8/7/2019 10_Contract Procurement Methods
1/33
constructionsite
Contract Procurement Methods
8/7/2019 10_Contract Procurement Methods
2/33
8/7/2019 10_Contract Procurement Methods
3/33
constructionsite
Traditional
This method usually uses the standard form ofcontract by the Joint Contracts Tribunal (JCT) or asimilar
The contract requires the contractor to carry out theconstruction according to the drawings andspecification drawn up by the design team
All work is supervised on behalf of the client by the
design team leader, which is normally the architector on civil engineering projects, the Consultant CivilEngineer.
8/7/2019 10_Contract Procurement Methods
4/33
constructionsite
Fixed Price Contract
A Fixed Price Contract involves the contractoragreeing to construct the building as specified in thedrawings and Bills of Quantities (B of Q) for the client
for an agreed sum, by an agreed date. Although it is called a fixed price contract it does
allow for the contractor to claim additional costs forany variations to the specification.
Allowance can also be claimed by the contractor foran extension of time if there is a delay which isbeyond his control.
8/7/2019 10_Contract Procurement Methods
5/33
constructionsite
When constructing new buildings it is possible
to assess the cost of the work to be done, in
which case a fixed price can be the basis for
the contract.
A fixed price can, however, be on the whole
contract, a section of work or can apply to a
unit rate. The price is fixed although the
amount of work is not known.
8/7/2019 10_Contract Procurement Methods
6/33
constructionsite
Fluctuating Price Contract
Used if the contract is due to last more than
12 months has provision to be made for the
results of inflation.
8/7/2019 10_Contract Procurement Methods
7/33
constructionsite
Reimbursement Contract
In refurbishment contracts it is more difficult
to assess the cost of work to be done, in
which case a Cost Reimbursement contract
can be used which reimburses the contractor
for the amount that it costs him to carry out
the work, plus a fee to cover overheads and
profit.
8/7/2019 10_Contract Procurement Methods
8/33
constructionsite
Payment of the Contractor
The contractor is paid according to the value of thework done which is assessed each month by theQuantity Surveyor,
It is normal to withhold 3%, which goes into theretention fund. The moneys due to the contractormust be paid within 14 days.
If the JCT Contract is used, half of the retention fundis paid to the contractor on practical completion and
the balance is paid on the architect's final certificate.Alternatively, the whole of the retention money ispaid on the final certificate.
8/7/2019 10_Contract Procurement Methods
9/33
constructionsite
Advantages
All parties have a clear picture as to the extent
of their commitments.
It gives a clear breakdown of the cost of allaspects of the project.
The unit rates allow ease of valuation for the
stage payments of work carried out and for
any variation to the original design.
8/7/2019 10_Contract Procurement Methods
10/33
constructionsite
Disadvantages
Length of time taken in the design and
preparation of the Bill of Quantities
Cost of preparation for the Bill of Quantities(approximately 3.5% of the contract sum).
8/7/2019 10_Contract Procurement Methods
11/33
constructionsite
Design And Build
Contractor who is responsible for the design,
specification and the construction
The contract may be on a fixed price or costreimbursement basis, which may be either
negotiated, or subject to tender.
8/7/2019 10_Contract Procurement Methods
12/33
constructionsite
Uses
Normally used for standard type buildings i.e.
industrial units.
Useful for repetitive types of buildings, whichthe contractor has constructed previously
Past experience and familiarity of the design
and construction should result in cost savings
for the client.
Design And Build
8/7/2019 10_Contract Procurement Methods
13/33
constructionsite
Novated Design' or Develop and
Construct'
A variation is for a design team to be
appointed to produce concept drawings for
the project prior to going out to tender.
Design And Build
8/7/2019 10_Contract Procurement Methods
14/33
constructionsite
Advantages
The developer is only dealing with one
organisation that has sole responsibility for
the success or failure of the design and
construction.
It allows the developer to be aware of the
total amount of financial commitment prior to
the commencement of construction.
Design And Build
8/7/2019 10_Contract Procurement Methods
15/33
constructionsite
Management Contracting
design team to specify the building requirements
specialist subcontractors are supervised and co-ordinated bythe management contractor to carry out the construction.
The management contractor receives a fee, which may be a
set fee or a percentage of the contract cost. The management contractor will be responsible for providing
site accommodation for which he will be reimbursed either atcost or as a laid down lump sum in the tender document.
Generally used on complex projects that require a short
contract period, though which must have flexibility formodifications during construction.
8/7/2019 10_Contract Procurement Methods
16/33
constructionsite
Subcontractors
Subcontractors enter into a standard JCT type ofcontract with the management contractor carry outconstruction work.
It is the management contractor who has acontractual relationship with the subcontractors whocarry out the work, not the client.
If any problems arise it is the managementcontractor who must pursue the subcontractor for a
remedy. Subcontractors are normally appointed by
competitive tendering based on the drawings andbills of quantities.
8/7/2019 10_Contract Procurement Methods
17/33
constructionsite
Advantages
To the contractor: very few risks as they are guaranteed a return of costs
and they do not have the problems associated with theemployment of labour.
important that the project manager and quantity surveyorcontrol costs, for the management contractor has noincentive to control costs within the cost budget, althoughincentives can be introduced.
Any costs that exceed the budget are borne by the client.
To the developer work can begin as soon as the first few work packages are
produced, thus allowing design and construction tooverlap.
8/7/2019 10_Contract Procurement Methods
18/33
constructionsite
Construction Management
Construction management is similar in most respectsto management contracting except that whereaswith management contracting the contract isbetween the client and the contractor (the
subcontractors are engaged through the maincontractor) in construction management thecontracts for the work packages are with the client.
The construction manager is employed to managethe construction work. This system tends to be usedonly on large, specialist technical projects such aspower stations.
8/7/2019 10_Contract Procurement Methods
19/33
constructionsite
Project Management
"the overall planning, control and co-
ordination of a project from inception to
completion aimed at meeting a client's
requirements and ensuring completion on
time, within cost and to required quality
standards".
8/7/2019 10_Contract Procurement Methods
20/33
constructionsite
Project management can be used on
projects of any size, though it is normally
used on larger developments. Becoming increasingly popular and is
reducing the architect's influence within
the construction industry.
8/7/2019 10_Contract Procurement Methods
21/33
constructionsite
Project Manager
May be an organisation or an individual.
Guides the client in the selection of a suitableprocurement system, appoint all members of
the construction team and control andorganise the project.
Appointed on a fee basis, which is notdependent on the cost of the contract. This
tends to ensure that the project managerworks solely for the client's interest, as heearns no commission.
8/7/2019 10_Contract Procurement Methods
22/33
constructionsite
Partnering
The creation of a special relationship betweencontracting parties in the design/constructionindustry.
This relationship encourages the parties tochange their traditional adversarialrelationships to a more co-operative, teambased approach, which promotes theachievement of mutually beneficial goals,including the prevention of major disputes.
8/7/2019 10_Contract Procurement Methods
23/33
constructionsite
Features
Commitment from top management
Continual improvement
Time for benefits to emerge
Based on equality of all partners
Interest in mutual profitability
Free and open exchange of information
Keeps project teams together
Well thought out incentive schemes
Problem Resolution
Mutual Objectives
8/7/2019 10_Contract Procurement Methods
24/33
constructionsite
Consideration
All parties seek a win-win solution
Value is placed on long-term relationships
Trust and openness are encouraged
An environment for long-term profitability exists All are encouraged to openly address any problems
All understand the no one benefits form exploitingthe other
Innovation is encouraged
Each partner is aware of the others needs, concerns,objectives and is interested in helping their partnerto achieve this
Overall performance is improved.
8/7/2019 10_Contract Procurement Methods
25/33
constructionsite
Objectives
Improved efficiency
Reduction in costs
Guaranteed profits
Reliable product quality
Speedier construction
More reliable completion time
Continuity of workload
Shared risk
Reliable flow of design information
Lower legal costs
8/7/2019 10_Contract Procurement Methods
26/33
constructionsite
Potential Benefits
Reduced exposure to litigation
Better productivity
Lower risk of overrun in time and cost
Better quality
Lower costs
Greater potential for profit
Better decision and problem solving systems
8/7/2019 10_Contract Procurement Methods
27/33
constructionsite
Cost Implications
Reduction in:
Project cost - approx 5%
Client cost approx 6%
Profits increase by between 4% and 9%
8/7/2019 10_Contract Procurement Methods
28/33
constructionsite
Potential Problems
Lowest bid mentality
Complacency
Intellectual Property Corruption
The wrong people used
Loss of opportunity
8/7/2019 10_Contract Procurement Methods
29/33
constructionsite
Private Finance Initiative (PFI)
An arrangement where public sector assets
and services are acquired through private
sector funding which reduces
government/public sector borrowing.
Used for roads, bridges, schools, hospitals,
prisons normally over 20 million value
8/7/2019 10_Contract Procurement Methods
30/33
constructionsite
Procedure
Public sector sponsor establishes abusiness case strategy
Project advertised in the Official Journal
of European Union (OJEU)
Bidders short listed (Normally aconsortium set up specifically for the
project which forms a Special PurposeCompany (SPC)
Contract awarded and notified in OJEC
8/7/2019 10_Contract Procurement Methods
31/33
constructionsite
Finance
SPC provides 10% of finance remainder from
banks
Finance is recouped of 25-30 years from tollsor service charge
8/7/2019 10_Contract Procurement Methods
32/33
constructionsite
Advantages
Potential for high returns
Continuity of work
Involvement in design Buildability input
More control over programme
8/7/2019 10_Contract Procurement Methods
33/33
constructionsite
Disadvantages
Very high bidding costs
Competitive market
Long bidding process
High level of resources required
Complex and demanding
Tough contract terms
High level of liquidated and ascertaineddamages
Fixed price for contractor