1 Project Management Seminar Project Management Seminar Project Scheduling Project Scheduling
Dec 31, 2015
1
Project Management SeminarProject Management SeminarProject SchedulingProject Scheduling
2
• Importance of Project Management
• Three Components of Project Management
• Project Evaluation and Review Technique (PERT) & Critical Path Method (CPM)
• Estimate the Probability of Project Completion
OutlineOutline
• Ford Redesign of Mustang Project:– 450 member project team– Cost $700-million– 25% faster, which leads to 30% cheaper than 25% faster, which leads to 30% cheaper than
comparable projects at Fordcomparable projects at Ford
3
Strategic Importance of Project ManagementStrategic Importance of Project Management
4
Strategic Importance of Project ManagementStrategic Importance of Project Management
• Microsoft Windows Vista:– thousands of programmers– millions of lines of code– three months late, missed 2006 holiday season, three months late, missed 2006 holiday season,
estimated loss of revenue: $384 million ~ $1.92 estimated loss of revenue: $384 million ~ $1.92 billionbillion (Business Software Alliance,
2007)
5
Why Learn ProjectWhy Learn Project Management?Management?• Leadership opportunity
– Understanding Project Management can improve your effectiveness when working on projects
– Projects are a natural proving ground to help identify and develop leadership and managerial talent.
• Project Management is increasingly a key job skill.
(MSP) Monster 10/2001
Monster 10/2004
Monster 5/2011
Project related openings 500 1500 10k+
Related to project management
150 650 10k+
(MSP) Monster 10/2001
Monster 10/2004
Monster 5/2011
Project related openings 500 1500 10k+
Related to project management
150 650 10k+
6
• Planning– Goal setting (time, cost, output)– Team organization
Three Components of Project ManagementThree Components of Project Management
On time On budget Quality output
• Scheduling –Schedule the sequence of activities and resources
• Controlling–Monitoring time, cost, and quality of output
7
Project Scheduling QuestionsProject Scheduling Questions
• When will the entire project be completed?
• What are the critical activities that will delay the entire project if they are late?
• What are the non-critical activities – The ones that can run late without delaying the whole project’s completion?
• What is the probability that the project will be completed by a specific date?
8
• Critical Path Method (CPM)
- developed by DuPont for chemical plants (1957)
• Program Evaluation & Review Technique (PERT)- developed by Booz, Allen &
Hamilton with the U.S. Navy, for Polaris missile (1958)
• Different terminology, similar objectives
Project Scheduling MethodsProject Scheduling Methods
© 1995 Corel Corp.
J F M A M J J
MonthActivity
Design
Build
Test
PERT
9
How to Draw PERT & CPM: the Steps How to Draw PERT & CPM: the Steps
Identify relationships among the activities. (Decide which activities must precede and which must follow others.)
Draw the network connecting all of the activities
Assign time estimates to each activity
Compute the longest time path through the network. (critical path)
10
Example Example Milwaukee General Hospital ProjectMilwaukee General Hospital Project
The environmental protection agency has recently given Milwaukee General Hospital 16 weeks to install a complex air filter system in its extensive laundry/cleaning operations facility.
Milwaukee General has identified eight activities that need to be performed in order for the project to be completed.
11
Activities & Relationships Among the Activities Activities & Relationships Among the Activities
Activity Description
A Build internal components
B Modify roof and floor
C Construct collection stack
D Pour concrete and install frame
E Build high-temperature burner
F Install pollution control system
G Install air pollution device
H Inspect and test
Immediate Predecessors
-
-
A
A, B
C
C
D, E
F, G
12
Activities & Relationships Among the Activities Activities & Relationships Among the Activities
Activity
A
B
C
D
E
F
G
H
Immediate Predecessors
-
-
A
A, B
C
C
D, E
F, G
13
Activity Network Activity Network
B
A
D
C
G
F
HEStart
Arrows show
precedence
relationships
END
Activity Immediate Predecessors
A -
B -
C A
D A, B
E C
F C
G D, E
H F, G
14
Time Estimates Time Estimates
Activity Description
A Build internal components
B Modify roof and floor
C Construct collection stack
D Pour concrete and install frame
E Build high-temperature burner
F Install pollution control system
G Install air pollution device
H Inspect and test
Total (weeks)
Time (Weeks)
2
3
2
4
4
3
5
2
25
15
Assign Time Estimates to Each ActivityAssign Time Estimates to Each Activity
Arrows show
precedence
relationships
3
Start
A
B
C
D
E
F
G
H
2
3
2
4
4
5
2END
Paths fromPaths from Start Start toto End EndPath Time (Weeks)
1 ACFH 9
2 ACEGH 15
3 ADGH 13
4 BDGH 14
3
Start
A
B
C
D
E
F
G
H
2
3
2
4
4
5
2END
Activity Network Activity Network
17
• Identify critical path– critical path is the path with the longest time– critical path is the Shortest time a project can be completed– Any delay on critical path activities delays project
Critical Path AnalysisCritical Path Analysis
Path Time (Weeks)
1 ACFH 92 ACEGH 153 ADGH 134 BDGH 14
18
The Critical Path The Critical Path
Start
A
B
C
D
E
F
G
H
Arrows show
precedence
relationships
END
2
3
2
4
4
3
5
2
19
• Three estimates for each activity– Earliest Possible Time (a)– Most-likely Time (m)– Latest Possible Time (b)
Estimate Activity TimesEstimate Activity Times
• Assumption: Follow BETA distribution• Expected time: t = (a + 4m + b)/6• Variance of time: v = [(b - a) /6]2
20
Milwaukee General Hospital ProjectMilwaukee General Hospital ProjectActivity Earliest
Possible
(a)
Most Likely
(m)
Latest Possible
(b)
A 1 2 3
B 2 3 4
C 1 2 3
D 2 4 6
E 1 4 7
F 1 2 9
G 3 4 11
H 1 2 3
[(3-1)/6]2 = 0.11
3 0.11
2 0.11
4 0.44
4 1.00
3 1.78
5 1.78
2 0.11
Expected Timet= (a+4m+b)/6
Variance
[(b - a) /6]2
(1+4*2+3)/6 = 2
21
Used to obtain probability of project completion!
Project TimesProject Times
• Expected project time (T)– Sum of critical path
activity times, t
• Project variance (V)
–Sum of critical path activity variances, v
22
Critical Path
Activity
Earliest Possible
(a)
Most Likely
(m)
Latest Possible
(b)
Expected Time
t= (a+4m+b)/6
Variance
[(b - a) /6]2
A 1 2 3 2 0.11
C 1 2 3 2 0.11
E 1 4 7 4 1.00
G 3 4 11 5 1.78
H 1 2 3 2 0.11
Expected project time T = 2 + 2 + 4 + 5 + 2 = 15Project variance V = 0.11+0.11+1.00+1.78+0.11= 3.11Project Standard Deviation S = square root of variance = 3.11**0.5 = 1.76
Expected Project Time and VarianceExpected Project Time and Variance
23
Application - 1Application - 1 The deadline for Milwaukee General Hospital is 16 weeks. What is the chance that the project can be finished on or before the deadline?
Formula:
Z = (due date – expected completion date) / Std. Dev.
Z is a normal score
Apply the formula to Milwaukee hospital Project:
Z = (16 weeks – 15 weeks) /1.76 = 0.57
24
Z0.57
Z .00 …
0.0 .5000 …
: : : :
0.5 .6915 … .7157
Standardized Normal Probability Table (Portion)Standardized Normal Probability Table (Portion)
Probabilities in bodyProbabilities in body
Obtaining the ProbabilityObtaining the Probability
.007
.5279
.7157
There is a 71.57% chance that the project can be There is a 71.57% chance that the project can be put in place in 16 weeks.put in place in 16 weeks.
25
Application - 2 Application - 2
What’s the date that Milwaukee Hospital Project can be finished with a 99% chance?Formula:
date = expected completion date + Z (0.99) * Std. Dev.
Z (0.99): normal score corresponding to probability 0.99
Z (0.99) = 2.33Apply the formula to Milwaukee hospital project:
date = 15 weeks + 2.33 * 1.76 = 19.1 weeks
Conclusion: we are 99% sure that the project can Conclusion: we are 99% sure that the project can be finished within 19.1 weeksbe finished within 19.1 weeks
26
Advantages & Disadvantages of PERT/CPMAdvantages & Disadvantages of PERT/CPM
• Straightforward (visual) and easy to use;• Unique strength in managing complex projects;• Pinpoint activities that need to be closely watched;• Provides quantitative results that facilitate planning,
communication, and negotiation (for due date and additional resources)
• Need to clearly define activities and relationships among activities;
• Assume activity times follow a BETA distribution.
27
Thank you!Thank you!