Page 1: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

1

Project Planning

Page 2: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

2

Project

Group of Activities

Beginning, Middle, End

Well-Defined End Result

Page 3: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

3

Projects Example

Page 4: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

4

Examples of Projects

Construction Research and Development Design of New Product or Process Space Shuttle Wedding Can You Think of Projects? Can You Think of Non-Projects?

Page 5: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

5

Project Life Cycle

Page 6: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

6

Project Layout

Layout is Oriented Around Project

Page 7: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

7

Growth in Project Management

Decline of Repetitive Manufacturing in U.S. Growth of U.S. Service & Project Oriented Industries Lack of Foreign Competition in Defense, Construction Need to Rebuild U.S. Infrastructure Greater Demand for New Product Introduction Proliferation of Project Management Software

(Over 100 Kinds - $20 to $8000) Project Management Institute (PMI)

Page 8: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

8

Growth in Project Management

Growing Demand for Complex Goods, Services

And Exponential Explosion of Human Knowledge

Results in Larger and Larger Projects.

This Creates Need for Sophisticated Management System

Page 9: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

9

Project Planning Consists of:

Purpose Objectives Overview and General Approach Schedules (PERT/CPM) Resources Personnel Risk Management Plans Evaluation and Control (Feedback)

Page 10: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

10

Planning and Managing Risk

Risk Management Planning – Form Team Risk Identification – Delphi Method Qualitative Risk Analysis – Subjective Likelihood Quantitative Risk Analysis – Use Probabilities Risk Response Planning – Avoid, Mitigate,

Accept, Control Risk Monitoring and Control Risk Management Register

Page 11: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

11

Initial Project Planning:Draw System Boundaries

A System Consists of the Following: Mission and Goals

- Objectives

- Performance

- Effectiveness

- Cost Environment Resources Subsystems

Page 12: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

12

In Project Planning Activities Must be Identified

Activities are Groups of Work Elements or Tasks with:

Similar Technology & Groups of Personnel

Single Duration of Time (Activity Completion is Event)

Definite Beginning & End

Page 13: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

13

List of Activities Can Be Developed with:

“Gozinto” Chart

Bill of Materials

Work Breakdown Structure (WBS) Basically a “Bill of Work Units”

Page 14: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

14

Work Breakdown Structure (WBS)

Page 15: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

15

WBS Information

For Each Work Element (Activity) We Can Record:

Work Statement (Input/Output) Vendors, Contacts, Subcontractors End Item Specifications Cost Accounting Numbers & Costs (ABC) Resource Needs Probability Personnel (Linear Responsibility Chart, Trend) Times (Scheduling, PERT/CPM, Gantt Charts) Sequence Requirements

Page 16: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

16

Activity Analysis:Example One

Activity Description Follows Days

A Define Problem --- 3

B Lease Computer --- 5

C Obtain Data A, B 4

D Determine Alternatives A, B 1

E Feasible Alternatives D 1

F Evaluation & Modeling C, E 5

G Find Best Alternative F 1

H Implementation G 3

Page 17: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

17

Activity Analysis:Example Two

Activity Description Follows Days

X --------------- --- 1

Y --------------- --- 2

Z --------------- --- 3

A --------------- X, Y 1

B --------------- X, Y, Z 2

Draw Activity-On-Node (AON or CPM) Diagram.

Draw Activity-On-Arrow (AOA or PERT) Diagram.

Page 18: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.

18

Activity Analysis:Example Three

Activity Description Follows

a Plan Survey ---b Hire Personnel ac Design Questionnaire a d Train Personnel b,ce Select Households cf Print Questionnaire cg Conduct Survey d,e,fh Analyze Results g

Draw Activity-On-Node (AON or CPM) Diagram.Draw Activity-On-Arrow (AOA or PERT) Diagram.

Page 19: 1 Project Planning. 2 Project Group of Activities Beginning, Middle, End Well-Defined End Result.