumerated stating the type and the size. Anti-vibration material and sound-insulating material in plant bases shall be given in square metres stating the nature of the material and the thickness.

MEASUREMENT RULES

Page 98: 11-Air Conditioning Installations - Centralized

98

EQUIPMENT AND ANCILLLARIES

Q.21 Equipment supports

1. Equipment supports shall be enumerated and described.

2. Particulars of the method of fixing shall be given in the description in accordance with clauses Q.1.5-6.

MEASUREMENT RULES

Page 99: 11-Air Conditioning Installations - Centralized

99

HANGER TO DUCTWORKS

Page 100: 11-Air Conditioning Installations - Centralized

100

c

Page 101: 11-Air Conditioning Installations - Centralized

DUCTWORK SUPPORT

Page 102: 11-Air Conditioning Installations - Centralized

102

ELBOW

Page 103: 11-Air Conditioning Installations - Centralized

103

Q.22 JOINTING (PENYAMBUNGAN)

1. Particulars of the method of jointing – shall be given in the description of the equipment.

MEASUREMENT RULES

Page 104: 11-Air Conditioning Installations - Centralized

104

EQUIPMENT AND ANCILLARIES

Q.24 IDENTIFICATION PLATES

■ Plates, discs and labels for identification plants shall be

deemed to be included with the item concerned. (Q.24)

■ Charts giving the keys – shall be enumerated

MEASUREMENT RULES

Page 105: 11-Air Conditioning Installations - Centralized

MEASUREMENT RULES

AIR CONDITIONING INSTALLATIONS

Page 106: 11-Air Conditioning Installations - Centralized

INSULATION

Q.25 GENERALLY

1. Particulars of the following shall be given: (Q.25.1)

– Kind and quality of material

– Thickness of material

– Finish of material

– Method of fixing

2. Includes smoothing the material and working around supports.(Q.25.2)

MEASUREMENT RULES

AIR CONDITIONING INSTALLATIONS

Page 107: 11-Air Conditioning Installations - Centralized

Q.26 INSULATION TO PIPEWORK

1. Insulation to pipework – meter – stating types and size of the

pipe.

2. Working insulation around ancillaries shall be enumerated

separately – in numbers – extra over

3. Working insulation over flanges and pipe fitting shall be

deemed.

4. Insulation boxes shall be enumerated separately – in

numbers – stating types of material and infill.

MEASUREMENT RULES

AIR CONDITIONING INSTALLATIONS

Page 108: 11-Air Conditioning Installations - Centralized

Q.27 INSULATION TO DUCTWORK

1. Insulation to ductwork – meter – stating types and size of the ducting.

2. Working insulation around ducting fittings, special fittings and ancillaries – in numbers – extra over

INSULATION TO DUCTWORK

AIR CONDITIONING INSTALLATIONS

Page 109: 11-Air Conditioning Installations - Centralized

Q.28 INSULATION TO EQUIPMENT

1. Insulation to equipment – enumerated – stating overall size of the unit. Particular shall be given of any protection to the insulation.

2. Providing detachable mattresses and working insulation around special fittings and ancillaries – shall be deemed.

INSULATION TO EQUIPMENT

AIR CONDITIONING INSTALLATIONS

Page 110: 11-Air Conditioning Installations - Centralized

Q.29 SUNDRY INSULATION

1. Loose insulation in trench, ducts, tank casings and like - shall be given separately in cubic metres stating nature of materials.

2. Cellular concrete insulation in trench and ducts (grouped together) - shall be given in cubic metres stating mix of the concrete.

3. Special protection or finish at opening through wall, valve chambers and the like – shall each be described enumerated.

SUNDRY INSULATION

AIR CONDITIONING INSTALLATIONS

Page 111: 11-Air Conditioning Installations - Centralized

111

BILL OF QUANTITIES: INSULATION TO DUCTWORKS

Insulation to duct works

50 mm Thick fibreglass insulation to 200 mm X 100 mm galvanised iron ducting, with clips at 450 mm centres and covered with single side aluminium foil for supply air duct.

Insulation to pipe works

50mm Thick “Aeroflax” or other approved flexible expanded rubber compound insulation to 40mm diameter copper tubing.

Page 112: 11-Air Conditioning Installations - Centralized

MEASUREMENT RULES

AIR CONDITIONING INSTALLATIONS

Page 113: 11-Air Conditioning Installations - Centralized

Q.30 SUNDRIES

1. Testing each installation shall be given as an ITEM.

stating any required qualifications, no of stage tests in

addition to the final, purpose, instruments and appliances

required, special insurances etc.

MEASUREMENT RULES

AIR CONDITIONING INSTALLATIONS

Page 114: 11-Air Conditioning Installations - Centralized

114

BILL OF QUANTITIES: TESTING TESTING

Upon completion allowed for testing the foregoing Air Cooled

Chiller System air conditioning, make good any defects and leave

the whole of the installation in perfect working order to the

satisfaction of engineer.

Page 115: 11-Air Conditioning Installations - Centralized

MEASUREMENT RULES

AIR CONDITIONING INSTALLATIONS

Page 116: 11-Air Conditioning Installations - Centralized

BUILDER’S WORK

Q.31 GENERALLY

1. Unless otherwise stated, all items of builder’s shall be given

in accordance with the appropriate section.

2. Builder’s works in connection with plumbing and mechanical

engineering installations shall be grouped together under an

appropriate heading.

MEASUREMENT RULES

AIR CONDITIONING INSTALLATIONS

Page 117: 11-Air Conditioning Installations - Centralized

BUILDER’S WORK

Q.32 PARTICULARLY

1. Excavation works.

2. Inspection chamber-V.6.

3. Bedding and pointing equipments or unit of equipment.

4. Cutting away for and making goods after the plumbing and

mechanical installations.

5. Etc

MEASUREMENT RULES

AIR CONDITIONING INSTALLATIONS

Page 118: 11-Air Conditioning Installations - Centralized

118

BQs: BUILDER’S WORKS BUILDER’S WORK

50 mm thick concrete grade 15 as base of 300 mm wide (m3)

Page 119: 11-Air Conditioning Installations - Centralized

© 2009 Sarajul Fikri Mohamed

TAKING OFF LIST

Page 120: 11-Air Conditioning Installations - Centralized

120

1. Preamble 2. Equipment – Chiller unit, water pump, water tank, AHU. 3. Ducting - supply duct, return duct 4. Ducting Fitting 5. Ductwork Support 6. Pipe work 7. Insulation to ductwork/pipe 8. Equipment - Diffuser, Grille, Damper 9. Builder’s Work 10. Electrical system 11. Testing

TAKING OFF LIST

AIR CONDITIONING SYSTEM

Page 121: 11-Air Conditioning Installations - Centralized

121

1) Air cond Equipment (NO)

- Air cooled chiller

- Chilled water tank

- Chilled water pump - Air handling unit

2) Ducting (M)

3) Ducting Fitting (NO)

-Elbow

-Tee

-Branch

4) Ducting Support (NO)

-Hanger

5) Pipe Work (M)

-Refrigerant pipe

-Suction pipe

-Drain Pipe

6) Insulation (M)

-To ductwork

- To pipe work

7) Equipment (NO)

-Diffuser

-Grill

-Damper

8) Sundries

9) Builders work

TAKING OFF LIST

Page 122: 11-Air Conditioning Installations - Centralized

AIR CONDITIONING INSTALLATIONS – CENTRAL SYSTEM

PROJECT TITLE

CADANGAN MEMBINA DAN MENYIAPKAN KOMPLEKS

PERNIAGAAN LARKIN MALL

Fakulti Alam Bina

Page 123: 11-Air Conditioning Installations - Centralized

DUCTING SYSTEM

AIR HANDLING UNIT

Page 124: 11-Air Conditioning Installations - Centralized

A/C CHILLED WATER EXPANSION TANK

CHILLED WATER PUMP

AIR COOLED CHILLERS