Top Banner
1 Overview of the MYRRHA accelerator & presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012
28

1 Overview of the MYRRHA accelerator presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

Jan 19, 2018

Download

Documents

Esmond Wood

3 The MYRRHA project MYRRHA Project Multi-purpose hYbrid Research Reactor for High-tech Applications At Mol (Belgium) Development, construction & commissioning of a new large fast neutron research infrastructure to be operational in 2023  ADS demonstrator  Fast neutron irradiation facility  Pilot plant for LFR technology J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012 See Introduction talk by H. Aït Abderrahim (SCKCEN)
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

1J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

Overview of the MYRRHA accelerator & presentation of the MAX project

Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France

EURATOM FP7 MAX project coordinator

Page 2: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

2J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

1.Background

2. The MYRRHA accelerator concept3. Review of the MYRRHA linac design

Page 3: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

3

The MYRRHA project

MYRRHA Project Multi-purpose hYbrid Research Reactor for High-tech Applications

At Mol (Belgium)

Development, construction & commissioning of a new large fast neutron research infrastructure

to be operational in 2023

ADS demonstrator Fast neutron irradiation facility Pilot plant for LFR technology

J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

See Introduction talk by H. Aït Abderrahim (SCK•CEN)

Page 4: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

4J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

The MYRRHA accelerator: background

End 90’s: several collaborative R&D activities worldwide on ADS accelerators (APT/AAA, TRASCO, etc. w/ especially a CEA/CNRS/INFN collaboration)

2001: “The European roadmap for developing ADS for Nuclear Waste Incineration”, European Technical Working Group on ADS (chaired by C. Rubbia, ENEA)

2002: pre-design “Myrrha Draft 1” (cyclotron 350 MeV)

2002-2004: MYRRHA is studied as one of the 3 reactor designs within the PDS-XADS FP5 project (coord. Framatome/AREVA)(cyclotron turns into linac, first reliability analyses show a need for fault-tolerance capability)

Page 5: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

5J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

The MYRRHA accelerator: background

2005: updated pre-design “Myrrha Draft 2” (linac 350 MeV)

2005-2010: MYRRHA is studied as the XT-ADS demo within the EUROTRANS FP6 project (coord. FZK)(600 MeV linac conceptual design, R&D activities w/ focus on reliability)

2010: MYRRHA is on the ESFRI list, and officially supported by the Belgium government at a 40% level (384M€, w/ 60M€ already engaged)

2010-2014: MYRRHA accelerator advanced design phase w/ support from the EURATOM FP7 projects (MAX especially)

2015-2019: possible construction phase 2020-2023: possible commissioning phase & progressive start-up

Page 6: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

6J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

MYRRHA within EURATOM FP7: 2010-2014

FREYAGUINEVERE experiment

SCK●CEN

CDTReactor design

SCK●CEN

MAXAccelerator

designCNRS

See Conclusion talk by R. Garbil (EC)

Page 7: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

7

The MAX project

J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

MAX = “Myrrha Accelerator eXperiment, research & development programme” 3 years & coordinated by CNRS

2011 – 2012 – 2013 (February 2011 to January 2014)

Goal of the project = support the transition from the EUROTRANS “conceptual design phase” to the MYRRHA pre-construction “engineering design phase” Pursue the R&D related to ADS-type accelerators, that request a “beyond the

state-of-the-art” reliability level Follow up of FP5 PDS-XADS & FP6 EUROTRANS activities

Fine-tune the design of the driver accelerator for the MYRRHA system To initiate a possible MYRRHA detailed engineering design & subsequent construction phase

starting at the end of the MAX project

Key data Call identifier: FP7-FISSION-2010

Collaborative Project – Small/medium-scale Focused (CP-FP) Project cost: 4.9 M€ total cost – 2.9 M€ EU contribution

With a total involvement of about 300 p.m. (8 persons FTE) from 11 partners

Page 8: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

8

The MAX project

J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

http://ipnweb.in2p3.fr/MAX/

WP1: Global accelerator design

WP2: Injector developments

WP3: Main linac developments

WP4: System optimisation

Page 9: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

9J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

1. Background

2. The MYRRHA accelerator concept

3. Review of the MYRRHA linac design

Page 10: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

10J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

MYRRHA as an ADS demonstrator

Main features of the ADS demo50-100 MWth power

Highly-enriched MOX fuel

Pb-Bi Eutectic coolant & target

keff around 0.95 in subcritical mode

600 MeV, 2.5 - 4 mA proton beam

Demonstrate the physics and technology of an Accelerator Driven System (ADS) for transmuting long-lived radioactive waste Demonstrate the ADS concept (coupling accelerator + spallation source + power reactor) Demonstrate the transmutation(experimental assemblies)

Page 11: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

11J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

Choice of the proton beam energy: 600 MeV

Accelerator cost

Power density deposited in LBE

Page 12: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

12J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

Choice of the proton beam current: 4mA

Current / Energy / Sub-Criticity for a 80 MWtherm ADS demo

(simulation by ANSALDO)

Page 13: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

13J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

MYRRHA proton beam requirements

Proton energy 600 MeV

Proton beam current 2.5 mA (up to 4 mA for burn-up compensation)

Allowed beam trip number (>3 sec) <10 per 3-month operation cycle

Beam entry into the reactor Vertically from above

Beam stability on target Energy < ±1% Current < ±2% Position & size < ±10%

Beam time structure TBD (CW with regular beam interruptions >200µs for keff monitoring)

High power proton beam (up to 2.4 MW)

Extreme reliability level

Page 14: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

14J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

The ADS reliability requirement Beam trips longer than 3 sec must be very rare: To limit thermal stress & fatigue on the target window, reactor structures & fuel

assemblies To ensure a 80% availability – given the foreseen reactor start-up procedures

Present MYRRHA spécifications: <10 beam trips per 3-month operation period (i.e. MTBF > 250h) – derived from the PHENIX reactor operation analysis

Far above present HPPA accelerator performance – MTBF is a few hours at PSI or SNS

Far above present ADS specifications in US or Japan – mainly based on simulations

D. Vandeplassche, IPAC2012

Page 15: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

15J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

The ADS reliability requirement

In any case, reliability guidelines are needed for the ADS accelerator design: Strong design i.e. robust optics, simplicity, low thermal stress, operation margins… Redundancy (serial where possible, or parallel) to be able to tolerate failures Repairability (on-line where possible) and efficient maintenance schemes

Beam trips longer than 3 sec must be very rare: To limit thermal stress & fatigue on the target window, reactor structures & fuel

assemblies To ensure a 80% availability – given the foreseen reactor start-up procedures

Present MYRRHA spécifications: <10 beam trips per 3-month operation period (i.e. MTBF > 250h) – derived from the PHENIX reactor operation analysis

Far above present HPPA accelerator performance – MTBF is a few hours at PSI or SNS

Far above present ADS specifications in US or Japan – based on simulations

Page 16: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

16J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

Generic scheme of the European ADS accelerator Modular SC main linac

Upgradeable concept (demo, transmuter) Independently-controlled elements The function of a missing element can be

replaced by retuning adjacent elements (“FAULT-TOLERANCE”)

Redundant injector Fault-tolerance is non applicable

(β<0.15) Minimized number of elements Spare stand-by injector with fast

switching capabilities

Page 17: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

17

+

Operational injector 1: RF + PS + beam ON

Warm stand-by injector 2: RF+ PS ON, beam OFF (on FC)

Initial configuration

-

The failure is localized in injector

The switching magnet polarity is changed

(~1s)

+

A failure is detected anywhereBeam is stopped in injector 1 by the Machine Protection System @t0

-

Beam is resumed

Injector 2 operational (@t1 < t0 +3sec)

Failed injector 1, to be repaired on-line if possible

Need for an efficient fault diagnostic system !

Strategy for a fault case in the injector

J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

Page 18: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

18

A failure is detected anywhere→ Beam is stopped by the MPS in injector at t0

The fault is localized in a SC cavity RF loop→ Need for an efficient fault diagnostic system

New V/φ set-points are updated in cavities adjacent to the failed one→ Set-points determined via virtual accelerator application and/or at the commissioning phase

The failed cavity is detuned (to avoid the beam loading effect)→ Using the Cold Tuning System

Once steady state is reached, beam is resumed at t1 < t0 + 3sec→ Failed RF cavity system to be repaired on-line if possible

Failed cavity Failed cavity positionposition

Failed cavity Failed cavity positionposition

Fast fault-recovery procedure

J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

Page 19: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

19J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

1. Background2. The MYRRHA accelerator concept

3. Review of the MYRRHA linac design

Page 20: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

20J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

Layout of the MYRRHA linac

Page 21: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

21J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

Layout of the MYRRHA linac

Page 22: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

22

WP1 – Global accelerator design

J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

H. Klein (IAP): MYRRHA injector design (Monday 11:00)

J-L. Biarrotte (CNRS): SC linac design & associated MEBT (Monday 11:35)

F. Bouly (CNRS): Beam tolerance to RF faults (Monday 14:30)

L. Perrot (CNRS): High-energy beam lines (Monday 12:10) from the CDT work

D. Uriot (CEA): Instrumentation & operation aspects (Monday 15:00)

Page 23: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

23

WP2 – Injector developments

J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

C. Zhang (IAP): Injector layout & beam dynamics (Monday 15:50)

H. Podlech (IAP): Cavity development for MYRRHA (Monday 16:25)

D. Vandeplassche (SCK•CEN): MYRRHA injector at UCL (Monday 17:00) → towards a MYRRHA R&D platform

Page 24: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

24

WP3 – Main linac developments

J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

H. Saugnac (CNRS): Spoke cryomodule design (Tuesday 08:30)

R. Paparella (INFN): SC elliptical cavities design & associated R&D (Tuesday 09:05)

F. Bouly (CNRS): Fault-recovery procedures & associated R&D (Tuesday 09:40)

Page 25: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

25

WP4 – System optimisation

J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

N. Chevalier (ACS): Cryogenic system for the MYRRHA linac (Tuesday 10:30)

D. Vandeplassche (SCK•CEN): RF and control aspects (Tuesday 11:05)

A. Pitigoï (EA): Reliability analysis (Tuesday 11:35)

L. Medeiros (SCK•CEN): Conclusion (Tuesday 13:50) → Roadmap towards MYRRHA accelerator construction

Page 26: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

26

Charge to the review: Q/A

Q: What is the goal of the MAX Euratom FP7 project (Feb 11 – Jan 14)? Deliver a consolidated reference layout of the MYRRHA linac in 2014 so as to

initiate its engineering design and subsequent construction phase

Q: What is the goal of this MYRRHA linac review ? Review, at MAX mid-project, the design choices and the technical progress made

so far and give recommendations for the forthcoming activities

Q: What documentation does the review team need to consider ? Because we have no fully consistent TDR-like document yet, the review is to be made

on the basis of the slides shown at the meeting. Nevertheless, possibly useful additional documentation has also been made available. o EUROTRANS final report on XT-ADS accelerator design (March 2010)o Already issued MAX deliverables: Project presentation (March 2011), Detailed work programme (April 2011),

Cryogenic analysis (Jan 2012), Injector conceptual design (Fev 2012)o CDT deliverables on: Myrrha HEBT design (Feb 2012) and instrumentation needs (March 2012)

J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

Page 27: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

27

Charge to the review: Q/A

Q: On which specific points should the review team focus in particular ? Besides a critical analysis (Findings/Comments/Recommendations) of the various technical contributions,

we would like the review team to answer specifically to the following questions:

1) May the adopted general philosophy and methodology lead to the design of a highly reliable accelerator?

2) Are the different design choices appropriate for such a machine?

3) Is the R&D programme coherent, adequately focused and efficient at this stage of the project?

4) In a more global view, what should be the essential points of concern for the MYRRHA project team in the two following years (2013-2014) to prepare for the accelerator construction?

J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

Page 28: 1 Overview of the MYRRHA accelerator  presentation of the MAX project Jean-Luc BIARROTTE CNRS-IN2P3 / IPN Orsay, France EURATOM FP7 MAX project coordinator.

28J-Luc Biarrotte, 1st Int. MYRRHA accelerator design review, Brussels, November 12th, 2012

Thank You for your kind involvement !

http://ipnweb.in2p3.fr/MAX/

http://myrrha.sckcen.be/