1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA
39

1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

Dec 27, 2015

Download

Documents

Reynard Roberts
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

1

‘Ohana Delay Line

Installation at the summit

Friday, October 13th 06

Pierre Fedou, LESIA

Page 2: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

2

Agenda

1. Background

2. Delay Line Installation

3. Road Map

Page 3: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

3

Background

‘Ohana will connect

CFHT and Gemini telescopes

Via a fiber link

Main sub systems:

- Injection modules

- Optical fiber links

- Delay Line, our topic today

- Beam combiner and IR camera

Page 4: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

4

Background

CFHT Jun and Aug 02,

J, H, K band

Keck I, Dec 02, K

Gemini, Jul 03,

H, K

Injection modules status

Page 5: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

5

Background

Keck, installation Aug 04

Tests: Dec 04, Jun 05, K band

May 06, H and K

Fiber link status

Page 6: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

6

Background

Jun 03 & Oct 03 on IOTA,

H, K band

Jun 06, J, H, K

Beam combiner

& IR camera status

Page 7: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

7

Delay Line

• Designed in 03 and before• Built and tested, in France, mid 04 to mid 06• Now ready to be re-installed at CFHT

Page 8: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

8

Delay Line

Input #1Input #2

Output #1 Output #2Central carriage

Translating stage Translating stage

Fast scan

Page 9: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

9

Delay Line

3 or 4 missions of 3 weeks

Oct 06 Hardware

Jan 07 Opto-mechanical & first lignment

Mar 07 Alignment continued

May 07 Optional

Page 10: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

10

Delay line subsystem

• Translating stage Aerotech

• Translating stage Schneeberger

• Central carriage

• Railways

• 6 metallic frames

• Fast Scan

• One computer

Page 11: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

11

Page 12: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

12

Dec 03

Module #1, version 1.0

Page 13: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

13

New Module #1

Stone

Page 14: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

14

SchneeBerger end

Aerotech end Control command

Page 15: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

15

Module #6

Module #5

rails

Schneeberger trans. stage

Schneeberger end, looking outside

Central carriage

Page 16: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

16

Central carriage

Module #3

rails

Schneeberger end, looking inside

Module #5

Module #4

Page 17: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

17

Aerotech end, looking outside

Aerotech translation stage

Module #1

Driving belt

MeterDrive

Stone

Page 18: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

18

Aerotech end, looking inside

Stone

Aerotech

Module #1

Page 19: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

19

Delay line

• Our goals for this mission

• Opening crates

• Moving “big hardware” in Coude Room

• Make first alignment of structure

• Rails positioning 1 mm over 12.50 m

Page 20: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

20

• Here is the line just before leaving

Delay line

Page 21: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

21

Delay line

And now at the summit

Page 22: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

22

7 crates: 6 + 1

2 metallic frames

2 metallic frames

Aero metallic frame

Schnee metallic frame

Rails

Aerotech on its stone bed

The 7th crate concerns injection modules

Delay line

Open question:

where do we stock this 7th?

Closed? Opened?

Page 23: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

23

Delay lineOK, let’s open

crates!

Nail draw

Hammer

Page 24: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

24

Delay line One module weighs ~80 kg and is 210 cm long

One crate,

two modules

Page 25: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

25

Delay line

Small parcels

Page 26: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

26

Delay line

rails

Small parcel

Page 27: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

27

Delay line

wedges

Need a (transportable)

lifting jack

Page 28: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

28

Delay line

Thermal soldering

Metallic paper

Page 29: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

29

Delay line

Vacuum cleaner

Thermal soldering

Page 30: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

30

Delay line

Stabilized air

Plastic film

Page 31: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

31

Delay line

In progress

Ready to be closed

Wedge

Page 32: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

32

Delay line

Wall of wood

Wedge

Page 33: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

33

Delay line

Need a Nail Puller?

Electric Hammer

Page 34: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

34

Delay line

Plastic film

Roof of wood

Page 35: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

35

Delay line

We did it!

Page 36: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

36

Delay line

Aerotech side

Schnee side

Beam combiner Table

Total Length = 14390mm

Total Width = 930mm

Page 37: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

37

Delay line

Beam combiner

Table

Page 38: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

38

Delay line

Week #1, Monday 16th : crates opened and all heavy parts moved in the Coude Room, Day Crew and Meudon

Week #2, Monday 23rd : small pieces are moved and alignment made by Meudon

Week #3, Monday 30th : continued, overturning, extra time just in case…

Page 39: 1 ‘Ohana Delay Line Installation at the summit Friday, October 13th 06 Pierre Fedou, LESIA.

39

Road map

• Delay Line installation: Oct 06 -> spring 07

• Injection Modules: time has been asked on Keck

• Fiber Link beetween Gemini and CFHT: summer 07

• Beam Combiner installation: spring to summer 07

• Determination of length of the base: on going effort with IGN and OCA

• First light: when ready, fall 07?