Top Banner
Minutes of 410 th SEAC Meeting Dated 11/07/2019 The 410 th meeting of SEAC was held in Directorate of Environment, U.P. on 11/07/2019 following members were present in the SEAC: 1. Dr. (Prof.) S.N. Singh, Chairman 2. Dr. Sarita Sinha, Member 3. Dr. Arvind Mathur, Member 4. Dr. Virendra Misra, Member 5. Dr. Pramod Kumar Mishra, Member 6. Dr. Richhpal Singh Sangu, Member 7. Dr. Ajoy Kumar Mandal, Member 8. Shri Meraj Uddin, Member 9. Shri Rajive Kumar, Member The Chairman welcomed the members to the 410 th SEAC meeting. The SEAC unanimously took following decisions on the agenda points discussed: 1. Sugar Factory Production Expansion from 10000 TCD to 12500 TCD at Gata No.-471mi, 472/1, 473mi, 474, 476/1, 506/1, 4, L H Sugar Factory, District- Pilibhit U.P., M/s Lalit Hari Sugar Factories Ltd. File No. 4870/4463/Proposal No. SIA/UP/IND2/35031/2018 A presentation was made by the project proponent M/s Lalit Hari Sugar Factory along with their consultant M/s Sawen Consultancy Services Pvt. Ltd. The proponent, through the documents submitted and the presentation made, informed the committee that:- 1. The environmental clearance is sought for Sugar Factory Production Expansion from 10000 TCD to 12500 TCD at Gata No.-471mi, 472/1, 473mi, 474, 476/1, 506/1, 4, L H Sugar Factory, District- Pilibhit U.P., M/s Lalit Hari Sugar Factories Ltd. 2. Terms of reference in the matter were issued through SEIAA, U.P. letter no. 608/parya/SEAC/4463/2018 dated 28/12/2018. 3. Area details of the project: 1 Total Land area 58.23 Ha. 100 % 2 Greenbelt 20.48 Ha 35.18 % 3 Factory Land 27.23 Ha. 46.76 % 4 Open Area 10.52 Ha 18.06 % 4. Salient features of the project: Parameter Existing Plant Proposed Expansion Total Land area (ha) 27.23 ha (factory land area) No extra Land required 58.23 ha 2. Raw water (m 3 /day) 2300 m 3 /day 900 m 3 /day 3200 m 3 /day 3. Power Generation 44.25 MW No extra power requirement 44.25 MW
45

1. Sugar Factory Production Expansion from 10000 TCD to ...

Feb 27, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

The 410th

meeting of SEAC was held in Directorate of Environment, U.P. on 11/07/2019

following members were present in the SEAC:

1. Dr. (Prof.) S.N. Singh, Chairman

2. Dr. Sarita Sinha, Member

3. Dr. Arvind Mathur, Member

4. Dr. Virendra Misra, Member

5. Dr. Pramod Kumar Mishra, Member

6. Dr. Richhpal Singh Sangu, Member

7. Dr. Ajoy Kumar Mandal, Member

8. Shri Meraj Uddin, Member

9. Shri Rajive Kumar, Member

The Chairman welcomed the members to the 410th SEAC meeting.

The SEAC unanimously took following decisions on the agenda points discussed:

1. Sugar Factory Production Expansion from 10000 TCD to 12500 TCD at Gata No.-471mi,

472/1, 473mi, 474, 476/1, 506/1, 4, L H Sugar Factory, District- Pilibhit U.P., M/s Lalit Hari

Sugar Factories Ltd. File No. 4870/4463/Proposal No. SIA/UP/IND2/35031/2018

A presentation was made by the project proponent M/s Lalit Hari Sugar Factory along with their

consultant M/s Sawen Consultancy Services Pvt. Ltd. The proponent, through the documents submitted and the

presentation made, informed the committee that:-

1. The environmental clearance is sought for Sugar Factory Production Expansion from 10000 TCD to

12500 TCD at Gata No.-471mi, 472/1, 473mi, 474, 476/1, 506/1, 4, L H Sugar Factory, District- Pilibhit

U.P., M/s Lalit Hari Sugar Factories Ltd.

2. Terms of reference in the matter were issued through SEIAA, U.P. letter no.

608/parya/SEAC/4463/2018 dated 28/12/2018.

3. Area details of the project:

1 Total Land area 58.23 Ha. 100 %

2 Greenbelt 20.48 Ha 35.18 %

3 Factory Land 27.23 Ha. 46.76 %

4 Open Area 10.52 Ha 18.06 %

4. Salient features of the project:

Parameter Existing Plant Proposed Expansion Total

Land area (ha) 27.23 ha (factory land

area)

No extra Land required 58.23 ha

2. Raw water

(m3/day)

2300 m3/day 900 m

3/day 3200 m

3/day

3. Power Generation 44.25 MW No extra power

requirement

44.25 MW

Page 2: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 2 of 45

4. Power Consumption 15.0 MW 1.7 MW 16.7 MW

5. Waste water (effluent

generation) (m

3/day)

1752 m3/ day 748 m

3/ day 2500 m

3/

day

Main Products

1. Sugar

198000 Ton 49500 Ton 247500 Ton

B. By-Products 1. Bagasse

540000 Ton 135000 Ton 675000 Ton

2. Molasses 90000 Ton 22500 Ton 112500 Ton

3. Press Mud 72000 Ton 18000 Ton 90000 Ton

6. ETP capacity 2.0 MLD 0.7 MLD 2.7 MLD

7. Rain Water Harvesting Pits 04 01 05

5. Chemicals and materials required and their source along with mode of transportation:

List of raw materials to

be used at all stages of

manufacture

Physical and chemical

nature of raw material

Quantity

(tonnes/month) full

production capacity

Source of

materials

Means of transportation (Source

to

storage site) with justification

Sugar Cane Crop (Biomass) 3 Lac ton Farmers By Road- Pilibhit Tanakpur

Road & Gandhi Stadium Road

through Trucks and lorry and then to different storage

sections by conveyor belts.

Lime Quick Lime CaO - 57% ,

Mg- 33%

553 ton Suppliers

Sulphur Powder; Negligible

solubility in water

162 ton Suppliers

Phosphoric Acid H3 PO3; Crystals ; Boiling

Point: 200 deg C @760mmHg ( 392.00°F)

6.2 ton Suppliers

Biocide Freezing/Melting Point:

73 deg C

1.5 ton Suppliers

6. Water requirement details: Other Details Exiting Unit Expansion Total

1 Water Requirement 2300 M3/Day 900 M3/Day 3200 M3/Day

2 Source of Water 03 no of Bore well none 03 no of Bore well

3 Waste water generation 1752 M3/Day 748 M3/Day 2500 M3/Day

4 Effluent Treatment Plant (Capacity)

2 MLD 0.7 MLD 2.7 MLD

7. Population details: S.No. Detail Nos. during crushing season Nos. during non crushing season

1 Administrative 50 50

2 Visitors 500 100

3 Residential 50 ( Permanent) + 200 (

seasonal)

50

4 Factory Workers 100 30

Total Population 900 230

8. The project proposal falls under category–5(j) of EIA Notification, 2006 (as amended).

RESOLUTION AGAINST AGENDA NO-01

The committee discussed the matter and recommended grant of environmental clearance for the

project proposal along with following conditions:

I. Soft green area should be minimum 33% of the plot area.

II. Statutory compliance:

I. The project proponent shall obtain forest clearance under the provisions of Forest

(Conservation) Act, 1986, in case of the diversion of forest land for non-forest purpose

involved in the project.

Page 3: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 3 of 45

II. The project proponent shall obtain clearance from the National Board for Wildlife, if

applicable.

III. The project proponent shall prepare a Site-Specific Conservation Plan & Wildlife

Management Plan and approved by the Chief Wildlife Warden. The recommendations of

the approved Site-Specific Conservation Plan / Wildlife Management Plan shall be

implemented in consultation with the State Forest Department. The implementation report

shall be furnished along with the six - monthly compliance report. (in case of the presence

of schedule-I species in the study area).

IV. The project proponent shall obtain Consent to Establish / Operate under the provisions of

Air (Prevention & Control of Pollution) Act, 1981 and the Water (Prevention & Control of

Pollution) Act, 1974 from the concerned State pollution Control Board/ Committee.

V. The project proponent shall obtain authorization under the Hazardous and other Waste

Management Rules, 2016 as amended from time to time.

VI. The Company shall strictly comply with the rules and guidelines under Manufacture,

Storage and Import of Hazardous Chemicals (MSIHC) Rules, 1989 as amended time to

time. All transportation of Hazardous Chemicals shall be as per the Motor Vehicle Act

(MVA), 1989

III. Air quality monitoring and preservation:

I. The project proponent shall install 24x7 continuous emission monitoring system at

process stacks to monitor stack emission with respect to standards prescribed in

Environment (Protection) Rules 1986 and connected to SPCB and CPCB online servers

and calibrate these system from time to time according to equipment supplier specification

through labs recognized under Environment (Protection) Act, 1986 or NABL accredited

laboratories.

II. The project proponent shall install system carryout to Ambient Air Quality

monitoring for common/criterion parameters relevant to the main pollutants released (e.g.

PM10 and PM2.s in reference to PM emission , and SO2 and NOx in reference to SO2 and

NOx emissions) within and outside the plant area at least at four locations (one within

and three outside the plant area at an angle of 12 0° each), covering upwind and downwind

direct ions. (case to case basis small plants: Manual; Large plants: Continuous).

III. The project proponent shall submit monthly summary report of continuous stack

emission and air quality monitoring and results of manual stack monitoring and manual

monitoring of air quality /fugitive emissions to Regional Office of MoEF&CC, Zonal

office of CPCB and Regional Office of SPCB along with six- monthly monitoring report.

IV. Appropriate Air Pollution Control (APC) system shall be provided for all the dust

generating points including fugitive dust from all vulnerable sources, so as to comply

prescribed stack emission and fugitive emission standards.

V. The National Ambient Air Quality Emission Standards issued by the Ministry vide G.S.R.

No. 826(E) dated 16th November, 2009 shall be complied with.

VI. Sulphur content should not exceed 0.5% in the coal for use in coal fired boilers to

control particulate emissions within permissible limits (as applicable). The gaseous

emissions shall be dispersed through stack of adequate height as per CPCB/SPCB

guidelines.

VII. The DG sets shall be equipped with suitable pollution control devices and the

adequate stack height so that the emissions are in conformity with the extant regulations

and the guidelines in this regard.

VIII. Storage of raw materials, coal etc shall be either stored in silos or in covered areas to

prevent dust pollution and other fugitive emissions.

Page 4: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 4 of 45

IV. Water quality monitoring and preservation

I. For online continuous monitoring of effluent, the unit shall install web camera with

night vision capability and flow meters in the channel/drain carrying effluent within the

premises (applicable in case of the projects achieving ZLD) and connected to SPCB and

CPCB online servers.

II. Zero Liquid Discharge shall be ensured and no waste/treated water shall be discharged

outside the premises (applicable in case of the projects achieving the ZLD).

III. Process effluent /any wastewater shall not be allowed to mix with storm water. The storm

water from the premises shall be collected and discharged through a separate conveyance

system.

IV. The effluent discharge shall conform to the standards prescribed under the Environment

(Protection) Rules, 1986, or as specified by the State Pollution Control Board while

granting Consent under the Air/Water Act, whichever is more stringent.

V. Total fresh water requirement shall not exceed the proposed quantity or as specified by the

Committee. Prior permission shall be obtained from the concerned regulatory

authority/CGWA in this regard.

VI. Industrial/trade effluent shall be segregated into High COD/TDS and Low COD/TDS

effluent streams. High TDS/COD shall be passed through stripper followed by MEE and

ATFD (agitated thin film drier). Low TDS effluent stream shall be treated in ETP and then

passed through RO system.

VII. The Company shall harvest rainwater from the roof tops of the buildings and storm

water drains to recharge the ground water and utilize the same for different industrial

operations within the plant.

V. Noise monitoring and prevention

I. Acoustic enclosure shall be provided to DG set for controlling the noise pollution.

II. The overall noise levels in and around the plant area shall be kept well within the

standards by providing noise control measures including acoustic hoods, silencers ,

enclosures etc. on all sources of noise generation.

III. The ambient noise levels should conform to the standards prescribed under E(P)A

Rules, 1986 viz. 75 dB(A) during day time and 70 dB(A) during night time

VI. Energy Conservation measures

I. The energy sources for lighting purposes shall preferably be LED based.

VII. Waste management

I. Hazardous chemicals shall be stored in tanks, tank farms, drums, carboys etc. Flame

arresters shall be provided on tank farm and the solvent transfer through pumps.

II. Process organic residue and spent carbon, if any, shall be sent to cement industries. ETP

sludge, process inorganic & evaporation salt shall be disposed off to the TSDF.

III. The company shall undertake waste minimization measures as below :-

a. Metering and control of quantities of active ingredients to minimize waste .

b. Reuse of by-products from the process as raw materials or as raw material substitutes in other

processes.

c. Use of automated filling to minimize spillage.

d. Use of Close Feed system into batch reactors.

Page 5: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 5 of 45

e. Venting equipment through vapour recovery system.

f. Use of high pressure hoses for equipment clearing to reduce wastewater generation

VIII. Green Belt

I. Green belt shall be developed in an area equal to 33% of the plant area with a native tree

species in accordance with CPCB guidelines. The greenbelt shall inter alia cover the entire

periphery of the plant.

IX. Safety, Public hearing and Human health issues

I. Emergency preparedness plan based on the Hazard identification and Risk Assessment

(HIRA) and Disaster Management Plan shall be implemented.

II. The PP shall provide Personal Protection Equipment (PPE) as per the norms of

Factory Act.

III. Training shall be imparted to all employees on safety and health aspects of chemicals

handling. Pre-employment and routine periodical medical examinations for all employees

shall be undertaken on regular basis. Training to all employees on handling of chemicals

shall be imparted.

IV. Provision shall be made for the housing of construction labour within the site with all

necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP,

safe drinking water, medical health care, creche etc. The housing may be in the form of

temporary structures to be removed after the completion of the project.

V. Occupational health surveillance of the workers shall be done on a regular basis and

records maintained as per the Factories Act.

VI. There shall be adequate space inside the plant premises earmarked for parking of vehicles

for raw materials and finished products, and no parking to be allowed outside on public

places

X. Corporate Environment Responsibility

I. The project proponent shall comply with the provisions contained in this Ministry's OM

vide F.No. 22-65/2017-IA.III dated 1st May 2018, as applicable, regarding Corporate

Environment Responsibility.

II. The company shall have a well laid down environmental policy duly approve by the

Board of Directors. The environmental policy should prescribe for standard operating

procedures to have proper checks and balances and to bring into focus any infringements

/deviation/violation of the environmental / forest /wildlife norms / conditions. The

company shall have defined system of reporting infringements / deviation/ violation of the

environmental/ forest / wildlife norms I conditions and / or shareholders / stake holders.

The copy of the board resolution in this regard shall be submitted to the MoEF&CC as a

part of six-monthly report.

III. A separate Environmental Cell both at the project and company head quarter level,

with qualified personnel shall be set up under the control of senior Executive , who will

directly to the head of the organization.

IV. Action plan for implementing EMP and environmental conditions along with responsibility

matrix of the company shall be prepared and shall be duly approved by competent

authority. The year wise funds earmarked for environmental protection measures shall be

kept in separate account and not to be diverted for any other purpose. Year wise progress

Page 6: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 6 of 45

of implementation of action plan shall be reported to the Ministry/Regional Office along

with the Six Monthly Compliance Report.

V. Self environmental audit shall be conducted annually. Every three years third party

environmental audit shall be carried out.

XI. Miscellaneous

I. The project proponent shall make public the environmental clearance granted for their

project along with the environmental conditions and safeguards at their cost by

prominently advertising it at least in two local newspapers of the District or State, of

which one shall be in the vernacular language within seven days and in addition this shall

also be displayed in the project proponent's website permanently.

II. The copies of the environmental clearance shall be submitted by the project proponents

to the Heads of local bodies, Panchayats and Municipal Bodies in addition to the relevant

offices of the Government who in turn has to display the same for 30 days from the date

of receipt.

III. The project proponent shall upload the status of compliance of the stipulated environment

clearance conditions, including results of monitored data on their website and update the

same on half-yearly basis.

IV. The project proponent shall monitor the criteria pollutants level namely; PM10, SO2,

NOx (ambient levels as well as stack emissions) or critical sectoral parameters, indicated

for the projects and display the same at a convenient location for disclosure to the public

and put on the website of the company.

V. The project proponent shall submit six-monthly reports on the status of the compliance

of the stipulated environmental conditions on the website of the ministry of

Environment, Forest and Climate Change at environment clearance portal.

VI. The project proponent shall submit the environmental statement for each financial year

in Form-V to the concerned State Pollution Control Board as prescribed under the

Environment (Protection) Rules, 1986, as amended subsequently and put on the website of

the company.

VII. The project proponent shall inform the Regional Office as well as the Minis try, the date of

financial closure and final approval of the project by the concerned authorities ,

commencing the land development work and start of production operation by the project.

VIII. The project authorities must strictly adhere to the stipulations made by the State Pollution

Control Board and the State Government.

IX. The project proponent shall abide by all the commitments and recommendations made in

the EIA/EMP report, commitment made during Public Hearing and also that during their

presentation to the Expert Appraisal Committee.

X. No further expansion or modifications in the plant shall be carried out without prior

approval of the Ministry of Environment, Forests and Climate Change

(MoEF&CC)/SEIAA.

XI. Concealing factual data or submission of false /fabricated data may result in revocation of

this environmental clearance and attract action under the provisions of Environment

(Protection) Act, 1986.

XII. The Ministry may revoke or suspend the clearance, if implementation of any of the above

conditions is not satisfactory.

XIII. The Ministry reserves the right to stipulate additional conditions if found necessary.

Page 7: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 7 of 45

XIV. The Company in a time bound manner shall implement these conditions.

XV. The Regional Office of this Ministry shall monitor compliance of the stipulated conditions.

The project authorities should extend full cooperation to the officer (s) of the Regional

Office by furnishing the requisite data / information/monitoring reports.

XVI. The above conditions shall be enforced, inter-alia under the provisions of the Water

(Prevention & Control of Pollution) Act, 1974, the Air (Prevention & Control of Pollution)

Act, 1981, the Environment (Protection) Act, 1986, Hazardous and Other Wastes

(Management and Transboundary Movement) Rules, 2016 and the Public Liability

Insurance Act, 1991 along with their amendments and Rules and any other orders passed

by the Hon'ble Supreme Court of India / High Courts and any other Court of Law

relating to the subject matter.

XVII. Any appeal against this EC shall lie with the National Green Tribunal, if preferred, within

a period of 30 days as prescribed under Section 16 of the National Green Tribunal Act,

2010.

2. Residential Complex "Gulmohar Residency" at Khasra No.-527/1, 519, Village- Kanawani,

Distt.- Ghaziabad, U.P., M/s SVP Builders (I) Ltd. File No. 4881/Proposal No.

SIA/UP/MIS/108734/2018

A presentation was made by project proponent along with their consultant M/s Ambiental Global

Private Limited. The proponent, through the documents submitted and the presentation made, informed the

committee that:-

1- The environmental clearance is sought for Residential Complex "Gulmohar Residency" at Khasra No.-

527/1, 519, Village- Kanawani, Distt.- Ghaziabad, U.P., M/s SVP Builders (I) Ltd.

2- The committee discussed the matter in light of MOEFCC Notification dated 08/03/2018 under violation

project & recommended to issue terms of reference (TOR) for the preparation of EIA. The terms of

reference in the matter were issued by SEIAA vide letter no. 610/Parya/SEAC/4222/2018 dated

28/12/2018.

3- Environmental Clearance for the earlier proposal was issued by SEIAA, U.P. vide letter no.

3139/Parya/SEAC/1195/2012/DD(Y), dated 05.03.2013 for the plot area 12,698.27 m2 and built-up area

54,539.43 m2.

4- Salient features of the project:

Description Proposed

Plot Area 12,698.27 m2

Built-up Area 61,378.86 m2

Green Area 1,904.74 m2 @ 15 % of Total Plot Area

Total Water Requirement 299 KLD

Fresh Water Requirement 232 KLD

Wastewater Generation 165 KLD

Capacity of STP 100 KLD

Solid Waste Generation 1,153 kg/day

Parking Required & Provided 532 ECS & 542 ECS

Power Demand & Source 2,865 kVA (Paschimanchal Vidyut Vitran Nigam Limited)

Back up 375 kVA (250 + 125 kVA)

RWH Pits 4 pits

Expansion Project Cost 22.18 Cr.

5- Comparative area details for earlier and expansion project:

Page 8: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 8 of 45

S. No. Particulars Area (m2)

Area Approved as

per earlier EC

Expansion

Occurred under

Violation

Total/Final After

Compounding

1. Total Plot Area 12,698.27 Nil 12,698.27

2. Net Plot Area 10,793.53 Nil 10,793.53

3. Permissible Ground Coverage 3,777.73

(@ 35% of Net Plot

Area)

Nil 3,777.73

(@ 35% of Net

Plot Area)

4. Total Achieved Ground Coverage 2007.38

(@ 19.08% of Net

Plot Area)

369.67 2,377.05

(@ 22.02% of Net

Plot Area)

5. Total Permissible F.A.R

Permissible F.A.R as per 2.5

Purchasable F.A.R Area @ 1.25

10% Compounding Area of 2.5

F.A.R

40,475.73

26,983.82 13,491.91

Nil

2,698.38

Nil Nil

2,698.38

43,174.11

26,983.82 13,491.91

2,698.38

6. Total Proposed/Achieved F.A.R Area

Residential F.A.R Area

Community F.A.R Area

36,423.80

36,203.80

220.00

4,508.03

4,282.62

225.41

40,931.83

40,486.42

445.41

7. Total Proposed/Achieved Non F.A.R Area

Upper Basement Area

Lower Basement Area

Stilt Area

Fire Staircase Area

Mumty Area

Machine Room Area Guard & Meter Room Area

18,115.63

7478.00

7303.00

1948.76

1204.28

109.56

72.03 Nil

2,848.32

985.62

1160.62

279.82

258.46

60.72

51.73 51.35

20,447.03

8,463.62

8,463.62

2,228.58

945.82

170.28

123.76 51.35

8. Built Up Area (6 + 7) 54,539.43 7,356.35 61,378.86

9. Open Area 10,690.89

(@ 84.1% of Total

Plot Area

369.67

(Deduction)

10,321.22

(@ 81.3% of

Total Plot Area

10. Total Achieved Landscape Area

@15% of Total Plot Area

1,904.74 Nil 1,904.74

11. Height of the Building 58.20 meters Nil 58.70 meters

6- Population details:

S. No. Type Dwellings Units/ F.A.R. PPU Total Population

A. Residential 418 5 2,090

(a) Staff @ 5% of the total residential population 105

(b) Visitors/Floating @10% of the total residential population 209

B. Community 445.41 1 Person/1.5 m2

(a) Staff @ 20% of the community population 59

(b) Visitors @ 80% of the community population 238

Grand Total (A + B) 2,701

7- Water requirement details:

S. No.

Description Total Area (m2)

Total Occupancy

Rate of water demand(lpcd)

Total Water Requirement (KLD)

A. Domestic Water Requirement

Residents 2090 86 180

Staff 105 30 3.15

Visitor/Floating 209 15 3.13

B. Community Centre

Staff 59 30 1.77

Visitor 238 15 3.57

Total Domestic Water Demand (A + B) 191.62 Say 192

Page 9: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 9 of 45

C. Horticulture 1,904.74 5 lt./sqm/day 9.5

D. Swimming Pool (Main +

Kids)

98

Total Water Requirement (A + B + C + D) 299.12 say 299 KLD

8- Solid waste generation details:

S. No. Category kg per capita

per day

Waste generated

(kg/day)

A. Residents 2,090 @ 0.5 kg/day 1045

(a) Staff 105 @ 0.25 kg/day 26.25

(b) Visitors 209 @ 0.15 kg/day 31.35

B. Community

(a) Staff 59 @ 0.25 kg/day 14.75

(b) Visitors 238 @ 0.15 kg/day 35.7

C. Landscape waste

(0.47 acres)

@ 0.2 kg/acre/day 0.094

TOTAL SOLID WASTE GENERATED

(A + B + C)

1,153.144 kg/day say

1,153 kg/day

9- The project proposal falls under category–8(a) of EIA Notification, 2006 (as amended) and MoEF&CC

Notification dated 08/03/2018 under the violation of E.P. Act.

RESOLUTION AGAINST AGENDA NO-02

The committee discussed the matter in view of EIA Notification, 2006 (as amended) and also

notification dated 08/03/2018 of MoEF&CC and recommended grant of environmental clearance under

violation category for the project proposal along with general conditions as earlier prescribed by

authority for construction project and following specific conditions :

Specific Conditions:

1. The project proponent shall be submit a bank guarantee of Rs. 5.20 Lakhs equivalent to the amount of

remediation plan and natural and community resource augmentation plan within 15 days to the SPCB.

The bank guarantee shall be released after successful implementation of the EMP, and after the recommendations of the concerned Regional Office of the Ministry, the SEAC and approval of the

regulatory authority.

2. The State Govt./SPCB to take action against the project proponent under the provisions of section 19 of Environment Protection Act, 1986.

3. Adequate parking for visitors should be provided at the entrance gate of buildings.

4. Maids working in the flats have to be essentially provided toilets and the rest room in the campus. Similarly the security guards may be provided these facilities separately.

5. A convenient shopping center has to be provided to meet the requirement of the residents on day to day

basis.

6. Solar energy to be used alternatives on the road and common places for illumination to save conventional energy.

7. Use of reflecting paints on the roof top and side walls of the building for cooling effect.

8. The project proponent shall submit within the next 3 month the data of ground water quality including fluoride parameter to the limit of minimum deduction level for all six monitoring stations.

9. 15% area of the total plot area shall be compulsorily made available for the green area development

including the peripheral green area. Plantation of trees should be of indigenous species and may be as per the consultation of local district Forest Officer.

10. The waste water generated should be treated properly in scientific manner i.e. domestic waste water to

be treated in STP and effluent such as RO rejects with high TDS and other chemical bearing effluent

shall be treated separately. 11. Permission from local authority should be taken regarding discharge of excess water into the sewer line.

12. The height, Construction built up area of proposed construction shall be in accordance with the existing

FAR norms of the competent authority & it should ensure the same along with survey number before

Page 10: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 10 of 45

approving layout plan & before according commencement certificate to proposed work. Plan approving

authority should also ensure the zoning permissibility for the proposed project as per the approved

development plan of the area. 13. "Consent for Establishment" shall be obtained from UP Pollution Control Board.

14. All required sanitary and hygienic measures should be in place before starting construction activities

and to be maintained throughout the construction phase. 15. Project proponent shall ensure completion of STP, MSW disposal facility, green area development prior

to occupation of the buildings.

16. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste (Management and Handling) Rules, 20016.

17. Provision shall be made for the housing of construction labour within the site with all necessary

infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water,

medical health care, creche and First Aid Room etc. 18. Adequate drinking water and sanitary facilities should be provided for construction workers at the site.

Provision should be made for mobile toilets. The safe disposal of wastewater and solid wastes generated

during the construction phase should be ensured. 19. The solid waste generated should be properly collected and segregated. Dry/inert solid waste should be

disposed off to the approved sites for land filling after recovering recyclable material.

20. Corporate Environmental Responsibility (CER) shall be submitted by the project proponent and the details of the various heads of expenditure to be submitted as per the guidelines provide in the recent

CER notification No. 22-65/2017-IA.III dated 01/05/2018. A copy of resolution of board of directors

shall be submitted to the authority. A list of beneficiaries with their mobile nos./address should be

submitted along with six monthly compliance reports. 21. No parking shall be allowed outside the project boundary.

22. Digging of basement shall be undertaken in view of structural safety of adjacent buildings under

information/consultation with District Administration/Mining Department. All the topsoil excavated during construction activities should be stored for use in horticulture /landscape development within the

project site. Additional soil for leveling of the proposed site shall be generated within the sites (to the

extent possible) so that natural drainage system of the area is protected and improved.

23. Surface rain water has to be collected in kacchha pond for ground water recharging and irrigation of horticulture and peripheral plantation.

24. The approval of competent authority shall be obtained for structural safety of the buildings due to any

possible earthquake, adequacy of fire fighting equipments etc. as per National Building Code including measures from lighting.

25. Disposal of muck during construction phase should not create any adverse effect on the neighboring

communities and be disposed taking the necessary precautions for general safety and health aspects of people, only in approved sites with the approval of competent authority.

26. Any hazardous waste generated during construction phase should be disposed off as per applicable rules

and norms with necessary approvals of the UP Pollution Control Board.

27. The diesel generator sets to be used during construction phase should be low sulphur diesel type and should conform to Environments (Protection) Rules prescribed for air and noise emission standards.

28. Ambient noise levels should conform to residential standards both during day and night. Incremental

pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be made to reduce ambient air and noise level during construction

phase, so as to conform to the stipulated standards by CPCB/UPPCB.

29. The green area design along the periphery of the plot shall achieve attenuation factor conforming to the

day and night noise standards prescribed for residential area. The open spaces inside the plot should be landscaped and covered with grass and shrubs. Green area Development shall be carried out considering

CPCB guidelines including selection of plant species and in consultation with the local DFO/

Agriculture Dept. 30. The building should have adequate distance between them to allow movement of fresh air and passage

of natural light, air and ventilation.

Page 11: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 11 of 45

31. Pavements shall be so constructed as to allow infiltration of surface run-off of rain water. Construction

of pavements around trees should be able to facilitate suitable watering, aeration and nutrition to the

tree. 32. Ready Mix Concrete and Sprinkler to be used for curing and quenching during construction phase.

33. Roof top water to be only channelized to RWHs. Arrangement shall be made that waste water and

storm water do not get mixed. 34. All the internal drains are to be covered till the disposal point.

35. This environmental clearance is issued subject to land use verification. Local authority / planning

authority should ensure this with respect to Rules, Regulations, Notifications, Government Resolutions, Circulars, etc. issued if any.

36. The bank guarantee shall be released after successful implementation of remediation plan and natural

and community resource augmentation plan, and after recommendation by Regional Office of Ministry,

Expert Appraisal Committee or State or Union Territory level Expert appraisal committee and approval of the regulatory authority.

3. Proposed Hotel Project "Holiday Inn" at Khasra No.- 285, 286, 287, 288 of Village- Behsa &

Khasra No.-348 of Village- Farukhabad Chilawan, Lucknow. M/s Awasthi Hotels and

Resorts Pvt. Ltd. File No. 4832/Proposal No. SIA/UP/MIS/105877/2019

A presentation was made by project proponent along with their consultant M/s Ind Tech House Consult.

The proponent, through the documents submitted and the presentation made, informed the committee that:-

1- The environmental clearance is sought for Proposed Hotel Project "Holiday Inn" at Khasra No.- 285,

286, 287, 288 of Village- Behsa & Khasra No.-348 of Village- Farukhabad Chilawan, Lucknow. M/s

Awasthi Hotels and Resorts Pvt. Ltd.

2- Total plot area and built-up area of the project is 10,655 sq. m. and 25438.54 sqm. respectively. Total

Hotel Suites will be 196 nos.

3- Estimated cost of project is Rs. 117.87 Crores.

4- Salient features of the project:

Sl. No. Description Quantity Unit

GENERAL

1 Gross Plot Area 10655 SQMT

2 Area Under Rd Widening 1053.41 SQMT

3 Net Plot Area 9601.59 SQMT

4 Proposed Built Up Area 25438.54 SQMT

5 Number of Building Blocks 1 No.

6 Proposed No of Hotel Suites 196

7 Max Height of Building (Upto Terrace) 39.9 M

8 Max No of Floors 2B+G+SER+8 No.

9 Expected Total Population (Fixed 392+1597 floating) 1989 No.

10 Cost of Project 117.87 CR

AREAS

11 Permissible Ground Coverage Area (40%) 3840.64 SQMT

12 Proposed Ground Coverage Area (28.6%) 2746.51 SQMT

13 Permissible FAR Area (200) 19203.18 SQMT

14 Proposed FAR Area 14452.43 SQMT

15 Non FAR areas - Total Basement Area 9942.72 SQMT

16 Other Non FAR areas - Service Floor Mumty Machine Rm etc. 1043.39 SQMT

17 Proposed Total Built Up Area 25438.54 SQMT

WATER

18 Total Water Requirement 293 KLD

19 Fresh water requirement 164 KLD

Page 12: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 12 of 45

20 Treated Water Requirement 129 KLD

21 Waste water Generation 162 KLD

22 Capacity of Proposed STP 195 KLD

23 Treated Water Available for Reuse 129 KLD

24 Surplus treated water to be discharged in Municipal Sewer 0 KLD

RAIN WATER HARVESTING

25 Rain Water Harvesting Potential 2949.66 KL

26 No of RWH Pits (Recharge) Proposed 3 No.

PARKING

27 Total Parking Required as / Building Bye Laws 166 ECS

28 Proposed Total Parking 168 ECS

29 Parking on Surface NIL

30 Parking in Basements 168 ECS

GREEN AREA

31 Required Green Area (15% of plot area) 1440.2385 SQMT

32 Proposed Green Area (17% of plot area) 1632.1 SQMT

WASTE

33 Total Solid Waste Generation 0.55 TPD

34 Organic waste 0.33 TPD

35 Quantity of Hazardous waste Generation 1.07 LPD

36 Quantity of Sludge Generated from STP 33 KG/DAY

ENERGY

37 Total Power Requirement 1737 KW

38 DG set backup 1875 KVA

39 No of DG Sets 3 No.

5- Population details:

Hotel (24 Hrs Use) Suites/ Serv Appt Pop/ Suit/ Appt Total Population

Hotel Suites 196 2 392

Total 196

Total 392

Non Residential (8to 10 Hrs Use)

Employees Rate Population

Hotel Staff As/Norms 340

Banquet, Conference Halls and Meeting Rooms Staff L.S. 138

Hotel Kitchen Staff L.S. 60

Facility Management Staff/Drivers L.S. 43

Total 581

Visitors (1.5 To 2 Hrs Use) Area In Sqm

Banquet & Conference Halls 1292 1/1.4 Sqm 923

Other Visitors L.S. 93

Total Visitors 1016

Total Population 1989

6- Water calculation details:

POPULATION/ AREA/UNIT

RATE IN LTS TOTAL QTY IN KL

HOTEL SUITES ( 4 STAR HOTEL) Population

DOMESTIC 392 260 101.92

FLUSHING 392 60 23.52

FACILITIES- BANQ HALL /CONFERENCES/

MEETING (Working Population)

DOMESTIC 241 25 6.04

FLUSHING 241 20 4.83

VISITORS TO- BANQ HALL /CONFERENCES/

MEETING (Working Population)

Page 13: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 13 of 45

DOMESTIC 923 15 13.85

FLUSHING 923 10 9.23

GENERAL VISITORS

DOMESTIC 93 5 0.47

FLUSHING 93 10 0.93

LAUNDARY 862 Kg 25 21.6

GARDENING 1632 Sqm 1 1.63

D G COOLING 1875 Kva 0.9 6.75

AIR CONDITIONING 650 TON 81.90

SWIMMING POOL/WATER BODY 1 No. 10

FILTER BACK WASH 10

TOTAL WATER REQUIREMENT 293

Head Source Quantity

Fresh Water Requirement Municipal Supply 164 KLD

Treated Water Requirement On site STP 129 KLD

Estimated waste water Generation: 162 KLD

Waste water to be treated in onsite STP: 195 KLD

Proposed treatment methodology : MBBR

Proposed STP (Capacity): 195 KLD

Treatment up to tertiary level.

STP shall have power back-up for uninterrupted operation during power failure.

Treated waste water will be used for flushing, DG cooling, HVAC & gardening.

7- The project proposal falls under category–8(a) of EIA Notification, 2006 (as amended).

RESOLUTION AGAINST AGENDA NO-03

The committee discussed the matter and recommended to grant the environmental clearance for

the above project proposal along with general conditions as earlier prescribed by authority for

construction project and following specific conditions:

1. Laundry effluent should not be discharged in STP.

2. Solar energy to be used alternatives on the road and common places for illumination to save

conventional energy as per ECBC Code. 3. The project proponent shall submit within the next 3 month the data of ground water quality including

fluoride parameter to the limit of minimum deduction level for all six monitoring stations.

4. 15% area of the total plot area shall be compulsorily made available for the green area development including the peripheral green area. Plantation of trees should be of indigenous species and may be as

per the consultation of local district Forest Officer.

5. The waste water generated should be treated properly in scientific manner i.e. domestic waste water to

be treated in STP and effluent such as RO rejects with high TDS and other chemical bearing effluent shall be treated separately.

6. Permission from local authority should be taken regarding discharge of excess water into the sewer line.

7. The height, Construction built up area of proposed construction shall be in accordance with the existing FAR norms of the competent authority & it should ensure the same along with survey number before

approving layout plan & before according commencement certificate to proposed work. Plan approving

authority should also ensure the zoning permissibility for the proposed project as per the approved development plan of the area.

8. "Consent for Establishment" shall be obtained from UP Pollution Control Board.

9. All required sanitary and hygienic measures should be in place before starting construction activities

and to be maintained throughout the construction phase. 10. Project proponent shall ensure completion of STP, MSW disposal facility, green area development prior

to occupation of the buildings.

11. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste (Management and Handling) Rules, 2016.

Page 14: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 14 of 45

12. Provision shall be made for the housing of construction labour within the site with all necessary

infrastructure and facilities such as cylinder for cooking, mobile toilets, mobile STP, safe drinking

water, medical health care, creche and First Aid Room etc. 13. Adequate drinking water and sanitary facilities should be provided for construction workers at the site.

Provision should be made for mobile toilets. The safe disposal of wastewater and solid wastes generated

during the construction phase should be ensured. 14. The solid waste generated should be properly collected and segregated. Dry/inert solid waste should be

disposed off to the approved sites for land filling after recovering recyclable material.

15. Corporate Environmental Responsibility (CER) shall be prepared by the project proponent and the details of the various heads of expenditure to be submitted as per the guidelines provided in the recent

CER notification No. 22-65/2017-IA.III dated 01/05/2018. A copy of resolution of board of directors

shall be submitted to the authority. A list of beneficiaries with their mobile nos./address should be

submitted along with six monthly compliance reports. 16. No parking shall be allowed outside the project boundary.

17. Digging of basement shall be undertaken in view of structural safety of adjacent buildings under

information/consultation with District Administration/Mining Department. All the topsoil excavated during construction activities should be stored for use in horticulture /landscape development within the

project site. Additional soil for leveling of the proposed site shall be generated within the sites (to the

extent possible) so that natural drainage system of the area is protected and improved. 18. Surface rain water has to be collected in kacchha pond for ground water recharging and irrigation of

horticulture and peripheral plantation.

19. The approval of competent authority shall be obtained for structural safety of the buildings due to any

possible earthquake, adequacy of fire fighting equipments etc. as per National Building Code including measures from lighting.

20. Disposal of muck during construction phase should not create any adverse effect on the neighboring

communities and be disposed off taking the necessary precautions for general safety and health aspects of people, only in approved sites with the approval of competent authority.

21. Any hazardous waste generated during construction phase should be disposed off as per applicable rules

and norms with necessary approvals of the UP Pollution Control Board.

22. The diesel generator sets to be used during construction phase should be low sulphur diesel type and should conform to Environments (Protection) Rules prescribed for air and noise emission standards.

23. Ambient noise levels should conform to residential standards both during day and night. Incremental

pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be made to reduce ambient air and noise level during construction

phase, so as to conform to the stipulated standards by CPCB/UPPCB.

24. The green area design along the periphery of the plot shall achieve attenuation factor conforming to the day and night noise standards prescribed for residential area. The open spaces inside the plot should be

landscaped and covered with grass and shrubs. Green area Development shall be carried out considering

CPCB guidelines including selection of plant species and in consultation with the local DFO/

Agriculture Dept. 25. The building should have adequate distance between them to allow movement of fresh air and passage

of natural light, air and ventilation.

26. Pavements shall be so constructed as to allow infiltration of surface run-off of rain water. Construction of pavements around trees should be able to facilitate suitable watering, aeration and nutrition to the

tree.

27. Ready Mix Concrete and Sprinkler to be used for curing and quenching during construction phase.

28. Roof top water in rainy season is to be discharged into RWH pits for ground water recharging. Arrangement shall be made that waste water and storm water do not get mixed.

29. NOC from Ground Water Board is to be submitted for drilling of tube well for use of Water Supply.

30. All the internal drains are to be covered till the disposal point.

Page 15: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 15 of 45

31. This environmental clearance is issued subject to land use verification. Local authority / planning

authority should ensure this with respect to Rules, Regulations, Notifications, Government Resolutions,

Circulars, etc. issued if any. 32. Reflecting paint should be used on the roof top and side walls of the building tower for cooling effect.

4. "Gaur World Street" at Plot No.-C-1A, Sector-16B, Greter Noida, District-Gautam Buddha

Nagar. M/s Fastidious Build Mart Pvt. Ltd. File No. 4862/Proposal No.

SIA/UP/MIS/107183/2019

RESOLUTION AGAINST AGENDA NO-04

The project proponent did not appear. The committee discussed and deliberated that the project file should be closed and be opened only after request from the project proponent. The file shall not be treated as

pending at SEAC. The matter will be discussed only after submission of online request on prescribed online

portal.

5. Development of Technical Training and Development Center Complex at Plot No.- A 3&4,

Sector- 62, Phase-II, Noida, Gautam Budh Nagar. File No. 4869/Proposal No.

SIA/UP/MIS/108100/2019

RESOLUTION AGAINST AGENDA NO-05

The project proponent through the letter dated 11/07/2019 requested to defer the matter in upcoming SEAC meeting. The committee discussed matter and directed to defer the matter as per the request made by the

project proponent. The file shall not be treated as pending at SEAC. The matter will be discussed only after

submission of online request on prescribed online portal.

6. Expansion of Tikaula Distillery From 45 KLD to 98 KLD with 3.0 MW Co-gen. Power Plant

at Village- Tikaula, Post- Ramraj, Distt.-Muzaffarnagar, U.P. M /s Tikaula Sugar Mills Ltd.

File No. 4875/Proposal No.SIA/UP/IND2/37795/2019

RESOLUTION AGAINST AGENDA NO-06

The project proponent did not appear. The committee discussed and deliberated that the project file should be closed and be opened only after request from the project proponent. The file shall not be treated as

pending at SEAC. The matter will be discussed only after submission of online request on prescribed online

portal.

7. Proposed Group Housingh Scheme "Aarna Apartment" at Khasra No.-139, 143, 144, 145,

146, 147, 2413, at Batawali, Mustakham, Kanth Road, District-Moradabad, U.P. M/s Shail

Promoters And Consultants. File No. 4889/Proposal No.SIA/UP/MIS/108571/2019

RESOLUTION AGAINST AGENDA NO-07

The project proponent did not appear. The committee discussed and deliberated that the project file

should be closed and be opened only after request from the project proponent. The file shall not be treated as

pending at SEAC. The matter will be discussed only after submission of online request on prescribed online portal.

Page 16: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 16 of 45

8. Group Housing at Plot No.-Gh-2 & 3, Scheme No.-03, Ambedkar Puram, District-Kanpur.

M/s Geetika Builders & Developers Pvt. Ltd. File No. 4891/Proposal

No.SIA/UP/MIS/108946/2019

RESOLUTION AGAINST AGENDA NO-08

The project proponent requested to defer the matter in upcoming SEAC meeting due to non availability

of structure stability certificate. The committee discussed matter and directed to defer the matter as per the request made by the project proponent. The file shall not be treated as pending at SEAC. The matter will be

discussed only after submission of online request on prescribed online portal.

9. Expansion of Group Housing Project "Mahagun Mantra- II " at Plot No.- GH- 01/A, Sector-

10, Greater Noida,, Tehsil & District - Gautam Buddha Nagar, U.P. File No. 4486/Proposal

No. SIA/UP/NCP/79295/2018

A presentation was made by project proponent along with their consultant M/s Perfact Enviro Solutions

Pvt. Ltd. The proponent, through the documents submitted and the presentation made, informed the committee

that:-

1- The environmental clearance is sought for Expansion of Group Housing Project "Mahagun Mantra- II "

at Plot No.- GH- 01/A, Sector-10, Greater Noida,, Tehsil & District - Gautam Buddha Nagar, U.P., M/s

Hebe Infrastructure Pvt. Ltd.

2- Environment Clearance for the earlier proposal was issued by MoEF&CC vide letter no. F. No. 21-

98/2017-IA-III dated 29th August, 2017 for plot area of 23,657.31 m2 and built-up area of 1,38,294.52

m2.

3- Comparative details of earlier and expansion project:

S.No. Details Units As per EC

granted

Proposed/

additional

Total after

expansion

Impact

1 Total Plot area m2 23657.31 882.69 24540 Increase

2 Ground coverage Permissible m2 8280.05 0 8280.05 No

Change

3 Ground coverage (Achieved) m2 4738.88 154.76 4893.64 Increase

4 FAR Area (Permissible)

FAR (permissible) m2 65057.575 2427.4 67485.0 Increase

FAR (Purchasable) m2 17742.975 662.02 18405.0 Increase

IGBC FAR m2 4140.03 154.47 4294.5 Increase

Total Permissible FAR m2 86940.58 3089.42 90184.5 Increase

5 Achieved FAR

FAR Residential m2 84895.42 3767.34 88662.76 Increase

FAR Commercial m2 868.04 (-)15.94 852.1 Decrease

FAR Community m2 816.08 (-)200.14 615.94 Decrease

Total Achieved FAR m2 86579.54 3551.26 90130.8 Increase

6 Upper Basement m2 18923.17 193.91 19117.08 Increase

Lower basement m2 18630.08 1143.21 19773.29 Increase

Total Basement Area m2 37553.25 1337.12 38890.37 Increase

7 Non-FAR(Service area+ stilt area &

other Non-FAR)

m2 14161.73 2091.94 16253.67 Increase

8 Total Built up area m2 138294.52 6980.32 145274.84 Increase

9 Total Green Area m2 9540.87 500.21 10041.08 Increase

10 Max. Height of building m 94.69 - 94.69 Same

11 No. of Floors No. S+G+26 0 S+G+26 Same

12 No. of Towers No. 3 + commercial - 3 + Commercial Same

Page 17: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 17 of 45

13 No. of Basement No. 2 0 2 Same

14 No. of Dwelling Unit No. 1076 60 1136 Increase

4- Population details:

Type As per earlier EC granted Proposed/Additional After expansion

Residence 4842 270 5112

Staff 300 - 300

Visitors 487 13 500

Total 5629 283 5912

5- Other details:

WASTE WATER, RAIN WATER & SOLID WASTE DETAILS

Particulars As per earlier EC Granted

Proposed/ Additional

Total Details After expansion

Total water requirement 503 KLD 24 KLD 527 KLD

Total waste water generation 382 KLD 21 KLD 403 KLD

STP capacity 620 KLD - 620 KLD

No. of Rain water harvesting pits 6 no. - 6 no.

Total Municipal Solid waste

generated

2297 Kg/day 123 Kg/day 2420 Kg/day

Power Source Uttar Pradesh Power Corporation Ltd

Total Power load 3582 KVA - 3582 KVA

No. of DG sets 2 x 1500 KVA - 2 x 1010 KVA & 1 x 500 KVA

6- Land use details:

Land Use As per EC Granted After Expansion

Area (sqm) Percentage (%) Area (sqm) Percentage (%)

Ground Coverage 4738.88 m2 20.03 % 4893.64 m2 19.94%

Green Area 9540.27 m2 40.33 % 10041.1 m2 40.92%

Road & Open area 8238.15 m2 34.82 % 8988.01 m2 36.94%

Surface Parking area 1140 m2 4.81 % 617.25 m2 2.20%

Total 23657.3 m2 100 % 24540 m2 100%

7- Water requirement details:

PARTICULARS AS PER EARLIER EC

GRANTED

PROPOSED/

ADDITIONAL

TOTAL DETAILS AFTER

EXPANSION

Source Of Water Municipal Supply

Total Water

Requirement

503 KLD 24 KLD 527 KLD

Fresh Water Requirement

306 KLD 12 KLD 318 KLD

Total Wastewater

Generated

382 KLD 21 KLD 403 KLD

STP Capacity 620 KLD - 620 KLD

8- The project proposal falls under category–8(a) of EIA Notification, 2006 (as amended).

RESOLUTION AGAINST AGENDA NO-09

The committee discussed the matter and recommended grant the environmental clearance for the

above project proposal along with general conditions as earlier prescribed by authority for construction

project and following specific conditions:

1. Solar energy to be used alternatives on the road and common places for illumination to save

conventional energy as per ECBC Code. 2. The project proponent shall submit within the next 3 month the data of ground water quality including

fluoride parameter to the limit of minimum deduction level for all six monitoring stations.

3. 15% area of the total plot area shall be compulsorily made available for the green area development including the peripheral green area. Plantation of trees should be of indigenous species and may be as

per the consultation of local district Forest Officer.

Page 18: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 18 of 45

4. The waste water generated should be treated properly in scientific manner i.e. domestic waste water to

be treated in STP and effluent such as RO rejects with high TDS and other chemical bearing effluent

shall be treated separately. 5. Permission from local authority should be taken regarding discharge of excess water into the sewer line.

6. The height, Construction built up area of proposed construction shall be in accordance with the existing

FAR norms of the competent authority & it should ensure the same along with survey number before approving layout plan & before according commencement certificate to proposed work. Plan approving

authority should also ensure the zoning permissibility for the proposed project as per the approved

development plan of the area. 7. "Consent for Establishment" shall be obtained from UP Pollution Control Board.

8. All required sanitary and hygienic measures should be in place before starting construction activities

and to be maintained throughout the construction phase.

9. Project proponent shall ensure completion of STP, MSW disposal facility, green area development prior to occupation of the buildings.

10. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste (Management and

Handling) Rules, 2016. 11. Provision shall be made for the housing of construction labour within the site with all necessary

infrastructure and facilities such as cylinder for cooking, mobile toilets, mobile STP, safe drinking

water, medical health care, creche and First Aid Room etc. 12. Adequate drinking water and sanitary facilities should be provided for construction workers at the site.

Provision should be made for mobile toilets. The safe disposal of wastewater and solid wastes generated

during the construction phase should be ensured.

13. The solid waste generated should be properly collected and segregated. Dry/inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material.

14. Corporate Environmental Responsibility (CER) shall be prepared by the project proponent and the

details of the various heads of expenditure to be submitted as per the guidelines provided in the recent CER notification No. 22-65/2017-IA.III dated 01/05/2018. A copy of resolution of board of directors

shall be submitted to the authority. A list of beneficiaries with their mobile nos./address should be

submitted along with six monthly compliance reports.

15. No parking shall be allowed outside the project boundary. 16. Digging of basement shall be undertaken in view of structural safety of adjacent buildings under

information/consultation with District Administration/Mining Department. All the topsoil excavated

during construction activities should be stored for use in horticulture /landscape development within the project site. Additional soil for leveling of the proposed site shall be generated within the sites (to the

extent possible) so that natural drainage system of the area is protected and improved.

17. Surface rain water has to be collected in kacchha pond for ground water recharging and irrigation of horticulture and peripheral plantation.

18. The approval of competent authority shall be obtained for structural safety of the buildings due to any

possible earthquake, adequacy of fire fighting equipments etc. as per National Building Code including

measures from lighting. 19. Disposal of muck during construction phase should not create any adverse effect on the neighboring

communities and be disposed off taking the necessary precautions for general safety and health aspects

of people, only in approved sites with the approval of competent authority. 20. Any hazardous waste generated during construction phase should be disposed off as per applicable rules

and norms with necessary approvals of the UP Pollution Control Board.

21. The diesel generator sets to be used during construction phase should be low sulphur diesel type and

should conform to Environments (Protection) Rules prescribed for air and noise emission standards. 22. Ambient noise levels should conform to residential standards both during day and night. Incremental

pollution loads on the ambient air and noise quality should be closely monitored during construction

phase. Adequate measures should be made to reduce ambient air and noise level during construction phase, so as to conform to the stipulated standards by CPCB/UPPCB.

Page 19: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 19 of 45

23. The green area design along the periphery of the plot shall achieve attenuation factor conforming to the

day and night noise standards prescribed for residential area. The open spaces inside the plot should be

landscaped and covered with grass and shrubs. Green area Development shall be carried out considering CPCB guidelines including selection of plant species and in consultation with the local DFO/

Agriculture Dept.

24. The building should have adequate distance between them to allow movement of fresh air and passage of natural light, air and ventilation.

25. Pavements shall be so constructed as to allow infiltration of surface run-off of rain water. Construction

of pavements around trees should be able to facilitate suitable watering, aeration and nutrition to the tree.

26. Ready Mix Concrete and Sprinkler to be used for curing and quenching during construction phase.

27. Roof top water in rainy season is to be discharged into RWH pits for ground water recharging.

Arrangement shall be made that waste water and storm water do not get mixed. 28. NOC from Ground Water Board is to be submitted for drilling of tube well for use of Water Supply.

29. All the internal drains are to be covered till the disposal point.

30. This environmental clearance is issued subject to land use verification. Local authority / planning authority should ensure this with respect to Rules, Regulations, Notifications, Government Resolutions,

Circulars, etc. issued if any.

31. Reflecting paint should be used on the roof top and side walls of the building tower for cooling effect.

10. Expansion of Group Housing Project located at Plot No.- GH- 05B,Sector- 16, Greater Noida,

District- Gautam Budha Nagar, U.P., M/s Rudhar Buildwell Constructions Pvt. Ltd. File No.

4718/Proposal No. SIA/UP/MIS/97656/2019

RESOLUTION AGAINST AGENDA NO-10

The project proponent through the letter dated 11/07/2019 requested to defer the matter in upcoming

SEAC meeting. The committee discussed matter and directed to defer the matter as per the request made by the project proponent. The file shall not be treated as pending at SEAC. The matter will be discussed only after

submission of online request on prescribed online portal.

11. "Industrial (IT/ITES) Building" at Plot No.- A-10, Sector- 68, District-Gautam Buddh

Nagar, U.P. M/s Krishna Computech Internatiol Pvt. Ltd. File No. 4747/Proposal No.

SIA/UP/MIS/102340/2019

A presentation was made by project proponent along with their consultant M/s Geogreen Enviro House

Pvt. Ltd. The proponent, through the documents submitted and the presentation made, informed the committee

that:-

1- The environmental clearance is sought for "Industrial (IT/ITES) Building" at Plot No.- A-10, Sector- 68,

District-Gautam Buddh Nagar, U.P. M/s Krishna Computech International Pvt. Ltd.

2- Total Plot area measures 8,000 m2 (1.96 acre) and estimated built-up area is 33,083.29 m

2.

3- Salient features of the project:

DESCRIPTION DETAILS

Type of Project “Industrial (IT/ITES) Building”

Project Proponent M/s Krishna Computech International Pvt. Ltd.

Location Plot no. A-10, sector – 68, Noida, Uttar Pradesh

Total Plot Area 8,000 m2

Total Built-Up Area 33,083.29 m2

Estimated Population 2204 persons.

Fresh Water Requirement 65 KLD

Page 20: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 20 of 45

Solid Waste Generated 540 kg/day

Electrical load 2823.9 KW; Source: UPPCL

DG set (3×1010+1×500) kVA

4- Area details of the project:

S. No Particulars Total (m2)

1 Total plot area 8,000 (1.96 acre)

2 Permissible Ground Coverage (@30% of Total Plot area) 2,400

3 Total Proposed Ground Coverage (@29.98% of Total plot area) 2398.884

4 Permissible FAR @2.5 21,000.00

5 Proposed FAR 20,998.884

6. Permissible Services area @15% of permissible FAR 3,000.0

7. Proposed Services area 2267.850

8. Services floor 2335.646

9. Basement 5408.00

10. Stilt 2072.91

Total Built up Area (F.A.R+ Non F.A.R)

a) Proposed FAR 20,998.884

b) Proposed Service Area 2,267.850

c) Services floor 2,335.646

d) Basement 5,408.00

e) Stilt 2,072.91

11. Total Built Up Area (BUA) 33,083.29

13 Required Green Area (@25% open area) 1400

14 Total proposed green area @26.47% 1482.484

5- Population details:

S. No. Particulars FAR (m2) PPU/no. of person/m2 Total Population

1 IT 20998.884m2 1-person per 10 m2 2099

2 Visitor @ 5% of total population 105

Total Population 2204

6- Water calculation details:

S. No. Description Area

(in m2)

Total Occupancy Rate of water

demand (lpcd)

Total Water Requirement (KLD)

A. Domestic water requirement

For Staff 2099 30 62.97

For visitor 105 15 1.57

Fresh water requirement 64.54 Say 65 KLD

B. Horticulture

area

1482.484 m2 Approx. 4.5

lit/sqm.

6.67

C. D.G Cooling (3X 1010 +

1X 500)

0.9lit X Capacity

X 8 hours

25 KLD

Total Water Requirement 96.67 KLD says 97 KLD

7- Solid waste generation details:

S. No. Category Kg per capita per day Waste generated (kg/day)

1 Staff 2099 @ 0.25 kg / day 524

2 Visitor 105 @ 0.15 kg /day 15.75

3 Landscape waste (0.366 acres) 0.366@ 0.2 kg/acres 0.0732

Total Solid Waste Generated 539.83 kg/day Say 540 kg/day

8- The project proposal falls under category–8(a) of EIA Notification, 2006 (as amended).

RESOLUTION AGAINST AGENDA NO-11

The committee discussed the matter and recommended grant the environmental clearance for the

above project proposal along with general conditions as earlier prescribed by authority for construction

project and following specific conditions:

Page 21: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 21 of 45

1. Minimum 05 nos. of RWH pits to be proposed for ground water recharging.

2. Solar energy to be used alternatives on the road and common places for illumination to save

conventional energy as per ECBC Code. 3. The project proponent shall submit within the next 3 month the data of ground water quality including

fluoride parameter to the limit of minimum deduction level for all six monitoring stations.

4. 15% area of the total plot area shall be compulsorily made available for the green area development including the peripheral green area. Plantation of trees should be of indigenous species and may be as

per the consultation of local district Forest Officer.

5. The waste water generated should be treated properly in scientific manner i.e. domestic waste water to be treated in STP and effluent such as RO rejects with high TDS and other chemical bearing effluent

shall be treated separately.

6. Permission from local authority should be taken regarding discharge of excess water into the sewer line.

7. The height, Construction built up area of proposed construction shall be in accordance with the existing FAR norms of the competent authority & it should ensure the same along with survey number before

approving layout plan & before according commencement certificate to proposed work. Plan approving

authority should also ensure the zoning permissibility for the proposed project as per the approved development plan of the area.

8. "Consent for Establishment" shall be obtained from UP Pollution Control Board.

9. All required sanitary and hygienic measures should be in place before starting construction activities and to be maintained throughout the construction phase.

10. Project proponent shall ensure completion of STP, MSW disposal facility, green area development prior

to occupation of the buildings.

11. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste (Management and Handling) Rules, 2016.

12. Provision shall be made for the housing of construction labour within the site with all necessary

infrastructure and facilities such as cylinder for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, creche and First Aid Room etc.

13. Adequate drinking water and sanitary facilities should be provided for construction workers at the site.

Provision should be made for mobile toilets. The safe disposal of wastewater and solid wastes generated

during the construction phase should be ensured. 14. The solid waste generated should be properly collected and segregated. Dry/inert solid waste should be

disposed off to the approved sites for land filling after recovering recyclable material.

15. Corporate Environmental Responsibility (CER) shall be prepared by the project proponent and the details of the various heads of expenditure to be submitted as per the guidelines provided in the recent

CER notification No. 22-65/2017-IA.III dated 01/05/2018. A copy of resolution of board of directors

shall be submitted to the authority. A list of beneficiaries with their mobile nos./address should be submitted along with six monthly compliance reports.

16. No parking shall be allowed outside the project boundary.

17. Digging of basement shall be undertaken in view of structural safety of adjacent buildings under

information/consultation with District Administration/Mining Department. All the topsoil excavated during construction activities should be stored for use in horticulture /landscape development within the

project site. Additional soil for leveling of the proposed site shall be generated within the sites (to the

extent possible) so that natural drainage system of the area is protected and improved. 18. Surface rain water has to be collected in kacchha pond for ground water recharging and irrigation of

horticulture and peripheral plantation.

19. The approval of competent authority shall be obtained for structural safety of the buildings due to any

possible earthquake, adequacy of fire fighting equipments etc. as per National Building Code including measures from lighting.

20. Disposal of muck during construction phase should not create any adverse effect on the neighboring

communities and be disposed off taking the necessary precautions for general safety and health aspects of people, only in approved sites with the approval of competent authority.

Page 22: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 22 of 45

21. Any hazardous waste generated during construction phase should be disposed off as per applicable rules

and norms with necessary approvals of the UP Pollution Control Board.

22. The diesel generator sets to be used during construction phase should be low sulphur diesel type and should conform to Environments (Protection) Rules prescribed for air and noise emission standards.

23. Ambient noise levels should conform to residential standards both during day and night. Incremental

pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be made to reduce ambient air and noise level during construction

phase, so as to conform to the stipulated standards by CPCB/UPPCB.

24. The green area design along the periphery of the plot shall achieve attenuation factor conforming to the day and night noise standards prescribed for residential area. The open spaces inside the plot should be

landscaped and covered with grass and shrubs. Green area Development shall be carried out considering

CPCB guidelines including selection of plant species and in consultation with the local DFO/

Agriculture Dept. 25. The building should have adequate distance between them to allow movement of fresh air and passage

of natural light, air and ventilation.

26. Pavements shall be so constructed as to allow infiltration of surface run-off of rain water. Construction of pavements around trees should be able to facilitate suitable watering, aeration and nutrition to the

tree.

27. Ready Mix Concrete and Sprinkler to be used for curing and quenching during construction phase. 28. Roof top water in rainy season is to be discharged into RWH pits for ground water recharging.

Arrangement shall be made that waste water and storm water do not get mixed.

29. NOC from Ground Water Board is to be submitted for drilling of tube well for use of Water Supply.

30. All the internal drains are to be covered till the disposal point. 31. This environmental clearance is issued subject to land use verification. Local authority / planning

authority should ensure this with respect to Rules, Regulations, Notifications, Government Resolutions,

Circulars, etc. issued if any. 32. Reflecting paint should be used on the roof top and side walls of the building tower for cooling effect.

12. "Windsor IT Park" located at Plot No.- 1 C, Sector- 126, Noida, District- Gautam Buddha

Nagar, M/s Star Propwell Pvt. Ltd. File No. 4775/Proposal No. SIA/UP/MIS/103007/2019

A presentation was made by project proponent along with their consultant M/s Geogreen Enviro House

Pvt. Ltd. The proponent, through the documents submitted and the presentation made, informed the committee

that:-

1- The environmental clearance is sought for "Windsor IT Park" located at Plot No.- 1 C, Sector- 126,

Noida, District- Gautam Buddha Nagar, M/s Star Propwell Pvt. Ltd.

2- Salient features of the project:

DESCRIPTION DETAILS

Type of Project Windsor IT Park Project

Project Proponent M/s Star Propwell Pvt. Ltd.

Location Plot no.- 1C, sector – 126, Noida, Uttar Pradesh

Total Plot Area 6,995.16 m2

Total Built-Up Area 31,114.301 m2

Estimated Population 2096 persons.

Fresh Water Requirement 105 KLD

Solid Waste Generated 489.26 kg/day

Electrical load 2710 KVA; Source: NPCL

DG set 4 DG Sets (3x 1010 kVA + 1 x 750 kVA.)

Parking 453 ECS

Page 23: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 23 of 45

3- Area details of the project:

S. No. Particulars Total (m2)

1 Total plot area 6,995.16

2 Permissible Ground Coverage @30% 2,098.548

3 Proposed Ground [email protected]% 2,066.196

4 Permissible FAR @2.5 17,487.90

5 Proposed [email protected] 17,475.430

6 Non FAR 11,198.793

a Upper basement 3,522.743

b Lower basement 3,522.743

c Stilt/Ground Floor 1,741.500

d 5th Floor (service Floor-1) 1,536.630

e 11th Floor (service Floor-2) 875.177

7 Services area 2,440.441

8 Total Built up Area (F.A.R+ Non F.A.R)

a) Proposed FAR 17,475.430

b) Non FAR 11,198.430

c) Service Area 2,440.441

Total Built up Area 31,114.301

9 Required Green Area @25% 1,232.29

10 Total proposed green area @25.42% 1,253

11 Height of the building 56 m

4- Population details:

S. No. Particulars FAR (m2)/ Seats/

Nos./Rooms/DU

PPU/no. of person/m2 Total Population

1. Proposed FAR 17475.430 10 sq.m 1 person 1748

2. Visitor 10% of total population 174

3. Maintenance Staff 10% of total population 174

Total Population 2096

5- Water calculation details:

S. No. Description Area

(in m2)

Total Occupancy Rate of water

demand

(lpcd)

Total Water Requirement

(KLD)

Domestic water

A. Staff 1748 45 78.66

B. Visitor 174 15 7.83

C. Maintenance Staff 174 45 7.83

D. Swimming Pool Make Up 10

Fresh water requirement 104.32 KLD says 105

KLD

D. Horticulture area 1,253 m2 Approx. 4.5

lit/sqm.

5.6 KLD

E. D.G cooling

D.G. sets operation period is 8 hrs.)

3X 1010 KVA,

1X 750KVA)

0.9 X

KVAXHr

27 KLD

F. HVAC Cooling 1246 TR 10x12hr xTR 149 KLD

Total water requirement 286.6 KLD says 287

KLD

6- Solid waste generation details:

S. No. Category kg per capita per day Waste generated (kg/day)

1 Staff 1748 @ 0.25 kg/day 437

2 Visitors 348@ 0.15 kg / day 52.2

3 Landscape waste 0.3096 @ 0.2 kg/acres 0.061

TOTAL SOLID WASTE GENERATED 489.26 kg/day

7- The project proposal falls under category–8(a) of EIA Notification, 2006 (as amended).

Page 24: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 24 of 45

RESOLUTION AGAINST AGENDA NO-12

The committee discussed the matter and recommended grant the environmental clearance for the

above project proposal along with general conditions as earlier prescribed by authority for construction

project and following specific conditions:

1. Minimum 05 nos. of RWH pits to be proposed for ground water recharging.

2. Solar energy to be used alternatives on the road and common places for illumination to save

conventional energy as per ECBC Code.

3. The project proponent shall submit within the next 3 month the data of ground water quality including fluoride parameter to the limit of minimum deduction level for all six monitoring stations.

4. 15% area of the total plot area shall be compulsorily made available for the green area development

including the peripheral green area. Plantation of trees should be of indigenous species and may be as per the consultation of local district Forest Officer.

5. The waste water generated should be treated properly in scientific manner i.e. domestic waste water to

be treated in STP and effluent such as RO rejects with high TDS and other chemical bearing effluent shall be treated separately.

6. Permission from local authority should be taken regarding discharge of excess water into the sewer line.

7. The height, Construction built up area of proposed construction shall be in accordance with the existing

FAR norms of the competent authority & it should ensure the same along with survey number before approving layout plan & before according commencement certificate to proposed work. Plan approving

authority should also ensure the zoning permissibility for the proposed project as per the approved

development plan of the area. 8. "Consent for Establishment" shall be obtained from UP Pollution Control Board.

9. All required sanitary and hygienic measures should be in place before starting construction activities

and to be maintained throughout the construction phase.

10. Project proponent shall ensure completion of STP, MSW disposal facility, green area development prior to occupation of the buildings.

11. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste (Management and

Handling) Rules, 2016. 12. Provision shall be made for the housing of construction labour within the site with all necessary

infrastructure and facilities such as cylinder for cooking, mobile toilets, mobile STP, safe drinking

water, medical health care, creche and First Aid Room etc. 13. Adequate drinking water and sanitary facilities should be provided for construction workers at the site.

Provision should be made for mobile toilets. The safe disposal of wastewater and solid wastes generated

during the construction phase should be ensured.

14. The solid waste generated should be properly collected and segregated. Dry/inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material.

15. Corporate Environmental Responsibility (CER) shall be prepared by the project proponent and the

details of the various heads of expenditure to be submitted as per the guidelines provided in the recent CER notification No. 22-65/2017-IA.III dated 01/05/2018. A copy of resolution of board of directors

shall be submitted to the authority. A list of beneficiaries with their mobile nos./address should be

submitted along with six monthly compliance reports. 16. No parking shall be allowed outside the project boundary.

17. Digging of basement shall be undertaken in view of structural safety of adjacent buildings under

information/consultation with District Administration/Mining Department. All the topsoil excavated

during construction activities should be stored for use in horticulture /landscape development within the project site. Additional soil for leveling of the proposed site shall be generated within the sites (to the

extent possible) so that natural drainage system of the area is protected and improved.

18. Surface rain water has to be collected in kacchha pond for ground water recharging and irrigation of horticulture and peripheral plantation.

19. The approval of competent authority shall be obtained for structural safety of the buildings due to any

possible earthquake, adequacy of fire fighting equipments etc. as per National Building Code including

measures from lighting.

Page 25: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 25 of 45

20. Disposal of muck during construction phase should not create any adverse effect on the neighboring

communities and be disposed off taking the necessary precautions for general safety and health aspects

of people, only in approved sites with the approval of competent authority. 21. Any hazardous waste generated during construction phase should be disposed off as per applicable rules

and norms with necessary approvals of the UP Pollution Control Board.

22. The diesel generator sets to be used during construction phase should be low sulphur diesel type and should conform to Environments (Protection) Rules prescribed for air and noise emission standards.

23. Ambient noise levels should conform to residential standards both during day and night. Incremental

pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be made to reduce ambient air and noise level during construction

phase, so as to conform to the stipulated standards by CPCB/UPPCB.

24. The green area design along the periphery of the plot shall achieve attenuation factor conforming to the

day and night noise standards prescribed for residential area. The open spaces inside the plot should be landscaped and covered with grass and shrubs. Green area Development shall be carried out considering

CPCB guidelines including selection of plant species and in consultation with the local DFO/

Agriculture Dept. 25. The building should have adequate distance between them to allow movement of fresh air and passage

of natural light, air and ventilation.

26. Pavements shall be so constructed as to allow infiltration of surface run-off of rain water. Construction of pavements around trees should be able to facilitate suitable watering, aeration and nutrition to the

tree.

27. Ready Mix Concrete and Sprinkler to be used for curing and quenching during construction phase.

28. Roof top water in rainy season is to be discharged into RWH pits for ground water recharging. Arrangement shall be made that waste water and storm water do not get mixed.

29. NOC from Ground Water Board is to be submitted for drilling of tube well for use of Water Supply.

30. All the internal drains are to be covered till the disposal point. 31. This environmental clearance is issued subject to land use verification. Local authority / planning

authority should ensure this with respect to Rules, Regulations, Notifications, Government Resolutions,

Circulars, etc. issued if any.

32. Reflecting paint should be used on the roof top and side walls of the building tower for cooling effect.

13. Common Biomedical Waste Treatment Plant at Khasra No.- 906/13, Village-Gadery,

District-Mainpur,M/s Green House Waste Management. File No. 4588/Proposal No.

SIA/UP/MIS/30136/2018(Referred back by SEIAA to SEAC)

RESOLUTION AGAINST AGENDA NO-13

The committee opined that the complainer should be asked to appear in next SEAC meeting along with documentary evidence regarding his complaint.

14. Model Exims (India) Pvt. Ltd., at Gata No-1698, 1726, 1729, 1735, 1736 & 1739, Vill-Banthar,

Distt-Unnao, U.P., File No. 3479/Proposal No. SIA/UP/IND/37649/2015

A presentation was made by project proponent along with their consultant M/s Earth Protection Group

Environmental Consultants Pvt. Ltd. The proponent, through the documents submitted and the presentation

made, informed the committee that the terms of reference (TOR) for the above project was issued by SEIAA,

U.P. vide letter no. 70/praya/SEAC/3479/2015/AD(H) dated 03/06/2016. The validity period of the terms of

reference (TOR) letter dated 03/06/2016 was expired on 02/06/2019. The project proponent through letter dated

Page 26: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 26 of 45

30/05/2019 applied for the extension of validity period of terms of reference (TOR) letter dated 03/06/2016 for

the period of 01 years as per MoEF&CC O.M. No. J-11013/41/2006-IA-II(I) dated 29/08/2017.

The committee discussed the matter and recommended to extend the validity of terms of reference

(TOR) letter no. 70/praya/SEAC/3479/2015/AD(H) dated 03/06/2016 for the period of 01 years i.e. 03/06/2019

to 02/06/2020.

All other contents mentioned in the terms of reference (TOR) letter no. 70/praya/SEAC/3479/

2015/AD(H) dated 03/06/2016 shall remain unchanged.

15. Expansion of Production Capacity from 3 MTPA to 4MTPA at Cement Grinding plant at

Kundanganj, District-Raebareli, U.P., M/s RCCPL Pvt. Ltd. File No. 4859/Proposal No.

SIA/UP/IND/37475/2019

RESOLUTION AGAINST AGENDA NO-15

The committee discussed the matter and directed the project proponent to submit certified copy of the compliance report of the previous EC issued by the SEIAA. The matter will be discussed only after submission

of information as above in online prescribed portal

16. Proposed Cement Grinding Unit at Plot No.- D-11, UPSIDE, Shidhwan Industrial Area,

District- Jaunpur, U.P., M/s T T S Cement. File No. 4865/Proposal No.

SIA/UP/IND/37675/2019

A presentation was made by project proponent M/s T T S Cement. The proponent, through the

documents submitted and the presentation made, informed the committee that:-

1- The environmental clearance is sought for proposed Cement Grinding Unit at Plot No.- D-11, UPSIDE,

Shidhwan Industrial Area, District- Jaunpur, U.P., M/s T T S Cement. 2- Proposed item to be manufactured:

Portland Prozzolana Cement

� Proposed manufacturing capacity:

300 TPD or 90000 TPA

� Proposed manufacturing technology:

Mixing, Grinding, Blending & Packing .

� Proposed Investment:

Rs. 325.50 lacs

� Employment Potential:

20 Nos

� Land Area:

0.55 Acres

� Energy requirement:

Electricity – 250 KVA from PBBCL, UP

Standby D G sets – 20 KVA

� Water Requirement:

4 M3 per day – make up water

3- Land use details: SL No Usage at final stage Area acres

1 Manufacturing Plant Shed 0.09

2 Administrative offices, security etc. 0.04

Page 27: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 27 of 45

3 Entrance, Roads and Paved Area. 0.03

4 Green Belt 0.02

5 Vacant Space 0.19

Total 0.55

4- List of plant & machinery:

5- Material details: SL

No

Raw Materials Finished Goods

Raw

material

Quantity

(T/Ton of

Product)

Proposed

( Ton /

Day)

Source of Raw

Material

Finished Goods Proposed

Output

Quantity

1 Clinker 0.55 165 OCL Rajgagjpur/

Dalmia Cement

factory

Cement 300

2 Gypsum 0.05 15 Paradip / Rajasthan Waste (Process re-

use)

-

3 Fly Ash 0.40 120 Uttar Pradesh --

Total 1.00 300 Total 300

6- Solid waste generation & utilisation: Solid Waste Proposed Utilization

APC Dust & Process Loss 9 TPD Recycled to process

7- The project proposal falls under category–3(b) of EIA Notification, 2006 (as amended).

RESOLUTION AGAINST AGENDA NO-16

The committee discussed the matter and recommended to issue the terms of reference (TOR) for

the preparation of EIA as annexed at annexure-1 to these minutes.

17. Proposed Cement Grinding Unit at Plot No.- E-7,UPSIDC, Shidhwan Industrial Area,

District- Jaunpur, U.P, M/s Diamond Industries. File No. 4866/Proposal No.

SIA/UP/IND/37699/2019

A presentation was made by project proponent M/s Diamond Industries. The proponent, through the

documents submitted and the presentation made, informed the committee that:-

1- The environmental clearance is sought for Proposed Cement Grinding Unit at Plot No.- E-7,UPSIDC,

Shidhwan Industrial Area, District- Jaunpur, U.P, M/s Diamond Industries. 2- Proposed item to be manufactured :

Portland Prozzolana Cement

• Proposed manufacturing capacity:

200 TPD or 60000 TPA

• Proposed manufacturing technology:

Mixing, Grinding, Blending & Packing.

• Proposed Investment:

Rs. 246.50 lacs

• Employment Potential:

Page 28: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 28 of 45

20

• Land Area:

0.30 Acres

• Energy requirement:

Electricity – 200 KVA from PBBCL, UP

Standby D G sets – 20 KVA

• Water Requirement

4 M3 per day – make up water

3- Land use details: SL No Usage at final stage Area acres

1 Manufacturing Plant Shed 0.08

2 Administrative offices, security etc. 0.03

3 Entrance, Roads and Paved Area. 0.04

4 Green Belt 0.02

5 Vacant Space 0.13

Total 0.30

4- List of plant & machinery:

5- Material details: SL No Raw Materials Finished Goods

Raw

material

Quantity

(T/Ton of

Product)

Proposed

( Ton / Day)

Source of Raw

Material

Finished

Goods

Proposed Output

Quantity

1 Clinker 0.55 110 OCL Rajganjpur/

Dala Cement

factory

Cement 200

2 Gypsum 0.05 10 Paradip /

Rajasthan

Waste (Process

re-use)

-

3 Fly Ash 0.40 80 Uttar Pradesh --

Total 1.00 200 Total 200

6- Solid waste generation & utilisation: Solid Waste Proposed Utilization

APC Dust & Process Loss 6 TPD Recycled to process

7- The project proposal falls under category–3(b) of EIA Notification, 2006 (as amended).

RESOLUTION AGAINST AGENDA NO-17

The committee discussed the matter and recommended to issue the terms of reference (TOR) for

the preparation of EIA as annexed at annexure-1 to these minutes.

Page 29: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 29 of 45

18. Proposed Cement Grinding Unit at Plot No.-312, 313 & 314, UPSIDC, Shidhwan Industrial

Area, District- Jaunpur, U.P., M/s Avdhesh Cement Industries. File No. 4867/Proposal No.

SIA/UP/IND/37711/2019

A presentation was made by project proponent M/s Diamond Industries. The proponent, through the

documents submitted and the presentation made, informed the committee that:-

1- The environmental clearance is sought for Proposed Cement Grinding Unit at Plot No.-312, 313 & 314,

UPSIDC, Shidhwan Industrial Area, District- Jaunpur, U.P., M/s Avdhesh Cement Industries. 2- Proposed item to be manufactured :

Portland Prozzolana Cement

� Proposed manufacturing capacity

200 TPD or 60000 TPA

� Proposed manufacturing technology.

Mixing, Grinding, Blending & Packing .

� Proposed Investment

Rs. 246.50 lacs

� Employment Potential

20 Nos

� Land Area

1.30 Acres

� Energy requirement

Electricity – 200 KVA from PBBCL, UP

Standby D G sets – 20 KVA

� Water Requirement

4 M3 per day – make up water

3- Land use details:

SL No Usage at final stage Area acres

1 Manufacturing Plant Shed 0.26

2 Administrative offices, security etc. 0.163

3 Entrance, Roads and Paved Area. 0.07

4 Green Belt 0.43

5 Vacant Space 0.38

Total 1.30

4- List of plant & machinery:

5- Material details: SL No Raw Materials Finished Goods

Raw

material

Quantity

(T/Ton of

Product)

Proposed

( Ton / Day)

Source of Raw

Material

Finished

Goods

Proposed Output

Quantity

1 Clinker 0.55 110 OCL Rajganjpur/

Dala Cement

factory

Cement 200

2 Gypsum 0.05 10 Paradip /

Rajasthan

Waste (Process

re-use)

-

Page 30: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 30 of 45

3 Fly Ash 0.40 80 Uttar Pradesh --

Total 1.00 200 Total 200

6- Solid waste generation & utilisation: Solid Waste Proposed Utilization

APC Dust & Process Loss 6 TPD Recycled to process

7- The project proposal falls under category–3(b) of EIA Notification, 2006 (as amended).

RESOLUTION AGAINST AGENDA NO-18

The committee discussed the matter and recommended to issue the terms of reference (TOR) for

the preparation of EIA as annexed at annexure-1 to these minutes.

19. Expansion of "Sharda Institutional Area" at Plot No.-32 and 34, Knowledge Park- III,

Greater Noida, District- Gautam Budh Nagar, U.P., M/s Sharda Education Trust. File No.

4868/Proposal No. SIA/UP/NCP/37738/2019

A presentation was made by the project proponent along with their consultant M/s Aplinka Solutions &

Technologies Pvt. Ltd. The proponent, through the documents submitted and the presentation made, informed

the committee that:-

1. The environmental clearance is sought for Expansion of "Sharda Institutional Area" at Plot No.-32 and

34, Knowledge Park- III, Greater Noida, District- Gautam Budh Nagar, U.P., M/s Sharda Education

Trust.

2. Environment Clearance for the earlier proposal was issued by SEIAA, U.P. vide letter no.

1090/SEAC/308/2009/AD(H) dated 09th July 2010.

3. Comparative details for the earlier and expansion project:

Sr. No. PARTICULARS Existing Revision Expansion Total

1. Total Plot Area 2,53,964.68 m2

2. Total Built up Area 3,17,356.56 m2 0 1,56,577.54 m2 4,73,934.096 m2

3. Landscape Area 1,06,963.4513 m2 11,130.0412 m2 0 95,833.41 m2

4. Estimated Population 6,520 0 6580 13100

5. Total water requirement 762 KLD 0 732 KLD 1494KLD

6. Fresh water 320 KLD 0 389 KLD 709 KLD

6. Wastewater generation 518 KLD 0 511 KLD 1029KLD

7. STP capacity 400 KLD 0 800 KLD 1200 KLD

8. ETP Capacity 30 KLD 20 KLD 50 KLD

8. Total Power

Requirement

8,800 kVA (demand load)

9. Total Power Backup 3,250 KVA (1 x 1,500 kVA + 1x 1,000 +1 x 750 kVA )

10. Total solid waste

generated

2,577.78 Kg/day 3079.7kg/day 5657.48 kg/day

11. Bio medical waste 270 Kg/day 180 Kg/day 450 Kg/day

12. No. RWH pits for storm

water Management

27 Pits

13. Parking Details

(in ECS)

3,146 ECS

4. Area details of the project:

S. No. Particulars Existing Expansion Revision Total

(in m2) (in m2) (in m2) (in m2)

1 Plot Area 2,53,964.68

Page 31: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 31 of 45

2 Permissible Ground

Coverage (@30% of the

plot area)

76189.40

3 Proposed Ground

Coverage

41,735.61 22,137.00 0.00 63,872.61

(16.43 % of Plot

Area)

(8.71 % of Plot

area)

….. (25.15 % of plot

area)

4 Open Area (1-3) 2,12,229.07 0.000 -22,137.000 1,90,092.070

5 Required Green Area 1,06,114.54 ………. ……….. 95,046.04

6

Green Area Achieved

1,06,963.4513 0 -11,130.04128 95,833.41

(50.4% of Open

area)

(50.41% of Open

area

7 Surface Parking Area 57,819

8 Area under Road

pavements

36,440

9 Total Permissible FAR

[9(a)+9(b)

438,089

9(a) Permissible FAR @ 1.5 3,80,947.02

9(b) Permissible Ancillary FAR

@15%

57,142.053

10 Total Proposed FAR [10(a)+10(b)]

2,93,787.9 1,24,420.76 0 4,18,208.66

10(a) Proposed FAR 2,61,064.84 @1 1,19,882.18 0 3,80,947.02 @1.5

10(b) Proposed Ancillary FAR 32,723.06

@12.53%

4,538.58 0 37,261.64

@ 9.78 %

11 Proposed Non FAR area 23,568.66 32,156.78 0.00 55,725.44

11(a) Non FAR of Towers 12,880.66 1,950.42 0.00 14,831.08

11(b) Basement area 10,688.00 30,206.36 0.00 40,894.36

12 Built Up Area (10+11) 3,17,356.56 1,56,577.54 0.00 4,73,934.096

13 Maximum Building Height 29.9 meter … …… 49.5 meter

5. Population details:

Particular Existing (A) Revision/Expansion(B) Total (A+B)

Population 6,520 6580 13,100

6. Water requirement for the entire project:

Sr. No. Particular Existing(A)

(in KLD)

Revision/Expansion(B) (in KLD) Total (A+B) (in KLD)

1 Total water Demand 762 732 1494

2 Fresh water Demand 320 389 709

3 Treated water 442 343 785

4 Wastewater 518 511 1029

5 STP Capacity 400 800 1200

6 ETP capacity 30 20 50

7. The total water demand during the operation phase (after revision & expansion) will be 1494 KLD. The

fresh water requirement for the project will be estimated approx. 709 KLD and treated water

requirement will be estimated approx. 785 KLD.

8. The Fresh Water requirement for the project will be met by Municipal Supply (Greater Noida authority)

9. STP of capacity 1200 KLD provisioned for treating the wastewater of quantum 989 KLD and ETP of

capacity 50 KLD for treating 40 KLD effluent ( 400 KLD STP and 30 KLD ETP already has been

installed at project site).

10. Treated water will be used in flushing, Chiller plant and horticulture within the project site.

11. 42 KLD treated water will be discharged through drain during non rainy season.

12. Parking details:

S. N. Parking No. of Car No. of Bus No. Of ambulance

1 Open area 1,847 298 212

Page 32: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 32 of 45

2 Basement 1,007 …. ….

3 Multilevel Parking 1,500 … ….

Total 4,354 298 212

13. Solid waste details:

Sr. No. Particular Solid waste generation in Kg /day

1 Solid waste generation in existing Phase 2,577.78

2 Solid Waste Generation in expansion phase 3079.7

3 Total waste generation for complete project 5657.48

14. The project proposal falls under category–8(b) of EIA Notification, 2006 (as amended).

RESOLUTION AGAINST AGENDA NO-19

For the preparation of EIA report, the request was made by the project proponent to consider the

baseline data for the period of March to May, 2019 vide letter dated 07/07/2019. The committee discussed

the matter and concurred with the request and recommended to issue the terms of reference (TOR) for

the preparation of EIA as mentioned in MoEFCC, OM No. J-11013/41/2008-IA-II(I) (Part) dated

29/08/2017:-

1. Certified compliance report issued by Regional Office, MoEF&CC, Lucknow for the earlier EC issued

by SEIAA.

2. Master plan of the area showing proposed project. Permissible uses of the proposed site as per zoning

regulation.

3. Allotment letter from concerned development authority.

4. All approved drawings/maps alongwith approved services plans.

5. Structural design certificate signed by the architect and vetting authority should be submitted. All

structural design drawings should be signed by architect and counter signed by vetting authority.

6. Area details showing proposed uses as residential, commercial, parks, parking, roads, other services,

facilities of the project also in percentage.

7. Physical features within 30 m of the project sites with their ownership.

8. Complete Details of facilities to be developed by the project proponent i.e. for which environment

clearance is sought.

9. Use of reflecting paints on roof top and side walls.

10. Details of rain water harvesting are to be given.

11. Provision of 100% solar lighting along the road site, stair cases, common places.

12. Plan for EWS / LIG housing provision as per Development Authority bye-laws.

13. Examine in detail the proposed site with reference to impact on infrastructure covering water supply,

storm water drainage, sewerage, power, etc., and the disposal of treated/raw wastes from the complex on

land/water body and into sewerage system. Consider soil characteristics and permeability for rainwater

harvesting proposals, should be made to prevent ground water contamination. Maximize use of treated

water by recycling and utilization of rainwater.

14. Water requirement and its management plan along with necessary permissions for discharge.

15. An underground Pucca tank with kaccha base for collection/reuse of rain water may be constructed.

16. Hydro-geological investigations to be carried out and obtain permission from Central Ground Water

Authority for withdrawal of ground water.

17. Make provision for safety against failure in the operation of wastewater treatment facilities. Identify

acceptable outfall for treated effluent.

18. Details of green belt as a measure for mitigation of dust and noise and buffer between habitation and

proposed project.

Page 33: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 33 of 45

19. Landscape plan, green belts and open spaces may be described separately.

20. Study the existing flora and fauna of the area and the impact of the project on them. There should be no

basement below 15 m setback. Accordingly, the Plan should be revised and submitted.

21. Section of all internal roads should be provided. Right of way and carriage way width should be clearly

marked on the map. Avoid entry/exit at point of junction of roads. Traffic movement plan in and out

should be shown.

22. Examine existing crèche, education, health facilities, police, post Office, Banks and other services and

make adequate provisions in the proposal.

23. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.

24. Application of renewable energy/alternate energy, such as solar and wind energy may be described

including solar water heating in the guidelines for entrepreneurs.

25. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.

26. Identification of recyclable wastes and waste utilization arrangements may be made.

27. Explore possibility of generating biogas from biodegradable wastes.

28. Arrangements for hazardous waste management may be described as also the common facilities for

waste collection, treatment, recycling and disposal of all effluent, emission and refuse including MSW,

biomedical and hazardous wastes. Special attention should be made with respect to bird menace.

29. Provisions made for safety in storage of materials, products and wastes may be described.

30. Disaster management plan should be prepared.

31. Traffic management plan including parking and loading/unloading areas may be described. Traffic

survey should be carried out both on weekdays and weekend.

32. Parking provision is to be made for higher ECS worked out either as per state bye-laws or construction

manual of the MoEF. Additional parking (more than required nos. as per norms) will not be permitted.

33. Exclusive Parking area in the basement (excluding other facilities) and surface is to be clearly

mentioned.

34. Provide service road for entry and exit to project site.

35. Use of local building materials should be described.

36. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with provisions

of sampling port for monitoring to be described. Power backup should be restricted to 50-60 % of power

requirement. Plan should be revised and submitted.

37. Work out MGLC for the combined capacity of DG sets.

38. Provide for conservation of resources, energy efficiency and use of renewable sources of energy in the

light of ECBC code.

39. Application of resettlement and rehabilitation policy may be described. Project affected persons should

be identified and rehabilitation and resettlement plan should be prepared.

40. Examine separately the details for construction and operation phases both for Environmental Monitoring

Plan and Environmental Management Plan.

41. Corporate Environmental Responsibility (CER) shall be prepared by the project proponent and the

details of the various heads of expenditure to be submitted as per the guidelines provided in the recent

CER notification No. 22-65/2017-IA.III dated 01/05/2018.A copy of resolution as above shall be

submitted to the authority along with list of beneficiaries with their mobile nos./address.

42. Required no of trees should be proposed @ 01 tree/80 m2, submit plan.

43. Project falling within 10 Km. area of Wild Life Sanctuary is to obtain a clearance from National Board

Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.

44. Declare/submit the running cost of STP and other environmental management services (e.g., Municipal

Solid Waste Disposal, Green belt Maintenance, Water Management etc.) in the proposals which are to

Page 34: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 34 of 45

be including in the allotment letters. Vendors should be identified for Municipal Solid Waste

Management and submitted.

45. The proponent will submit the schedule of monitoring/data collection programme to the Office of

Directorate, Member Secretary, UP Pollution Control Board and District Magistrate of related District.

General Guidelines:

a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly attested by Public

Notary, stating that:

I. “There is no litigation pending against the project and/or land in which the project is proposed to be

set up (please give name & ownership etc. of the project) and that for any such litigation what so

ever, the sole responsibility will be borne by the Project proponent.”

II. “No activity relating to this project (i.e. name of the project) including civil construction has been

undertaken at site except fencing of the site to protect it from getting encroached and construction of

temporary shed(s) for the guard(s). (if fencing has not been done, then the same may be deleted).

III. “I/We hereby give undertaking that the data and information given in the application, enclosures

and other documents are true to the best of my knowledge and belief and I/We am/are aware that if

any part of the data and information submitted is found to be false or misleading at any stage, the

project will be rejected and clearance given, if any to the Project will be revoked at our risk and

cost.”

IV. Project does not fall under any buffer zone of no-development as declared /identified under any law.

b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been complied with

(to be deleted if not applicable) & (b) that details and the data presented are factually correct”, as per

MoEF circular dated 04.08.2009 is also to be submitted along with EIA.

c. Current site photographs viewing towards the project area from four directions indicating date of

photograph taken, direction from which taken, name of the project, and signature of Project proponent

along with consultant with seal should be submitted, so as to ensure that no construction has been

started before the grant of EC.

d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification of 2006 and

the Methods of Monitoring and analysis (Annexure-IV): Guidance for assessment of representativeness

and reliability of baseline environmental attributes detailed under EIA manual January, 2001 and other

guidelines in the matter.

e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically mentioned. The

consultant shall certify that his accreditation is for the sector for which this EIA is prepared.

f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along with their

complete details including their accreditation, if any shall be indicated.

g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in the

preparation of these reports and the Name of laboratory through which the samples have been got

analysed should be stated in the report. It shall clearly be indicated whether said laboratory is accredited

by NABL or approved under the Environment (Protection) Act, 1986 (Please refer MoEF office

memorandum dated 4th August, 2009). The name project leader of the EIA study shall also be

mentioned.

h. The EIA document shall be printed on both sides, as far as possible.

The Information’s no (a I , II, III & c) asked under the general guidelines is to be submitted

within 15 days from the date of receipt of the letter and remaining of the information’s is to be

submitted along with the EIA.

Page 35: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 35 of 45

20. Revision & Expansion of Commercial Project “Spectrum@Metro-II” Plot No.- A & B, Eco

City, Sector- 75, Noida, U.P., M/s AIMS Max Gardenia Developers Pvt. Ltd. File No.

4874/Proposal No. SIA/UP/NCP/37899/2019

A presentation was made by the project proponent along with their consultant M/s Ambential Global

Pvt. Ltd. The proponent, through the documents submitted and the presentation made, informed the committee

that:-

1. The environmental clearance is sought for Revision & Expansion of Commercial Project

Spectrum@Metro-II" Plot No.- A & B, Eco City, Sector- 75, Noida, U.P., M/s AIMS Max Gardenia

Developers Pvt. Ltd.

2. Environment Clearance for the earlier proposal was issued by SEIAA, U.P. vide letter no.

535/Parya/SEAC/4544/2018 dated November 29, 2018 for the built-up area 1,40,360.19 m2 and plot

area 30,934 respectively.

3. Salient features of the project:

Description Proposed

Plot Area 34,531.00 m2

Built-up Area 1,53,380.492 m2

Green Area 10,784.825 m2 @ 31.23 % of Total Plot Area

Total Water Requirement 915 KLD

Fresh Water Requirement 194 KLD

Wastewater Generation 608 KLD

Capacity of STP 750 KLD

Solid Waste Generation 2,833 kg/day

Parking Required & Provided 2071 ECS & 2135 ECS

Power Demand & Source 8,493kVA (Noida Power Company Limited)

Back up 13,010 kVA (6 x 2000 kVA + 1 x 1010 kVA)

RWH Pits 10 pits

Project Cost 1,600 Crores

Expected Date of Completion of project 5 years

4. Comparative area details:

S. No. Particulars Area (m2)

As per Earlier EC Post Revision & Expansion

1. Total Plot Area 30,934.00 34,531.00

2. Permissible Ground Coverage 12,373.60 (@ 40% of Total Plot Area)

13,812.400 (@ 40% of Total Plot Area)

3. Proposed Ground Coverage 10,188.00

(@ 32.93% of Plot Area)

13,164.785

(@ 38.12% of Plot Area)

4. Total Permissible F.A.R.

Permissible Commercial F.A.R.

92,802.00

(@ 3.00 of the Plot Area)

1,03,593.000

(@ 3.00 of the Plot Area)

5. Total Proposed F.A.R.

Proposed Commercial F.A.R.

Meter Room

76,074.59

76,074.59

Nil

1,03,532.268

1,03,520.268

12.00

6. Non F.A.R. Area

Basement 1

Basement 2

Basement 3

Service Floor

49,725.16

9063.82

20330.67

20330.67

Not Included In Non FAR *1

40,898.987

19221.989

20380.763

Nil

1296.235

(Included In Non FAR *2)

7. Proposed Area in 15% Facility Area (Fire Stair Case + Lift Lobby + Mumty +

Machine Room + Lift Shafts + Service

Shafts+ Guard Room +Visitor Toilets)

11,348.57 8,949.237

Page 36: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 36 of 45

8. Service Floor Area 3,211.87 (Included In Non FAR *2)

9. Total Built-Up Area (5+6+7+8) 1,40,360.19

(5+6+7+8)

1,53,380.492

(5+6+7+8)

10. Open Area 20,746.00

(@ 67.06% of Total Plot Area)

21,366.215

(@ 61.88% of Total Plot

Area)

11. Landscape Area 10,550.00

(@ 34.10% of Total Plot Area)

10,784.825

(@ 31.23% of Total Plot

Area)

12. Height of the Highest Building 85.45 m 84.90 m

5. Water requirement details:

S. No. Description Occupancy Rate of water

demand (lpcd)

Total Water

Requirement

(KLD)

A. DOMESTIC WATER

(a)

(b)

(c)

(d)

Staff – (Including Shops, Food Courts,

Restaurants, Auditorium, Banquet/Club,

Entertainment Zones & Service Apartments)

Visitor – (Including Shops, Auditorium,

Banquet/Club, Entertainment Zones & Service

Apartments)

Visitor– (Food Court & Restaurants)

Guest – (Services Apartments)

2,115

16,182

3,237

960

@ 45

@ 15

@ 70

@ 86

95.17

242.73

226.59

82.56

TOTAL DOMESTIC WATER DEMAND 647.05 say 647 KLD

B. HORTICULTURE 10,784.825

m2

3 lt/sqm/day 33

C. HVAC COOLING

(12 Hours)

2800 TR 7 lt/Tr/hr 235

GRAND TOTAL (A+B+C) 915 KLD

6. Solid waste generation details:

S. No. Category kg per capita per day Waste generated (kg/day)

1. Domestic Waste

(a) Staffs 2,115 @ 0.25 kg/day 528.75

(b) Visitors 19,419 @ 0.15 kg/day 2,912.85

(c) Service Apartment Guests 960 @ 0.50 kg/day 480

2. Landscape waste

(2.66 acres)

@ 0.2 kg/acre/day 0.6

TOTAL SOLID WASTE GENERATED 3,922.2 kg/day say

3,922 kg/day

7. Parking details:

Description As Per Earlier EC Post Revision & Expansion

Parking Required 1521 ECS 2071 ECS

Parking Proposed 2211ECS 2135 ECS

8. The project proposal falls under category–8(b) of EIA Notification, 2006 (as amended).

RESOLUTION AGAINST AGENDA NO-20

The committee discussed the matter and recommended to issue the terms of reference (TOR) for

the preparation of EIA regarding the project:

1. Master plan of the area showing proposed project. Permissible uses of the proposed site as per zoning

regulation.

Page 37: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 37 of 45

2. Allotment letter from concerned development authority.

3. All approved drawings/maps alongwith approved services plans.

4. Structural design certificate signed by the architect and vetting authority should be submitted. All

structural design drawings should be signed by architect and counter signed by vetting authority.

5. Area details showing proposed uses as residential, commercial, parks, parking, roads, other services,

facilities of the project also in percentage.

6. Physical features within 30 m of the project sites with their ownership.

7. Complete Details of facilities to be developed by the project proponent i.e. for which environment

clearance is sought.

8. Use of reflecting paints on roof top and side walls.

9. Details of rain water harvesting are to be given.

10. Provision of 100% solar lighting along the road site, stair cases, common places.

11. Plan for EWS / LIG housing provision as per Development Authority bye-laws.

12. Examine in detail the proposed site with reference to impact on infrastructure covering water supply,

storm water drainage, sewerage, power, etc., and the disposal of treated/raw wastes from the complex on

land/water body and into sewerage system. Consider soil characteristics and permeability for rainwater

harvesting proposals, should be made to prevent ground water contamination. Maximize use of treated

water by recycling and utilization of rainwater.

13. Water requirement and its management plan along with necessary permissions for discharge.

14. An underground Pucca tank with kaccha base for collection/reuse of rain water may be constructed.

15. Hydro-geological investigations to be carried out and obtain permission from Central Ground Water

Authority for withdrawal of ground water.

16. Make provision for safety against failure in the operation of wastewater treatment facilities. Identify

acceptable outfall for treated effluent.

17. Details of green belt as a measure for mitigation of dust and noise and buffer between habitation and

proposed project.

18. Landscape plan, green belts and open spaces may be described separately.

19. Study the existing flora and fauna of the area and the impact of the project on them. There should be no

basement below 15 m setback. Accordingly, the Plan should be revised and submitted.

20. Section of all internal roads should be provided. Right of way and carriage way width should be clearly

marked on the map. Avoid entry/exit at point of junction of roads. Traffic movement plan in and out

should be shown.

21. Examine existing crèche, education, health facilities, police, post Office, Banks and other services and

make adequate provisions in the proposal.

22. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.

23. Application of renewable energy/alternate energy, such as solar and wind energy may be described

including solar water heating in the guidelines for entrepreneurs.

24. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.

25. Identification of recyclable wastes and waste utilization arrangements may be made.

26. Explore possibility of generating biogas from biodegradable wastes.

27. Arrangements for hazardous waste management may be described as also the common facilities for

waste collection, treatment, recycling and disposal of all effluent, emission and refuse including MSW,

biomedical and hazardous wastes. Special attention should be made with respect to bird menace.

28. Provisions made for safety in storage of materials, products and wastes may be described.

29. Disaster management plan should be prepared.

30. Traffic management plan including parking and loading/unloading areas may be described. Traffic

Page 38: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 38 of 45

survey should be carried out both on weekdays and weekend.

31. Parking provision is to be made for higher ECS worked out either as per state bye-laws or construction

manual of the MoEF. Additional parking (more than required nos. as per norms) will not be permitted.

32. Exclusive Parking area in the basement (excluding other facilities) and surface is to be clearly

mentioned.

33. Provide service road for entry and exit to project site.

34. Use of local building materials should be described.

35. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with provisions

of sampling port for monitoring to be described. Power backup should be restricted to 50-60 % of power

requirement. Plan should be revised and submitted.

36. Work out MGLC for the combined capacity of DG sets.

37. Provide for conservation of resources, energy efficiency and use of renewable sources of energy in the

light of ECBC code.

38. Application of resettlement and rehabilitation policy may be described. Project affected persons should

be identified and rehabilitation and resettlement plan should be prepared.

39. Examine separately the details for construction and operation phases both for Environmental Monitoring

Plan and Environmental Management Plan.

40. Corporate Environmental Responsibility (CER) shall be prepared by the project proponent and the

details of the various heads of expenditure to be submitted as per the guidelines provided in the recent

CER notification No. 22-65/2017-IA.III dated 01/05/2018.A copy of resolution as above shall be

submitted to the authority along with list of beneficiaries with their mobile nos./address.

41. Required no of trees should be proposed @ 01 tree/80 m2, submit plan.

42. Project falling within 10 Km. area of Wild Life Sanctuary is to obtain a clearance from National Board

Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.

43. Declare/submit the running cost of STP and other environmental management services (e.g., Municipal

Solid Waste Disposal, Green belt Maintenance, Water Management etc.) in the proposals which are to

be including in the allotment letters. Vendors should be identified for Municipal Solid Waste

Management and submitted.

44. The proponent will submit the schedule of monitoring/data collection programme to the Office of

Directorate, Member Secretary, UP Pollution Control Board and District Magistrate of related District.

General Guidelines:

a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly attested by Public

Notary, stating that:

I. “There is no litigation pending against the project and/or land in which the project is proposed to be

set up (please give name & ownership etc. of the project) and that for any such litigation what so

ever, the sole responsibility will be borne by the Project proponent.”

II. “No activity relating to this project (i.e. name of the project) including civil construction has been

undertaken at site except fencing of the site to protect it from getting encroached and construction of

temporary shed(s) for the guard(s). (if fencing has not been done, then the same may be deleted).

III. “I/We hereby give undertaking that the data and information given in the application, enclosures

and other documents are true to the best of my knowledge and belief and I/We am/are aware that if

any part of the data and information submitted is found to be false or misleading at any stage, the

project will be rejected and clearance given, if any to the Project will be revoked at our risk and

cost.”

IV. Project does not fall under any buffer zone of no-development as declared /identified under any law.

Page 39: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 39 of 45

b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been complied with

(to be deleted if not applicable) & (b) that details and the data presented are factually correct”, as per

MoEF circular dated 04.08.2009 is also to be submitted along with EIA.

c. Current site photographs viewing towards the project area from four directions indicating date of

photograph taken, direction from which taken, name of the project, and signature of Project proponent

along with consultant with seal should be submitted, so as to ensure that no construction has been

started before the grant of EC.

d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification of 2006 and

the Methods of Monitoring and analysis (Annexure-IV): Guidance for assessment of representativeness

and reliability of baseline environmental attributes detailed under EIA manual January, 2001 and other

guidelines in the matter.

e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically mentioned. The

consultant shall certify that his accreditation is for the sector for which this EIA is prepared.

f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along with their

complete details including their accreditation, if any shall be indicated.

g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in the

preparation of these reports and the Name of laboratory through which the samples have been got

analysed should be stated in the report. It shall clearly be indicated whether said laboratory is accredited

by NABL or approved under the Environment (Protection) Act, 1986 (Please refer MoEF office

memorandum dated 4th August, 2009). The name project leader of the EIA study shall also be

mentioned.

h. The EIA document shall be printed on both sides, as far as possible.

The Information’s no (a I , II, III & c) asked under the general guidelines is to be submitted

within 15 days from the date of receipt of the letter and remaining of the information’s is to be

submitted along with the EIA.

21. "Gomti River Front Channelization Project from Harding to Gomti Weir, District-

Lucknow, U.P. M/s Irrigation and Water Resource Department. File No. 4576/4206/Proposal

No. SIA/UP/MIS/29978/2018

RESOLUTION AGAINST AGENDA NO-21

The committee noted that the matter was earlier discussed in 289th SEIAA Meeting dated 01/07/2019

and directed is as follows:

“A revised EIA has been submitted by the project proponent in response to the query of SEIAA raised

in its meeting dated 09-03-2019. SEIAA opined that the revised EIA shall be referred to SEAC for its

appraisal/assessment before consideration of SEIAA.”

As per the direction of SEIAA, the matter was listed in SEAC meeting dated 11/07/2019. A presentation

was made by the project proponent along with their consultant M/s Voyants. The committee discussed the

matter and directed the project proponent to submit following information:

1. The data on aquatic ecology presented seems to be erroneous as it shows no change in aquatic ecology

in project site as compared to upstream and downstream. The data needs revision in terms of total

species indentified, densities of biotic communities, species diversity of phytoplankton/zooplankton,

Page 40: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 40 of 45

macro-invertebrates, benthic organism, quantitative analysis of phytoplankton/zooplankton and benthic

organisms.

2. The no. of samples taken for study should also be mentioned.

3. The amount of sample taken for counts should be mentioned to know the unit.

4. The species found in abundance is also to be mentioned.

5. The data of aquatic biodiversity is to be co-related with the physico chemical characteristics of the water

of Gomti River.

6. Shernor Wiener index may be applied on the data to account species richness and proportion of each

species within the local aquatic community. The value of this index will indicate the status of pollution

in river.

The matter will be discussed only after submission of online information on prescribed online portal.

(Dr. Sarita Sinha)

Member

(Dr. Arvind Mathur)

Member

(Dr. Virendra Misra)

Member

(Dr. Pramod Kumar Mishra)

Member

(Dr. Richhpal Singh Sangu)

Member

(Dr. Ajoy Kumar Mandal)

Member

(Shri Meraj Uddin)

Member

(Shri Rajive Kumar)

Member

(Dr. (Prof.) S. N. Singh)

Chairman

Page 41: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 41 of 45

Annexure-1

Terms of reference (TOR) for the Cement Grinding Unit Project

1) Independent chapter in the EIA report by the accredited consultants.

2) Executive Summary 3) Introduction

i. Details of the EIA Consultant including NABET accreditation

ii. Information about the project proponent iii. Importance and benefits of the project

4) Project Description

i. Cost of project and time of completion.

ii. Products with capacities for the proposed project. iii. If expansion project, details of existing products with capacities and whether adequate land is

available for expansion, reference of earlier EC if any.

iv. List of raw materials required and their source along with mode of transportation.

v. Other chemicals and materials required with quantities and storage capacities vi. Details of Emission, effluents, hazardous waste generation and their management.

vii. Requirement of water, power, with source of supply, status of approval, water balance diagram, man-

power requirement (regular and contract)

viii. Process description along with major equipments and machineries, process flow sheet

(quantative) from raw material to products to be provided

ix. Hazard identification and details of proposed safety systems. x. Expansion/modernization proposals:

a. Copy of all the Environmental Clearance(s) including Amendments thereto obtained for the

project from MOEF/SEIAA shall be attached as an Annexure. A certified copy of the latest

Monitoring Report of the Regional Office of the Ministry of Environment and Forests as per

circular dated 30th May, 2012 on the status of compliance of conditions stipulated in all the

existing environmental clearances including Amendments shall be provided. In addition,

status of compliance of Consent to Operate for the ongoing existing operation of the project

from SPCB shall be attached with the EIA-EMP report.

b. In case the existing project has not obtained environmental clearance, reasons for not taking

EC under the provisions of the EIA Notification 1994 and/or EIA Notification 06 shall be

provided. Copies of Consent to Establish/No Objection Certificate and Consent to Operate (in

case of units operating prior to EIA Notification 2006, CTE and CTO of FY 2005-2006)

obtained from the SPCB shall be submitted. Further, compliance report to the conditions of

consents from the SPCB shall be submitted.

5) Site Details i. Location of the project site covering village, Taluka/Tehsil, District and State, Justification for

selecting the site, whether other sites were considered.

ii. A toposheet of the study area of radius of 10km and site location on 1:50,000/1:25,000 scale on an

A3/A2 sheet. (including all eco-sensitive areas and environmentally sensitive places)

iii. Details w.r.t. option analysis for selection of site

iv. Co-ordinates (lat-long) of all four corners of the site.

v. Google map-Earth downloaded of the project site. vi. Layout maps indicating existing unit as well as proposed unit indicating storage area, plant area,

greenbelt area, utilities etc. If located within an Industrial area/Estate/Complex, layout of

Page 42: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 42 of 45

Industrial Area indicating location of unit within the Industrial area/Estate.

vii. Photographs of the proposed and existing (if applicable) plant site. If existing, show

photographs of plantation/greenbelt, in particular.

viii. Landuse break-up of total land of the project site (identified and acquired), government/

private - agricultural, forest, wasteland, water bodies, settlements, etc shall be included. (not

required for industrial area)

ix. A list of major industries with name and type within study area (10km radius) shall be

incorporated. Land use details of the study area

x. Geological features and Geo-hydrological status of the study area shall be included.

xi. Details of Drainage of the project upto 5km radius of study area. If the site is within 1 km

radius of any major river, peak and lean season river discharge as well as flood occurrence

frequency based on peak rainfall data of the past 30 years. Details of Flood Level of the

project site and maximum Flood Level of the river shall also be provided. (mega green field

projects)

xii. Status of acquisition of land. If acquisition is not complete, stage of the acquisition process and

expected time of complete possession of the land.

xiii. R&R details in respect of land in line with state Government policy

6) Forest and wildlife r elated issues (if applicable):

i. Permission and approval for the use of forest land (forestry clearance), if any, and

recommendations of the State Forest Department. (if applicable)

ii. Landuse map based on High resolution satellite imagery (GPS) of the proposed site delineating the

forestland (in case of projects involving forest land more than 40 ha).

iii. Status of Application submitted for obtaining the stage I forestry clearance along with latest

status shall be submitted.

iv. The projects to be located within 10 km of the National Parks, Sanctuaries, Biosphere Reserves,

Migratory Corridors of Wild Animals, the project proponent shall submit the map duly

authenticated by Chief Wildlife Warden showing these features vis-à-vis the project location and

the recommendations or comments of the Chief Wildlife Warden-thereon.

v. Wildlife Conservation Plan duly authenticated by the Chief Wildlife Warden of the State

Government for conservation of Schedule I fauna, if any exists in the study area

vi. Copy of application submitted for clearance under the Wildlife (Protection) Act, 1972, to the

Standing Committee of the National Board for Wildlife

7) Environmental Status:

i. Determination of atmospheric inversion level at the project site and site-specific micro-

meteorological data using temperature, relative humidity, hourly wind speed and direction and

rainfall.

ii. AAQ data (except monsoon) at 8 locations for PM10, PM2.5, SO2, NOX, CO and other

parameters relevant to the project shall be collected. The monitoring stations shall be based

CPCB guidelines and take into account the pre-dominant wind direction, population zone and

sensitive receptors including reserved forests.

iii. Raw data of all AAQ measurement for 12 weeks of all stations as per frequency given in the

NAQQM Notification of Nov. 2009 along with - min., max., average and 98% values for each

of the AAQ parameters from data of all AAQ stations should be provided as an annexure to the EIA

Page 43: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 43 of 45

Report.

iv. Surface water quality of nearby River (100m upstream and downstream of discharge point) and

other surface drains at eight locations as per CPCB/MoEF&CC guidelines.

v. Whether the site falls near to polluted stretch of river identified by the CPCB/MoEF&CC, if yes

give details.

vi. Ground water monitoring at minimum at 8 locations shall be included. vii. Noise levels monitoring at 8 locations within the study area.

viii. Soil Characteristic as per CPCB guidelines.

ix. Traffic study of the area, type of vehicles, frequency of vehicles for transportation of materials,

additional traffic due to proposed project, parking arrangement etc.

x. Detailed description of flora and fauna (terrestrial and aquatic) existing in the study area shall

be given with special reference to rare, endemic and endangered species. If Schedule- I fauna

are found within the study area, a Wildlife Conservation Plan shall be prepared and furnished.

xi. Socio-economic status of the study area.

8) Impact and Environment Management Plan

i. Assessment of ground level concentration of pollutants from the stack emission based on site-

specific meteorological features. In case the project is located on a hilly terrain, the AQIP

Modelling shall be done using inputs of the specific terrain characteristics for determining the

potential impacts of the project on the AAQ. Cumulative impact of all sources of emissions

(including transportation) on the AAQ of the area shall be assessed. Details of the model used and

the input data used for modelling shall also be provided. The air quality contours shall be plotted

on a location map showing the location of project site, habitation nearby, sensitive receptors, if

any.

ii. Water Quality modelling - in case of discharge in water body iii. Impact of the transport of the raw materials and end products on the surrounding environment shall

be assessed and provided. In this regard, options for transport of raw materials and finished

products and wastes (large quantities) by rail or rail-cum road transport or conveyor- cum-rail

transport shall be examined.

iv. A note on treatment of wastewater from different plant operations, extent recycled and reused for

different purposes shall be included. Complete scheme of effluent treatment. Characteristics of

untreated and treated effluent to meet the prescribed standards of discharge under E(P) Rules.

v. Details of stack emission and action plan for control of emissions to meet standards.

vi. Measures for fugitive emission control

vii. Details of hazardous waste generation and their storage, utilization and management. Copies of

MOU regarding utilization of solid and hazardous waste in cement plant shall also be

included. EMP shall include the concept of waste-minimization, recycle/reuse/recover

techniques, Energy conservation, and natural resource conservation.

viii. Proper utilization of fly ash shall be ensured as per Fly Ash Notification, 2009. A detailed plan

of action shall be provided.

ix. Action plan for the green belt development plan in 33 % area i.e. land with not less than

1,500 trees per ha. Giving details of species, width of plantation, planning schedule etc. shall be

included. The green belt shall be around the project boundary and a scheme for greening of the

roads used for the project shall also be incorporated.

x. Action plan for rainwater harvesting measures at plant site shall be submitted to harvest

rainwater from the roof tops and storm water drains to recharge the ground water and also to use

Page 44: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 44 of 45

for the various activities at the project site to conserve fresh water and reduce the water

requirement from other sources.

xi. Total capital cost and recurring cost/annum for environmental pollution control measures shall

be included.

xii. Action plan for post-project environmental monitoring shall be submitted.

xiii. Onsite and Offsite Disaster (natural and Man-made) Preparedness and Emergency Management Plan

including Risk Assessment and damage control. Disaster management plan should be linked

with District Disaster Management Plan.

9) Occupational health:

i. Plan and fund allocation to ensure the occupational health & safety of all contract and casual

workers

ii. Details of exposure specific health status evaluation of worker. If the workers' health is being

evaluated by pre designed format, chest x rays, Audiometry, Spirometry, Vision testing (Far &

Near vision, colour vision and any other ocular defect) ECG, during pre placement and

periodical examinations give the details of the same. Details regarding last month analyzed data

of above mentioned parameters as per age, sex, duration of exposure and department wise.

iii. Details of existing Occupational & Safety Hazards. What are the exposure levels of hazards and

whether they are within Permissible Exposure level (PEL). If these are not within PEL, what

measures the company has adopted to keep them within PEL so that health of the workers can be

preserved,

iv. Annual report of heath status of workers with special reference to Occupational Health and

Safety.

10) Corporate Environment Policy: i. Does the company have a well laid down Environment Policy approved by its Board of

Directors? If so, it may be detailed in the EIA report.

ii. Does the Environment Policy prescribe for standard operating process / procedures to bring into

focus any infringement / deviation / violation of the environmental or forest norms /

conditions? If so, it may be detailed in the EIA.

iii. What is the hierarchical system or Administrative order of the company to deal with the

environmental issues and for ensuring compliance with the environmental clearance

conditions? Details of this system may be given.

iv. Does the company have system of reporting of non compliances / violations of environmental

norms to the Board of Directors of the company and / or shareholders or stakeholders at

large? This reporting mechanism shall be detailed in the EIA report

11) Details regarding infrastructure facilities such as sanitation, fuel, restroom etc. to be provided to the

labour force during construction as well as to the casual workers including truck drivers during

operation phase.

12) Corporate Environmental Responsibility (CER):

i. Adequate funds (at least 2.5 % of the project cost) shall be earmarked towards the Enterprise

Social Commitment based on Public Hearing issues and item-wise details along with time bound

action plan shall be included. Socio-economic development activities need to be elaborated upon.

ii. Any litigation pending against the project and/or any direction/order passed by any Court of Law

against the project, if so, details thereof shall also be included. Has the unit received any notice

under the Section 5 of Environment (Protection) Act, 1986 or relevant Sections of Air and Water

Page 45: 1. Sugar Factory Production Expansion from 10000 TCD to ...

Minutes of 410th

SEAC Meeting Dated 11/07/2019

Page 45 of 45

Acts? If so, details thereof and compliance/ATR to the notice(s) and present status of the case.

iii. A tabular chart with index for point wise compliance of above TOR.

13) Limestone and coal linkage documents along with the status of environmental clearance of limestone and coal mines

14) Quantum of production of coal and limestone from coal & limestone mines and the projects they cater

to;

15) For large Cement Units, a 3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from the proposal site.

16) Present land use shall be prepared based on satellite imagery. High-resolution satellite image data having

1m-5m spatial resolution like quick bird, Ikonos, IRS P-6 pan sharpened etc. for the 10 Km radius area from proposed site. The same shall be used for land used/land-cover mapping of the area.

17) If the raw materials used have trace elements, an environment management plan shall also be included.

18) Plan for the implementation of the recommendations made for the cement plants in the CREP guidelines must be prepared.

19) Energy consumption per ton of clinker and cement grinding

20) Provision of waste heat recovery boiler

21) Arrangement for use of hazardous waste