1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005
12

1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

Dec 28, 2015

Download

Documents

Meryl Green
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

1

NSTARTRANSMISSION

RELIABILITY PROJECT

ENVIRONMENTAL BUSINESS COUNCIL UPDATE

APRIL 21, 2005

Page 2: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

2

PROJECT NEED DRIVEN BY INCREASING GROWTH WITH DECLINING GENERATION

• Load Growth over Past 6 Years Exceeded Historic Average In Greater Boston Area & Communities

• Area Older & Some Newer Generation Stations Have Retired or Announced Plans to Retire

• By June 2006, System Overloads Are Experienced throughout the System without Relief

• Overloads Get Worse with Time, Lead to Outages

Page 3: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

3

GOAL WAS TO FIND MOST COST-EFFECTIVE ALTERNATIVE TO MINIMIZE IMPACT ON

NATURAL & HUMAN ENVIRONMENT

• Type of Transmission Line—Underground

• Cable Technology—Pipe-Type Cable, Over 200 miles in Greater Boston Area

• Route Selected to be Most Direct with Least Impact to People & Environment

• Construction Impact – Tried to Minimize Interferences

Page 4: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

4

FINAL DESIGN

• Three 345 kV Underground Transmission Lines Located in One Trench Up to Route Split

• Pipe-type Cable, Proven Reliable Technology at 345 kV

• New Switchyard at Origin-Stoughton

• Expand Two Termination Substations-Hyde Park & K Street

• Heat Exchangers at Baker Street & Hyde Park Substations (Reverse Power Flow to W. Roxbury to Reinforce Area)

Page 5: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

5

Page 6: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

6

SUMMARY OF BENEFITS

• Increases Import Capability into Greater Boston & Surrounding Communities by 1200-1800MW

• Mitigates All Known Reliability Issues for More than 10 Years

• Reduces Dependence on Older Local Generation Stations that Plan to Retire

• Opens Corridor for Economic Generating Sources from SEMA/RI into Greater Boston Area

Page 7: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

7

PROJECT SCHEDULE OVERVIEW

Planning & Design

Permitting &Engineering

Station Construction

Street Construction

Install & Splice Cable

Mar 2004

Apr 2005

Jun 2006

Feb 2006

Install & Splice Cable

Dec 2007In-Service

Phase 1

Phase 2

June 2006In-Service

Page 8: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

8

PROJECT STATUS

• Major Permits Secured-MEPA, Siting Board, Con Coms

• Most Follow-on Permits Completed, Some Still in Process– Chapter 91 License for K Street Station-DEP– Stoughton Conservation Commission Appeal to DEP

• MOUs with Boston, Towns, & DCR bound Mitigation Risk, Define Extended Works Hours

• ISO-NE System Technical Issues Resolved (System Switching)

• Major Equipment, Property, and Easements Acquisition Complete

Page 9: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

9

PROJECT STATUS

• Major Equipment Purchases Complete; ISO Administered RFPs for high dollar items including Pipe-type cable and GIS Equipment

• NSTAR/ISO issued Construction Contract RFP in Nov 2004

• Bid as Single GC for Entire Project or Separately for Lines & Stations

• Transmission Line Contract Awarded; Station Contract in Final Negotiation

Page 10: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

10

PERMITING PROCESS WAS INTENSE

• EENF Filed 12/15/03; EFSB Petition Filed 1/16/04• MEPA Public Meetings Feb 04; EFSB Public Meetings Mar 04• NSTAR met with Boston & Supplemented EFSB Petition with

Additional Route Alternatives Mar 04• Additional EFSB Public Meeting on New Alternatives April 04• 2 EFSB Interveners Filed—ISO-NE & City of Boston• Siting Board Discovery followed by Intervener Discovery May 04• Submitted Single EIR to MEPA May 04• Unrest in Stoughton Led to Selectmen’s Meeting May 04• Stoughton Filed as Late EFSB Intervener June 04; Hired Counsel• EFSB Accepted Stoughton as Intervener; Stoughton Discovery Jul 04• Received MEPA Certificate July 16, 2004• EFSB Hearings began late July 04

Page 11: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

11

PERMITING CONTINUED ON

• EFSB Hearings Covered Each Section of Petition in Order• Initial Cross-Examination by Boston & Stoughton Tapered Off as

Hearings Progressed• NSTAR worked with Stoughton Counsel to Negotiate Agreement• Town Selectmen Rejected Proposed Agreement• NSTAR Testimony Concluded in Late Aug 04• Stoughton Presented Direct Case with Witnesses-Technical &

Environmental• Second Proposed Agreement with Town Approved; Stoughton

withdrew from Proceedings• Hearings Concluded Sept 04• Con Com Petitions filed Oct 04• Con Com Orders Received Dec 04 except Stoughton Jan 05• EFSB Tentative Decision Dec 04; Final Jan 14, 2005

Page 12: 1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.

12

NEXT STEPS

• Final Permits/Licenses needed to Complete – DEP is

lengthy; resource limited

• Construction Contract in Place; Shovels in the

Ground

• Community Relations Plan Developed, Ready for

Implementation

• Environmental Plan Ready for Implementation

• Target Completion June 2006