Activity ID Activity Name Original Duration Start Finish Budgeted Cost (UAE Dirhams) Al Ain Water Distribution Network 1218 29-Oct-09 27-Oct-13 592,527,196 General 1218 29-Oct-09 27-Oct-13 0 Key Dates 1218 29-Oct-09 27-Oct-13 0 KD1000 Effective Date of Agreement 0 29-Oct-09* 0 KD3330 Site Hand Over Certificate 0 29-Oct-09 0 KD3290 Performance Bank Guarantee 15 29-Oct-09 15-Nov-09 0 KD3310 Advance Payment Guarantee 0 18-Nov-09 0 KD3320 Insurance Polices 0 24-Nov-09 0 KD1040 Commencement of the Works 0 30-Nov-09 0 KD3340 Signing the Agreement Documents By Both Parties 0 10-Dec-09 0 KD3280 Advance Payment 26 12-Dec-09 10-Jan-10 0 KD1030 Completion of the Works and Issuance of FAC 0 27-Oct-13* 0 Contract Milestones 538 26-Jan-10 28-Oct-11 0 CM1060 Provision of Facilities for Owner/Engineer - Completion 0 26-Jan-10* 0 CM1070 Geo technical and Topographical Surveys - Completion 0 26-Jan-10* 0 CM1100 Suppliers Confirmation of Order of Pump Units 0 26-Jan-10* 0 CM1080 Hydraulic Analysis and Surge Analysis - Completion 0 27-Mar-10* 0 CM1090 Confirmation of Hydraulic Relevant Equipment Data for N-6821 Contract 0 27-Mar-10* 0 CM1110 Completion of Final Design 0 22-Dec-10* 0 CM1120 Latest Commencement of Delivery of Pump Units to Site 0 20-Feb-11* 0 CM1130 Latest Completion of Delivery of Pump Units to Site 0 23-Apr-11* 0 CM1140 Mechanical Completion 0 21-Jul-11* 0 CM1150 Commissioning - Completion 0 28-Oct-11* 0 CM1160 Completion of the Works and Issuance of PAC 0 28-Oct-11* 0 Preliminaries 26 28-Dec-09 26-Jan-10 0 PR1000 Geo Technical Survey 26 28-Dec-09 26-Jan-10 0 PR1010 Topographic Survey 26 28-Dec-09 26-Jan-10 0 Mobilization 611 29-Oct-09 27-Oct-11 8,085,000 MO1020 Site Office Facilities For Owner/Engineer/Contractor Staff 74 29-Oct-09 26-Jan-10 3,700,000 MO1030 Accommodation Facilities 74 29-Oct-09 26-Jan-10 1,380,000 MO1040 Provision of Vehicles 74 29-Oct-09 26-Jan-10 1,500,000 MO1050 Operation and Maintenance of the above Facilities until PAC as per specification 537 27-Jan-10 27-Oct-11 1,100,000 MO1060 Provision of Communication Equipment/ Services until PAC (Telephone, Fax,etc..) 611 29-Oct-09 27-Oct-11 405,000 Design & Engineering 480 02-Dec-09 25-Jun-11 4,545,000 General 129 05-Jan-10 03-Jun-10 45,450 DE1071 P & ID - Equipment List - Operation PhilosohpySubmittal 9 05-Jan-10 14-Jan-10 4,870 DE1081 P & ID - Equipment List - Operation Philosohpy Approval 18 16-Jan-10 04-Feb-10 9,739 DE1031 General Arrangement Drawing of Pump House-Elec.Building-Transformer Submittal 12 16-Feb-10 01-Mar-10 6,493 DE1041 General Arrangement Drawing of Pump House-Elec.Building-Transformer Approval 15 02-Mar-10 22-Mar-10 8,116 DE1051 General Arrangement Drawing of 33 KV Switch Gear Submittal 12 01-May-10 13-May-10 6,493 DE1061 General Arrangement Drawing of 33 KV Switch Gear Approval 18 15-May-10 03-Jun-10 9,739 Mechanical Package 278 02-Dec-09 24-Oct-10 2,727,000 Hydraulic & Surge Analysis 97 02-Dec-09 25-Mar-10 268,800 Hydraulic Analysis 46 02-Dec-09 25-Jan-10 50,000 DE4820 List of Deliverables 4 02-Dec-09 07-Dec-09 3,390 DE4830 Mechanism for Summarizing/Documenting Operational Issues 6 08-Dec-09 15-Dec-09 5,085 DE4840 Preliminary Steady-State Report to Torishima 4 16-Dec-09 21-Dec-09 3,390 DE4850 Detailed Steady-State Report for Pumping Station Including EPS 10 22-Dec-09 04-Jan-10 8,475 DE4860 Detailed Steady-State Report for Pipelines Including EPS 10 22-Dec-09 04-Jan-10 8,475 DE4870 List of Load Proposed Cases for Transient Runs 10 22-Dec-09 04-Jan-10 8,475 DE4990 TRANSCO Approval for Hydraulic Analysis 15 05-Jan-10 25-Jan-10 12,712 Surge Analysis 51 26-Jan-10 25-Mar-10 218,800 DE4940 Transient Report Pumping Station 29 26-Jan-10 05-Mar-10 48,437 DE4950 Transient Report Pumping Station Pipelines 29 26-Jan-10 05-Mar-10 48,437 DE4960 Risk Assessment of Potential Problems with Existing Components 29 26-Jan-10 05-Mar-10 48,437 DE4970 Assessment of Risks at Each Supply Point from Upstream Effects 29 26-Jan-10 05-Mar-10 48,437 DE5000 TRANSCO Approval for Surge Vessel Analysis 15 07-Mar-10 25-Mar-10 25,053 Main Pumps 138 26-Jan-10 05-Jul-10 262,722 Material Submittal 32 26-Jan-10 03-Mar-10 57,471 DE1000 Main Pumps Material Submittal 5 26-Jan-10 31-Jan-10 10,263 DE1011 Main Pumps Material Approval 23 01-Feb-10 03-Mar-10 47,208 Shop Drawings 36 04-Mar-10 14-Apr-10 67,733 DE1420 Submittal of Main Pumps Shop Drawings 18 04-Mar-10 24-Mar-10 36,945 DE1430 Approval of Main Pumps Shop Drawings 15 25-Mar-10 14-Apr-10 30,788 Installation Method Statement 70 15-Apr-10 05-Jul-10 137,519 DE1460 Submittal of Main Pumps Installation Method Statement 52 15-Apr-10 14-Jun-10 106,731 DE1470 Approval of Main Pumps Installation Method Statement 15 15-Jun-10 05-Jul-10 30,788 Auxiliary Pumps 107 23-Mar-10 25-Jul-10 5,653 Material Submittal 41 23-Mar-10 09-May-10 2,092 DE1150 Auxiliary Pumps Material Submittal 16 23-Mar-10 10-Apr-10 905 DE1160 Auxiliary Pumps Material Approval 21 11-Apr-10 09-May-10 1,187 Installation Method Statement 66 10-May-10 25-Jul-10 3,562 DE1540 Submittal of Auxiliary Pumps Installation Method Statement 47 10-May-10 03-Jul-10 2,657 DE1550 Approval of Auxiliary Pumps Installation Method Statement 16 04-Jul-10 25-Jul-10 905 External & Pump House Valves 45 26-Jan-10 18-Mar-10 581,347 Material Submittal 45 26-Jan-10 18-Mar-10 581,347 DE1200 Pump House Valves Material Submittal 18 26-Jan-10 15-Feb-10 127,613 O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 2010 2011 2012 Effective Date of Agreement Site Hand Over Certificate Performance Bank Guarantee Advance Payment Guarantee Insurance Polices Commencement of the Works Signing the Agreement Documents By Both Parties Advance Payment Provision of Facilities for Owner/Engineer - Completion Geo technical and Topographical Surveys - Completion Suppliers Confirmation of Order of Pump Units Hydraulic Analysis and Surge Analysis - Completion Confirmation of Hydraulic Relevant Equipment Data for N-6821 Contra Completion of Final Design Latest Commencement of Delivery of Pump Un Latest Completion of Delivery of Pump Un Mechanical Completion Commissioning - Completion Completion of the Works and Geo Technical Survey Topographic Survey Site Office Facilities For Owner/Engineer/Contractor Staff Accommodation Facilities Provision of Vehicles Operation and Maintenance Provision of Communication P & ID - Equipment List - Operation PhilosohpySubmittal P & ID - Equipment List - Operation Philosohpy Approval General Arrangement Drawing of Pump House-Elec.Building-Transform General Arrangement Drawing of Pump House-Elec.Building-Transfor m General Arrangement Drawing of 33 KV Switch Gear Submittal General Arrangement Drawing of 33 KV Switch Gear Approval List of Deliverables Mechanism for Summarizing/Documenting Operational Issues Preliminary Steady-State Report to Torishima Detailed Steady-State Report for Pumping Station Including EPS Detailed Steady-State Report for Pipelines Including EPS List of Load Proposed Cases for Transient Runs TRANSCO Approval for Hydraulic Analysis Transient Report Pumping Station Transient Report Pumping Station Pipelines Risk Assessment of Potential Problems with Existing Components Assessment of Risks at Each Supply Point from Upstream Effects TRANSCO Approval for Surge Vessel Analysis Main Pumps Material Submittal Main Pumps Material Approval Submittal of Main Pumps Shop Drawings Approval of Main Pumps Shop Drawings Submittal of Main Pumps Installation Method Statement Approval of Main Pumps Installation Method Statement Auxiliary Pumps Material Submittal Auxiliary Pumps Material Approval Submittal of Auxiliary Pumps Installation Method Statement Approval of Auxiliary Pumps Installation Method Statement Pump House Valves Material Submittal Al Ain Water Distribution Network Pump Station at AARC Data Date : 29-Oct-09 Page : 1 of 15 Printed On : 05-Jan-10 Actual Work Remaining Work Critical Remaining Work Milestone Project Implementation Schedule Overall Implementation Programme Date Revision Che... Appro... 08-Dec-09 Overall Implementation Programme Rev 00 04-Jan-10 Overall Implementation Programme Rev 01
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Activity ID Activity Name OriginalDuration
Start Finish Budgeted Cost(UAE Di rhams)
Al Ain Water DistributAl Ain Water Distribution Network 1218 29-Oct-09 27-Oct-13 592,527,196
GeneralGeneral 1218 29-Oct-09 27-Oct-13 0
Key DatesKey Dates 1218 29-Oct-09 27-Oct-13 0
KD1000 Effective Date of Agreement 0 29-Oct-09* 0KD3330 Site Hand Over Certificate 0 29-Oct-09 0KD3290 Performance Bank Guarantee 15 29-Oct-09 15-Nov-09 0KD3310 Advance Payment Guarantee 0 18-Nov-09 0KD3320 Insurance Polices 0 24-Nov-09 0KD1040 Commencement of the Works 0 30-Nov-09 0KD3340 Signing the Agreement Documents By Both Parties 0 10-Dec-09 0KD3280 Advance Payment 26 12-Dec-09 10-Jan-10 0KD1030 Completion of the Works and Issuance of FAC 0 27-Oct-13* 0
CM1060 Provision of Facilities for Owner/Engineer - Completion 0 26-Jan-10* 0CM1070 Geo technical and Topographical Surveys - Completion 0 26-Jan-10* 0CM1100 Suppliers Confirmation of Order of Pump Units 0 26-Jan-10* 0CM1080 Hydraulic Analysis and Surge Analysis - Completion 0 27-Mar-10* 0CM1090 Confirmation of Hydraulic Relevant Equipment Data for N-6821 Contract 0 27-Mar-10* 0CM1110 Completion of Final Design 0 22-Dec-10* 0CM1120 Latest Commencement of Delivery of Pump Units to Site 0 20-Feb-11* 0CM1130 Latest Completion of Delivery of Pump Units to Site 0 23-Apr-11* 0CM1140 Mechanical Completion 0 21-Jul-11* 0CM1150 Commissioning - Completion 0 28-Oct-11* 0CM1160 Completion of the Works and Issuance of PAC 0 28-Oct-11* 0
MO1020 Site Office Facilities For Owner/Engineer/Contractor Staff 74 29-Oct-09 26-Jan-10 3,700,000MO1030 Accommodation Facilities 74 29-Oct-09 26-Jan-10 1,380,000MO1040 Provision of Vehicles 74 29-Oct-09 26-Jan-10 1,500,000MO1050 Operation and Maintenance of the above Facilities until PAC as per specification 537 27-Jan-10 27-Oct-11 1,100,000MO1060 Provision of Communication Equipment/ Services until PAC (Telephone, Fax,etc..) 611 29-Oct-09 27-Oct-11 405,000
DE1200 Pump House Valves Material Submittal 18 26-Jan-10 15-Feb-10 127,613
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D2010 2011 2012
Effective Date of AgreementSite Hand Over CertificatePerformance Bank GuaranteeAdvance Payment GuaranteeInsurance PolicesCommencement of the WorksSigning the Agreement Documents By Both Parties
Advance Payment
Provision of Facilities for Owner/Engineer - CompletionGeo technical and Topographical Surveys - CompletionSuppliers Confirmation of Order of Pump Units
Hydraulic Analysis and Surge Analysis - CompletionConfirmation of Hydraulic Relevant Equipment Data for N-6821 Contra
Completion of Final DesignLatest Commencement of Delivery of Pump Un
Latest Completion of Delivery of Pump UnMechanical Completion
Commissioning - CompletionCompletion of the Works and
Geo Technical SurveyTopographic Survey
Site Office Facilities For Owner/Engineer/Contractor StaffAccommodation FacilitiesProvision of Vehicles
Operation and Maintenance Provision of Communication
P & ID - Equipment List - Operation PhilosohpySubmittalP & ID - Equipment List - Operation Philosohpy Approval
General Arrangement Drawing of Pump House-Elec.Building-TransformGeneral Arrangement Drawing of Pump House-Elec.Building-Transform
General Arrangement Drawing of 33 KV Switch Gear SubmittalGeneral Arrangement Drawing of 33 KV Switch Gear Approval
List of DeliverablesMechanism for Summarizing/Documenting Operational IssuesPreliminary Steady-State Report to TorishimaDetailed Steady-State Report for Pumping Station Including EPSDetailed Steady-State Report for Pipelines Including EPSList of Load Proposed Cases for Transient Runs
TRANSCO Approval for Hydraulic Analysis
Transient Report Pumping StationTransient Report Pumping Station PipelinesRisk Assessment of Potential Problems with Existing ComponentsAssessment of Risks at Each Supply Point from Upstream Effects
TRANSCO Approval for Surge Vessel Analysis
Main Pumps Material SubmittalMain Pumps Material Approval
Submittal of Main Pumps Shop DrawingsApproval of Main Pumps Shop Drawings
Submittal of Main Pumps Installation Method StatementApproval of Main Pumps Installation Method Statement
Auxiliary Pumps Material SubmittalAuxiliary Pumps Material Approval
Submittal of Auxiliary Pumps Installation Method StatementApproval of Auxiliary Pumps Installation Method Statement
Pump House Valves Material Submittal
Al Ain Water Distribution NetworkPump Station at AARC
Data Date : 29-Oct-09 Page : 1 of 15Printed On : 05-Jan-10
Air Compressor SystAir Compressor System for Surge Vessels 102 27-Mar-10 22-Jul-10 174,444Material SubmittalMaterial Submittal 40 27-Mar-10 11-May-10 68,261
DE1260 Air Compressor Material Submittal 13 27-Mar-10 10-Apr-10 24,650DE1270 Air Compressor Material Approval 23 11-Apr-10 11-May-10 43,611
Manufacture DrawinManufacture Drawings 31 12-May-10 16-Jun-10 53,092DE2280 Submittal of Air Compressor Manufacture Drawings 13 12-May-10 26-May-10 24,650DE2290 Approval of Air Compressor Manufacture Drawings 15 27-May-10 16-Jun-10 28,442
Shop DrawingsShop Drawings 31 17-Jun-10 22-Jul-10 53,092DE2320 Submittal of Air Compressor Shop Drawings 13 17-Jun-10 01-Jul-10 24,650DE2330 Approval of Air Compressor Shop Drawings 15 04-Jul-10 22-Jul-10 28,442
Cooling Water SystemCooling Water System 127 23-Mar-10 17-Aug-10 42,921For VFD ConvertersFor VFD Converters 127 23-Mar-10 17-Aug-10 18,723
Material SubmiMaterial Submittal 65 23-Mar-10 06-Jun-10 9,684DE1090 Cooling Water System for VSD Material Submittal 39 23-Mar-10 06-May-10 6,295DE1100 Cooling Water System for VSD Material Approval 21 09-May-10 06-Jun-10 3,389
DE1631 Cooling Water System for Pump/Motors Material Submittal 39 23-Mar-10 06-May-10 8,136DE1641 Cooling Water System for Pump/Motors Material Approval 21 09-May-10 06-Jun-10 4,381
Wash Water SystemWash Water System 70 19-May-10 08-Aug-10 2,513Material SubmittalMaterial Submittal 38 19-May-10 01-Jul-10 1,378
DE1220 Wash Water System Submittal 12 19-May-10 01-Jun-10 486DE1230 Wash Water System Approval 22 02-Jun-10 01-Jul-10 892
Shop DrawingsShop Drawings 32 03-Jul-10 08-Aug-10 1,135DE2060 Submittal of Wash Water System Shop Drawings 12 03-Jul-10 15-Jul-10 486DE2070 Approval of Wash Water System Shop Drawings 16 18-Jul-10 08-Aug-10 648
DE1560 Distribution Transformers Material Submittal 16 23-Sep-10 11-Oct-10 862DE1570 Distribution Transformers Material Approval 22 12-Oct-10 10-Nov-10 1,186
Shop DrawingsShop Drawings 30 11-Nov-10 21-Dec-10 1,455DE2780 Submittal of Distribution Transformers Shop Drawings 12 11-Nov-10 28-Nov-10 647DE2790 Approval of Distribution Transformers Shop Drawings 15 29-Nov-10 21-Dec-10 808
Installation Method Installation Method Statement 70 22-Dec-10 15-Mar-11 3,611DE2820 Submittal of Distribution Transformers Installation Method Statement 52 22-Dec-10 22-Feb-11 2,802DE2830 Approval of Distribution Transformers Installation Method Statement 15 23-Feb-11 15-Mar-11 808
DE1621 Material Submittal for Sewege System 192 15-May-10 30-Dec-10 5,141Shop DrawinShop Drawings 212 01-Jun-10 10-Feb-11 5,677
DE1633 Shop Drawings for Sewege System 212 01-Jun-10 10-Feb-11 5,677Method of SMethod of Statement 191 26-Jun-10 10-Feb-11 5,114
DE1644 Method of Statement of Sewege System 191 26-Jun-10 10-Feb-11 5,114Stormwater DrainagStormwater Drainage System Works 262 04-Apr-10 10-Feb-11 9,362
DesignDesign 27 04-Apr-10 04-May-10 406DE5740 Design for Stormwater Drainage System (Incl. Approvals) 27 04-Apr-10 04-May-10 406
DE1655 Material Submittal for Stormwater Drainage System 192 15-May-10 30-Dec-10 2,890Shop DrawinShop Drawings 212 01-Jun-10 10-Feb-11 3,191
DE1666 Shop Drawings for Stormwater Drainage System 212 01-Jun-10 10-Feb-11 3,191Method of SMethod of Statement 191 26-Jun-10 10-Feb-11 2,875
DE1677 Method of Statement of Stormwater Drainage System 191 26-Jun-10 10-Feb-11 2,875Drinking Water SystDrinking Water System Works 222 13-Jun-10 07-Mar-11 2,809
DesignDesign 27 13-Jun-10 13-Jul-10 148DE5750 Design for Drinking Water System (Incl. Approvals) 27 13-Jun-10 13-Jul-10 148
DE1688 Material Submittal for Drinking Water System 163 14-Jul-10 27-Jan-11 896Shop DrawinShop Drawings 158 21-Aug-10 01-Mar-11 868
DE1699 Shop Drawings for Drinking Water System 158 21-Aug-10 01-Mar-11 868Method of SMethod of Statement 163 21-Aug-10 07-Mar-11 896
DE1707 Method of Statement of Drinking Water System 163 21-Aug-10 07-Mar-11 896Utility Water SystemUtility Water System Works 222 13-Jun-10 07-Mar-11 2,809
DesignDesign 27 13-Jun-10 13-Jul-10 148DE5760 Design for Utility Water System (Incl. Approvals) 27 13-Jun-10 13-Jul-10 148
Fire FightingFire Fighting 149 19-May-10 09-Nov-10 58,105DetectionDetection System 149 19-May-10 09-Nov-10 29,052
MateriaMaterial Submittal 62 19-May-10 29-Jul-10 12,036DE13 Detection System Submittal 38 19-May-10 01-Jul-10 7,886DE14 Detection System Approval 20 04-Jul-10 29-Jul-10 4,150
ManufaManufacture Drawings 43 31-Jul-10 19-Sep-10 8,508DE25 Submittal of Detection System Manufacture Drawings 26 31-Jul-10 29-Aug-10 5,395DE25 Approval of Detection System Manufacture Drawings 15 30-Aug-10 19-Sep-10 3,113
Shop DShop Drawing 44 20-Sep-10 09-Nov-10 8,508DE24 Submittal of Detection System Shop Drawings 26 20-Sep-10 19-Oct-10 5,395DE24 Approval of Detection System Shop Drawings 15 20-Oct-10 09-Nov-10 3,113
Fire HydrFire Hydrant System 149 19-May-10 09-Nov-10 29,052MateriaMaterial Submittal 62 19-May-10 29-Jul-10 12,036
DE18 Fire Hydrant System Submittal 38 19-May-10 01-Jul-10 7,886DE18 Fire Hydrant System Approval 20 04-Jul-10 29-Jul-10 4,150
ManufaManufacture Drawings 43 31-Jul-10 19-Sep-10 8,508DE29 Submittal of Fire Hydrant System Manufacture Drawings 26 31-Jul-10 29-Aug-10 5,395DE29 Approval of Fire Hydrant System Manufacture Drawings 15 30-Aug-10 19-Sep-10 3,113
Shop DShop Drawing 44 20-Sep-10 09-Nov-10 8,508DE28 Submittal of Fire Hydrant System Shop Drawings 26 20-Sep-10 19-Oct-10 5,395DE28 Approval of Fire Hydrant System Shop Drawings 15 20-Oct-10 09-Nov-10 3,113
DE14 Spray System Submittal 38 19-May-10 01-Jul-10 3,434DE16 Spray System Approval 20 04-Jul-10 29-Jul-10 1,807
ManufaManufacture Drawings 43 31-Jul-10 19-Sep-10 3,705DE25 Submittal of Spray System Manufacture Drawings 26 31-Jul-10 29-Aug-10 2,349DE25 Approval of Spray System Manufacture Drawings 15 30-Aug-10 19-Sep-10 1,355
Shop DShop Drawing 44 20-Sep-10 09-Nov-10 3,705DE25 Submittal of Spray System Shop Drawings 26 20-Sep-10 19-Oct-10 2,349DE25 Approval of Spray System Shop Drawings 15 20-Oct-10 09-Nov-10 1,355
CO2 SystCO2 System 149 19-May-10 09-Nov-10 12,650MateriaMaterial Submittal 62 19-May-10 29-Jul-10 5,241
DE16 CO2 System Submittal 38 19-May-10 01-Jul-10 3,434DE17 CO2 System Approval 20 04-Jul-10 29-Jul-10 1,807
ManufaManufacture Drawings 43 31-Jul-10 19-Sep-10 3,705DE26 Submittal of CO2 System Manufacture Drawings 26 31-Jul-10 29-Aug-10 2,349DE26 Approval of CO2 System Manufacture Drawings 15 30-Aug-10 19-Sep-10 1,355
Shop DShop Drawing 44 20-Sep-10 09-Nov-10 3,705DE25 Submittal of CO2 System Shop Drawings 26 20-Sep-10 19-Oct-10 2,349DE25 Approval of CO2 System Shop Drawings 15 20-Oct-10 09-Nov-10 1,355
Fire FightingFire Fighting 149 19-May-10 09-Nov-10 12,948DetectionDetection System 149 19-May-10 09-Nov-10 4,337
MateriaMaterial Submittal 62 19-May-10 29-Jul-10 1,815DE13 Detection System Submittal 39 19-May-10 03-Jul-10 1,199DE13 Detection System Approval 20 04-Jul-10 29-Jul-10 615
ManfacManfacture Drawings 43 31-Jul-10 19-Sep-10 1,261DE24 Submittal of Detection System Manufacture Drawings 26 31-Jul-10 29-Aug-10 800DE24 Approval of Detection System Manufacture Drawings 15 30-Aug-10 19-Sep-10 461
Shop DShop Drawings 44 20-Sep-10 09-Nov-10 1,261DE23 Submittal of Detection System Shop Drawings 26 20-Sep-10 19-Oct-10 800DE23 Approval of Detection System Shop Drawings 15 20-Oct-10 09-Nov-10 461
CO2 SystCO2 System 149 19-May-10 09-Nov-10 4,306MateriaMaterial Submittal 62 19-May-10 29-Jul-10 1,784
DE17 CO2 System Submittal 38 19-May-10 01-Jul-10 1,169DE17 CO2 System Approval 20 04-Jul-10 29-Jul-10 615
ManufaManufacture Drawings 43 31-Jul-10 19-Sep-10 1,261DE26 Submittal of CO2 System Manufacture Drawings 26 31-Jul-10 29-Aug-10 800DE26 Approval of CO2 System Manufacture Drawings 15 30-Aug-10 19-Sep-10 461
Shop DShop Drawing 44 20-Sep-10 09-Nov-10 1,261DE26 Submittal of CO2 System Shop Drawings 26 20-Sep-10 19-Oct-10 800DE26 Approval of CO2 System Shop Drawings 15 20-Oct-10 09-Nov-10 461
External PipesExternal Pipes 304 15-Apr-10 13-Apr-11 168,659,621PR1303 Delivery of External Pipes to Site 304 15-Apr-10 13-Apr-11 168,659,621
Surge VesselsSurge Vessels 306 10-May-10 10-May-11 32,183,588PR1050 Delivery of Surge Vessels to Site 306 10-May-10 10-May-11 32,183,588
Air Compressor SystAir Compressor System for Surge Vessels 152 12-May-10 06-Nov-10 13,885,397PR1273 Delivery of Air Compressor to Site 152 12-May-10 06-Nov-10 13,885,397
Cooling Water SystemCooling Water System 201 07-Jun-10 03-Feb-11 3,416,456For VFD ConvertersFor VFD Converters 201 07-Jun-10 03-Feb-11 1,490,275
PR1110 Delivery of Cooling Water System for VSD to Site 201 07-Jun-10 03-Feb-11 1,490,275For Pump/MotorsFor Pump/Motors 201 07-Jun-10 03-Feb-11 1,926,181
PR1650 Delivery of Cooling Water System for Pump/Motors to Site 201 07-Jun-10 03-Feb-11 1,926,181Wash Water SystemWash Water System 100 03-Jul-10 27-Oct-10 39,788
PR1233 Delivery of Wash Water System to Site 100 03-Jul-10 27-Oct-10 39,788Cathodic ProtectionCathodic Protection 207 21-Aug-10 27-Apr-11 447,083
PR1140 Delivery of Cathodic Protection System to Site 207 21-Aug-10 27-Apr-11 447,083Optional ItemsOptional Items 292 20-Mar-10 03-Mar-11 7,344,095
MV Motor - Phase ShMV Motor - Phase Shift Transformers - VFD 305 20-Mar-10 19-Mar-11 40,958,874MV MotorMV Motor 281 20-Mar-10 19-Feb-11 14,853,722
PR3060 Delivery of MV Motor to Site 281 20-Mar-10 19-Feb-11 14,853,722Phase Shift TransfoPhase Shift Transformers 305 20-Mar-10 19-Mar-11 14,357,833
PR4900 Delivery of P.S Transformers to Site 305 20-Mar-10 19-Mar-11 14,357,833VFDVFD 305 20-Mar-10 19-Mar-11 11,747,318
PR4930 Delivery of VFD to Site 305 20-Mar-10 19-Mar-11 11,747,31833 KV Switch gears33 KV Switch gears 227 01-May-10 27-Jan-11 6,389,702
PR3030 Delivery of 33 KV Switchgear to Site 227 01-May-10 27-Jan-11 6,389,702UPS & Battery ChargUPS & Battery Charger 148 17-Jun-10 13-Dec-10 2,235,413
PR3210 Delivery of UPS&Battery Charger to Site 148 17-Jun-10 13-Dec-10 2,235,413Distribution TransforDistribution Transformers 103 11-Nov-10 19-Mar-11 871,545
PR3090 Delivery of Distribution Transformers to Site 103 11-Nov-10 19-Mar-11 871,545LV MCC'sLV MCC's 128 23-Sep-10 27-Feb-11 2,166,119
PR3180 Delivery of LV MCC's to Site 128 23-Sep-10 27-Feb-11 2,166,119Main Incomer Cable (Main Incomer Cable (33KV) 253 16-Jun-10 16-Apr-11 40,568,869
PR2199 Delivery of Main Incomer Cable to Site 253 16-Jun-10 16-Apr-11 40,568,869Cables & Cables TrayCables & Cables Trays 253 27-Jun-10 26-Apr-11 1,893,742
Cables TarysCables Tarys 131 27-Jun-10 30-Nov-10 645,786PR3070 Delivery of Cable Trays to Site 131 27-Jun-10 30-Nov-10 645,786
Power Cables (33 KVPower Cables (33 KV) 253 27-Jun-10 26-Apr-11 134,157PR3010 Delivery of MV Power Cables (33KV) to Site 253 27-Jun-10 26-Apr-11 134,157
Power Cables (4.16 Power Cables (4.16 KV ) 131 27-Jun-10 30-Nov-10 335,700PR3020 Delivery of MV Power Cables (4.16KV) to Site 131 27-Jun-10 30-Nov-10 335,700
LV Power CablesLV Power Cables 131 27-Jun-10 30-Nov-10 442,400PR3040 Delivery of LV Power Cables to Site 131 27-Jun-10 30-Nov-10 442,400
Control CablesControl Cables 131 27-Jun-10 30-Nov-10 335,700PR3050 Delivery of LV Control Cables to Site 131 27-Jun-10 30-Nov-10 335,700
Instrumentation & CInstrumentation & Control Packge 208 01-Feb-10 02-Oct-10 51,373,517
PR5600 Procurement of Instrumentation & Control 208 01-Feb-10 02-Oct-10 51,373,517Buildings PackageBuildings Package 241 19-Jun-10 04-Apr-11 17,214,168
HVAC of WQM HVAC of WQM Buildings 200 19-Jun-10 14-Feb-11 7,451,376PR1440 Delivery of HVAC to Site 200 19-Jun-10 14-Feb-11 7,451,376
Ventilation of PVentilation of Pump House 200 23-Jun-10 20-Feb-11 4,247,284PR1080 Delivery of Ventilation System to Site 200 23-Jun-10 20-Feb-11 4,247,284
HVAC of SubstHVAC of Substation Building 200 05-Aug-10 04-Apr-11 7,451PR1470 Delivery of HVAC to Site 200 05-Aug-10 04-Apr-11 7,451
HVAC of ElectrHVAC of Electrical Building 200 29-Jun-10 26-Feb-11 7,451PR1380 Delivery of HVAC to Site 200 29-Jun-10 26-Feb-11 7,451
HVAC of UtilityHVAC of Utility Building 200 19-Jun-10 14-Feb-11 372,569PR1410 Delivery of HVAC to Site 200 19-Jun-10 14-Feb-11 372,569
Fire FightingFire Fighting 199 31-Jul-10 28-Mar-11 5,128,036Detection SystDetection System 199 31-Jul-10 28-Mar-11 1,246,851
PR1253 Delivery of Detection Systems to Site 199 31-Jul-10 28-Mar-11 1,246,851Spray SystemSpray System 199 31-Jul-10 28-Mar-11 1,291,572
PR1263 Delivery of Spray Systems to Site 199 31-Jul-10 28-Mar-11 1,291,572CO2 SystemCO2 System 199 31-Jul-10 28-Mar-11 1,534,586
PR1283 Delivery of CO2 Systems to Site 199 31-Jul-10 28-Mar-11 1,534,586Sprinkler SysteSprinkler System 199 31-Jul-10 28-Mar-11 479,558
PR1313 Delivery of Sprinkler Systems to Site 199 31-Jul-10 28-Mar-11 479,558Fire HydrantFire Hydrant 199 31-Jul-10 28-Mar-11 575,470
PR1323 Delivery of Fire Hydrant Systems to Site 199 31-Jul-10 28-Mar-11 575,470
CO1624 Finish of Construction for Sewage System Works 0 15-Mar-11 0Civil WorkCivil Work 200 17-Jul-10 15-Mar-11 1,613,221
CO5760 Excavation of Sewege System 165 17-Jul-10 01-Feb-11 809,644CO5770 Formation Level and Compaction Test 163 28-Jul-10 10-Feb-11 128,916CO5780 Laying and Alignment of Pipes 171 29-Jul-10 22-Feb-11 453,272CO5840 Backfilling and Compaction Tests 183 01-Aug-10 10-Mar-11 131,175CO5850 Laying Warning Tape and Final Tests 4 12-Mar-11 15-Mar-11 90,212
Stormwater DrStormwater Drainage System Works 200 17-Jul-10 15-Mar-11 906,813GeneralGeneral 200 17-Jul-10 15-Mar-11 0
CO1634 Start of Construction for Stormwater Drainage System Works 0 17-Jul-10 0CO1644 Finish of Construction for Stormwater Drainage System Works 0 15-Mar-11 0
Civil WorkCivil Work 200 17-Jul-10 15-Mar-11 906,813CO5860 Excavation Storm Water System 165 17-Jul-10 01-Feb-11 421,440CO5870 Formation Level and Compaction Test 163 28-Jul-10 10-Feb-11 62,190CO5880 Laying and Alignment of Pipes 171 29-Jul-10 22-Feb-11 280,981CO5890 Backfilling and Compaction Tests 183 01-Aug-10 10-Mar-11 112,108CO5900 Laying Warning Tape and Final Tests 4 12-Mar-11 15-Mar-11 30,093
Drinking WaterDrinking Water System Works 164 14-Sep-10 31-Mar-11 272,044GeneralGeneral 164 14-Sep-10 31-Mar-11 0
CO1866 Start of Construction for Drinking Water System Works 0 14-Sep-10 0CO1877 Finish of Construction for Drinking Water System Works 0 31-Mar-11 0
Civil WorkCivil Work 164 14-Sep-10 31-Mar-11 272,044CO5910 Excavation Drinking Water System 126 14-Sep-10 14-Feb-11 108,841CO5920 Formation Level and Compaction Test 126 23-Sep-10 24-Feb-11 28,126CO5930 Laying and Alignment of Pipes 132 25-Sep-10 05-Mar-11 62,535CO5940 Backfilling and Compaction Tests 18 06-Mar-11 26-Mar-11 51,223CO5950 Laying Warning Tape and Final Tests 5 27-Mar-11 31-Mar-11 21,321
Utility Water SyUtility Water System Works 164 14-Sep-10 31-Mar-11 272,044GeneralGeneral 164 14-Sep-10 31-Mar-11 0
CO1881 Start of Construction for Utility Water System Works 0 14-Sep-10 0CO1882 Finish of Construction for Util ity Water System Works 0 31-Mar-11 0
Civil WorkCivil Work 164 14-Sep-10 31-Mar-11 272,044CO5960 Excavation of Utility Water System 126 14-Sep-10 14-Feb-11 108,841CO5970 Formation Level and Compaction Test 126 23-Sep-10 24-Feb-11 28,126CO5980 Laying and Alignment of Pipes 132 25-Sep-10 05-Mar-11 62,535CO5990 Backfilling and Compaction Tests 18 06-Mar-11 26-Mar-11 51,223CO6000 Laying Warning Tape and Final Tests 5 27-Mar-11 31-Mar-11 21,321
CO1134 Issueance of Buidling Permits for Pump House 0 22-Apr-10 0CO1204 Start of Construction for Pump House 0 24-Apr-10 0CO1214 Finish of Construction for Pump House 0 09-Jul-11 0
Sub-Structure Sub-Structure Works 230 24-Apr-10 24-Jan-11 7,707,914CO1000 Excavation Of Pump House 79 24-Apr-10 24-Jul-10 892,957CO1100 Formation Level and Compaction Test 79 04-May-10 03-Aug-10 125,975CO1110 Casting of Blinding and Curing 85 06-May-10 12-Aug-10 524,857CO1320 Casting Screed Over Water Proofing&Curing 86 16-May-10 23-Aug-10 497,857CO1330 Reinf.Steel,Shuttering Works and Casting Foundation 99 25-May-10 18-Sep-10 3,317,557CO1340 Reinf.Steel,Shuttering Works and Casting of Walls,Columns 79 24-Jul-10 24-Oct-10 1,750,057CO1120 Laying Water Proofing 212 15-May-10 24-Jan-11 598,657
Super StructurSuper Structure Works 129 18-Sep-10 22-Feb-11 1,904,308CO1350 Reinforcement Steel, Shuttering and Casting for Ground Slab 53 18-Sep-10 21-Nov-10 144,239CO1360 Reinforcement Steel, Shuttering and Casting for Columns 53 18-Sep-10 21-Nov-10 144,239CO1370 Supply and Erection of Metal Roofing System 76 22-Nov-10 22-Feb-11 1,615,831
Architectural WArchitectural Works 112 23-Feb-11 04-Jul-11 1,406,300CO1060 Instalaltion of Block Works 77 23-Feb-11 23-May-11 251,335CO1380 Instalaltion of Sandlime Bricks 77 23-Feb-11 23-May-11 208,675CO1390 Installation of Thermal Insulation 77 23-Feb-11 23-May-11 398,185CO1400 Internal Plaster 77 24-Mar-11 21-Jun-11 82,585CO1090 Installation of Doors& Windows 79 24-Mar-11 23-Jun-11 161,864CO2020 Instalaltion of Access Ladder to Roof,etc.. 19 09-Jun-11 02-Jul-11 46,080CO1410 Internal Paint 79 03-Apr-11 04-Jul-11 257,575
Steel Platform Steel Platform Works 25 23-Feb-11 23-Mar-11 226,703CO1798 Installation of Servise Platform 25 23-Feb-11 23-Mar-11 149,147CO1808 Instalaltion of Walkways & Stairs 13 09-Mar-11 23-Mar-11 77,556
CO5160 Installation of Single Fan Filtter Units for PS1 18 23-Feb-11 15-Mar-11 262,500CO5340 Installation of Duct Work PS1 18 16-Mar-11 05-Apr-11 262,500CO5580 Installation of Single Fan Filtter Units for PS2 18 16-Mar-11 05-Apr-11 262,500CO6190 Installation of Duct Work PS2 18 06-Apr-11 26-Apr-11 262,500
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D2010 2011 2012
Finish of Construction for Sewage System W
Excavation of Sewege SystemFormation Level and Compaction TestLaying and Alignment of PipesBackfilling and Compaction TestsLaying Warning Tape and Final Tests
Start of Construction for Stormwater Drainage System WorksFinish of Construction for Stormwater Draina
Excavation Storm Water SystemFormation Level and Compaction TestLaying and Alignment of PipesBackfilling and Compaction TestsLaying Warning Tape and Final Tests
Start of Construction for Drinking Water System WorksFinish of Construction for Drinking Water Sy
Excavation Drinking Water SystemFormation Level and Compaction TestLaying and Alignment of Pipes
Backfilling and Compaction TestsLaying Warning Tape and Final Tests
Start of Construction for Utility Water System WorksFinish of Construction for Util ity Water Syste
Excavation of Utility Water SystemFormation Level and Compaction TestLaying and Alignment of Pipes
Backfilling and Compaction TestsLaying Warning Tape and Final Tests
Start of Construction for Road WorksFinish of Construction for Road Work
Sub Grade PreparationFixing of Kerb Stone
PavementRoad MarkingTraffic Signs
Restoration of Existing Facitlities
Issueance of Buidling Permits for Pump HouseStart of Construction for Pump House
Finish of Construction for Pump Hou
Excavation Of Pump HouseFormation Level and Compaction TestCasting of Blinding and CuringCasting Screed Over Water Proofing&Curing
Reinf.Steel,Shuttering Works and Casting FoundationReinf.Steel,Shuttering Works and Casting of Walls,Col
Laying Water Proofing
Reinforcement Steel, Shuttering and Casting for GrouReinforcement Steel, Shuttering and Casting for Colu
Supply and Erection of Metal Roofing System
Instalaltion of Block WorksInstalaltion of Sandlime BricksInstallation of Thermal Insulation
Internal PlasterInstallation of Doors& WindowsInstalaltion of Access Ladder to RoofInternal Paint
Installation of Servise PlatformInstalaltion of Walkways & Stairs
Installation of Single Fan Filtter Units for PS1Installation of Duct Work PS1Installation of Single Fan Filtter Units for PS
Instal lation of Duct Work PS2
Al Ain Water Distribution NetworkPump Station at AARC
Data Date : 29-Oct-09 Page : 9 of 15Printed On : 05-Jan-10
DetectionDetection System 66 31-Mar-11 15-Jun-11 32,068CO1899 Installation of Detection System 66 31-Mar-11 15-Jun-11 32,068
Fire HydrFire Hydrant 87 29-Mar-11 09-Jul-11 76,963CO1908 Installation of Fire Hydrant 87 29-Mar-11 09-Jul-11 51,309CO1917 Connection with Existing Fire Hydrant 24 11-Jun-11 09-Jul-11 25,654
CO1144 Issueance of Buidling Permits for Electrical Buidl ing 0 21-Jun-10 0CO1224 Start of Construction for Electrical Building 0 18-Sep-10 0CO1404 Finish of Construction for Electrical Building 0 19-Jul-11 0
Sub-Structure Sub-Structure Works 132 18-Sep-10 26-Feb-11 1,630,632CO1001 Excavation Of Electrical Building 9 18-Sep-10 27-Sep-10 186,196CO1420 Formation Level and Compaction Test 3 28-Sep-10 30-Sep-10 27,043CO1430 Casting of Blinding and Curing 7 02-Oct-10 09-Oct-10 160,526CO1450 Casting Screed Over Water Proofing&Curing 9 11-Oct-10 20-Oct-10 185,246CO1460 Reinf.Steel,Shuttering Works and Casting Foundation 45 21-Oct-10 18-Dec-10 468,996CO1470 Reinf.Steel,Shuttering Works and Casting of Walls,Columns 46 28-Oct-10 26-Dec-10 213,846CO1440 Laying Water Proofing 113 10-Oct-10 26-Feb-11 388,782
Super StructurSuper Structure Works 82 29-Nov-10 08-Mar-11 4,171,342CO1138 Reinforcement Steel, Shuttering and Casting for Ground Slab 38 29-Nov-10 15-Jan-11 1,781,728CO1156 Reinforcement Steel, Shuttering and Casting for Columns and Staircase 9 16-Jan-11 25-Jan-11 441,477CO1166 Reinforcement Steel, Shuttering and Casting for Roof and Parapet 35 26-Jan-11 08-Mar-11 1,948,138
Architectural WArchitectural Works 79 09-Mar-11 08-Jun-11 3,527,438CO1041 Installation of Water Proof Works at roof Slab 28 09-Mar-11 10-Apr-11 153,551CO1061 Instalaltion of Block Works 28 26-Mar-11 26-Apr-11 396,000CO1071 Internal Plaster 24 09-Apr-11 05-May-11 282,360CO1571 Installation of Internal PVE Tile 9 07-May-11 16-May-11 231,360CO1581 Installation of Internal Ceramic Tile 9 07-May-11 16-May-11 64,800CO1591 Installation of Internal Terrazo Tile 9 07-May-11 16-May-11 124,800CO1601 Installation of Suspended Ceiling 9 07-May-11 16-May-11 130,080CO1480 Instalaltion of Sandlime Bricks 28 27-Apr-11 29-May-11 198,000CO1490 Installation of Thermal Insulation 28 27-Apr-11 29-May-11 846,600CO1091 Installation of Doors& Windows 29 07-May-11 08-Jun-11 112,843CO1561 Internal Paint 37 27-Apr-11 08-Jun-11 715,000CO2030 Instalaltion of Access Ladder to Roof,etc.. 29 07-May-11 08-Jun-11 272,044
CO6150 Installation of Chillers 18 11-Apr-11 01-May-11 143,640CO6160 Installation of Air Handling Units 26 25-Apr-11 24-May-11 207,480CO6170 Installation of Duct Work 34 07-May-11 14-Jun-11 271,320CO6180 Installation of Connecting Pipe Work 22 21-May-11 14-Jun-11 175,560
Fire FightingFire Fighting 63 07-May-11 19-Jul-11 237,267SprinklerSprinklers System 24 07-May-11 02-Jun-11 30,785
CO1324 Installation of Sprinklers System 18 07-May-11 26-May-11 23,089CO1334 Testing 6 28-May-11 02-Jun-11 7,696
DetectionDetection System 52 19-May-11 19-Jul-11 38,482CO1909 Installation of Detection System 52 19-May-11 19-Jul-11 38,482
Spray SysSpray System 24 07-May-11 02-Jun-11 168,000CO1888 Installation of Spray System 18 07-May-11 26-May-11 126,000CO1916 Testing 6 28-May-11 02-Jun-11 42,000
Sanitary WoSanitary Works 24 09-Apr-11 05-May-11 181,363CO1145 Installation of Gratings Cover for Drainage Channel 24 09-Apr-11 05-May-11 35,316CO1167 Erection and Installation of All Sanitary Work, incl. Toilets,etc 24 09-Apr-11 05-May-11 73,023CO1198 Erection and Installation of Watertight Cover for Emergency Exit 24 09-Apr-11 05-May-11 73,023
CO1414 Start of Construction for Transformer Foundation 0 28-Nov-10 0CO1424 Finish of Construction for Transformer Foundation 0 14-Jun-11 0
Sub-Structure Sub-Structure Works 107 28-Nov-10 05-Apr-11 328,086CO5750 Excavation Of Transformers Boxs 12 28-Nov-10 13-Dec-10 24,996CO1500 Formation Level and Compaction Test 10 05-Dec-10 16-Dec-10 10,863CO1510 Casting of Blinding and Curing 9 08-Dec-10 18-Dec-10 25,896CO1520 Laying Water Proofing 11 15-Dec-10 27-Dec-10 55,596CO1530 Casting Screed Over Water Proofing&Curing 11 16-Dec-10 28-Dec-10 22,746CO1540 Reinf.Steel,Shuttering Works and Casting Foundation 35 26-Dec-10 05-Feb-11 114,996CO1550 Reinf.Steel,Shuttering Works and Casting of Walls 50 06-Feb-11 05-Apr-11 72,996
Architectural WArchitectural Works 36 06-Apr-11 17-May-11 788,994CO1188 Epoxy Paint for Cable Duct 15 06-Apr-11 23-Apr-11 50,000CO1199 Erection and Fixing Gratings 15 06-Apr-11 23-Apr-11 205,200CO1222 Internal and External Walls Finishing 15 06-Apr-11 23-Apr-11 206,250CO1213 Erection and Installation of Gates 15 06-Apr-11 23-Apr-11 272,044CO1178 Internal Floor Painting with Oil Resistant Coating 21 24-Apr-11 17-May-11 55,500
CO2 SystCO2 System 24 18-May-11 14-Jun-11 123,142CO1344 Installation of CO2 System 18 18-May-11 07-Jun-11 92,356CO1354 Testing 6 08-Jun-11 14-Jun-11 30,785
External WorksExternal Works 28 24-Apr-11 25-May-11 725,451CO1243 Formation Level and Subgrade 10 24-Apr-11 04-May-11 181,363
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D2010 2011 2012
Instal lation of Exhust Fans
Installation of Detection System
Instal lation of Fire HydrantConnection with Existing Fire Hydran
Sanitary Installations
Issueance of Buidling Permits for Electrical BuidlingStart of Construction for Electrical Building
Finish of Construction for Electrical
Excavation Of Electrical BuildingFormation Level and Compaction TestCasting of Blinding and CuringCasting Screed Over Water Proofing&Curing
Reinf.Steel,Shuttering Works and Casting FoundatReinf.Steel,Shuttering Works and Casting of Walls
Laying Water Proofing
Reinforcement Steel, Shuttering and Casting for GReinforcement Steel, Shuttering and Casting for
Reinforcement Steel, Shuttering and Casting
Instal lation of Water Proof Works at roof SlInstalaltion of Block WorksInternal PlasterInstal lation of Internal PVE TileInstal lation of Internal Ceramic TileInstal lation of Internal Terrazo TileInstal lation of Suspended CeilingInstalaltion of Sandlime BricksInstallation of Thermal InsulationInstallation of Doors& WindowsInternal PaintInstalaltion of Access Ladder to Roof,e
Instal lation of ChillersInstallation of Air Handling Units
Installation of Duct WorkInstallation of Connecting Pipe Work
Installation of Sprinklers SystemTesting
Instal lation of Detection System
Installation of Spray SystemTesting
Instal lation of Gratings Cover for DrainagErection and Installation of All Sanitary WErection and Installation of Watertight Co
Start of Construction for Transformer FoundationFinish of Construction for Transformer
Excavation Of Transformers BoxsFormation Level and Compaction TestCasting of Blinding and CuringLaying Water ProofingCasting Screed Over Water Proofing&Curing
Reinf.Steel,Shuttering Works and Casting FounReinf.Steel,Shuttering Works and Casting o
Epoxy Paint for Cable DuctErection and Fixing GratingsInternal and External Walls FinishingErection and Instal lation of Gates
Internal Floor Painting with Oil Resistant
Installation of CO2 SystemTesting
Formation Level and Subgrade
Al Ain Water Distribution NetworkPump Station at AARC
Data Date : 29-Oct-09 Page : 10 of 15Printed On : 05-Jan-10
CO1154 Issueance of Buidling Permits for 33KV Substation 0 05-Jul-10 0CO1434 Start of Construction for 33KV Substation 0 06-Jul-10 0CO1444 Finish of Construction for 33KV Substation 0 04-Jul-11 0
Sub-Structure Sub-Structure Works 107 06-Jul-10 08-Nov-10 663,310CO1101 Excavation Of Substation Building 17 06-Jul-10 25-Jul-10 134,665CO1560 Formation Level and Compaction Test 4 26-Jul-10 29-Jul-10 80,043CO1570 Casting of Blinding and Curing 2 31-Jul-10 01-Aug-10 42,465CO1610 Laying Water Proofing 5 08-Aug-10 12-Aug-10 95,145CO1580 Casting Screed Over Water Proofing&Curing 5 09-Aug-10 14-Aug-10 71,265CO1590 Reinf.Steel,Shuttering Works and Casting Foundation 17 21-Aug-10 08-Sep-10 148,665CO1600 Reinf.Steel,Shuttering Works and Casting of Walls,Columns 51 09-Sep-10 08-Nov-10 91,065
Super StructurSuper Structure Works 90 09-Nov-10 01-Mar-11 1,658,275CO1176 Reinforcement Steel, Shuttering and Casting for Columns and Staircase 52 09-Nov-10 15-Jan-11 340,668CO1186 Reinforcement Steel, Shuttering and Casting for Roof and Parapet 38 16-Jan-11 01-Mar-11 1,317,607
Architectural WArchitectural Works 98 02-Mar-11 23-Jun-11 1,283,580CO1051 Installation of Water Proof Works at roof Slab 26 02-Mar-11 31-Mar-11 300,801CO1131 Instalaltion of Block Works 25 02-Apr-11 30-Apr-11 94,141CO1630 Instalaltion of Sandlime Bricks 25 02-Apr-11 30-Apr-11 91,501CO1620 Installation of Thermal Insulation 25 02-Apr-11 30-Apr-11 185,301CO1611 Internal Plaster 22 23-Apr-11 17-May-11 56,686CO1621 Installation of Doors& Windows 22 18-May-11 12-Jun-11 101,392CO2040 Instalaltion of Access Ladder to Roof,etc.. 22 18-May-11 12-Jun-11 221,103CO1631 Internal Paint 43 03-May-11 21-Jun-11 161,101CO1641 Installation of Internal PVE Tile 20 01-Jun-11 23-Jun-11 71,551
CO6110 Installation of Chillers 18 05-Apr-11 25-Apr-11 15,000CO6120 Installation of Air Handling Units 18 19-Apr-11 09-May-11 15,000CO6130 Installation of Duct Work 30 18-May-11 21-Jun-11 25,000CO6140 Installation of Connecting Pipe Work 18 01-Jun-11 21-Jun-11 15,000
Fire FightingFire Fighting 52 04-May-11 04-Jul-11 147,513Sprinkler Sprinkler System 24 18-May-11 14-Jun-11 33,351
CO1364 Installation of Sprinklers System 18 18-May-11 07-Jun-11 25,013CO1374 Testing 6 08-Jun-11 14-Jun-11 8,338
CO2 SystCO2 System 24 18-May-11 14-Jun-11 82,094CO1384 Installation of CO2 System 18 18-May-11 07-Jun-11 61,571CO1394 Testing 6 08-Jun-11 14-Jun-11 20,524
DetectionDetection System 52 04-May-11 04-Jul-11 32,068CO1923 Installation of Detection System 52 04-May-11 04-Jul-11 32,068
Drainage WoDrainage Works 14 01-Nov-10 20-Nov-10 44,257CO1921 Instalation of Drainage System 14 01-Nov-10 20-Nov-10 44,257
GeneralGeneral 292 22-Jul-10 09-Jul-11 0CO1164 Issueance of Buidling Permits for WQM.01 0 22-Jul-10 0CO1454 Start of Construction for WQM.01 0 24-Jul-10 0CO1464 Finish of Construction for WQM.01 0 09-Jul-11 0
Sub-StructuSub-Structure Works 64 24-Jul-10 06-Oct-10 221,103CO1231 Excavation Of WQM Buliding .01 17 24-Jul-10 11-Aug-10 41,814CO1640 Formation Level and Compaction Test 16 27-Jul-10 14-Aug-10 21,533CO1650 Casting of Blinding and Curing 18 01-Aug-10 21-Aug-10 9,814CO1660 Laying Water Proofing 15 14-Aug-10 30-Aug-10 96,314CO1670 Casting Screed Over Water Proofing&Curing 16 16-Aug-10 02-Sep-10 9,814CO1680 Reinf.Steel,Shuttering Works and Casting Foundation 34 28-Aug-10 06-Oct-10 41,814
Super StrucSuper Structure Works 92 07-Oct-10 29-Jan-11 552,758CO1196 Reinforcement Steel, Shuttering and Casting for Columns and Staircase 51 07-Oct-10 11-Dec-10 99,153CO1206 Reinforcement Steel, Shuttering and Casting for Roof and Parapet 41 12-Dec-10 29-Jan-11 453,605
ArchitecturaArchitectural Works 92 30-Jan-11 17-May-11 487,818CO1111 Installation of Water Proof Works at roof Slab 26 30-Jan-11 01-Mar-11 161,278CO1081 Instalaltion of Block Works 27 02-Mar-11 02-Apr-11 61,333CO1690 Instalaltion of Sandlime Bricks 27 02-Mar-11 02-Apr-11 61,333CO1700 Installation of Thermal Insulation 27 02-Mar-11 02-Apr-11 51,733CO1121 Internal Plaster 31 03-Apr-11 08-May-11 25,461CO1141 Installation of Doors& Windows 8 09-May-11 17-May-11 90,333CO1651 Internal Paint 8 09-May-11 17-May-11 27,733CO1661 Fixing Ceramic Tiles 8 09-May-11 17-May-11 8,613
CO5190 Installation of Split Units for WQM Building.01 6 18-May-11 24-May-11 467Fire FightFire Fighting 52 09-May-11 09-Jul-11 10,689
DetectDetection System 52 09-May-11 09-Jul-11 10,689CO19 Installation of Detection System 52 09-May-11 09-Jul-11 10,689
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D2010 2011 2012
Erection and Fixing Manholes Water TighLaying Kerb-StoneLaying Interlocking Pavement
Issueance of Buidl ing Permits for 33KV SubstationStart of Construction for 33KV Substation
Finish of Construction for 33KV Subs
Excavation Of Substation BuildingFormation Level and Compaction TestCasting of Blinding and CuringLaying Water ProofingCasting Screed Over Water Proofing&Curing
Reinf.Steel,Shuttering Works and Casting FoundationReinf.Steel,Shuttering Works and Casting of Walls,Co
Reinforcement Steel, Shuttering and Casting for CReinforcement Steel, Shuttering and Casting f
Instal lation of Water Proof Works at roof SlaInstalaltion of Block WorksInstalaltion of Sandlime BricksInstal lation of Thermal InsulationInternal Plaster
Installation of Doors& WindowsInstalaltion of Access Ladder to Roof,eInternal PaintInstallation of Internal PVE Tile
Formation Level and SubgradeLaying Kerb-StoneLaying Interlocking Pavement
Installation of ChillersInstallation of Air Handling Units
Instal lation of Duct WorkInstal lation of Connecting Pipe Work
Installation of Sprinklers SystemTesting
Installation of CO2 SystemTesting
Instal lation of Detection System
Instalation of Drainage System
Issueance of Buidl ing Permits for WQM.01Start of Construction for WQM.01
Finish of Construction for WQM.01
Excavation Of WQM Buliding .01Formation Level and Compaction TestCasting of Blinding and CuringLaying Water ProofingCasting Screed Over Water Proofing&Curing
Reinf.Steel,Shuttering Works and Casting Foundation
Reinforcement Steel, Shuttering and Casting for CoReinforcement Steel, Shuttering and Casting for
Installation of Water Proof Works at roof SlabInstalaltion of Block WorksInstalaltion of Sandlime BricksInstallation of Thermal Insulation
Internal PlasterInstal lation of Doors& WindowsInternal PaintFixing Ceramic Tiles
Laying Interlocking Pavement
Installation of Split Units for WQM Buildi
Instal lation of Detection System
Al Ain Water Distribution NetworkPump Station at AARC
Data Date : 29-Oct-09 Page : 11 of 15Printed On : 05-Jan-10
CO1174 Issueance of Buidling Permits for WQM.02 0 22-Jul-10 0CO1474 Start of Construction for WQM.02 0 24-Jul-10 0CO1484 Finish of Construction for WQM.02 0 09-Jul-11 0
Sub-StructuSub-Structure Works 64 24-Jul-10 06-Oct-10 221,103CO1381 Excavation Of WQM Buliding .02 17 24-Jul-10 11-Aug-10 41,814CO1710 Formation Level and Compaction Test 16 27-Jul-10 14-Aug-10 21,533CO1720 Casting of Blinding and Curing 18 01-Aug-10 21-Aug-10 9,814CO1730 Laying Water Proofing 15 14-Aug-10 30-Aug-10 96,314CO1740 Casting Screed Over Water Proofing&Curing 16 16-Aug-10 02-Sep-10 9,814CO1750 Reinf.Steel,Shuttering Works and Casting Foundation 34 28-Aug-10 06-Oct-10 41,814
Super StrucSuper Structure Works 92 07-Oct-10 29-Jan-11 552,758CO1216 Reinforcement Steel, Shuttering and Casting for Columns and Staircase 51 07-Oct-10 11-Dec-10 99,153CO1226 Reinforcement Steel, Shuttering and Casting for Roof and Parapet 41 12-Dec-10 29-Jan-11 453,605
ArchitecturaArchitectural Works 92 30-Jan-11 17-May-11 487,818CO1151 Installation of Water Proof Works at roof Slab 26 30-Jan-11 01-Mar-11 161,278CO1161 Instalaltion of Block Works 27 02-Mar-11 02-Apr-11 61,333CO1760 Instalaltion of Sandlime Bricks 27 02-Mar-11 02-Apr-11 61,333CO1770 Installation of Thermal Insulation 27 02-Mar-11 02-Apr-11 51,733CO1171 Internal Plaster 31 03-Apr-11 08-May-11 25,461CO1181 Installation of Doors& Windows 8 09-May-11 17-May-11 90,333CO1671 Internal Paint 8 09-May-11 17-May-11 27,733CO1691 Fixing Ceramic Tiles 8 09-May-11 17-May-11 8,613
CO1184 Issueance of Buidling Permits for WQM.03 0 22-Jul-10 0CO1494 Start of Construction for WQM.03 0 24-Jul-10 0CO1504 Finish of Construction for WQM.03 0 09-Jul-11 0
Sub-StructuSub-Structure Works 64 24-Jul-10 06-Oct-10 221,103CO1471 Excavation Of WQM Buliding .03 17 24-Jul-10 11-Aug-10 41,814CO1780 Formation Level and Compaction Test 16 27-Jul-10 14-Aug-10 21,533CO1790 Casting of Blinding and Curing 18 01-Aug-10 21-Aug-10 9,814CO1800 Laying Water Proofing 15 14-Aug-10 30-Aug-10 96,314CO1810 Casting Screed Over Water Proofing&Curing 16 16-Aug-10 02-Sep-10 9,814CO1820 Reinf.Steel,Shuttering Works and Casting Foundation 34 28-Aug-10 06-Oct-10 41,814
Super StrucSuper Structure Works 92 07-Oct-10 29-Jan-11 552,758CO1236 Reinforcement Steel, Shuttering and Casting for Columns and Staircase 51 07-Oct-10 11-Dec-10 99,153CO1246 Reinforcement Steel, Shuttering and Casting for Roof and Parapet 41 12-Dec-10 29-Jan-11 453,605
ArchitecturaArchitectural Works 92 30-Jan-11 17-May-11 487,818CO1191 Installation of Water Proof Works at roof Slab 26 30-Jan-11 01-Mar-11 161,278CO1301 Instalaltion of Block Works 27 02-Mar-11 02-Apr-11 61,333CO1830 Instalaltion of Sandlime Bricks 27 02-Mar-11 02-Apr-11 61,333CO1840 Installation of Thermal Insulation 27 02-Mar-11 02-Apr-11 51,733CO1311 Internal Plaster 31 03-Apr-11 08-May-11 25,461CO1321 Installation of Doors& Windows 8 09-May-11 17-May-11 90,333CO1701 Internal Paint 8 09-May-11 17-May-11 27,733CO1711 Fixing Ceramic Tiles 8 09-May-11 17-May-11 8,613
CO1194 Issueance of Buidling Permits for Utility Buidling 0 05-Sep-10 0CO1514 Start of Construction for Utility Building 0 19-Sep-10 0CO1524 Finish of Construction for Util ity Building 0 19-Jun-11 0
Sub-Structure Sub-Structure Works 48 19-Sep-10 13-Nov-10 663,310CO1201 Excavation Of Utili ty Building 9 19-Sep-10 28-Sep-10 156,642CO1850 Formation Level and Compaction Test 4 29-Sep-10 03-Oct-10 39,300CO1860 Casting of Blinding and Curing 10 04-Oct-10 14-Oct-10 53,442CO1870 Laying Water Proofing 7 16-Oct-10 23-Oct-10 185,442CO1880 Casting Screed Over Water Proofing&Curing 7 17-Oct-10 24-Oct-10 31,042CO1890 Reinf.Steel,Shuttering Works and Casting Foundation 15 27-Oct-10 13-Nov-10 197,442
Super StructurSuper Structure Works 75 14-Nov-10 16-Feb-11 1,658,275CO1256 Reinforcement Steel, Shuttering and Casting for Columns and Staircase 45 14-Nov-10 11-Jan-11 434,976CO1266 Reinforcement Steel, Shuttering and Casting for Roof and Parapet 30 12-Jan-11 16-Feb-11 1,223,299
Architectural WArchitectural Works 93 17-Feb-11 05-Jun-11 510,536CO1331 Installation of Water Proof Works at roof Slab 26 17-Feb-11 19-Mar-11 18,191CO1341 Instalaltion of Block Works 35 20-Mar-11 28-Apr-11 168,191CO1900 Instalaltion of Sandlime Bricks 35 20-Mar-11 28-Apr-11 168,191
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D2010 2011 2012
Issueance of Buidl ing Permits for WQM.02Start of Construction for WQM.02
Finish of Construction for WQM.02
Excavation Of WQM Buliding .02Formation Level and Compaction TestCasting of Blinding and CuringLaying Water ProofingCasting Screed Over Water Proofing&Curing
Reinf.Steel,Shuttering Works and Casting Foundation
Reinforcement Steel, Shuttering and Casting for CoReinforcement Steel, Shuttering and Casting for
Installation of Water Proof Works at roof SlabInstalaltion of Block WorksInstalaltion of Sandlime BricksInstallation of Thermal Insulation
Internal PlasterInstal lation of Doors& WindowsInternal PaintFixing Ceramic Tiles
Laying Interlocking Pavement
Installation of Split Units for WQM Buildi
Instal lation of Detection System
Issueance of Buidl ing Permits for WQM.03Start of Construction for WQM.03
Finish of Construction for WQM.03
Excavation Of WQM Buliding .03Formation Level and Compaction TestCasting of Blinding and CuringLaying Water ProofingCasting Screed Over Water Proofing&Curing
Reinf.Steel,Shuttering Works and Casting Foundation
Reinforcement Steel, Shuttering and Casting for CoReinforcement Steel, Shuttering and Casting for
Installation of Water Proof Works at roof SlabInstalaltion of Block WorksInstalaltion of Sandlime BricksInstallation of Thermal Insulation
Internal PlasterInstal lation of Doors& WindowsInternal PaintFixing Ceramic Tiles
Laying Interlocking Pavement
Installation of Split Units for WQM Buildi
Instal lation of Detection System
Issueance of Buidling Permits for Utility BuidlingStart of Construction for Utility Building
Finish of Construction for Util ity Buildin
Excavation Of Utili ty BuildingFormation Level and Compaction TestCasting of Blinding and CuringLaying Water ProofingCasting Screed Over Water Proofing&Curing
Reinf.Steel,Shuttering Works and Casting Foundation
Reinforcement Steel, Shuttering and Casting for CReinforcement Steel, Shuttering and Casting fo
Installation of Water Proof Works at roof SlabInstalaltion of Block WorksInstalaltion of Sandlime Bricks
Al Ain Water Distribution NetworkPump Station at AARC
Data Date : 29-Oct-09 Page : 12 of 15Printed On : 05-Jan-10
CO1534 Start of Construction for Air Compressor Shelter Foundation 0 31-Jul-10 0CO1544 Finish of Construction for Air Compressor Shelter Foundation 0 23-Dec-10 0
SubstructureSubstructure 120 31-Jul-10 23-Dec-10 434,184CO5650 Air Compressors Foundation Works 120 31-Jul-10 23-Dec-10 434,184
CO1554 Start of Construction for Surge Vessel Foundation 01 0 19-Sep-10 0CO1564 Finish of Construction for Surge Vessel Foundation 01 0 22-Dec-10 0
Sub-Structure Sub-Structure Works 77 19-Sep-10 22-Dec-10 260,000CO1002 Excavation Of Surge Vessel 9 19-Sep-10 28-Sep-10 35,000CO1920 Formation Level and Compaction Test 4 29-Sep-10 03-Oct-10 10,000CO1930 Casting of Blinding and Curing 4 04-Oct-10 07-Oct-10 50,000CO1940 Laying Water Proofing 5 14-Oct-10 19-Oct-10 15,000CO1950 Casting Screed Over Water Proofing&Curing 5 16-Oct-10 20-Oct-10 25,000CO1960 Reinf.Steel,Shuttering Works and Casting Foundation 46 25-Oct-10 22-Dec-10 125,000
Architectural WArchitectural Works 11 11-Dec-10 22-Dec-10 25,000CO1303 Finishing and Painting Works 11 11-Dec-10 22-Dec-10 25,000
CO1574 Start of Construction for Surge Vessel Foundation 02 0 19-Sep-10 0CO1584 Finish of Construction for Surge Vessel Foundation 02 0 22-Dec-10 0
Sub-Structure Sub-Structure Works 77 19-Sep-10 22-Dec-10 260,000CO1032 Excavation Of Surge Vessel 9 19-Sep-10 28-Sep-10 35,000CO1970 Formation Level and Compaction Test 4 29-Sep-10 03-Oct-10 10,000CO1980 Casting of Blinding and Curing 4 04-Oct-10 07-Oct-10 50,000CO1990 Laying Water Proofing 5 14-Oct-10 19-Oct-10 15,000CO2000 Casting Screed Over Water Proofing&Curing 5 16-Oct-10 20-Oct-10 25,000CO2010 Reinf.Steel,Shuttering Works and Casting Foundation 46 25-Oct-10 22-Dec-10 125,000
Architectural WArchitectural Works 11 11-Dec-10 22-Dec-10 25,000CO1316 Finishing and Painting Works 11 11-Dec-10 22-Dec-10 25,000
CO5310 Installation of Pump House Pipes and Valves 161 28-Dec-10 06-Jul-11 469,817External PumpExternal Pump House 221 05-Oct-10 27-Jun-11 31,387,953
CO5320 Installation of External Pipes and Valves 221 05-Oct-10 27-Jun-11 31,387,953Cooling Water SysteCooling Water Systems 54 07-May-11 09-Jul-11 641,900
For VFDFor VFD 54 07-May-11 09-Jul-11 280,000CO5630 Installation of Chillers 27 07-May-11 06-Jun-11 86,897CO5640 Installation of Pipe Work 33 21-May-11 27-Jun-11 106,207CO5660 Installation of Heatexchanger for VFD 27 07-Jun-11 09-Jul-11 86,897
For Pump/MotoFor Pump/Motors 43 09-May-11 27-Jun-11 361,900CO5420 Installation of Circulation Pipe Work(Primiray Cycle) 19 09-May-11 30-May-11 61,394CO5430 Installation of Circulation Pumps(Primiray Cycle) 18 23-May-11 12-Jun-11 58,163CO5440 Installation of Heatexchanger 18 23-May-11 12-Jun-11 58,163CO5450 Installation of Circulation Pipe Work(SecondryCycle) 19 06-Jun-11 27-Jun-11 61,394CO5710 Installation of Circulation Pumps(SecondryCycle) 19 06-Jun-11 27-Jun-11 61,394CO5720 Installation of Expansion Tank(SecondryCycle) 19 06-Jun-11 27-Jun-11 61,394
Wash Water SystemWash Water System 28 23-Feb-11 27-Mar-11 40,000CO5360 Installation of Pumps in Pump House 6 23-Feb-11 01-Mar-11 7,500CO6010 Installation of Pressure Vessel 4 02-Mar-11 06-Mar-11 5,000
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D2010 2011 2012
Instal lation of Thermal InsulationInternal PlasterInstallation of Doors& WindowsFixing Interlock FlooringInternal Paint
Instal lation of Split Unit for Uti lity Build
Instalaltion of Detection System
Sanitary Installations
Start of Construction for Air Compressor Shelter FoundationFinish of Construction for Air Compressor Shelter F
Air Compressors Foundation Works
Start of Construction for Surge Vessel Foundation 01Finish of Construction for Surge Vessel Foundation
Excavation Of Surge VesselFormation Level and Compaction TestCasting of Blinding and CuringLaying Water ProofingCasting Screed Over Water Proofing&Curing
Reinf.Steel,Shuttering Works and Casting Foundat
Finishing and Painting Works
Start of Construction for Surge Vessel Foundation 02Finish of Construction for Surge Vessel Foundation
Excavation Of Surge VesselFormation Level and Compaction TestCasting of Blinding and CuringLaying Water ProofingCasting Screed Over Water Proofing&Curing
Reinf.Steel,Shuttering Works and Casting Foundat
Finishing and Painting Works
Start of Construction for Valve ChambersFinish of Construction for Valve Cham
Construction of Valve Chambers
Preliminary Instal lation of PumpsPreliminary Alignment of Pumps
Preliminary Base Leveling&GravtingFinal Alignment
Final Gravting
Installation&Alignment of Runway BeamInstallation&Alignment of CraneThird Party Inspection Using Temp. Power S
Instal lation of Pump House Pipes an
Installation of External Pipes and Valv
Instal lation of ChillersInstallation of Pipe WorkInstal lation of Heatexchanger for VFD
Installation of Circulation Pipe Work(PriInstallation of Circulation Pumps(PrimirInstallation of HeatexchangerInstallation of Circulation Pipe Work(SInstallation of Circulation Pumps(SecoInstallation of Expansion Tank(Secon
Installation of Pumps in Pump HouseInstallation of Pressure Vessel
Al Ain Water Distribution NetworkPump Station at AARC
Data Date : 29-Oct-09 Page : 13 of 15Printed On : 05-Jan-10
CO1133 Sub Contarctor Awarding 7 16-Jun-10 23-Jun-10 42,723CO5480 Cordination to determine the Service Corridor,NOC's and Permits 26 24-Jun-10 24-Jul-10 158,684CO5490 Excavation 42 06-Sep-10 25-Oct-10 256,336CO5500 Fill ing the Sand Layer Under the Cable 34 21-Sep-10 30-Oct-10 207,510CO5510 Cable Laying,Joint and Test 43 04-Nov-10 29-Dec-10 262,439CO5520 Fill ing the Sand Layer Above the Cable and Partial Back Fil ling 43 14-Nov-10 09-Jan-11 262,439CO5530 Warning Tapes 43 23-Nov-10 15-Jan-11 262,439CO5540 Complete Back Filling 43 30-Nov-10 22-Jan-11 262,439
Variable Frequency Variable Frequency Drive 54 07-May-11 09-Jul-11 192,780CO5070 VFD Concrete Base Leveling 13 07-May-11 21-May-11 48,195CO5080 VFD Leveling & Alignment 13 22-May-11 05-Jun-11 48,195CO5180 Fixation of VFD 13 06-Jun-11 20-Jun-11 48,195CO5090 Cooling System Connection 13 23-Jun-11 09-Jul-11 48,195
Pump HousePump House 52 22-May-11 21-Jul-11 5,177CO1220 4.16 KV Cable Pulling at Pump house 6 22-May-11 28-May-11 1,071CO1200 4.16 KV Cable Tagging at Pump house 5 29-May-11 02-Jun-11 893CO1210 4.16 KV Cable Laying & Fixation at Pump house 5 04-Jun-11 08-Jun-11 893CO1230 4.16 KV Cable Termination at Pump house for MV Motor 13 07-Jul-11 21-Jul-11 2,321
ElectricalElectrical 143 01-Feb-11 19-Jul-11 13,745CO2130 4.16 KV Cable Pulling at Electrical Buidling 12 01-Feb-11 14-Feb-11 2,142CO2140 4.16 KV Cable Tagging at Electrical Buidling 10 16-Feb-11 27-Feb-11 1,785CO2150 4.16 KV Cable Laying & Fixation at Electrical Buidling 10 28-Feb-11 10-Mar-11 1,785CO2380 4.16 KV Cable Termination at Electrical Buidling for DistributionTransformer 8 28-May-11 05-Jun-11 1,428CO2400 4.16 KV Cable Termination at Electrical Buidling for VFD 20 21-Jun-11 14-Jul-11 3,570CO2160 4.16 KV Cable Termination at Electrical Buidling for P.S.Transformer 17 30-Jun-11 19-Jul-11 3,035
LV Power CablLV Power Cables 136 01-Feb-11 11-Jul-11 24,936Pump HousePump House 29 22-May-11 23-Jun-11 5,022
CO1260 LV Cable Pulling at Pump house 5 22-May-11 26-May-11 866CO1240 LV Cable Tagging at Pump house 4 28-May-11 31-May-11 693CO1250 LV Cable Laying & Fixation at Pump house 4 01-Jun-11 05-Jun-11 693CO1270 LV Cable Termination at Pump house 16 06-Jun-11 23-Jun-11 2,771
Electrical BuElectrical Building 136 01-Feb-11 11-Jul-11 9,871CO2330 LV Cable Pulling at Electrical Buidling 10 01-Feb-11 12-Feb-11 1,732CO2340 LV Cable Tagging at Electrical Buidling 8 13-Feb-11 22-Feb-11 1,385CO2350 LV Cable Laying & Fixation at Electrical Buidling 8 23-Feb-11 03-Mar-11 1,385CO2360 LV Cable Termination at Electrical Buidling for UPS 3 17-May-11 19-May-11 520CO2370 LV Cable Termination at Electrical Buidling for Distribution Transformer 8 28-May-11 05-Jun-11 1,385CO2390 LV Cable Termination at Electrical Buidling for LV MCC's 20 18-Jun-11 11-Jul-11 3,463
Utility buildiUtility building 29 26-May-11 28-Jun-11 5,022CO2170 LV Cable Pulling at Utility Building 5 26-May-11 31-May-11 866CO2180 LV Cable Tagging at Utility Building 4 01-Jun-11 05-Jun-11 693CO2190 LV Cable Laying & Fixation at Util ity Building 4 06-Jun-11 09-Jun-11 693CO2200 LV Cable Termination at Utili ty Building 16 11-Jun-11 28-Jun-11 2,771
Water QualitWater Quality Monitoring Buildings 29 23-May-11 25-Jun-11 5,022CO2250 LV Cable Pulling at WQM 5 23-May-11 28-May-11 866CO2260 LV Cable Tagging at WQM 4 29-May-11 01-Jun-11 693CO2270 LV Cable Laying & Fixation at WQM 4 02-Jun-11 06-Jun-11 693CO2280 LV Cable Termination at WQM 16 07-Jun-11 25-Jun-11 2,771
Control CablesControl Cables 136 01-Feb-11 11-Jul-11 18,922Pump HousePump House 31 22-May-11 26-Jun-11 3,599
CO1300 Control Cable Pulling at Pump house 6 22-May-11 28-May-11 697CO1280 Control Cable Tagging at Pump house 5 29-May-11 02-Jun-11 580CO1290 Control Cable Laying & Fixation at Pump house 5 04-Jun-11 08-Jun-11 580CO1310 Control Cable Termination at Pump house 15 09-Jun-11 26-Jun-11 1,741
Electrical BuElectrical Building 136 01-Feb-11 11-Jul-11 8,126CO2090 Control Cable Pulling at Electrical Buidling 20 01-Feb-11 24-Feb-11 2,322CO2100 Control Cable Tagging at Electrical Buidling 15 26-Feb-11 14-Mar-11 1,741CO2110 Control Cable Laying & Fixation at Electrical Buidling 15 15-Mar-11 31-Mar-11 1,741CO2120 Control Cable Termination at Electrical Buidling for LV MCC's 20 18-Jun-11 11-Jul-11 2,322
Utility BuildiUtility Building 31 26-May-11 02-Jul-11 3,599CO2210 Control Cable Pulling at Util ity Building 6 26-May-11 01-Jun-11 697CO2220 Control Cable Tagging at Util ity Building 5 02-Jun-11 07-Jun-11 580CO2230 Control Cable Laying & Fixation at Util ity Building 5 08-Jun-11 13-Jun-11 580CO2240 Control Cable Termination at Utility Building 15 14-Jun-11 02-Jul-11 1,741
Water QualitWater Quality Monitoring Buildings 31 23-May-11 27-Jun-11 3,599CO2290 Control Cable Pulling at WQM 6 23-May-11 29-May-11 697CO2300 Control Cable Tagging at WQM 5 30-May-11 04-Jun-11 580CO2310 Control Cable Laying & Fixation at WQM 5 05-Jun-11 09-Jun-11 580CO2320 Control Cable Termination at WQM 15 11-Jun-11 27-Jun-11 1,741