PPP IN INDIAN RAILWAYS- A CASE STUDY OF PIPAVAV PORT
CONNECTIVITY
A dissertationSubmitted toPunjab University ChandigarhFor the
award ofMaster of Philosophy in Social SciencesIn partial
fulfillment for40th Advanced Professional Programme in Public
Administration(2014-15)
ByBrijesh Kumar Gupta
INDIAN INSTITUTE OF PUBLIC ADMINISTRATION (IIPA)I.P. ESTATE,
RING ROAD, NEW DELHI-110002CERTIFICATEI have the pleasure to
certify that Shri Brijesh Kumar Gupta has pursued his research work
and prepared the dissertation titled PPP In Indian Railways- A Case
Study of Pipavav Port Connectivity under my guidance and
supervision. The dissertation is the result of his own research and
to the best of my knowledge, does not contain any part of work,
which has been submitted for the award of any degree either in this
university or any other University/Deemed University without proper
citation. This is being submitted to Punjab University, Chandigarh
for the degree of Master of Philosophy in Social Sciences (M. Phil)
in partial fulfillment of the requirements for the Advanced
Professional Programme in Public Administration (APPPA) of the
Indian Institute of Public Administration (IIPA), New Delhi.
I recommend that the dissertation of Shri Brijesh Kumar Gupta is
worthy of consideration for the award of the degree of Master of
Philosophy (M. Phil) of Punjab University, Chandigarh.
(Prof. Rakesh Gupta)SupervisorIndian Institute of Public
Administration I.P. Estate, Ring Road, New Delhi-110002
AcknowledgementsI am grateful to the Indian Institute of Public
Administration and Department of Personnel and training, Government
of India for giving me this opportunity to further enhance and
enrich my skill set through participation in 40th APPPA. I have
found the programme extremely useful and enlightening even after
such long years of service. I would like to express my heartfelt
gratitude to my guide Prof. Rakesh Gupta, who has always put me at
ease, even in difficult circumstances, when I found the going
tough. He has been extremely prompt in going through the manuscript
word by word. Prof. Nand Dhameja has been the inspiring spirit
behind the study. The way he brought out various aspects of
Infrastructure management made me confident of dealing this
topic.This study would not have been possible without the active
guidance and support from officers of Ministry of Railway Shri S.
K. Pathak ED/CE, Shri Mukul Saran Mathur ED/PPP/Traffic, Shri R. C.
Rai ED/PPP/Finance and Shri Achal Khare ED/Infra/Civil. I am also
very grateful to Shri Ashish Sharma GM/CRIS for valuable
suggestions and help provided by him during writing of thesis. They
all, were very helpful and kind enough to give me access to
documents required for completing this work. Our course director
Shri Suresh Mishra and APPPA office Staff Shri Manish Rawat have
been extremely helpful and supportive during the writing of
thesis.My wife Mrs. Sunita Agarwal and my son Rishabh Gupta have
been pillar of strength during this study. They have allowed me to
work without any disturbance whatsoever and motivated me to work
harder. My son Rishabh Gupta helped me out whenever I had problems
with WORD Software. I am also thankful to Shri Mool Chand for
meticulous typing for long time.
Brijesh Kumar GuptaNew Delhi CONTENTSContentsPage
Certificate
Acknowledgements
Abbreviations
Chapter -1 Introduction
Chapter -2 Objectives & Methodology
Chapter -3 Literature Survey
Chapter -4 Private Investments
Chapter -5 Pipavav Port Rail Connectivity
Chapter -6 Analysis & Finding
Chapter -7 Conclusions
Annexure A
Annexure B
Annexure C
Annexure D
Annexure E
Bibliography
AbbreviationsBOT Build Operate and Transfer
BBOBuy Build Operate
BOOBuy Own Operate
BOOTBuild Own Operate Transfer
BLOTBuild Lease Operate Transfer
CAConcession Agreement
CAGRCompounded Annual Growth Rate
CCCash Contract
CONCORContainer Corporation of India
DBDesign and Build
DBFODesign Build Finance Operate
DBFOTDesign Build Finance Operate Transfer
DPDelivery Period
FDIForeign Direct Investment
GDPGross Domestic Product
GOIGovernment of India
GPPLGujarat Pipavav Port Limited
MCAModel Concession Agreement
MORMinistry of Railways
NPMNew Public Management
O & MOperation & Maintenance
PCPlanning Commission
PFIPrivate Finance Initiative
PRCLPipavav Railway Corporation Limited
PPPPublic Private Partnership
RPFRequest for Proposal
RFQRequest for Qualification
SPVSpecial Purpose Vehicle
VGFViability Gap Funding
WBWorld bank
Chapter 1INTRODUCTION
Indian Railways, the worlds third largest railway network has
suffered due to lack of sufficient investment and populist policies
of subsidising the fares. Lack of investments has turned once a
mighty system into a slow and congested network, that crimps the
economic growth. Indian Railways, an engine of economic growth of
the country requires continuous infusion of funds and technology
for its infrastructure and modernization. In order to arrange the
sufficient funds for investment in infrastructure, Minister of
Railways in his budget speech in Indian parliament in 2014 has
announced that bulk of future projects requiring bulk investments
in IR will be executed on PPP model.Indian railways (IR) started
its 53 km journey between Mumbai and Thane on April 16, 1853 and is
today one of the largest Railways in the world. The railway
network, invariably referred to as the lifeline of the Indian
economy. is spread over 109,221 Km. covering 6906 stations.
Operating on three gauges, trains in India carry over 481 Billion
Tonne Kilometres (BTKMs) and 695 Billion Passenger Kilometres
(BPKMs) of goods and passenger traffic respectively every year. IR
carries around 40% of freight traffic and 20% of the passenger
traffic in the countryIR is one of the premier infrastructural
wings of the economy ,builds and maintains infrastructure assets
like Track, Electric traction, Signalling Systems, Telecom network,
Stations / Terminals etc. Apart from operating goods and passenger
trains, it operates suburban trains in various metros. It
manufactures locomotives, coaching stock, wagon and components of
rolling stock like Wheel & Axle. It runs workshops to maintain
its rolling stock & is also involved in ancillary activities
like catering, tourism etc.
1.1 PPP initiative in PastThe current legal framework under the
Railways Act 1989 allows private railway systems in all forms.
However, the government policy enunciated under Industrial Policy
Resolution of 1991 as amended from time to time, reserves railway
transportation for the public sector. It means that train operation
can only be done by the public sector, while all other activities
of design, construction, financing, and maintenance can be
undertaken through private participation through award of
concessions by Government of India. Presently, the Railways are
managed through 17 Railway Administrations which are legal
entities. In addition there are six port and other railways. These
railway systems are members of the Indian Railway Conference
Association, a body which deals with issues of inter railway
movement of wagons and locomotives such as levy of hire charges for
use of rolling stock belonging to other railways and neutral train
examination for ensuring that railways do not pass on deficient
wagons to other railways.The Railway Board was constituted under
the Railway Board Act, 1905 and it is also a railway regulator,
dealing with a large number of issues including tariff regulation.
Railway Board and the Commissioner of Railway Safety, whose office
is under administrative control of Ministry of Civil Aviation,
jointly work as safety regulator. There are only two kinds of rail
systems that lie outside the integrated IR network. The first
includes the close circuit systems that is, the Merry- Go-Round
systems created and operated by the NTPC for super thermal power
plants. The other kind includes standalone metro rail systems which
are planned for and financed by the Ministry of Urban Development.
The private sector has been largely associated in design,
financing, construction, and maintenance of fixed infrastructure in
railways. Construction activity in rail sector is normally
undertaken by the private sector through contracts. However, no
large Engineering Procurement and Construction contracts are being
awarded to Construction Supervision Consultants. Design, build,
finance, maintain, and operate concessions are being given to SPVs,
which are JVs between IR and private sector strategic
partners.Unlike ports, highways & airports, where a regulator
offers certain level of stable returns to private investors,
railways by virtue of their monopolistic nature of operation, do
not offer an alternative to customers among various Railways. The
tariff policy is also fixed by the Government. There is thus a need
for separate accounting for infrastructure and train operations for
initiating any long term PPP regulatory framework. 28. It would
thus be seen that Ministerial, commercial, and regulatory powers
are vested with a single entity. While it is possible for other
infrastructure projects in ports, highways & airports to be an
independent system which could be operated and maintained
independently of the existing system, the same is not possible for
Railways. Here any project has to be supplementary or an extension
to an existing larger railway network. Due to this historical
perspective, railway activities are not readily available to
private sector which poses a new challenge of building capacity
with private sector through PPPDuring the XI FYP, the share of the
private investment in major infrastructure sectors is: electricity
(49%), telecom (80%), roads (20%), ports (81%) and airports (64%).
In contrast, share of the private investment in railways has been
negligible (5%).1.2 Risks in PPPA project under PPP mode may be
subjected to a number of technical, environmental, economic and
political risks particularly in developing countries and emerging
markets. Financial institutions and project sponsors may
occationally find that the risks inherent in project development
and operation are unacceptable. To cope with these risks, projects
in these industries (such as power plants or railway lines) are
generally completed by a number of specialist companies operating
in a network with each other that allocates risk in a way that is
proportional to their exposure to the project.Infrastructure
projects have at least three phases, namely preparation and
promotion, construction and operating phase. Thus, task of the
project management is to find a way to mitigate these phase
specific risks . The key issue of the promotion and preparation
stage is the commercial and political risks related to the
procurement .The major risks in different infrastructure project
are summarized below in the table.
Phase namePrimary riskRisk subgroups
Promotion and preparing phaseCommercial and political
riskCompetitiveness risk,legislative delay risk
Construction phaseConstruction and political riskTechnological
risk, Supply risk,Regulatory risk, Government intervention risk
Operating phaseCommercial and political riskDemand risk, Revenue
risk, Technological risk, Government intervention risk
1.2.1 Preparation and promotion phase
The success of this stage is highly dependent on how government
arranges the procurement of PPP project. The ultimate goal is to
have competitive and short procurement. High competition lowers the
total cost of PPP project for the government. Secondly, short
procurement means cost savings for both public and private
sector.Government can make procurement more efficient by preparing
project well in advance. In this way, government can speed up the
procurement process. Government can also help competition by making
procurement process transparent, providing clear bidding criteria
and avoiding legislative delays.Before announcing procurement,
government should consider carefully what exactly is needed to be
achieved by PPP. The aim of the project should be crystal clear for
the government, because only then negotiations with a private
sector can go immediately into details. Also, clarity over PPP
project objectives should exist among the public authorities. Well
defined project proposal including full scope and objectives of the
project is likely draw more attention among the private sector
actors than vague and unclear project description.Moreover, the PPP
project should have full support of government, without political
unity exists, problems are likely occur in the procurement process.
Lack of political support can cause legislative delays. For
instance, difficulties may appear while PPP company is applying for
necessary legal permissions for the project from various government
offices.In sum, the commercial and political risks are always
present in the preparation and promotion phase. Thus, the key
behind the successful outcome of this phase is governments strong
political engagement and unity over project objectives in
procurement process, and competitive procurement.1.2.2 Construction
phaseThe risk of construction phase is that project will not be
completed on time and for the price stated in contract. The
availability problems and increased price of input supplies may
incur extra costs on project. In addition, delivery of supplies may
not arrive in time for the construction. Moreover, one of the
sub-contractors may pull out of the pack and leave the project
causing severe damage to other parties. Sub-contractors might not
perform as expected resulting in delays on the project. Moreover,
government may partly delay construction work by demanding certain
assessments during the construction and halting the work. In sum,
project management is facing construction and political risks on
construction phase. To overcome these risks project management
should avoid cost overruns and delays.1.2.3 Operating
phaseOperating phase includes political and commercial risks. Here,
the risks comprise mainly technical, market and regulatory risks,
which may effect on returns. The main source of the revenue in
railway partnerships is usually the operating payments; passenger
service fees, cargo tolls, license fees, provisions and government
subsidies. Cuts and disruptions in service are likely to effect
negatively on the revenue. Indeed, customers might change their
type of transportation if they cannot account on it.The change in
government policies may cause remarkable expenses for the private
sector. For instance, new safety regulations increasing the safety
standards may force private sector to reform some of its railway
assets. Even small changes in signaling systems may lead into
replacement of whole signaling system and cost fortunes for the
private sector.In the operating phase in particular commercial risk
is significant. A private sector provider of infrastructure must be
able to generate sufficient operating profits to repay private
sector contributions to financing. Predictability of the future
revenues is, therefore, of crucial importance particularly in PPPs
which include very time-consuming construction period where a
strong negative cash flow appears during the long construction
period. After the start of the operation period, cash flow grows
slowly due to large interest payments1.3 Windfall gains/ losses
These are gains/losses which occur due to unforeseen circumstances
in a service may be due to unexpected demand or due to change in
government regulation since these profits/gains are unforeseen
hence there is no uniform formula to distribute these gains/losses
among the various stakeholders. Up till now no provisions are made
in the contract for the windfall gains/losses however in recently
issued document Overview of Framework for Participative Models of
Rail Connectivity and Domestic & Foreign Direct Investment for
BOT Model it is brought out that in case actual user fee in a
particular year is in excess of 120% or 150% of the projected
revenue, 50% or 75% of the excess revenue respectively will be paid
to MoR by the concessionaire. This system has in built incentive
for the concessionaire to make efforts to bring more revenue.
Chapter 2Objectives & Methodology
2.1 Objective of ResearchBalancing of the risk among the
different stakeholders according to their responsibilities and
shared equity as decided by various provisions of concession
contracts is of utmost importance for the success of any PPP
projects. On the basis of projected investment for initial scope of
work to be provided by different stakeholders and projected likely
revenues to be shared during the different phases of project
construction and operation are normally covered under the
provisions of concessionaire contract. However, it has been
observed there are huge uncertainties in the original projected
estimates of investments for meeting their obligations and
availability of projected revenues during the execution and
operation of PPP projects, hence it is quite imperative that
necessary provisions are included in concession contracts for
sharing windfall gains/losses which cannot be foreseen at the time
of formulation of project proposal. These provisions will not only
satisfy different stakeholders to share uncertain risks/revenues at
various stages of project execution and maintenance but also
necessary for maintaining transparency requirements which are very
important involving the public agencies like IR. Proper drafting of
provisions for sharing windfall gains and losses will ensure
building trust and confidence among the various stakeholders of the
PPP project, hence, these are very important for the success of
these projects undertaken by agencies from using the public
funds.
The process of the PPP project is often itself a learning
process for many organizations. Thus, it is important to look
already established PPP projects under magnifying class to identify
potential pitfalls to avoid them in future. The aspect of learning
from PPP projects makes case studies very valuable for all
governments planning to reform railway sector . Study of PRCL rail
connectivity project involves a systematic approach for a better
railway PPP mechanisms and methods, with the expectation that these
can improve future results. Provisions of PRCL concessionaire
agreement are scrutinized with an objective to identify the most
efficient ways of mitigating the risks and overcome challenges
specific to ppp projects .We try to identify those mechanisms,
techniques, elements and principles behind the success or failure
to overcome these specific challenges.
2.2 Research QuestionsIn view of above an attempt was made to
study the answer of following questions.a) How risk sharing and
revenue sharing are balanced in concession agreement between PRCL
and Indian Railways.b) Are the existing provisions in PRCL
concession agreement are adequate to take care uncertainties due to
wind fall gains/losses. If not, what are problems faced in this
regard during construction and operation of a rail connectivity
project of Pipavav port in Gujarat c) What are suggested provisions
to taking care uncertainties due to windfall gains/losses during
concessionaire period?
2.3 MethodologyRelevant documents pertaining to rail
connectivity project of Pipavav port in Gujarat on Indian railways
were collected in regards conceptualization, construction phase,
operation phase and other aspects like maintenance etc. All these
details will be analyzed on the basis of actual problems faced in
pipavav port connectivity project financed by arranging the
investments through PPP model.2.4 LIMITATIONSThe concept of
public-private partnership encompasses a variety of different
partnerships and relationships, which are not covered fully in the
thesis. The paper focuses on one particular case study of PPP JV
model port connectivity project, within which the topic is analyzed
.To get generalized conclusion it is pertinent that results of
numbers of PPP projects are studied , hence this is a
limitation.
CHAPTER 3LITERATURE SURVEYIt is widely acknowledged within the
relevant literature that there is no clear definition for PPP which
would cover all aspects of different relationships that these PPPs
encompass (Daube, Vollrath, & Alfen, 2007; Hodge & Greve,
2007; OECD, 2008) and at the same time restricting it to a more
narrow description. As Weihe (2006) argues, the concept of PPP is
nebulous it allows for great variance across parameters such as
time, closeness of cooperation, types of products/services, costs,
complexity, level of institutionalization as well as number of
actors involved, as a result, nearly any type of the relationships
that include both the private and the public sector (whether it is
a service contract or a joint venture) may be called a
public-private partnership (PwC, 2005). In order to make some
distinction between the variety of definitions present, Weihe
(2006) attempted to classify them into 5 categories: local
regeneration, policy, infrastructure3, development and governance
approaches. The local regeneration and the policy approaches are
similar due to perceiving PPP concept as a very wide definition
that covers changes in policies of environment, economic renewal,
development, and institutional set up. The difference between the
two is that the local regeneration approach focuses on the local
level while policy approach on the national. The third approach the
infrastructure approach covers the cooperation of private and
public sector in order to create and maintain infrastructure, as
well as deal with the financial and legal aspects of such projects.
The fourth approach the development approach concentrates on the
development of infrastructure in developing countries where
corruption, social deprivation, global disasters are present. This
approach includes many forms of cooperation between the public and
private sectors such as strategic or entrepreneurial partnerships.
The last approach is the governance approach which does not specify
any context or policy as it emphasizes on organizational and
management side, as well as new ways of cooperation and governing.
For the purpose of this thesis, the concept of PPP will be limited
to the infrastructure approach.3.1 DEFINITIONEven thought the
concept has been narrowed down, there are still many definitions
explaining what a PPP is under the approach chosen. For example,
the European Commission (2004, p. 3) defines PPPs as forms of
cooperation between public authorities and the world of business
which aim to ensure the funding, construction, renovation,
management or maintenance of an infrastructure or the provision of
a service; whereas OECD (2008, p. 12) defines it as an arrangement
between the government and one or more private partners (which may
include the operators and the financers) according to which the
private partners deliver the service in such a manner that the
service delivery objectives of the government are aligned with the
profit objectives of the private partners and where the
effectiveness of the alignment depends on a sufficient transfer of
risk to the private partners. Further examples of definition
include the one proposed by IMF (2006, p. 1) that explains the
concept as the arrangements where the private sector supplies
infrastructure assets and infrastructure-based services that
traditionally have been provided by the government, and EIB (2004,
p. 2) that views PPP as a relationship of the two sectors which has
an aim of introducing private sector resources and/or expertise in
order to help provide and deliver public sector assets and
services... used to describe a wide variety of working arrangements
from loose, informal and strategic partnerships, to design build
finance and operate (DBFO) type service contracts and formal joint
venture companies. An overview of the PPP definitions under the
variety of international organizations draws someConclusions on the
basic set of features that characterise PPP under the
infrastructure approach: long term contractual arrangement between
the public and private sector; functions are bundled;
responsibility for the provision of the services is shared;
resources are shared: the private sector brings in capital, skills,
experience, commercial innovation, etc.; the public sector delivers
skills, political authority, access to publicly run services,
assets, etc.; risks and rewards are shared.In order to understand
the PPP concept fully, it is also useful to distinguish it from the
traditional procurement mode. The reason for this is that the
boundaries between the two modes are ambiguous. In order to remove
this ambiguity the main differences between the two modes are
identified and explained.First of all, the main differentiating
point between PPP and traditional procurement is that in PPPs risks
are shared between the private and public partners whereas in a
conventional procurement most of the risks are retained by the
government4 (European Commission, 2005; OECD, 2008) . This is in
line with the functions included in the contracts. In a PPP
different tasks are bundled together and, as a result, private
partner takes responsibility for the whole package of the
associated risks. In the conventional procurement, on the other
hand, the government usually purchases a single function from a
private partner and, as a result, the private partner is
responsible only for the risks associated with this function.
Consequently, in the traditional procurement the private partner
has no incentives to incorporate decisions that may favour future
operations as after completion of the task, the private partner is
no longer involved in the operations of the asset/service. For
instance, if the government proposed a tender to deliver a package
of services, such as design, build and maintain a facility, the
private partner involved would be incentivized from the very
beginning to make decision that could minimize the future risks
associated with cost overruns. Such an example has been identified
in the international experience by Grimsey and Lewis (2004, p.
135), where an innovative decision to construct 45-degrees
windowsills in UK hospital was proposed with an intention to save
future cleaning costs. It is hardly likely that such a decision
would have been made in the conventional procurement case. A
government would propose a tender to design a facility with input
requirements already specified. The specific requirements can be
seen as a frame from the private partners point of view as these
requirements restrict private partner to innovate and come up with
more efficient solutions. The aim of the private partner
responsible for a design function is to design a facility while
incorporating all the details required and within the budget
stated. The review of function bundling and risk allocation in both
procurement cases help to determine what defines a PPP and a
traditional procurement approach.Secondly, the two modes differ
between each other when the function specification is considered.
What this means is that, in a PPP, government states what it
expects from the private partner in output terms, whereas in the
conventional procurement it does that through input specification.
Considering the aforementioned example, in a PPP case, government
might require a hospital to be big enough to accommodate 300 people
and to be kept in a good condition by clarifying what good
condition means, whereas in the conventional procurement option, a
government would request a certain size, with a certain number of
rooms, with specific materials used, etc. In the PPP case, private
partner is free to use its skills and innovation in order to
provide the outputs required in a most efficient way, whereas the
latter case does not allow such a freedom as a private sector is
restricted to the requirements specified.Thirdly, in a PPP
approach, returns to the private partner are linked to the
performance of their functions, i.e. the provision of outputs
specified by the government, whereas in a conventional procurement
approach, private partner is remunerated for the completion of a
specific function. This contributes to the level of incentives
attached to the private partner: in a PPP case, if a private
partner does not operate as expected, it might incur some sort of
penalties (Harris, 2004), if it operates better than expected, it
may be awarded by, for example, receiving higher portion of
additional profits. In a traditional procurement case, on the other
hand, private partner is not awarded for an extra value added to
the task it was responsible for, however, it might be penalized for
the uncompleted function. Considering all this, the private partner
in a traditional procurement is not encouraged to provide more than
the government requested for, which means some possible gains might
be overlooked.Fourthly, the relationships involved in both of the
procurement modes differ (OECD, 2008). In the traditional
procurement, in order to deliver the services and infrastructure
required, the government acts as an intermediary on the one side it
deals with direct users of the services, taxpayers, and financial
markets, and on the other side with other private companies. The
idea behind such a relationship structure is that the government
gathers financing directly from the users of the service, taxpayers
and financial markets, and uses it to remunerate the other side the
private companies for the capital goods provided to deliver the
public service and develope the infrastructure. If the project is
handled through a public-private partnership, the intermediary role
of the government is decreased public authority deals with the
taxpayers and the single private operator only. The role of the
private operator, on the other hand, is enhanced: private operator
becomes responsible for the intermediary role it collects financing
from the direct users of the service and financial markets and
remunerates the other side other private companies for the capital
goods provided.
3.2. TYPES OF PPPSThe spectrum of different PPPs range from the
short term service contracts to concessions. Nevertheless, as the
focus of this thesis is the concept of PPP under an infrastructure
approach, the overview of different PPP modes will be limited to
the ones that are covered by the PPP approach chosen. These modes
have common characteristics, such as: being long term, involving
risk transfer, shared responsibility, resources and rewards.In
general, private partner involvement arrangements in PPPs differ
between each other depending on the level of responsibilities and
risks transferred to the private partner (Amekudzi & Morallos,
2008). The responsibilities concerned include activities such as:
designing, building, financing, maintaining, operating, and owning
the facilities. The allocation of risks will be discussed in more
detail later in the paper; however, what matters at this point is
the amount of risks transferred and retained by the government.Most
common forms in the infrastructure approaches are: Turnkey
procurement, which includes: BOT (build-operate-transfer), BBO
(buy-build-operate), etc. (European Commission, 2003, 2005); DBFO
(Design-Build-Finance-Operate), which includes: DBOM
(designbuild-operate-maintain), BOOT (build-own-operate-transfer),
concessions, etc. (Deloitte Research, 2006; European Commission,
2005; IMF, 2004).Turnkey procurement6 is described as the scheme
where the private partner takes on the responsibility to design,
construct and operate the asset, whereas the public sector retains
the responsibility for the financial risks involved. Using this
procurement mode, public sector sets the quality outputs required
and by doing so it ensures that the private sector brings the
necessary efficiency gains as well as the asset is maintained to
the standards expected. This mode of procurement is used in water
and waste projects as it ensures incentivized management and
maintenance of the asset through the bundling of functions passed
on to the private partner (European Commission, 2005).DBFO scheme7
is characterized by involving a private partner with
responsibilities (financing, designing, building, constructing, and
operating the asset/service) attached to it. Public sectors role is
to set the specific output requirements for the private partner,
whereas private partners role is to fulfill those requirements. The
DBFO schemes are usually long term and involve bundling of
functions in order to provide private partners with the necessary
incentives for it to operate in the most efficient and innovative
way. These schemes involve performance linked payment mechanisms
with an aim to ensure the presence of motivation for the private
partner to operate on its full capacity. The idea behind such
schemes is that the private partner designs, builds, operates and
maintains the asset for the agreed term. At the end of this term,
the asset is either transferred back to the government or is left
under the ownership of the private partner depending on the
specific structure of the scheme chosen. For example, one of the
most common schemes under DBFO is concession. Concession is
described as a PPP scheme, where exclusive rights to operate an
asset or provide certain services are granted to a private company
(usually a SPV8), which in return has to design, build, finance and
operate the asset/service for the time agreed upon. These exclusive
rights usually permit the private partners to collect the revenues
from the direct users of the asset/service. Concessionaires
typically own the rights to the asset/service during the time of
concession, however, at the end of this period the ownership of the
asset/service is usually transferred back to the public sector
(Deloitte Research, 2006; European Commission, 2005; IMF, 2006).
Literature overview shows that concession is usually assumed to be
a form of PPP (Deloitte Research, 2006; European Commission, 2004;
IMF, 2006; Ng, Xie, Cheung, & Jefferies, 2007; PwC, 2005),
however, OECD (2008) argues the opposite. First of all, it states,
that the amount of risk transferred differs in PPPs and
concessions: concessions involve higher level of risks allocated to
the private partner, compared to other forms of PPPs. Secondly, it
is usual for concessionaires to collect revenues from the direct
users of the asset/service and, according to OECD, this feature
differentiates concession from other PPP forms. As a result, OECD
concludes that concessions should not be treated as a PPP. The
international experience shows that most of the time DBFO schemes
are used in transport sector for building highways, bridges,
railways, whereas concessions are chosen for mobile phone services,
toll roads or provision of municipal water.The similarities between
the turnkey procurement and DBFO schemes are that the activities
involved are same in both of the schemes, differing only in the
amount of functions involved in the arrangements. What
differentiates the two schemes is that in the first one the
majority of risks remains within the public sector, whereas in the
latter risks are shared between the partners, allowing for the
possibility to transfer the optimal amount of risks to the private
partner.3.3 REASONS FOR IMPLEMENTING PPPSThe main objective of
procuring a public project through a PPP mechanism is to achieve
value for money (VFM) (Grimsey & Lewis, 2004; Harris, 2004; New
South Wales Government; Quiggin, 2004; Shaoul, 2005) which as
Grimsey and Lewis (2005, p. 347) argue is the optimum combination
of whole life cycle costs, risks, completion time and quality in
order to meet public requirements. This definition assents to the
one implied by the European Commission (2003, p. 55) which
identifies a set of factors that determine value for money: life
cycle costs, allocation of risks, time required to implement a
project, quality of a service, and ability to generate additional
revenues. Following this, a general principal used to determine
whether a project should be implemented through a PPP or a
traditional procurement is to evaluate which procurement mode
ensures lower life cycle costs, better allocation of risks, quicker
implementation, higher quality and additional profits. In other
words, additional value for money represents additional efficiency
gains delivering or maintaining the same service or asset in a more
cost efficient or a more qualitative way than it would have been if
the government retained the full responsibility for
delivering/maintaining service/asset concerned (EIB, 2004, p. 4;
Meidute & Paliulis, 2011; Nisar, 2006). EIB (2004) argues that
the critical aspect in order to reach value for money is the
ability to share risks and rewards appropriately. OECD (2008)
confirms this view recognizing that main reasons for PPP
establishment are the appropriate risk allocation and value for
money gains9. Grimsey and Lewis (2005, p. 347), however, imply that
the value for money gains can only be achieved if the following
conditions are present: a competitive environment, optimal risk
allocation and if the comparison between the financing options is
handled in a fair, realistic and comprehensive way. Furthermore,
when questioning PPPs ability to deliver additional gains, one
should consider the qualitative benefits of PPPs whether they are
achievable and whether they really provide the benefits expected.
It is essential therefore to check whether the private partner is
capable of bringing in skills that the government lacks and whether
it has the expertise and know-how necessary to operate more
efficiently compared to the government (PwC, 2005).According to the
literature review, further reasons that lie behind the use of PPP
as a procurement mode differ between countries depending on the
environment present. For example, the main aim of a PPP at the
early stage of its development in the United Kingdom was to finance
the public infrastructure projects (Grimsey & Lewis, 2004; IMF,
2006; Meidute & Paliulis, 2011). The issue at that time
consisted of a growing need for public infrastructure development
(as it also is the case in Hong Kong (Cheung, Chan, & Kajewski,
2009)) and a lack of available public funds to finance this need.
As a result, a new initiative took place Private Finance Initiative
(PFI) with the purpose to provide additional funds for public
infrastructure projects. On the other hand, countries like
Australia do not have such an issue. They are capable of financing
projects by themselves, however, they still choose to involve the
private sector for the possibility of achieving additional value
(Cheung et al., 2009). Moreover, Hong Kong and Australia involve a
private partner into the procurement of public services with the
aim to ensure a better quality of services. This, on the other
hand, does not seem to be the prioritized reason for the PPP
development in the United Kingdom, which emphasizes the point that
reasons to implement PPP depend on the circumstances surrounding
countries economic and political environment.In many of the
countries the choice for PPPs, however, is due to financial reasons
(such as lack of public funds and restricted public investment).
This reason is amplified when a tight fiscal environment following
the development of European Monetary Union (EIB, 2004, p. 4) is
considered as due to this European countries experience
difficulties in organizing large investment sums to finance public
infrastructure projects from the public funds only.All in all, in
theory, the main reason to develop PPPs lies behind the concept of
value for money, creating additional benefits due to private
partners expertise, know-how, ability to operate efficiently and
generate additional revenues. Despite the theoretical foundations,
it is evident that PPPs are also often used in cases when there is
a lack of public funds for the growing need for public
infrastructure.3.4. VALUE FOR MONEYThe allocation and valuation of
projects risks is inherent in the value for money concept (European
Commission, 2003; Grimsey & Lewis, 2004; Nisar, 2006; Sarmento,
2010). The aim of the risk transfer is to transfer only those risks
that the private partner could offset in a most efficient and least
costly way(Grimsey & Lewis, 2004; Harris, 2004; Nisar, 2006).
Risk allocation produces highest value for money once the optimal
risk transfer point is identified: transferring too much or too
little risks results in either procuring an inefficient project or
procuring a project with excess costs incurred by the government
(for example, if risks are transferred to the private partner that
it does not have control over or cannot control it at least-cost,
then the private partner will require higher premium for these
additional risks assumed (Hodge, 2004)), consequently, producing
lower value for money (Amekudzi & Morallos,
2008).Unfortunately, there is no universal solution regarding risks
allocation for every single project, however, there is a general
agreement on how different risks should be allocated. To begin
with, risks in general are allocated to different categories, such
as, for example, proposed by OECD (2008): legal and political risks
in addition to the commercial ones. Categories are differentiated
on the basis of who takes the responsibility for the risks
concerned private partner or the government authority. For example,
construction, supply and demand side risks lie under the commercial
risk category (market risk, project risk and internal risk) as they
are handled better by the private partner, whereas legal and
political risks are assumed to be handled better by the government.
Other categorization is proposed by Li, Akintoye, and Hardcastle
(2001), who distribute risks into three levels: macro, meso and
micro. Macro level covers risks outside the project environmental,
political, legal risks that are concerned with national or industry
level. Meso level risks emerge within the projects implementation
phase design, construction, operation. Finally, the micro level
risks concern risks that appear between the partners involved, they
rest on the idea that both of the parties have different incentives
and objectives, and therefore, risks due to power struggle,
differences in working methods and environment between the partners
may emerge. 3.5. ADVANTAGES AND DISADVANTAGES OF PPPAs it has
already been reviewed, the appropriately constructed PPPs entail
the advantage of delivering better value for money compared to the
traditional procurement approach. Delivering projects on time and
on budget set (Meidute & Paliulis, 2011) are two of the most
important advantages that are hidden under the concept of value for
money. As study conducted by UKs National Audit Office (2003)
showed, from all conventionally procured projects, 70% were
delivered late and 73% with costs exceeding the initial budget
(data of 1999), whereas only 22% of PFI projects were late and only
24% delivered project in excess of the budget (data of 2002). The
reason for such a difference lies behind the risks transferred in
line with additional responsibility and accountability attached to
the private partner in the case of PPP, what incentivizes the
private partner to operate in the most efficient way. In addition,
due to the long term characteristics of the partnerships, partners
involved tend to act in a more cooperative way to each other in
this case creating additional synergy benefits. Private partner
manages complex financial arrangements as well as highly technical
tasks more efficiently by using its innovative skills, on the other
hand the public sector preferably controls the legal system,
regulation and policies. As a result, a combination of the leading
features of both of the partners produces a higher value (Harris,
2004).The other advantage of PPPs lies behind the construction of
the proposal to procure a public project. Government constructs PPP
proposals that focus more on outputs rather than inputs. As a
result, such mindset encourages government to perform a thorough
discussion on which services should be provided, what standards
should be expected, and what is the aim of the service
provided/asset developed. Such a detailed discussion on service
provision or asset development requires a detailed analysis of the
project which in some of the cases may hinder the government from
moving ahead if the project becomes inadequate. In addition, such
kind of initial discussions encourage the government to think about
the project with long term strategic goals in mind rather than
focus on short term objectives.Furthermore, PPPs ability to spread
the costs of large investments over the lifetime of the asset is
seen as an attractive advantage for the public sector. This eases
the current debt of the government sector as it does not have to
incur large cash outflows immediately. It follows, that the
government can get projects financed even though in reality there
are no public funds available. This advantage could be considered
from two points of view: first large investment costs are spread
out, and second private funds are considered as the new financing
opportunities for the government (Meidute & Paliulis, 2011). On
the other hand, this advantage should be considered with caution as
sometimes the government might be incentivized to prove better
value for money for a PPP project than it actually is just to
guarantee the financing of the project.Finally, from the private
partners point of view, PPPs deliver opportunity for the private
sector to get involved in the new markets (telecommunication,
municipal water systems, energy, etc.) that otherwise would be
closed for the private sectors participation. In addition to this,
the private partner involved in the new markets has a support of
the government, which may facilitate gathering the funds
required.On the other hand, one of the main disadvantages of PPPs
is large bidding and contractual costs, which refer both to the
government and the private partner. Large bidding costs of the PPP
projects act as a rejecting force for the private parties as they
are unwilling to invest heavily in the bidding process just to be
rejected later. What concerns government, large preparation costs
consist of feasibility studies, lawyers, etc. Moreover, PPP
projects are highly complicated. Usually, they involve more than
two parties: public, private and banking sectors, and all of these
parties have their own contradicting aims. In order to construct a
unified agreement, a lot of time and capital needs to be invested
on complex negotiations.Furthermore, PPPs are said to deliver
benefits because they transfer a significant amount of risks to the
private partner. Nevertheless, it should be kept in mind that even
though most of the risks are transferred to the private partner,
the final entity that is responsible for providing services to the
public is the government. As a matter of fact, if the private
partner goes bankrupt, solely the government has to deal with the
consequences and try to find other expedients how to keep
delivering the service to the public. This implies that even though
the risks are contractually transferred to the private partner, in
practice, government retains a large portion of them in case of the
private partners failure.Moreover, in a PPP agreement, government
bounds itself to a single private partner for a long term period
and it agrees today for services/assets that will be in use in
further future. There is a certain amount of risk concerning the
future consumers need for the specific service. The idea behind the
risks concerned is that the partnership may end up delivering
services that are no longer required by the public. As a result,
the partnership will appear to be less valuable than initially
expected.Finally, PPPs work well only for specific projects, which
are complex and require specific private partners know-how, skills,
and experience. Therefore, advantages that are attached to PPPs are
attained only if certain project characteristics are met, whereas
if the project is simple, executing it trough a PPP implies higher
preparation costs, and as a result, lower value for
money.Considering all of the above, the main idea behind the PPP
option is to have a project intricate enough that its complexity
could justify additional preparation and negotiation costs.
Developing a project through a PPP usually ensures additional
benefits such as implementing the project on time and on budget.
Nevertheless, these benefits should be considered while keeping in
mind the risks involved in having the long term agreement between
private and public sectors for a certain service provisions.3.6
CRITICISM OF PPPSEven though the majority of the international
institutions seem to favour the PPP option (EC, UK Treasury, OECD,
IMF), some of the researchers see PPPs as a language game in the
politics PPP is regarded as another way of privatizing a
service/asset (Hodge & Greve, 2007). This point of view has
been neglected by many other researchers who represent arguments
proving that PPPs differ from the privatization (Grimsey &
Lewis, 2004; Harris, 2004; Hong Kong Efficiency Unit, 2008; OECD,
2008). One of the first differences identified is the sale/transfer
concerned. PPP involves government granting a right to the private
party to develop and provide certain services/assets for a period
of time, whereas privatization, in general terms, involves the sale
of the asset. This assents to the amount of risks transferred. In
PPP case, the amount transferred differs on the type of PPP chosen.
Concession is the mode of PPP that involves the largest amount of
risks transferred to the private partner; however, it still does
not encompass the transfer of all risks. On the other hand,
privatization includes the sale of the full package, which means
the transfer of all associated risks. In this case, government is
left with no direct responsibility for the service provided/asset
developed, whereas in a PPP case, government is the one that
retains the initial control and responsibility for the
service/asset (Harris, 2004). If the private partner goes bankrupt,
the service/asset is transferred back to the government. If the
private partner does not operate to the standard required, the
government has a right to intervene and punish the private partner.
All in all, it is true that privatization and PPP share some
similarities, but the idea of PPP is that it shares some superior
features of the privatization as well as of the conventional
procurement mode as Grimsey and Lewis (2004) argue: PPP fills in
the missing gap between privatization and the traditional
procurement approach.Other critiques concentrate on the idea that
the government should be fully responsible for the services
provided as this is the role of the government and not the private
sector. However, as Harris (2004, p. 3) argues, the provision of
public services (such as free education, transportation or health)
by the government is comparatively recent development. So the
question rises whether it is the actual provision of the services
or is it the regulation and control of the service provision (what
kind of services to deliver, what kind of standard should be kept,
what policy to follow, etc.) that is the role of the government? As
Harris (2004) concludes the role of the government is to ensure
that a policy is being adopted. If delivering the policy through
the parties that are able to do that in the best possible way while
additionally creating value for money to the public means that the
private partner should be involved, then the advantages of private
partners efficiency and innovative skills should be
utilized.Further critique concerns the view that PPPs are a trendy
politics. This means that countries might favour PPPs over the
conventional procurement due to the lack of public funds available.
Owing to this, the government is left with a choice not between a
PPP and a conventional procurement project but with a choice
between a project and no project at all as a government is unable
to finance the project from its own funds (Robinson, 2000; Shaoul,
2005). The problem of such a preference for PPPs is that there is a
high degree of possibility for approval of projects that do not
generate better value for money but are accepted for the financial
resources only getting a project procured while having debt off
governments balance sheet (Maski & Tirole, 2008). In addition
to this, as value of PPPs are most of the times assessed by using
PSC, problems appear when hypothetical risk-adjusted nature of the
model is considered. The PSC depends highly on the assumptions
employed (Amekudzi & Morallos, 2008), one of the most important
one being the rate used to discount the cash flows of the PSC.
Furthermore, when risks allocation is performed, it is criticized
that not all of the risks may be identified and valued (Amekudzi
& Morallos, 2008; OECD, 2008; Shaoul, 2005), thus leading to
inaccurate PSC estimate. As OECD (2008) argues some of the risks
may be left out and neither of the party initially agrees to take
responsibility for it, however, once the risk evolves, it is the
government and the public that have to bear the consequences and
not the private partner, leaving some element of value for money
out of the initial estimate. Considering all this, the value for
money estimate may be easily adjusted in order to make the PPP
proposal more attractive, which is seen as a problem when the only
reason for PPP project implementation is the lack of public
funds.Moreover, it has been noted that an advantage of PPP is its
ability to spread out the huge initial investment costs throughout
the years of the lifetime of the asset. This means that the
government avoids large investments today and is able to incur them
later on in smaller amounts. However, who may guarantee that the
government with increasing number of PPPs will be capable of
financing these payments in later years? Will it pass this
contingent liability to the future taxpayers (Harris, 2004)? In
addition, who can be reassured that the same service/infrastructure
will be necessary in, for example, 30 years? In addition, will the
taxpayers be happy for paying taxes for the services that are
unnecessary anymore? These questions are especially relevant to the
cases of PPPs where the government contracts to pay availability
payments for the services provided by the private partner.Overall,
PPPs attract some significant critiques, however, it should be
noted that PPPs are not a magic solution for the conventional
procurement issues. The true experiences of PPPs have not been
observed yet as it takes time to acknowledge the full impact of
each PPP, however, the initial stages of the PPP and the
theoretical foundations allow PPPs to be considered as a possible
way to bring on additional efficiency gains to the public
sector.
Chapter 4Private InvestmentsThere is a growing demand for
investment to improve the quality of public services. Public
sectors or governments worldwide are experiencing significant
challenges as public resources are often insufficient to meet the
increasing demand for new infrastructure projects to facilitate and
sustain economic growth. As a result, there has been a growing and
intense debate about the respective roles of the public and private
sectors in the delivery of traditional public services. The United
Kingdom and many other developed countries in Europe, United
States, Canada, Australia, New Zealand and many developing and
middle-income countries from Asia, Latin America and the Caribbean,
Eastern Europe, Africa and the Middle East have now recognised the
importance of the private sector in the delivery of traditional
public services.There are various definitions of the term
public-private partnership (PPP). PPP is a generic term for any
type of partnership involving the public and private sectors to
provide services. It is generally a contractual arrangement where
the private sector performs some part of a public sector service
delivery responsibilities or functions by assuming the associated
risks in return for payment. A recent research paper by the World
Bank (2007) defines a PPP broadly as an agreement between a
government and a private firm under which the private firm delivers
an asset, a service, or both, in return for payments contingent to
some extent on the long-term quality or other characteristics of
outputs delivered. The Indian definition of PPP states that Public
Private Partnership (PPP) Project means a project based on a
contract or concession agreement, between a Government or statutory
entity on the one side and a private sector company on the other
side, for delivering an infrastructure service on payment of user
charges. Private Sector Company means a company in which 51% or
more of the subscribed and paid up equity is owned and controlled
by a private entity. But regardless of the definitions, the
objective is to utilise the strengths of the different parties to
improve public service delivery and should always be underpinned by
clear principles and contractual commitment reflecting a balance
between profit and the need for regulation to ensure value for
money in the use of public resources. Under a PPP approach, public
sector expertise are complemented by the strengths of the private
sector such as technical knowledge, greater awareness of commercial
and performance management principles, ability to mobilise
additional investment, innovation, better risk management
practices, and knowledge of operating good business models with
high level of efficiency. In a developing country like India, the
model of this type has enormous opportunities in the upliftment of
economy specially in infrastructural and service sectors.4.1
Evolution and Development of PPPsPublicprivate partnerships have a
long history in many countries, but grew significantly more popular
during the 1980s. At this point, private sector thinking was
introduced and used in the public sector, and market-based criteria
were applied to the delivery of public products and services.
During the 1990s, New Public Management (NPM) and market-based
philosophies further influenced public management in many
countries. Because the degree of complexity of the problems needing
to be solved increased as a result of growing interdependencies
between assignments and parties involved, more partnerships between
public and private sectors were formed.Publicprivate partnerships
have the longest tradition in the USA. In the 1950s and 1960s, PPPs
in the USA were set out by the federal government as a tool for
stimulating private investment in intercity infrastructure and
regional economic development. They became an explicit instrument
during President Carters administration: the 1978 National Urban
Policy and Urban Development action grant (UDAG) encouraged cities
to go from private investment subsidies to joint equity venture
PPPs.Throughout the 1980s, PPPs increasingly became a derivative of
the privatization movement and government rethinks. Private
providers were assumed able to provide higher quality goods and
services at lower cost, thereby significantly reducing the
governments tasks and responsibilities. It was not only in the USA
that PPPs assumed greater importance in the latter half of the
twentieth century. In Spain, early examples occurred in the 1960s
and toll roads had already been developed by 1968. In the UK, the
1979 Conservative government believed that central government was
too involved in the economy and needed to step down in favour of
utilising private capital. Enterprise zones and urban development
corporations (UDCs) were important instruments in this ambition. In
the UK in the late 1980s, the Thatcher administration turned to
PPPs as the preferred method for economic regeneration. City
Challenge, the programme that encouraged local authorities to
propose schemes for economic regeneration in partnership with local
businesses, replaced UDCs. The UK thinking on partnerships was
significantly influenced by the best practices in the USA.Other
parts of Europe also started using PPPs in the late 1980s. Examples
of PPPs in developed countries can also be found outside Europe and
the USA. In Australia, for example, the introduction of
publicprivate arrangements for the provision of infrastructure
dates back to the early 1990s. In many countries worldwide we see
similar trends in private sector involvement and PPP developments.
At first sight the rationale behind publicprivate cooperation is
similar: in all countries, governments are relying increasingly on
private sector money and skills. However, there are major
differences in the motives and procurement rules in different forms
of PPP between countries.4.2 Types of PPP ModelsThere are various
types of PPPs, established for different reasons, across a wide
range of market segments, reflecting the different needs of
governments for infrastructure services. Although the types vary,
two broad categories of PPPs can be identified: the
institutionalised kind that refers to all forms of joint ventures
between public and private stakeholders; and contractual PPPs.
4.2.1 Concession ModelConcessions, which have the longest
history of public-private financing, are most associated with PPPs.
By bringing private sector management, private funding and private
sector know-how into the public sector, concessions have become the
most established form of this kind of financing. They are
contractual arrangements whereby a facility is given by the public
to the private sector, which then operates the PPP for a certain
period of time. Oftentimes, this also means building and designing
the facility as well. The normal terminology for these contracts
describes more or less the functions they cover. Contracts that
concern the largest number of functions are Concession and Design,
Build, Finance and Operate contracts, since they cover all the
above-mentioned elements: namely finance, design, construction,
management and maintenance. They are often financed by user fees
(e.g. for drinking water, gas and electricity, public transport
etc. but not for social PPPs e.g. health, prisons, courts,
education, and urban roads, as well as defence).4.2.2 Public
Finance Initiative (PFI) ModelAnother model is based on the UK
Private Finance Initiative (PFI) which was developed in the UK in
1992. This has now been adopted by parts of Canada, France, the
Netherlands, Portugal, Ireland, Norway, Finland, Australia, Japan,
Malaysia, the United States and Singapore (amongst others) as part
of a wider reform programme for the delivery of public services. In
contrast to the concession model, financing schemes are structured
differently. Under PFI schemes, privately financed contracts for
public facilities and public works cover the same elements but, in
general, are paid, for practical reasons, by a public authority and
not by private users. For Example, public lighting, hospitals,
schools etc. come under such scheme.There are a range of PPP models
that allocate responsibilities and risks between the public and
private partners in different ways.The following terms are commonly
used to describe typical partnership agreements:Buy-Build-Operate
(BBO): Transfer of a public asset to a private or quasi-public
entity usually under contract that the assets are to be upgraded
and operated for a specified period of time. Public control is
exercised through the contract at the time of
transfer.Build-Own-Operate (BOO): The private sector finances,
builds, owns and operates a facility or service in perpetuity. The
public constraints are stated in the original agreement and through
on-going regulatory authority.Build-Own-Operate-Transfer (BOOT): A
private entity receives a franchise to finance, design, build and
operate a facility (and to charge user fees) for a specified
period, after which ownership is transferred back to the public
sector.Build-Operate-Transfer (BOT): The private sector designs,
finances and constructs a new facility under a long-term Concession
contract, and operates the facility during the term of the
Concession after which ownership is transferred back to the public
sector if not already transferred upon completion of the facility.
In fact, such a form covers BOOT and BLOT with the sole difference
being the ownership of the facility.Build-Lease-Operate-Transfer
(BLOT): A private entity receives a franchise to finance, design,
build and operate a leased facility (and to charge user fees) for
the lease period, against payment of a
rent.Design-Build-Finance-Operate (DBFO): The private sector
designs, finances and constructs a new facility under a long-term
lease, and operates the facility during the term of the lease. The
private partner transfers the new facility to the public sector at
the end of the lease term.Finance Only: A private entity, usually a
financial services company, funds a project directly or uses
various mechanisms such as a long-term lease or bond
issue.Operation & Maintenance Contract (O & M): A private
operator, under contract, operates a publicly owned asset for a
specified term. Ownership of the asset remains with the public
entity. (Many do not consider O&Ms to be within the spectrum of
PPPs and consider such contracts as service contracts.)Design-Build
(DB): The private sector designs and builds infrastructure to meet
public sector performance specifications, often for a fixed price,
turnkey basis, so the risk of cost overruns is transferred to the
private sector. (Many do not consider DBs to be within the spectrum
of PPPs and consider such contracts as public works
contracts.)Operation License: A private operator receives a license
or rights to operate a public service, usually for a specified
term. This is often used in IT projects.4.2.3 PPP vs.
PrivatisationThe central question on governance from the
perspective of PPPs is how to organise the interaction between
public and private sector. The main goal is to improve efficiency,
quality of public services and products, and legitimacy. The
question how to organise a PPP cannot be answered in general for
every market, and, in most cases even for every project, the answer
has to be customised. Confusion about the PPP concept is striking
in the political and social discussion on these governance
questions. Often, PPP is used as a synonym for privatization.
Nevertheless, there are significant differences between PPP and
privatisation. In PPPs, public and private parties (actors) share
costs, revenues and responsibilities. Privatisation represents the
transfer of tasks and responsibilities to the private sector, with
both costs and revenues being in private hands. The confusion
impedes a rational discussion about PPPs since all the
disadvantages of privatisation are imputed to PPPs.The key
differences between public-private-partnership and privatisation
may be summarised as :Responsibility: Under privatisation the
responsibility for delivery and funding a particular service rests
with the private sector. PPP, on the other hand, involves full
retention of responsibility by the government for providing
service.Ownership: While ownership rights under privatisation are
sold to the private sector along with associated benefits and
costs, PPP may continue to retain the legal ownership of assets by
the public sector.Nature of Service : While nature and scope of
service under privatisation is determined by the private provider,
under PPP the nature and scope of service is contractually
determined between the two parties.Risk & Reward : Under
privatisation all the risks inherent in the business rest with the
private sector. Under PPP, risks and rewards are shared between the
government (public) and the private sector.4.3 PPPs in IndiaThere
is now over 10 years experience in India in the development and use
of PPPs for delivering infrastructure services. Policies in favor
of attracting private participation have met with varying degrees
of success, but real progress has been made in some sectors, first
in telecommunications, and now in ports and roads, and with
individual projects in other sectors. There has been considerable
innovation with different structures now being developed to attract
private participation. But at the same time progress has been
uneven.India had a few notable PPPs as early as the 19th century.
The Great Indian Peninsular Railway Company operating between
Bombay (now Mumbai) and Thana (now Thane) (1853), the Bombay
Tramway Company running tramway services in Bombay (1874), and the
power generation and distribution companies in Bombay and Calcutta
(now Kolkata) in the early 20th century are some of the earliest
examples of PPP in India. Since the opening of the economy in 1991
there have been several cautious and tentative attempts at PPP in
India. However, most PPPs have been restricted to the roads sector.
Large private financing in water supply has so far been limited to
a few cities like Visakhapatnam and Tirupur. Most PPPs in water
supply projects have been through municipal bonds in cities such as
Ahmedabad, Ludhiana, and Nagpur. West Bengal has recorded
significant success in housing and health sectors. For example, the
housing projects coming up on the outskirts of Kolkata City are a
good example of what a PPP model can deliver in terms of quality
housing and quality living conditions to the lower middle class and
the middle class. Gujarat and Maharashtra have had success
especially in ports, roads, and urban infrastructure. Karnataka
also has done well in the airport, power, and road sector. Punjab
has had PPPs in the road sectorA study conducted by the World Bank
of 12 states and 3 central agencies in 2005 in India found only 86
PPP projects awarded by states and select central agencies (not
including power and telecom). Their total project cost is Rs 339.5
billion. An optimistic projection of PPPs growing by, say, five
times between 2004 and 2006, in a country of Indias size, that is,
around 500 projects, is not very encouraging. The largest number of
PPP projects is in the roads and bridges sector, followed by ports,
particularly Greenfield Ports. Apart from these two sectors, there
are very few PPP initiativesAcross states and central agencies, the
leading users of PPPs by number of projects have been Madhya
Pradesh and Maharashtra, with 21 and 14 awarded projects,
respectively, all in the roads sector, and the National Highways
Authority of India (NHAI), with 16 projects. The other states or
central agencies that have been important users of PPPs are Gujarat
(9 projects) and Tamil Nadu (7), Karnataka (4) and Ministry of
Shipping, Road Transport and Highways (MOSRTH) (4). However,
looking at a breakdown by estimated project size, we see that MP
becomes significantly less prominent due to the large number of
relatively small-sized projects in its portfolio, falling to 3
percent of total project costs. States like Andhra Pradesh,
Gujarat, and Punjab have legislation which clearly defines what
infrastructure is and how these infrastructure projects are going
to be executed by the private sector. Some other states have
administrative frameworks in place for decision-making. Despite
these frameworks, in the last five years the number of successful
projects has not increased substantially. Madhya Pradesh and
Maharashtra have exhibited the possibility of developing a PPP
program in a single sector (roads) by building up capacities in
line departments. However, they have no PPPs in other sectors,
possibly in part because of the absence of platforms to transfer
acquired skills to other departments. Gujarat, Andhra Pradesh, and
Punjab have developed cross-sectoral enabling legislation and
dedicated agencies but have not had a very successful track record
in taking PPPs to the market. Some other states, such as Tamil
Nadu, have developed a few PPPs across a wide range of sectors,
without explicit cross-sectoral PPP units or legislation. Rajasthan
has a cross-sector policy/ regulatory framework and a project
development company but has concluded only one tourism project and
a few road projects. Therefore, there seems to be no clear link
between institutional structure and success of PPP. One possible
reason for this is the non-availability of sufficient skilled staff
in the Government of India as well as in the states, who could
actually look at how PPP projects should be structured. This is one
important area where significant capacity building is required,
both at the Centre and in the states.Various studies in developed
and developing countries have shown that there is a significant
shortfall in infrastructure investment and lack of maintenance
resulting in a deteriorating stock of public infrastructure capital
to support the deliveryof core public services. Public-private
partnership is an approach that is increasingly adopted to
facilitate the improvement of public services where there are
public sector budgetary constraints and there is a need for
innovation by stimulating private investment in infrastructure
facilities such as health, education, transport, defence and social
housing, regeneration and waste management. The alternative
public-private partnership is a whole-life or integrated approach
from design to facilities management and service delivery aimed at
addressing the problems associated with the traditional approach by
creating a shift in emphasis from building contracting and lump sum
payment to service contracting and performance-based payment.
However, it is important that appropriate policy, strategic and
implementation structures and processes are in place to address the
key objectives of the public sector in PFI/PPP projects. Another
critical success factor that should be added is sustainability to
reflect the increasing need to balance economic objectives with
environmental and social obligations. puttingTypically, in larger
countries, the national PPP units will not undertake the projects
but rather provide the policy, technical, legal and other support
mechanisms to local authorities and government ministries that have
the responsibility of the project together. Practically, it can
help the relevant procuring authority more confidently manage the
whole process from the development of the initial project design
through to the bid evaluation process and post-financial close. In
India, NHAI, MOSRTH attracting PPP projects, is an example of such
mechanism. Though PPP is a relatively new approach to procurement,
lessons could be drawn from the experiences of developed and
developing countries on the conditions for the success of PPP. As a
relatively late entrant in the PPP development process, India can
learn and benefit from these lessons.
Chapter 5Pipavav Port Rail Connectivity 5.1 General Port Pipavav
is located at Latitude 20 54N and Longitude 71 30E on the west
coast of India, in the state of Gujarat. For decades the port was
functioning as an anchorage serving the then existing minor Port
called Port Albert Victor. It is protected by islands on either
side, which act as a natural breakwater making the port safe in all
weather conditions. The presence of these islands also leads to the
tranquility in the harbor as well as ensures the wave height is
less than 0.5m most of the time.In 1992, it was decided to develop
the port as an all weather facility for handling bulk, liquid and
container cargo. A private limited company called Gujarat Pipavav
Port Limited (GPPL) was incorporated as a joint venture between Sea
King Infrastructure Limited and Gujarat Maritime Board, a state
owned organization.General cargo handling operations at the Port
commenced in November 1996 followed by container handling
operations in 1998. Presently, the container terminal offers direct
services to Europe, US East Coast, China and the Far East. Port
Pipavav is today recognized as one of the principal gateways on the
West Coast of India.The port is being developed for handling 19
million tonnes of cargo per annum including 13 million tonnes of
containerized cargo. APM Terminals is making an investment of US$
245 million to develop the facilities. With available draft of 13.5
metres, the port is also able to handle Post-Panamax vessels.
5. 2ConnectivityInitially, there was no rail connection to the
port. The nearest railhead was located at a distance of 18 km on
the Rajula-Surendranagar metre gauge line of Western Railway,
beyond which the broad gauge rail network was available. In the
absence of a rail connection, the Port could not be adequately
developed; hence its keenness for a proper rail connectivity,
preferably a broad gauge rail link.Indian Railways had earlier
sanctioned a project to convert the existing Rajula-Surendranagar
metre gauge line into broad gauge as a part of the railways
long-term plans for broad gauge network on the entire system.
However, financial constraints had prevented its timely execution.
In the meanwhile, the Ministry of Railways launched a programme for
undertaking rail projects through public-private partnership.In
1998, GPPL proposed a joint venture with the Ministry of Railways
to undertake the rail connectivity project which would include
provision of a rail link of 18 km and conversion of the existing
meter gauge line. Detailed feasibility studies and traffic
projections established the financial viability of the proposed
project. A memorandum of understanding (MoU) between Ministry of
Railways and Gujarat Pipavav Port Limited was signed on 28 January
2000.Based on the techno-economic studies, a business plan of the
proposed joint venture was prepared by financial consultants
engaged by GPPL. This plan was reviewed in the Ministry of
Railways, who then obtained formal approval of the Government of
India. As a follow-up, Pipavav Railway Corporation Limited was
incorporated in May 2000 as a joint venture with equal
participation between the Indian Railways and the Gujarat Pipavav
Port Limited.The above was followed by a host of agreements between
various stakeholders Ministry of Railways, Western Railway (a
constituent of Indian Railways), Gujarat Pipavav Port Limited,
Pipavav Railway Corporation Limited. A Shareholders Agreement
between MOR and GPPL was signed on 28 March 2001, Concession and
Lease Agreements between MOR and PRCL on 28 June 2001.The
Construction Agreement for the project between PRCL and Western
Railway was signed on 13 March 2002, followed by Operation and
Maintenance Agreement in January 2003. The Transportation and
Traffic Guarantee Agreement was signed between GPPL, PRCL and
Western Railway in February 2003. The table below shows the various
contractual agreements and the dates of their execution between
different parties.Table 1: Chronology of Agreements
Sl. No.AgreementParties to AgreementDate
1MoU for formation of SPVMOR & GPPL20.01..2000
2Concession AgreementMOR (GOI) & PRCL28.06.2001
3Lease AgreementMOR (GOI) & PRCL28.06.2001
4Construction AgreementPRCL & Western Railway
(GOI)13.03.2002
5Memorandum & Articles of Association of
PRCLPRCL17.04.2002
6Operation & Maintenance AgreementPRCL & WR
(GOI)15.01.2003
7Transportation & Traffic Guarantee AgreementGPPL; WR and
PRCL15.02.2003
8Shareholders AgreementMOR & GPPL28.03.2001
5.3 Concession AgreementUnder this agreement, the President of
India through the Ministry of Railways is the Licensor and PRCL is
the Concessionaire for the project. The concession period is for 33
years and permits PRCL to own and operate the project line both for
freight and passenger operations. It enjoins upon the SPV to pay
lease rent of Rs. 2 crore (20 million) per year to the Ministry of
Railways for the use of land and other assets. In turn, the
railways would pay to PRCL the apportioned revenue derived from the
freight moved on the rail line after deducting the operational
expenses. The revenue derived from passenger services is not
apportioned, since there is a heavy subsidy component in the fare
structure.5.4 Transportation and Traffic Guarantee Agreement Under
this agreement, WR guarantees evacuation of traffic from the port
by timely supply of wagons, and GPPL guarantees traffic of 1 MT in
the first year, 2 MT in the second year and 3 MT in the third and
each of the subsequent years. Failure on the part of either party
attracts penalties. Shortfalls in offering of traffic on the part
of GPPL or its evacuation by the railways is be converted into
deemed traffic and proportionate revenue is to be credited to PRCL
as compensation.5.5 Construction Agreement This agreement enjoins
upon Western Railway to design and construct the railway line with
the SPV procuring and supplying the construction materials. The
specifications and standards laid down by the Ministry of Railways
were to be followed.5.6 Operations and Maintenance Agreement It
lays down the process, procedure and accountal of operating and
maintenance practices to be followed by Western Railway and the
SPV.It would be seen that there was a considerable time lag from
the conceptualization of the project to the execution of various
contractual agreements specifying the roles and responsibilities of
the concerned stakeholders. This was mainly due to the fact that
PRCL was the first joint venture under the Ministry of Railways and
all agreements had to be evolved ab initio. There was also the
usual bureaucratic zeal observed for safeguarding the interests of
the government, with a mindset not fully attuned to the new
paradigm of public-private partnership. Furthermore, all agreements
had to be vetted by the Ministry of Law, Government of India.5.7
Project ProfileThe total length of project line is 268.84 km. A
metre gauge (MG) railway line existed between Surendranagar and
Rajula Junction. This stretch was converted to broad gauge. A new
line of 18 km length was constructed between Rajula and Pipavav
station. The alignment traverses Surendranagar, Amreli and
Bhavnagar districts in Gujarat.The broad gauge rail line (1,676 mm
gauge) was constructed fit for a maximum speed of 100 kmph.
Standard III inter-locking is provided with Multi-Aspect Colour
Light Signals and token-less block instruments. Level crossing
gates are inter-locked by signalling with adjoining stations.The
project involved construction of 198 bridges: 32 major and 166
minor bridges on the gauge conversion route and 3 major and 16
minor bridges on the new line section between Rajula and Pipavav.
In the gauge conversion section (between Surendranagar and Rajula),
the existing station buildings were utilised and two new stations
were built, one each at Rajula and Pipavav. There are 35 railway
stations on the rail route from Surendranagar to Pipavav.5.8 PRCLs
PromotersPRCL was promoted by the Ministry of Railways (Govt. of
India) and GPPL.Ministry of Railways: Railways are a full fledged
Ministry with a Minister of Cabinet rank holding charge. IR is
fully owned by the Government of India, administered by Railway
Board. Indian Railways (IR), the fourth largest railway network in
the world, has a route length of 63,500 km. IR has 1.5 million
employees running over 8,000 passenger trains and 5,500 freight
trains every day. It moves over 17 million passengers and 2.0
million tones of goods daily. Its rolling stock fleet includes some
8,300 locomotives, 4,400 coaching vehicles and 210,000 freight
wagons.Gujarat Pipavav Port Limited: Gujarat Pipavav Port Limited
(GPPL) is one of the first private sector ports in India. It was
incorporated in 1992, as a joint venture between Sea King
Infrastructure Limited (SKIL) and Gujarat Maritime Board for
developing and operating an all-weather port for handling bulk,
liquid and container cargo at Pipavav, in Amreli district of
Gujarat. The cargo handling operations had commenced in 1998.GPPLs
principal shareholders are:i. A.P.Moeller-Maersk Sealand
(APMT/Maersk), one of the largest port container terminal operators
in the world and the largest container shipping line, with around
20% worldwide market share. It holds 50.76% shares. APMT/Maersk is
in the process of developing the Pipavav port into a world-class
port with state-of-the-art container handling facilities and
terminal management.ii. AMP Capital Investors,iii. New York Life
International India Fund,iv. Industrial Development Bank of India
(IDBI),v. Unit Trust of India (UTI) and Infrastructure.vi. Leasing
& Financial Services Ltd. (IL&FS)The key developments from
conceptualisation of Pipavav port to APMT/Maersk taking over its
management control have been as follow: 1986 - Gujarat Maritime
Board (GMB) initiates development of Pipavav Port February 1992 GMB
enters into an MoU with Sea KingInfrastructure Ltd. (SKIL) group
led by Mr. Nikhil Gandhi June, 1992 MoU converted into Joint
Venture agreement July, 1997 Government of Gujarat (GoG) announces
BOOT Policy - June 1998 GMB divests its entire equity in favour of
SKIL Group - July 1998 GoG declares Model Concession Principles for
ports September, 1998 Concession Agreement based on Model
Principles signed September, 1998 Lead promoter SKIL licensed to
develop, operate, and maintain the port April, 2005 GoG agrees to
change the promoters SKIL group to A.P.Moller-Maersk group, Denmark
May, 2005 APM Terminals takes full management control of the
portGPPL is planning to enhance its cargo handling capacity to
19.16 MT by 2009-10, including 13.70 MT of containerised cargo and
5.56 MT of bulk cargo. The port expansion programme is being taken
up in three phases with a capital investment of Rs.1,167.30 crore
which is through equity contribution of Rs.200 crore, internal
accruals of Rs.289.04 crore and debt of Rs.596.26 crore.
A.P.MollerMaersk has committed an investment of Rs.1,200 crore for
port infrastructure development. Three quay cranes will be
installed for container-handling facilities in addition to the
existing three quay cranes to enhance the container handling
capacity to 1 million TEUs. GPPL commenced capital dredging project
in December 2005 which was completed by April, 2006 to increase the
draft to 13.5 m to handle post-Panamax vessels.Maersk Sealand, the
port operator, has started dedicated weekly service between Pipavav
and Salalah (Oman) and Jebel Ali (United Arab Emirates), which has
contributed to increase in container throughput at Pipavav port.5.9
Shareholders AgreementThe basic structure of the company (PRCL) is
defined in the Shareholders Agreement (SHA). In addition, the other
formalities like registration of the Company, Memorandum of
Articles of Association, registration with various government
revenue agencies like Sales Tax etc were also completed. The
salient features of the SHA are given in the table in Annexure - B.
5.10 Project Implementation ProcessProject Development Phase: The
gauge conversion of the SurendranagarRajula MG line was an approved
work of the WR to be completed at railways cost. However, it was
not a priority line and therefore annual fund allocations were very
meagre. In normal course, if the WR were to complete the
conversion, it could take anything between 10- 15 years. It was not
coinciding with the port development plans and hence the need for
GPPL to contribute to the gauge conversion costs.Construction
Phase: The construction phase started on the date of signing the
construction agreement on 13th March 2002. Till then WR had been
carrying out preliminary works on the erstwhile sanctioned Railway
Gauge Conversion Project which mainly related to the strengthening
of bridges and structures for BG trains.The Construction Phase was
divided into the following main activities: - Procurement of
material by PRCL Transportation to sites by PRCL Testing and
certification of specifications by WR Labour contracts for track
laying and linking by WR Signalling and telecom works, station
buildings by WR New bridges for the new line between Rajula-Pipavav
by WR Consolidation of track, testing and safety certification by
WR
The main items of procurement were the following: Rails Concrete
sleepers Stone ballast Rail switches Rail turnouts and traps CMS
rail crossings Glued joints Track fastenings Sleeper fastenings
Signalling cablesIn addition to the above materials, tools and
material handling and transportation equipments like motor
trolleys, road trucks and rail grinding and drilling machines, etc.
were also procured for reducing the man power requirement by
mechanization of processes. A Tender Committee was set up with
Directors of PRCL Board representing MOR, GPPL and the CEO of PRCL
to finalise procurements. Orders were placed and PRCL Board was
apprised of the progress periodically.Placement of Orders: A
strategy of splitting the orders for the same item among several
suppliers was adopted. Incentives were given to suppliers for
supplies made before time. Since Bhilai Steel Plant and IR had
initially regretted to supply rails, international bids were called
for. This process took a long time as it involved inspection of the
mills abroad