BUILDING CONSTRUCTION 1 ARC 1523PROJECT 1 : DOCUMENTATION AND ANALYSIS PREPARED BY : RENEE LIM WEI FEN (0311016) 8

Loader

Filling of soil is done on site studied instead of excavating because it is a lowline site which makes the land sloppy and earth is filled in to have a flat site wherebuildings can be set and built.

The machine used to transfer and fill soil is the loader. It is a heavy equipmentthat is versitile on moving on most soil conditions. The bucket infront helps load and fill in the areas that lacks of soil.

FILLING OF SOIL

1. Setting out of the building line.

2. Set out the base (frontage) line.

3. Set out the first right angle to the frontage line.

4. Set out the second right angle to the frontage line.

5. Set out the final (back) line.

6. Check the building setting out for square.

7. Put nails on top of the pegs.7. Put nails on top of the pegs.

8. Then run a rope around the pegs.

9. Establish a point by measuring out a setback from fence to the building line.

10. Finally establish the depth.

SETTING OUT PROCESS

Setback lines

Bucket

Corner Peg

Offset Peg

Base/ FInal Line

Right angle

3.1 EXTERNAL WORK