1 Monitoring and Monitoring and Controlling the Controlling the Project Project Key Concepts Key Concepts Plan-Monitor-Control Cycle Plan-Monitor-Control Cycle Data Collection and Reporting Data Collection and Reporting Earned Value Earned Value
Apr 01, 2015
1
Monitoring and Controlling Monitoring and Controlling the Projectthe Project
Key ConceptsKey Concepts
Plan-Monitor-Control CyclePlan-Monitor-Control Cycle
Data Collection and ReportingData Collection and Reporting
Earned ValueEarned Value
2
Plan-Monitor-Control CyclePlan-Monitor-Control Cycle
Closed loop processClosed loop process Planning-monitoring-controlling effort Planning-monitoring-controlling effort
often minimized to spend time on often minimized to spend time on “the real work”“the real work”
3
Designing the Monitoring SystemDesigning the Monitoring System
Identify special characteristics of Identify special characteristics of performance, cost, and time that performance, cost, and time that need to be controlledneed to be controlled
Real-time data should be collected Real-time data should be collected and compared against plansand compared against plans
Avoid tendency to focus on easily Avoid tendency to focus on easily collected datacollected data
4
Formats of DataFormats of Data
Frequency CountsFrequency Counts Raw NumbersRaw Numbers Subjective Numeric RatingsSubjective Numeric Ratings Indicators and SurrogatesIndicators and Surrogates Verbal CharacterisationsVerbal Characterisations
5
Data AnalysisData Analysis
Aggregation TechniquesAggregation Techniques Fitting Statistical DistributionsFitting Statistical Distributions Curve FittingCurve Fitting Quality Management TechniquesQuality Management Techniques
6
Report TypesReport Types
RoutineRoutine ExceptionException Special AnalysisSpecial Analysis
7
ReportingReporting
Not all stakeholders need to receive Not all stakeholders need to receive same informationsame information
Avoid periodic reportsAvoid periodic reports Impact of Electronic MediaImpact of Electronic Media Relationship between project’s Relationship between project’s
information system and overall information system and overall organisation’s information systemorganisation’s information system
8
Meeting GuidelinesMeeting Guidelines
Should be help primarily for group Should be help primarily for group decision makingdecision making
Distribute written agenda in advance of Distribute written agenda in advance of meetingmeeting
Ensure everyone is properly prepared for Ensure everyone is properly prepared for meetingmeeting
Chair of meeting should take minutesChair of meeting should take minutes Avoid excessive formalityAvoid excessive formality If held to address specific crisis, restrict If held to address specific crisis, restrict
meeting to this issue alonemeeting to this issue alone
9
Earned ValueEarned Value
Percent of task’s budget actually Percent of task’s budget actually spent not good indicator of percent spent not good indicator of percent completioncompletion
10
Earned ValueEarned ValueACWP = Actual Cost Work PerformedACWP = Actual Cost Work PerformedBCWP = Budgeted Cost Work PerformedBCWP = Budgeted Cost Work PerformedBCWS = Budgeted Cost Work ScheduledBCWS = Budgeted Cost Work ScheduledSV = Schedule VarianceSV = Schedule VarianceCV = Cost VarianceCV = Cost VarianceAC = Actual CostAC = Actual CostTE = Planned TimeTE = Planned TimeTA = Actual TimeTA = Actual TimeCPI = Cost Performance IndexCPI = Cost Performance IndexSPI = Scheduled Performance IndexSPI = Scheduled Performance IndexTPI = Time Performance IndexTPI = Time Performance IndexCSI = Cost-Schedule IndexCSI = Cost-Schedule IndexETC = Estimated Cost to CompleteETC = Estimated Cost to CompleteBAC = Budget at CompletionBAC = Budget at CompletionEAC = Estimated Cost to CompleteEAC = Estimated Cost to CompleteFAC = Computed Cost to CompleteFAC = Computed Cost to CompleteVAC = Variance at CompletionVAC = Variance at CompletionLOE = Level of EffortLOE = Level of Effort
11
Earned ValueEarned Value
CV = BCWP - ACWPCV = BCWP - ACWP
SV = BCWP – BCWSSV = BCWP – BCWS
CPI = BCWP/ACWPCPI = BCWP/ACWP
SPI = BCWP/BCWSSPI = BCWP/BCWS
12
Earned ValueEarned Value
13
Earned ValueEarned Value
14
PROJECT CONTROLPROJECT CONTROL
BackgroundBackground Acts which seek to reduce Acts which seek to reduce
differences between plan and differences between plan and actualityactuality
Difficult TaskDifficult Task human behavior involvedhuman behavior involved problems rarely clear cutproblems rarely clear cut
15
Purpose of ControlPurpose of Control
Stewardship of Organisational AssetsStewardship of Organisational Assets physical asset controlphysical asset control human resourceshuman resources financial controlfinancial control
Regulation of Results Through the Regulation of Results Through the Alteration of ActivitiesAlteration of Activities
16
DESIGNING THE DESIGNING THE CONTROL SYSTEMCONTROL SYSTEM
Purpose is to correct errors, not punish the Purpose is to correct errors, not punish the guiltyguilty
Investments in control subject to Investments in control subject to diminishing returnsdiminishing returns
Must consider impact on creativity and Must consider impact on creativity and innovationinnovation
Be careful not emphasise short-run results Be careful not emphasise short-run results at the expense of long-run objectivesat the expense of long-run objectives
Dangers of across the board cutsDangers of across the board cuts
17
Primary Mechanisms by Which Primary Mechanisms by Which PM Exerts ControlPM Exerts Control
Process ReviewsProcess Reviews Personnel AssignmentsPersonnel Assignments Resource AllocationsResource Allocations
18
Components of a Control SystemComponents of a Control System
SensorSensor StandardStandard ComparatorComparator Decision MakerDecision Maker EffectorEffector
19
Types of Control SystemsTypes of Control Systems
Go/No-Go ControlsGo/No-Go Controls predetermined standard must be met predetermined standard must be met
for permission to be granted to continuefor permission to be granted to continue Post-ControlPost-Control
done after project completeddone after project completed purpose is to allow future projects to purpose is to allow future projects to
learn from past project experiencelearn from past project experience
20
SCOPE CREEP AND CHANGE SCOPE CREEP AND CHANGE CONTROLCONTROL
Coping with changes frequently cited Coping with changes frequently cited by PMs as the single most important by PMs as the single most important problemproblem
Common Reasons for Change RequestsCommon Reasons for Change Requests ClientClient Availability of new technologies and Availability of new technologies and
materialsmaterials
21
Purpose of Change Control Purpose of Change Control SystemSystem
Review all requested changesReview all requested changes Identify impact of changeIdentify impact of change Evaluate advantages and disadvantages of Evaluate advantages and disadvantages of
requested changerequested change Install process so that individual with Install process so that individual with
authority may accept or reject changesauthority may accept or reject changes Communicate change to concerned partiesCommunicate change to concerned parties Ensure changes implemented properlyEnsure changes implemented properly Prepare reports that summarize changes Prepare reports that summarize changes
made to date and their impactmade to date and their impact
22
Rules for Controlling Rules for Controlling Scope CreepScope Creep
Include in contract change control Include in contract change control systemsystem
Require all changes be introduced by a Require all changes be introduced by a change orderchange order
Require approval in writing by the Require approval in writing by the client’s agent and senior managementclient’s agent and senior management
Consult with PM prior to preparation of Consult with PM prior to preparation of change orderchange order
Amend master plan to reflect changesAmend master plan to reflect changes