1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009
10

1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

Jan 17, 2016

Download

Documents

Cecil Clarke
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

1

MICE PM report

• Target News• Outcome of Spectrometer Solenoid Review• New plans for Steps II & III• RF Power news

MICE CMPB, 4th December, 2009

Page 2: 1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

Target News

• Online target working well• Now part of routine MICE shifts• Regular inspections, nothing to

report• Offline target/re-engineering going

OK• T3, all new parts are made except

bearing liners• Waiting for plastic bearing material,

Torlon/Vespel• Quite clear now that DLC coating of

metallic bearings is problematic, so have dismissed it

• Also DLC on DLC working in vacuum not such good idea

• First thing is to re-build T2 with plastic bearings and run it and see......

• Some minor open issues with plastics, but nothing thought serious2

Page 3: 1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

Target news

• Plans and Dates (only based on informal discussion):• Mid January – aim to have T2 rebuilt with Plastic bearings• Mid January – March – Run T2 and then assemble T3 in

identical format if worth doing• Easter shutdown – aim to have two identical targets to

resume on-line/offline programme

• Stator considerations:• In parallel to above, stator QA programme is

underway:• Mechanical field survey rig (G.Barber) to assess magnetic

assymetries• ASD at RAL have been asked to help Sheffield group with

precise coil winding – square conductors and precision coil formers and uniform vacuum impregnation

• Worry is that Jason Tarrant leaves MICE in January........

3

Page 4: 1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

Outcome of the Spectrometer Solenoid Review

• Very productive review held at Berkeley on 18th, 19th November, chaired by Pasquale Fabbricatori

• Briefly the important points are:• The overall thermal balance of the magnet is still not

completely understood, but this is being addressed by an ANSYS model and more experimental data

• Given the circumstances and schedule constraints, the addition of a fourth single-stage CCR to the HTS lead area is the right thing to do

• Operating margin of magnet two to be measured during cooldown

• The more complete fix to magnet one should be continued with

4

Page 5: 1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

Spectrometer solenoid

5

Page 6: 1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

Spectrometer Solenoid

Dates and decision points:– December – cooldown and training of magnet #2– Mid January, 2010:

• Magnet perfoms against acceptance criteria• Deliver to FNAL for field mapping, then RAL by mid April,

or:• Fails to meet acceptance criteria, so:• More complete fix required, then approx ten months’

work• Likely outcome here is that magnets one & two deliveries

converge

Important to remember: neither scenario will get Step II taking data before August 2010 (long ISIS shutdown)

So, the plan will have to change........

6

Page 7: 1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

New plans for Steps II & III

• At MICE TB this Monday, agreed that STEP II is abandoned

• And that we go straight to STEP III and have it ready for data-taking by February, 2011 (end of long shutdown)

• The scientific case for Step III.1 (LiH solid absorber is re-visited)

• Yet to be agreed by MICE EB – next week• FC #1 will arrive July ‘10, will need storage, but in reality

the ‘spare’ time will be very useful• Actions:

• Means we integrate two magnets in parallel• More space required, opened negotiations for R79• Installation staff profile will look different• Top-level schedule to be re-built around these dates

7

Page 8: 1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

RF PowerLifted from Andy Moss!

• Retest of medium power amplifiers have been done in the last month

• Electrical checks of large amplifier auxiliary electrical systems underway

• CERN HT connection used to speed up testing

• Connecting together medium and large power amplifiers

• Should have results of testing with RF in December for entire system into test load8

Page 9: 1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

RF Power

9

This is what we have to fit in R5.2,More complex than it was, this is a huge unknown!Really need to get on with design work as early as we can

Page 10: 1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.

RF PowerPresent RF project plan:• Test large 116 amplifier • Design hall coax in detail and work out how to fit it all in

space for steps 5 and 6• Assemble CERN amplifier and test with current power

supplies• Autumn 2010, move first amplifier system to MICE hall

and install

Conclusion:• Large amplifier ready and will re-commission to 1MW using old

tubes • Will run for as long as possible to develop understanding and look

for weak points • CERN amplifiers on site awaiting build• Hall layout needs careful work • search for smaller key coax components if possible• Two new TH116 tubes have been delivered to DL, two more due

soon 10