Page 1
1
1. INTRODUCTION
M/s RP Multimetals (P) Limited is already manufacturing Steel
Ingots, Billets, HR coils, MS Bars, flats, ERW/MS pipes etc., at
Village Salani, Amloh road, Mandi Gobindgarh, District
Fatehgarh Sahib Punjab. They now want to increase the capacity
of their unit by replacing existing induction furnace having
capacity 4TPHX2 & 5 TPHX1 with three no Induction furnaces
having capacity 15 TPH each. They also increase the capacity of
Rolling mill. The existing capacity of the unit is 200TPD of Steel
Ingots, Concast Billets and HR coils, MS Bars, flats, ERW/MS
pipes etc is 200 TPD. The capacity of the unit after expansion
will be 540 TPD of Billets, Steel Ingots and 540 TPD of HR
coils, MS Bars, flats, ERW/MS pipes. As per G.O.I Notification
dated 14/09/2006 they have to submit Form No- I along with Pre-
Feasibility Report and other relevant documents for getting
Environmental Clearance. Further, the project site falls within 5
km radius of the “Critically Polluted Areas” of Mandi
Gobindgarh as notified by the Central Pollution Control Board,
as such the project is to be treated as Category ‘A’ and thus the
Environmental Clearance will be given by the Ministry of
Environment and Forest, GOI, New Delhi. This Prefeasibility
report has, therefore, been prepared to assess the likely impact of
the proposed expansion on various factors which may be affected
with the implementation of the programme and to suggest
Page 2
2
remedial / precautionary measures, if any. Key plan of the site is
attached as Fig 1.1.
Page 3
3
FIGURE – 1.1 KEY - PLAN
PROJECT SITE
Page 4
4
2. PROFILE OF THE PROMOTORS & COMPANY
M/s RP Multimetals (P) Limited is a Private Limited Company.
The Director of the company are as under:
1. Sh. Narain Singla
2. Sh. Gopal Singla
3. Sh. Yograj Singla
4. Sh. Ashish Singla
All the promoters are well versed with the process involved &
can handle the project efficiently.
Page 5
5
3.0 DETAILS OF THE PROJECT
This is an existing unit for manufacturing of Steel Ingots,
Concast Billets, HR coils, MS Bars, flats, Rounds, ERW/MS
pipes. Now it is proposed to increase the capacity of the unit by
installing three numbers Induction furnace of capacity 15TPH
each and one number rolling mill of 340 TPD capacity, for
manufacturing of Steel Ingots, Billets, HR coil, MS Bars,
Rounds and flats etc at Village Salani, Amloh road, Mandi
Gobindgarh, Dist- Fatehgarh Sahib, Punjab. Plant & site location
of project is given in table 3.1. Layout plan of project is given
on Fig. 3.1. It is about 5 Kms from Mandi Gobindgarh bus stand
and about 60 km from Chandigarh and 40 km from Ludhiana on
SH-12A. The existing area of the plot is about 9.4 Acres. The
capacity of the unit after expansion will be Billets, Steel Ingots
& Blooms will be 540MTD and HR coils, rounds, ERW pipes,
flats will also be 540MTD.
3.1 Raw Materials
-The raw materials used in the manufacturing of steel Ingots /
Billets are as under:
i) MS/CI Scrap, Sponge / Pig Iron, Ferro Alloys:-
These will be sourced from Domestic as well as
International Markets.
-The raw materials used in the manufacturing of structural
sections are as under:
ii) Steel Ingots and Billets: -
These will be sourced from own unit.
Page 6
6
TABLE 3.1
Plant Site and Location S.No Particulars Details
1 Location
a Village Salani
b District / State Fatehgarh Sahib, Punjab
c Latitude 30°38'01.53” North
d Longitude 76o15’42.26” East
2 Elevation 261 mts.
3 Land use at the project site Industrial, As per notified Master Plan
4 Climatic Conditions Temperature Rainfall Relative Humidity, % Wind speed, Kms/hour
Min: 5.8oC, Max:41 oC 660 mm (average) Min: 22%, Max:80% 10 Km (approx.)
5 Nearest highway SH 12A and National Highway-44 (Delhi-Ludhiana)
6 Nearest railhead Mandi Gobindgarh (about 5 km)
7 Nearest airport Chandigarh (about 60 km)
8 Features with 10 km radius
a Defense installations Nil
b Archaeological important places
Nil
c Wild life sanctuaries Nil.
d Reserved/Protected forest Nil
e Industries in 10-Km radius Focal Point, Mandi Gobindgarh
9 Nearest major city Fatehgarh Sahib
10 Nearest major settlement Mandi Gobindgarh
11 Rivers in 10-Km radius Nil
12 Hill ranges Nil
Page 7
7
Figure-3.1 Layout Plan
Page 8
8
3.2 Power
The existing power of the unit is 12.78MW. The proposed power
requirement of the unit will be 10.00 MW. After expansion
power demand will be 22.78 MW. This demand will be met by
sourcing the power from Punjab State Power Corporation limited
from nearby Sub-station.
3.3 Water
Water consumption for the unit will be small as the requirements
are only for cooling system where water will be re-circulated in a
closed circuit. The existing requirement of the fresh water is
about 28 KLD which include 20.0 KLD for makeup water is
required for meeting the evaporation losses in the cooling circuit
and 8 KLD for domestic purpose. After expansion total fresh
water required will be 38 KLD which would be met from ground
water through a tube-well already existing within the premises.
Water balance of the project has been shown in Fig. 3.2
Page 9
9
Figure: 3.2
WATER BALANCE FLOW DIAGRAM
(KLD)
Supply Water over head Tank
38
Domestic Water Supply
(14)
Cooling Tower Tank (500)
STP (11.2)
Cooling for furnace
For Irrigation purpose for Plantation
Clear Water Tank (476)
Evaporation (24)
Consumption (2.8)
Page 10
10
3.4 Manpower
The requirement of personnel for the proposed plant has been
made keeping in view of the following:
• Technical concept of plant, including process control and
instrumentation.
• Smooth and efficient operation of the plant.
• Effective co-ordination between the various departments
within the plant.
• Optimum organization will well defined and judicious job
distribution
• Optimum utilization of different grades of workmen and
supervisory staff and
• Maximum capacity of the facilities.
In all there are about 225 persons working in the unit out
of which no persons will stay in the factory except
watchman. After expansion about 325 persons will be
working in the unit.
Page 11
11
3.5 Manufacturing Process
The industry produces Billets from melting scraps and cast iron
scraps. All operations are carried out in batch process. The
overall manufacturing process comprises of the following steps -
Furnace Loading -The raw material (Steel scrap crushed into
suitable sizes which can be accommodated in
the furnace) is loaded into the furnace
crucible, to the brim, with the furnace set on.
Heating/Melting - The loaded pieces are heated to melting
(temperature of about 1600� C) and steel
scrap is loaded incrementally till the furnace
crucible is completely filled (up to its rated
capacity) with molten volume.
Slag Removal - The impurities present in the molten content,
being light, gets collected as slag at the top
and requires regular removal from the top of
the molten volume.
Alloying - Calculated quantities of carbon, manganese,
silica, etc. are added to the molten metal, for
alloying, to obtain the steel of desired
grade/characteristics.
Laddle Pouring - The molten steel is tapped into the laddles for
onward pouring into the caster at other place.
Page 12
12
Caster - The High Speed Module Caster is meant for
conversion of the molten steel into Billets of
the requisite sizes as per particular
requirements. The whole process comprises of
tapping of the molten metal into moulds
Cooling - The tubes are allowed to cool at appropriate
temperature to obtain the solidified form of
metal. These castings in the form of Billets
are continuously withdrawn from the bottom
of the mould tubes covered with water-spray
from mould tube to the withdrawal section.
Billet - The square billets are shifted to the cooling
beds with the help of rollers and hydraulics.
Roughing Mill No. 1 -The billet from the Cooling beds is shifted
to Roughing Mill No.1with the help of Chain
Shifters and High Speed Conveyors. The
Billet automatically passes four times from
the roughing mill with the help of conveyors
and horizontal/vertical stands, making it
compatible for Intermediate Mill No. 2 and
giving it the basic shape of a MS Bar (Strip).
Intermediate Mill No. 3 -The basic strips are transferred to the 16”
intermediate Mill No. 3 through High Speed
Conveyors and manual operations.
Page 13
13
Finishing Mill Nos 4/5/6 -After the above intermediate processing, the
strips are passed through these three stages for
the finishing process.
Flat Bed Conveyor - It is used for carrying the above material to
the hot coiler. The strip is transferred to the
Hot Coilers through these flat bed high speed
conveyors.
Hot Coiler - The strip passed by the Flat Bed Conveyors
reaches out to the Hot Coiler and the same is
coiled into baby coils.
De Coiler - The hot coil is de-coiled further for the cutting
process.
Cutting - After passing through the De Coiler, the strips
are cut into pieces of the desired lengths.
Cold Coiler - After cutting, the strip pieces are now coiled
into cold coils as per requirement.
Final Product - After the cold coiler processing, the final
product of this stage, i.e. the strips become
ready for use.
Cold Strip / De coiler / These steps are initiated for conversion of the
cold strips into
Pipe Mill pipes of the requisite sizes.
Page 14
14
Welding - It is done to join the pipes.
Cutting - Cutting of the pipes is done with the purpose
to obtain the suitable smaller pieces of the
required sizes.
Final Product ERW PIPES After completion of the above mentioned
steps, the final product is available in the
shape of ERW Pipes.
Page 15
15
MS Scrap & Additives storage
Charging of Material in Furnace
Melting
Billets
Slag
Rolling Mill
Final Product
VD/VOD
CCM
LRF
Fig 3.3
Process flow chart
Page 16
16
3.6 OTHER FEATURES:
• The plant would incorporate the most modern control
system using the latest microprocessor based Dust Control
System.
• Cooling water circuit is close circuited, thereby ensuring
no generation of waste water.
• The process, selected envisages re-cycling all the material
collected in the pollution control equipment whereby
ensuring no generation of solid waste.
• The plant lay out is so arranged that the major production
units are laid in a straight line whereby minimizing/
avoiding the various transfer points.
Page 17
17
5. BASELINE ENVIRONMENTAL SETTINGS
4.1 The State
Punjab is one of the progressive States in the Northern part
of India. It derives its name from five rivers which used to
flow through the State before partition of the Country in
1947 viz Satluj, Beas, Ravi, Chenab, and Jehlam. After
partition two of the rivers i.e. Chenab and Jehlam went to
Pakistan Punjab and the other three remained in Indian
Punjab. The economy of the State is dependent mainly on
Agriculture. Punjab has over 2.04 lakh small and medium
industries and about 600 large scale industries. It leads in
the manufacture of machine and hand tools; printing and
paper cutting machinery; auto parts and electrical switch
gear. The State also provides more than 75% of the
country's requirement for bicycles, sewing machines,
hosiery and sports goods. It has also made big strides
towards industrialization. A number of Industrial areas
have been developed by the State. Ludhiana, Jallandhar,
Amritsar and Mohali are famous for Large and Medium
scale industrial units.
4.2 Fatehgarh Sahib District
The historic and pious district of Fatehgarh Sahib came
into existence with effect from 13th April, 1992, Baisakhi
Page 18
18
Day deriving its name from Sahibzada Fateh Singh, the
youngest son of Guru Gobind Singh. It is bounded by Distt
of Ropar in the North, Patiala in the South, Mohali and
Part of Patiala in the East Ludhiana in the West it is about
50 Kms towards the west of Chandigarh, the capital of
Punjab.
The economy of the district depends mainly on agriculture
and allied activities. The main towns are Sirhind, Bassi
Pathana, Amloh, Khamano & Mandi Gobindgarh. The last
is also known as the 'Steel Town of India' having a good
number of steel rolling mills. Besides, numerous industrial
units are engaged in the manufacturing of sewing machine
parts, centrifugal pumps, bus/truck body building and
mining machinery.
4.3 Project Site
The project is located at Village Salani, Amloh road Mandi
Gobindgarh of Fatehgarh Sahib Dist of Punjab on SH-12A.
It lies near Long 76o-15’42.26” and Lat: 30o-38’01.53” and
is at an Altitude of about 261m above mean sea level.
4.4 Climate:
There is a meteorological observatory at Chandigarh which
is at a distance of about 60 km from the site. Its data is
fairly representative of the conditions in the District in
Page 19
19
general. The climate of the district is generally dry except
in the brief monsoon season and is very hot in summer and
cold in winter. The cold season is from middle of
November to early part of March. Succeeding period up-to
the end of June is hot season. July, August and September
are the South West monsoon season.
4.5 Temperatures
The area is fairly plain. December and January are the
coldest months whereas in May and June the heat is quite
intense. The temperature varies from 5oC minimum to
41oC maximum during the year.
4.6 Rainfall
The rainfall in the Zone is caused by the South-West
monsoon. It starts in the month of July and extends up-to
the end of September. During this period the monsoon
rain-fall contributes about 70 to 80% of the total annual
rainfall. The average annual rain fall is in the range of 660
mm. The annual numbers of rainy days on an average are
about 34 in a year, out of which about 20 falls in the
monsoon period of July to September.
Page 20
20
4.7 Humidity
In summer months of April, May and June, which is the
driest part of the year, the afternoon humidity comes down
to 22% while the relative humidity during monsoon
months goes upto about 80%.
4.8 Cloudiness
During monsoon season skies are over cast with moderate
to heavy clouds. During rest of the year, the sky is mostly
clear. It is lightly clouded occasionally during winter
season.
4.9 Winds
The Wind direction in the area is mostly from North-West
to South-East. During January to May the winds are quite
strong while July to October is calm months. The general
trends of various meteorological data from meteorological
observatory at Chandigarh and field observations are used
to draw Wind Rose Diagram.
4.10 Drainage
The area is generally plain and has good slope from North-
East to South-West. The area is well drained and takes the
entire rain water flows to Sirhind Choe which ultimately
joins river Ghaggar near Haryana boundary.
Page 21
21
4.11 Land Use
The total area of the District is 1147 sq km. 89% is net
sown area and 11% is under non-agricultural use.
Agriculture is mostly dependent on tube-wells. Rice and
wheat are the main crops in the area.
4.12 Forest
There is no reserved forest near the project site. The area
under forest is hardly about 2000 Ha. The company also
proposes to plant about 200 trees and shrubs within the
project area.
4.13 Flora And Fauna
Ecological system consists of varieties of interrelationship
between both biotic and abiotic components. Biotic
components comprise of both plant and animal
communities, which interact not only within and between
them but also within the abiotic physical. Animal plant
communities in their natural habitat exist in a well
organized manner. The project does not disturb any natural
setting and is coming up in an already existing Industrial
area. Flora in the area generally consists of Dalbergia,
Prosopis, Albizzia, Ficus, Azolla, Hydrilla, Nelumbo,
Typha, Phragmites, Zizyphus Mauritiana, Syzgium cumini,
Ipomoea aquatica, Cyprus and Grasses. Animals like
Page 22
22
Smooth Indian Otter, Hog Deer, Wild Boar, Flying
Fox, Wildcat, Squirrel, Fruit bat, and Common
Mongoose are found in the area.
4.14 Ambient Air Quality
The Status of Ambient Air Quality in the study area will be
determined by monitoring air quality in the Area at
different locations after issuing Terms of Reference. The
study area is a mix of rural, urban and industrial area and
the various sources of pollution are dust arising from
agricultural activities, vehicular traffic and industries.
4.15 Water Quality
Water quality of ground as well as surface resources in the
study area will be studied for assessing the water
environment and to evaluate the anticipated impact of the
project on environment after issuing of Terms of
Reference.
Page 23
23
4.16 Ambient Noise Quality
Noise is defined as unwanted sound due to any operation.
Presently there are no noise creating machinery nor any
such has been added, except DG Sets which will be noise
less.
4.17 Soil
Soil is generally sandy loam almost all over the District
and soil depth is generally shallow except in areas having
good vegetative cover. It is generally dry, shallow and
deficient in organic matters. The study area comprises
mostly of alluvial deposits of Quaternary age. The
geological formations in the area comprise of sandstone
largely micacous and form major features. The top zone of
this stage consists of maroon clays and buff clays
alternating one by one.
4.18 Demography And Socio-Economic Scenario
Large scale Industrial development has taken place in and
around Mandi Gobindgarh. The socio-economic profile
has been studied through random sample primary surveys
and secondary data. The significant demographic and socio
economic statistics of the district are summarized and
given in Table- 4.1
Page 24
24
TABLE-4.1 Summary of Key Demographic Statistics
PUNJAB DIST. FATEHGARH SAHIB
Particulars 2011 2011
Male Population 1,46,34,819 3,20,603
Female Population 1,30,69,417 2,79,211
Total Population 2,77,04,236 5,99,814
Sex Ratio 893/1000 886
Density of Population/Km2
550 508
Literacy Rate: Total 76.68 % 80.30%
Male 81.48% 84.50%
Female 71.34% 75.50%
Source: censes 2011
Page 25
25
5.0 ENVIRONMENTAL IMPACT ASSESSMENT:
5.1 Present Environment:
Various Environment factors as existing in the project area
which possibly are liable to be affected by the activities
have been assessed & identified as below:
(i) Ambient Air
(ii) Water Quality
(iii) Noise
(iv) Land use pattern
(v) Demography and socio-economic pattern.
5.2 Probable Impact on Environment:
The above factors will be checked after the implementation
of the project to cross check the probable impact discussed
hereunder and remedial measures taken wherever
necessary. Broadly the impacts may be classified in two
categories as under:-
i) Short term -during construction/development stage
ii) Long term -during operational stage.
Both these categories have been considered while
predicting and evaluating the impacts as under:-
Page 26
26
5.3 Development Stage: - (Short Term)
This is a construction phase of the project and the impacts
are temporary due to construction related activities are as
under:-
i) Air Environment:
There is no point source of air pollution. The only
source will be the dust generation due to excavation,
construction and plying of vehicles within unit.
Some emission may be expected from vehicles
plying in the area for transportation of material etc.
Kerosene oil shall be provided to the labour so that
they do not burn wood for cooking etc. Since the
plant is an existing one and very few additions are to
be made there is no likely hood of any significant
effect on the overall air environment of the area.
ii) Water Environment :
Requirement of water during construction (Making
foundation & Platform of furnace) will be about 1.0
m3/day and there will be no discharge as the same
will be used completely. Labour during construction
is not very large. Hardly about 10-15 persons may
be working on an average that may be using water
for drinking and bathing etc. Toilet facilities already
exist at site which will be used by the labour.
Page 27
27
In view of this there is no likely hood of any
significant impact on the general environment of
water in the area.
iii) Noise Environment:
Some noise may be expected from the working of
the machinery for construction purposes and
movement of vehicles. Steps will be taken to reduce
its effect by resorting to staggering of various
operations Even otherwise since there will not be
any large scale machinery, the activity is not likely
to have any significant effect on the over all noise
environment.
iv) Land Environment:
The land at site is fairly level as such no leveling is
required. Natural drainage will not be disturbed.
Solid waste from construction activities will be used
within the premises under roads & refilling. There
will not be any significant impact on land in general.
Page 28
28
v) Socio Economic:
It is an existing project and it does not involve any
displacement of population or rehabilitation of any
kind. Rather it will provide employment to local
people and boost the economy of the area. It will
have some positive impact, although not to a large
extent.
5.4 Operational Stage: - (Long Term)
After completion, when the additions start production, the
operational impacts on the various parameters are
discussed as under:-
i) Ambient Air Environment:
There are only two sources of likely pollution:
a) SPM emission from the Induction furnaces
b) Steel Rolling Mills & Reverbratory Furnace
c) D.G. Sets (Proposed 320&500KVA).
There are three no existing Induction having capacity
4TPHX2and 5TPHX1 and one number steel rolling mill of
capacity 200 TPD. Now they want to enhance the capacity
of unit by replacing existing furnaces with addition 3
numbers Induction furnaces of capacity 15 TPH each and
one number rolling mill of capacity 340TPD. There will be
Page 29
29
generation of emission containing SPM. All these
processes are closed circuits as such emissions to the
atmosphere will be minimum. However, APCD like Bag
filters will be provided at the exit point to arrest particulate
matter for Induction furnace and scrubber on rolling mill.
Whatever solid waste is arrested through APCD the same
will be collected & disposed off at designated site.
Flue gas from the DG Sets will pass through a chimney of
adequate height and the final gas will be within
permissible limits. Thus air environment is not likely to be
affected significantly.
ii) Water Environment:
The total use of water after expansion will be about
38m3/day. The domestic waste water generated will be
about 11.2m3/day, which will be treated through STP. The
There will be no generation of industrial waste water after
expansion. The entire cooling water will be recirculated.
Thus water environment is not likely to be affected after
expansion. Further, ground water will be balanced through
recharge by rain water harvesting from the roof top
through recharge wells. Thus pressure on underground
water will be reduced.
Page 30
30
iii) Land Environment:
It is an existing steel manufacturing unit. No additional
land will required for expansion. Thus there will not be
any significant adverse effect on the existing general land
environment with the enhancement of the project.
iv) Noise Environment:
There is no noise producing machinery or equipment
except ID fans & Blower etc. which is placed in a room
causing least disturbance in the area. There is no likelihood
of any significant change in noise environment. The DG
Sets are of noiseless type.
v) Socio Economic Pattern
The project will provide extra employment to local people
in the field of running plants and maintenance of APCDs
and security etc. Thus it will have some positive effect on
the employment potential in the area.
Page 31
31
6.0 ENVIRONMENTAL MANAGEMENT PLAN:
6.1 General
Environment Management Plan (E.M.P) in a project is
prepared to mitigate the possible adverse effect of
various activities on the existing environmental factors,
during construction as well as in operational stages, to
avoid their deterioration, if any. It is desirable that
necessary steps are taken right from the beginning of the
project to be more effective. E.M.P. for this project has
been prepared keeping in view the existing conditions and
likely changes which may occur due to the proposed
project.
6.2 Air Environment
During construction stage water will be sprinkled on the
soil to avoid dust generation if any. The debris and unused
construction malbas shall be removed immediately for
recycling, if any, or for land fill.
APCDs like Bag filters, shall be provided to arrest SPM
from flue gases to keep it within permissible limits. All
vehicles for service activities at the project site shall be
checked for vehicular emission. The agencies will be asked
to keep them within prescribed limits. They will also be
asked to maintain them properly. A chimney of suitable
Page 32
32
height has been provided for the D.G. Set to control the
G.L.C. of S.P.M., SO2, & Nox levels. Extensive tree
plantation shall be resorted to for further improving the air
environment in general and minimize noise levels.
6.3 Water Environment:
Water shall be drawn from existing tube-well installed in
the factory area. During construction existing toilet
facilities shall be used by the labour. Finally waste water
from the toilets shall be taken to septic tank through
underground delivery system and treated up to tertiary
level. Treated water will be used for irrigation within the
premises. It will not be thrown outside either on land or in
any water body. Roof top Rain Water shall be harvested
and used for ground water recharge to minimize effect of
withdrawal of water from the underground.
6.4 Land Environment:
To avoid erosion of the top soil the development is planned
in the shortest possible time and land-clearing activity shall
be kept to the absolute minimum by working at the specific
sites one by one where construction is to take place so as to
increase detention and infiltration. The construction
activity is within the shed area. Natural
waterways/drainage pattern shall be maintained by
Page 33
33
providing culverts where needed. The requirements of sand
and aggregates for the construction works will be met
through venders. The land use is thus so planned that there
is minimum adverse impact.
6.5 Solid Waste
The other solid wastes from the bag filters shall be stored
in a dumping pit of R.C.C. and disposed off in the
designated land fill places. Slag from the manufacturing
process shall be given to cement plant for further use.
6.6 Green Belt
The main objective of the green belt is to provide a barrier
between the source of pollution and the surrounding areas.
The green belt helps to capture the fugitive emission and
to attenuate the noise generated, apart from improving the
aesthetics. Development of green belt and other forms of
greenery shall also prevent soil erosion and washing away
of topsoil besides helping in stabilizing the functional
ecosystem and further, to make the climate more
conducive and to restore water balance. It is planned that
the selected plants will be grown as per normal
horticultural (or forestry) practice and authorities
responsible for plantation will also make sure that adequate
provision for watering and protection of the saplings exists
at site.
Page 34
34
6.7 Occupational Health and Safety of workers
The only health hazards expected are heat & dust.
Following mitigation measures will be provided:-
1. HEAT:
• Workers working near the furnace and
handling moulds manually may be exposed to
heat.
• Fans will be provided near such places and hot
air shall be drawn through exhaust fans.
• All workers will be provided PPE like gloves,
helmets, gum boots, goggles etc.
• Fresh water shall be available near the working
area.
2. DUST:
• Exhaust fans have been provided for collection
of dust laden air within the shed and its further
disposal through bag filters.
• Face masks and side covered glasses have
been provided to all workers.
• Frequent check-up of the workers will be done
which shall include chest X-ray, ECG & vision
testing. Necessary treatment shall be provided
wherever required.
Page 35
35
• All check-ups will be documented and re-
viewed monthly for Occupational health and
safety of the workers.
Page 36
36
7.0 ENVIRONMENT MONITORING PROGRAMME
Regular monitoring of all significant environmental parameters is
essential to check the compliance status vis-à-vis the
environmental laws and regulation. The objectives of the
monitoring will be as follows:
� To verify the results of the impact assessment study
with respect to the proposed projects.
� To study the trend of concentrated values of the
parameters, which have been identified as critical and
then planning the mitigating measures.
� To check and assess the efficacy of pollution control
equipment.
� To ensure that any additional parameters, other than
those identified in the impact, do not turn critical after
the commissioning of proposed project.
To implement the EMP, a structured Environment Management
Cell (EMC) interwoven with the existing management system
will be created. EMC will undertake regular monitoring of the
environment and conduct yearly audit of the environmental
performance during the construction of the project. It will also
check that the stipulated measures are being satisfactorily
implemented and operated. It shall also co-ordinate with local
authorities to see that all environmental measures are well
coordinated.
Page 37
37
A comprehensive environmental monitoring program that has
been prepared for the purpose of implementation in the proposed
residential colony by the EMC is described below:
� The ambient Air quality shall be monitored at project
site and two upward and downstream locations once
every quarter for PM2.5, PM10, NOx & SO2 and CO
levels during the Construction Phase and Operational
Phase. The Ambient Noise Levels shall also be
monitored once every six months.
� The vehicles shall be checked for PUC once every
quarter during the development period and records shall
be maintained.
� Groundwater quality of the Tube-wells in site area will
be regularly monitored preferably once in a quarter
during the development period.
� Air Pollution Control System & ETP/STP shall be
provided with a small Laboratory and weekly
monitoring of the parameters shall be undertaken. In
addition monitoring shall be got done from an
independent agency as laid down by State Pollution
Control Board.
All the above observations will be complied and
documented by the EMC to serve the following
purposes.
Page 38
38
� Identification of any environmental problems that are
occurring in the area.
� Initiating or providing solution to those problems
through designed channels and verification of the
implementation status.
� Controlling activities inside the project, until the
environmental problem has been corrected.
� Suitably responding to emergency situations.
7.1 Environment Management Cell:
The Environment Management Cell shall include:
� Representative of Management (Head of Environment
Cell)
� Process Incharge
� Incharge Maintenance Department
� A representative of Environmental Consultants