Top Banner
1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.
18
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

1

Warm Magnets Work Package Status

J. Bauche, TE-MSC Technical Meeting,

9th January 2014.

Page 2: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

2

Outline

Magnet work packages

Warm magnets in LINAC and HEBT

Budget

Production status- Dipoles

- Quadrupoles

- H/V correctors

Magnetic measurements

Conclusions

Page 3: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

3

Magnet Work Packages

TE/MSC/MNC

Design of magnets

Procurement in industry

Tests and electro-mechanical measurements

Installation and commissioning

TE/MSC/MM

Magnetic characterization of pre-series magnets and check of series magnets

Fiducialization of quadrupole magnets

Hall probes for on-line B field measurement on dipoles

Page 4: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

4

4 + 3* dipoles(TESLA, UK)

24 + 8* quads(ELYTT, ES)

13 + 10*H/V steerers

(ANTEC, ES)

* Options additional to baseline order

Warm Magnets in LINAC and HEBT

HEBT magnet installation schedule: starts in September 2014

Page 5: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

5

Budget

Overall envelope ~ 2 MCHF

(incl. 200 kCHF for magnetic measurements, and 300 kCHF for supporting system)

Page 6: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

6

Dipoles

Curved C-shape magnet with PFR = ½ bending angle Glued laminated yoke with welded reinforcement plates Water-cooled racetrack coils (glass fiber - epoxy insulation)

Page 7: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

7

Supply Contractual delivery dates

Manufacturing file, schedules and samples 13th December 2013

Pre-series dipole 30th May 2014

One series dipole 1st August 2014

Two series dipoles + coils 10th October 2014

Two optional series dipoles 5th December 2014

One optional series dipole 5th January 2015

1st b

eam

line

Contract placed at Tesla (lamination stamping at Righton & Sons, UK) Manufacturing file received (final iteration before approval) Raw materials ordered, tooling manufacture in progress

Dipole Production Status

- On schedule so far; magnet and tooling design convincing

- Stamping at sub-contractor to be carefully followed-up

Page 8: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

8

Quadrupoles

Glued laminated yoke reinforced with solid end-plates and tie rods

Bolted assembly of quadrants Water-cooled racetrack coils (glass fiber -

epoxy insulation)

Page 9: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

9

Supply Contractual delivery dates

Manufacturing file, schedules and samples 14th October 2013

Two pre-series quadrupoles 14th April 2014

Four series quadrupoles (batch #1) 30th May 2014

Four series quadrupoles (batch #2) 27th June 2014

Four series quadrupoles (batch #3) 25th July 2014

Four series quadrupoles (batch #4) 15th September 2014

Four series quadrupoles (batch #5) 13th October 2014

Two series quadrupoles + coils (batch #6) 27th October 2014

Four series quadrupoles (optional batch #1) 24th November 2014

Four series quadrupoles (optional batch #2) 22nd December 2014

1st b

eam

line

Quadrupole Production Status Contract placed at Elytt (lamination stamping at Omedec, FR) Manufacturing file received (final iteration before approval) Raw materials ordered, tooling manufacture in progress

- On schedule so far; transparent attitude form manufacturer- Not experienced with laminated yokes, but reactive to proposals

Page 10: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

10

H/V correctors

Compact window frame solid iron yoke

Bolted assembly Water-cooled racetrack coils (glass

fiber - polyimide - epoxy insulation)

90 mm

Page 11: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

11

Supply Contractual delivery dates

Manufacturing file, schedules and samples 7th February 2014

One pre-series H/V steerer 20th June 2014

Four series H/V steerers (batch #1) 8th August 2014

Four series H/V steerers (batch #2) 29th August 2014

Four series H/V steerers (batch #3) 19th September 2014

Four series H/V steerers (optional batch #1) 10th October 2014

Four series H/V steerers (optional batch #2) 31st October 2014

Two series H/V steerers (optional batch #3) 14th November 2014

1st b

eam

line

H/V corrector Production Status

Contract placed Kick-off meeting held Insulated copper ordered (CERN supply via Luvata (FI) and Sofilec (FR))

- Quality issues experienced on products delivered in the past

- New chance given with this contract, to be carefully followed-up

Page 12: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

12

Magnetic Measurements (1/2)

Bent flux-meter development

Magnetic measurement specification discussed with beam optics physicists need longitudinal distribution of the field

Dipole:

– Pre-series: full characterization requires Hall probe 3D mapper (LEP tool to be refurbished)

– Series: integrated field mapping with bent flux-meter

Page 13: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

13

Magnetic Measurements (2/2)

Quadrupole:

– Pre-series: need measurement of field gradient in center + longitudinal profile (3D mapping, but few points and small size)

– Series: integrated field harmonics with rotating coil (existing equipment) + fiducialization with stretched wire

H/V correctors:

– Pre-series: measurement of field longitudinal profile (3D mapping, small size) + stray field at several locations (magnetic interference)

– Series: integrated field harmonics with rotating coil (existing equipment), possibly with sampling (one magnet per batch)

Important workload from this project, can be quite challenging in terms of resources

Page 14: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

14

Magnet production– All contracts placed; budget within estimates

– Dipoles and quadrupoles: manufacturing design completed; raw materials ordered; tooling manufacture in progress

– H/V correctors: manufacturing design in progress

Technical (and schedule) risks– Dipoles: lamination stamping sub-contractor not experienced with accelerator magnets

– Quadrupoles: manufacturer unexperienced with laminated yokes

– Steerers: quality issues from manufacturer in the past

Magnetic measurements– Scope defined; standard measurements for quadrupoles and steerers

– Refurbishment / development of tooling required for dipoles

– Important workload of this project will add to the present situation

Conclusions

Page 15: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

15

Spare slides

Page 16: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

16

Dipoles

Parameters

Page 17: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

17

Quadrupoles

Parameters

Page 18: 1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.

18

H/V correctors

Parameters