Top Banner

of 33

10_Contract Procurement Methods

Apr 09, 2018

Download

Documents

Max Escobar
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/7/2019 10_Contract Procurement Methods

    1/33

    constructionsite

    Contract Procurement Methods

  • 8/7/2019 10_Contract Procurement Methods

    2/33

  • 8/7/2019 10_Contract Procurement Methods

    3/33

    constructionsite

    Traditional

    This method usually uses the standard form ofcontract by the Joint Contracts Tribunal (JCT) or asimilar

    The contract requires the contractor to carry out theconstruction according to the drawings andspecification drawn up by the design team

    All work is supervised on behalf of the client by the

    design team leader, which is normally the architector on civil engineering projects, the Consultant CivilEngineer.

  • 8/7/2019 10_Contract Procurement Methods

    4/33

    constructionsite

    Fixed Price Contract

    A Fixed Price Contract involves the contractoragreeing to construct the building as specified in thedrawings and Bills of Quantities (B of Q) for the client

    for an agreed sum, by an agreed date. Although it is called a fixed price contract it does

    allow for the contractor to claim additional costs forany variations to the specification.

    Allowance can also be claimed by the contractor foran extension of time if there is a delay which isbeyond his control.

  • 8/7/2019 10_Contract Procurement Methods

    5/33

    constructionsite

    When constructing new buildings it is possible

    to assess the cost of the work to be done, in

    which case a fixed price can be the basis for

    the contract.

    A fixed price can, however, be on the whole

    contract, a section of work or can apply to a

    unit rate. The price is fixed although the

    amount of work is not known.

  • 8/7/2019 10_Contract Procurement Methods

    6/33

    constructionsite

    Fluctuating Price Contract

    Used if the contract is due to last more than

    12 months has provision to be made for the

    results of inflation.

  • 8/7/2019 10_Contract Procurement Methods

    7/33

    constructionsite

    Reimbursement Contract

    In refurbishment contracts it is more difficult

    to assess the cost of work to be done, in

    which case a Cost Reimbursement contract

    can be used which reimburses the contractor

    for the amount that it costs him to carry out

    the work, plus a fee to cover overheads and

    profit.

  • 8/7/2019 10_Contract Procurement Methods

    8/33

    constructionsite

    Payment of the Contractor

    The contractor is paid according to the value of thework done which is assessed each month by theQuantity Surveyor,

    It is normal to withhold 3%, which goes into theretention fund. The moneys due to the contractormust be paid within 14 days.

    If the JCT Contract is used, half of the retention fundis paid to the contractor on practical completion and

    the balance is paid on the architect's final certificate.Alternatively, the whole of the retention money ispaid on the final certificate.

  • 8/7/2019 10_Contract Procurement Methods

    9/33

    constructionsite

    Advantages

    All parties have a clear picture as to the extent

    of their commitments.

    It gives a clear breakdown of the cost of allaspects of the project.

    The unit rates allow ease of valuation for the

    stage payments of work carried out and for

    any variation to the original design.

  • 8/7/2019 10_Contract Procurement Methods

    10/33

    constructionsite

    Disadvantages

    Length of time taken in the design and

    preparation of the Bill of Quantities

    Cost of preparation for the Bill of Quantities(approximately 3.5% of the contract sum).

  • 8/7/2019 10_Contract Procurement Methods

    11/33

    constructionsite

    Design And Build

    Contractor who is responsible for the design,

    specification and the construction

    The contract may be on a fixed price or costreimbursement basis, which may be either

    negotiated, or subject to tender.

  • 8/7/2019 10_Contract Procurement Methods

    12/33

    constructionsite

    Uses

    Normally used for standard type buildings i.e.

    industrial units.

    Useful for repetitive types of buildings, whichthe contractor has constructed previously

    Past experience and familiarity of the design

    and construction should result in cost savings

    for the client.

    Design And Build

  • 8/7/2019 10_Contract Procurement Methods

    13/33

    constructionsite

    Novated Design' or Develop and

    Construct'

    A variation is for a design team to be

    appointed to produce concept drawings for

    the project prior to going out to tender.

    Design And Build

  • 8/7/2019 10_Contract Procurement Methods

    14/33

    constructionsite

    Advantages

    The developer is only dealing with one

    organisation that has sole responsibility for

    the success or failure of the design and

    construction.

    It allows the developer to be aware of the

    total amount of financial commitment prior to

    the commencement of construction.

    Design And Build

  • 8/7/2019 10_Contract Procurement Methods

    15/33

    constructionsite

    Management Contracting

    design team to specify the building requirements

    specialist subcontractors are supervised and co-ordinated bythe management contractor to carry out the construction.

    The management contractor receives a fee, which may be a

    set fee or a percentage of the contract cost. The management contractor will be responsible for providing

    site accommodation for which he will be reimbursed either atcost or as a laid down lump sum in the tender document.

    Generally used on complex projects that require a short

    contract period, though which must have flexibility formodifications during construction.

  • 8/7/2019 10_Contract Procurement Methods

    16/33

    constructionsite

    Subcontractors

    Subcontractors enter into a standard JCT type ofcontract with the management contractor carry outconstruction work.

    It is the management contractor who has acontractual relationship with the subcontractors whocarry out the work, not the client.

    If any problems arise it is the managementcontractor who must pursue the subcontractor for a

    remedy. Subcontractors are normally appointed by

    competitive tendering based on the drawings andbills of quantities.

  • 8/7/2019 10_Contract Procurement Methods

    17/33

    constructionsite

    Advantages

    To the contractor: very few risks as they are guaranteed a return of costs

    and they do not have the problems associated with theemployment of labour.

    important that the project manager and quantity surveyorcontrol costs, for the management contractor has noincentive to control costs within the cost budget, althoughincentives can be introduced.

    Any costs that exceed the budget are borne by the client.

    To the developer work can begin as soon as the first few work packages are

    produced, thus allowing design and construction tooverlap.

  • 8/7/2019 10_Contract Procurement Methods

    18/33

    constructionsite

    Construction Management

    Construction management is similar in most respectsto management contracting except that whereaswith management contracting the contract isbetween the client and the contractor (the

    subcontractors are engaged through the maincontractor) in construction management thecontracts for the work packages are with the client.

    The construction manager is employed to managethe construction work. This system tends to be usedonly on large, specialist technical projects such aspower stations.

  • 8/7/2019 10_Contract Procurement Methods

    19/33

    constructionsite

    Project Management

    "the overall planning, control and co-

    ordination of a project from inception to

    completion aimed at meeting a client's

    requirements and ensuring completion on

    time, within cost and to required quality

    standards".

  • 8/7/2019 10_Contract Procurement Methods

    20/33

    constructionsite

    Project management can be used on

    projects of any size, though it is normally

    used on larger developments. Becoming increasingly popular and is

    reducing the architect's influence within

    the construction industry.

  • 8/7/2019 10_Contract Procurement Methods

    21/33

    constructionsite

    Project Manager

    May be an organisation or an individual.

    Guides the client in the selection of a suitableprocurement system, appoint all members of

    the construction team and control andorganise the project.

    Appointed on a fee basis, which is notdependent on the cost of the contract. This

    tends to ensure that the project managerworks solely for the client's interest, as heearns no commission.

  • 8/7/2019 10_Contract Procurement Methods

    22/33

    constructionsite

    Partnering

    The creation of a special relationship betweencontracting parties in the design/constructionindustry.

    This relationship encourages the parties tochange their traditional adversarialrelationships to a more co-operative, teambased approach, which promotes theachievement of mutually beneficial goals,including the prevention of major disputes.

  • 8/7/2019 10_Contract Procurement Methods

    23/33

    constructionsite

    Features

    Commitment from top management

    Continual improvement

    Time for benefits to emerge

    Based on equality of all partners

    Interest in mutual profitability

    Free and open exchange of information

    Keeps project teams together

    Well thought out incentive schemes

    Problem Resolution

    Mutual Objectives

  • 8/7/2019 10_Contract Procurement Methods

    24/33

    constructionsite

    Consideration

    All parties seek a win-win solution

    Value is placed on long-term relationships

    Trust and openness are encouraged

    An environment for long-term profitability exists All are encouraged to openly address any problems

    All understand the no one benefits form exploitingthe other

    Innovation is encouraged

    Each partner is aware of the others needs, concerns,objectives and is interested in helping their partnerto achieve this

    Overall performance is improved.

  • 8/7/2019 10_Contract Procurement Methods

    25/33

    constructionsite

    Objectives

    Improved efficiency

    Reduction in costs

    Guaranteed profits

    Reliable product quality

    Speedier construction

    More reliable completion time

    Continuity of workload

    Shared risk

    Reliable flow of design information

    Lower legal costs

  • 8/7/2019 10_Contract Procurement Methods

    26/33

    constructionsite

    Potential Benefits

    Reduced exposure to litigation

    Better productivity

    Lower risk of overrun in time and cost

    Better quality

    Lower costs

    Greater potential for profit

    Better decision and problem solving systems

  • 8/7/2019 10_Contract Procurement Methods

    27/33

    constructionsite

    Cost Implications

    Reduction in:

    Project cost - approx 5%

    Client cost approx 6%

    Profits increase by between 4% and 9%

  • 8/7/2019 10_Contract Procurement Methods

    28/33

    constructionsite

    Potential Problems

    Lowest bid mentality

    Complacency

    Intellectual Property Corruption

    The wrong people used

    Loss of opportunity

  • 8/7/2019 10_Contract Procurement Methods

    29/33

    constructionsite

    Private Finance Initiative (PFI)

    An arrangement where public sector assets

    and services are acquired through private

    sector funding which reduces

    government/public sector borrowing.

    Used for roads, bridges, schools, hospitals,

    prisons normally over 20 million value

  • 8/7/2019 10_Contract Procurement Methods

    30/33

    constructionsite

    Procedure

    Public sector sponsor establishes abusiness case strategy

    Project advertised in the Official Journal

    of European Union (OJEU)

    Bidders short listed (Normally aconsortium set up specifically for the

    project which forms a Special PurposeCompany (SPC)

    Contract awarded and notified in OJEC

  • 8/7/2019 10_Contract Procurement Methods

    31/33

    constructionsite

    Finance

    SPC provides 10% of finance remainder from

    banks

    Finance is recouped of 25-30 years from tollsor service charge

  • 8/7/2019 10_Contract Procurement Methods

    32/33

    constructionsite

    Advantages

    Potential for high returns

    Continuity of work

    Involvement in design Buildability input

    More control over programme

  • 8/7/2019 10_Contract Procurement Methods

    33/33

    constructionsite

    Disadvantages

    Very high bidding costs

    Competitive market

    Long bidding process

    High level of resources required

    Complex and demanding

    Tough contract terms

    High level of liquidated and ascertaineddamages

    Fixed price for contractor