1 Requirements Conformance for SRF cryomodules 15-16 October 2014 Lund P. Bosland (on behalf of the CEA/Irfu and CNRS/IPNO teams) ESS elliptical cryomodules Two families of elliptical cavities: Medium beta: b=0,67 High beta: b=0,86 (geometrical beta values) Same cryostat for both types of cavities
28
Embed
1 Requirements Conformance for SRF cryomodules 15-16 October 2014 Lund P. Bosland (on behalf of the CEA/Irfu and CNRS/IPNO teams) ESS elliptical cryomodules.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
1Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
P. Bosland(on behalf of the CEA/Irfu and CNRS/IPNO teams)
ESS elliptical cryomodulesTwo families of elliptical cavities:
Medium beta: b=0,67High beta: b=0,86(geometrical beta values)Same cryostat for both types of cavities
2Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Cryomodule sub-system
Segmented LINAC:
Independent cryogenic cooling and control
Warm-up of a individual cryostat is possible
Individually removable cryostats for repair is
possible
Focusing elements at warm temperature
3Requirements Conformance for SRF cryomodules 15-16 October 2014
• Conical tip for stronger coupling• Water cooling
Outer conductor• Cooled with Liquid He in the vac. Vessel
Coax to rectangular RF transition (Door Knob)• HV bias with RF trap
CM integration• Large diameter flange with below on vacuum vessel• Diagnostic ports distribution
7Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Rods (TA6V, Diam. 6mm)
Magnetic shield
Half rings linked to the tank (under the magnetic shield)
Supports of the different cold components
• Cross rods fixed on 2 titanium
half rings fastened to the helium
tank on one side and on the
spaceframe on the other side
• 3000N pre-stress applied on the
rods, maximum force 8500N per
rod after cooling down
• Special boxes allowing the axial moving and
the thermalization of the thermal shield
Thermal shield
Supporting rods• 2 wheels fixed to the spaceframe at each extremity
• Guiding ensured by two rails welded to the vacuum vessel
3 jacks at 120° supporting the spaceframe after insertion
Rod
Pre-stress nut
Blocking nut
8Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Inter-cavities bellows
HIGH BETANumber of corrugations: 6Overall length 183mm (at rest)Axial stiffness for 6 corrugations 35N/mmRadial stroke for 6 corrugations +/-0.48mmRadial stiffness for 6 corrugations 7417N/mm
MEDIUM BETANumber of corrugations: 10Overall length 240,5mmAxial stiffness for 10 corrugations 21N/mmRadial stroke for 10 corrugations +/-0.80mmRadial stiffness for 10 corrugations 4450N/mm
Cold to warm transition
Mechanical cavity misalignment on the cavity stringsLongitudinal shrinkage of the cavitiesThermal isolation at the two extremities of the cryomodule
Distribution of the RF HOM modes
9Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Depl. Total(mm)
Depl. Struct.(mm)
Depl. Blocs(mm)
Contrainte max (Mpa)
1,321,24
(Z: -1,21 à +0,50)
0,12 à 1,08(Z: -0,89 à
+0,18)30
Spaceframe
Forces on Rods: 3000 to 9000N
Mass spaceframe: 400 - 430 KgTotal mass of cavities + thermal shielding: 1200Kg
Blocking by 3 jacks on two levels
Tuning (3 positions)
Spaceframe:• Aluminium alloy• Lower part can be
disassembled to insert the couplers
10Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Access traps
blocking of the cavities and
spaceframe during transport
Access in the tunnel Maintenance of cold tuning
system (change motor and piezo)
11Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Reflector brackets(coupler flange)
Reflector brackets(cavity flange)
Alignment made by laser tracker
Alignment of the cryomodule in the tunnel (source ESS)
1,5" Corner cube reflector
Additional fiducials will be set up inside the ECCTD cryomodule to check the alignment after cooling down.
Alignement of the cavities
Reflector brackets(vessel alignment)
Alignment of the cavity string within 1,5 mm of the beam axis
1 2
3 4
Beam axis reported to reflector bracket on beam flanges
Vessel alignment with respect to cavity string
12Requirements Conformance for SRF cryomodules 15-16 October 2014
13Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Helium cooling PID
• Special boxes allowing the axial moving and the thermalization of the thermal
shield
14Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Compliance with the PED97/23/EC
Vessels Pipes
PS<0,5bar:The equipment is not on the scope of the 97/23/CE directive
Article 3.3The equipment must be designed and manufactured according to workmanlike way
Category IThe manufacturing must be more documented, especially with internal production control
Objective: stay within « Article 3.3 » area
50 L
Elliptical cavity1 bar
Relative pressure
15Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
SAFETY DEVICES
European rules compliance Article 3.3
ESS Helium factory, circuits and operating modes
Helium Pressure relief devices
Working pressure = nominal pressureWP
PSET Set PressurePS
Maximum allowable overpressure PS + 10%
BURSTING DISK
SAFETY DEVICES
PSET
POPENING = + 5 % PSET
(overpressure when opening)PMAX APERTURE = + 10 % POPENING
PCLOSING = - 5 % PSET
PMIN CLOSING = - 10 % PCLOSING
(hysteresis before closing)
PSET + 10%
PSET – 10%
RELIEF VALVE
Bursting area
Opening area
WP upper limit
Max. allowable press.
Safety margin
Safety margin
1,9 bar
1,431 bar(1,3 +10%)
1,729 bar
1,301 bar
MAWP 1,58bar
1,670 bar
1,496 bar
1,891 bar
59mbar
65mbar
1,81 bar
Bursting disks+/- 10%
2,09 bar
Cavity pressure test1,43 PS 2,72 bar
1,609 bar
1,551 bar
Absolute pressure
16Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Helium low pressure circuit
2 bursting disk at each tip+ upstream safety relief valve (with he guard)
36°
Heat exchanger
The circuit is designed to reduce as low as possible the overpressure in case of beam vacuum failure by using a continuous DN100 diameter for the diphasic pipe, large curvatures and 2 DN100 bursting disks at each extremity.
A 36° angle is set up for the tank nozzle in order to allow the insertion of the cavity string and the cooling circuit inside the spaceframe
To valve box
Worst scenario: beam vacuum failure 38KW/m2 heat load on the cavity wall Accidental overpressure: 230mbar after rupture of the disks
17Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Status of the M-ECCTD
Cavities: Design finished Medium beta: fabrication started (KO meeting 03/09/2014)
Couplers: RF window and antenna ordered Call for tender for outer conductor (double wall) and door-knob to
be launched in the following weeks Tuners, magnetic shielding:
Design 95% finalized Fabrication to be launched
Spaceframe, vacuum vessel: Design finalized. Preparation of the procurement procedures in
progress(goal: launch the procurement before the end of January 2015)
Test stand: modification of the cryogenic line and HV modulator in progress
Clean room assembly toolings: studies started - still in progress
18Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
18
2 prototype high beta cavities haut béta have been tested: The 2 cavités ZANON et RI are within the ESS specifications.
19ESS cryomodules Workshop 15-16 October 2014 Lund
Cryomodule assembly
20Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
M-ECCTDTwo objectives:
1. To qualify the technology
2. To prepare the assembly procedures, the tools and the documentation for the serial elliptical cavity cryomodules
Assembly procedure
Integration tools
Documentation
Others
Items manufacturing
ECCTDintegration
Assembly procedure
Integration tools
Documentation
Others
Rea
dy f
or t
he s
eria
l cry
omod
ules
Preliminary Version Final Version
21Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Study of the assembling sequence and needs of toolings
Pre-study of the toolings: compatible with both types of cavities medium and high beta
Assembling in clean room Assembling outside clean room
Student: Amaury Martin09/2013 – 01/2014
Analyse of the assembling sequence
22Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Coupler / cavity assembly
State of the art: interface coupler / cavity parallel to the laminar air flow
Horizontal coupler
Rotation needed after assembly to get to the final vertical position of the coupler in the cryomodule
Complex tooling First rough analysis of the air flow around the
flange: the air flow may be pertubated because of the reinforcement sheets of the helium tank
Air speed Whirlwind
Cou
ple
r vert
ical
Cou
ple
r h
ori
zon
tal
Choice: vertical assembly
Tooling compatible for both types types of cavities
Adjustment of the coupler position relative to the cavity flange
23Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Frame and supports for the assembly in clean room
24Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Cavity string assembly in clean room
Design still in progress
Beam axis height: 1150 mm from the clean room ground
Individual position adjustment system of each cavity and bellow
Supports of the cold to warm transition bellows to be designed
25Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Assembly outside clean room
Thermal screen installed but not shown
•Wheels on the spaceframe
•Guiding rail on the vacuum
tank
26Requirements Conformance for SRF cryomodules 15-16 October 2014
Lund
Conclusion .
The implementation of the assembling process at Saclay will be based on the
SPIRAL2 and XFEL experience
Courtesy of Spiral 2 CEA team
Courtesy of Catherine MADEC - XFEL
27Requirements Conformance for SRF cryomodules 15-16 October 2014