8/21/2019 1 Introduction General
1/45
COURSEFACILITIES LAYOUT TRAINING
INTRODUCTION & GENERAL
1
8/21/2019 1 Introduction General
2/45
FACILITIES LAYOUT TRAINING COURSE
INTRODUCTION & GENERAL
• The layout process FieldLocation
Field Layout
Facility
Layout
Equipment /
Piping Layout
2
8/21/2019 1 Introduction General
3/45
INTRODUCTION & GENERAL
DEVELOPMENT CONCEPT SELECTION
3
Field
Deveopment
Concept
Existing Infra
Structure
Pipelines
Processing Facility Nearby
Heliport
Onshore Base FacilitiesSupply boats
Site Contingency /
emergency response (EER, oil spill)
Processing
Requirements
(BOD)
Water depth
Other
environmenta
l issues
Economy
CAPEX
OPEX
Value of production
Sub seaFloating
Fixed
FPSO
SPAR
Semisub
Art if ic ial is land
MOPUSTOR
Jacket supported complex
Integrated platform (GBS or jacket)
Minimal wellhead (STAR or equal)
8/21/2019 1 Introduction General
4/45
INTRODUCTION & GENERAL
SAFETY ASPECTS / LAYOUT
4
Choise of a location
Impact of environment on facility
Site Contingency Plan
SELECTION OF LOCATION (Y / N)
Operation Philosophy
Division into fire zones
Main equipment / unit divisioning
Main spacing
PLOT PLAN
EQUIPMENT LAYOUT
Special Studies
Additional Physical Protection
Risk Assessments
Development Concept
Special
Studies
Field / platformorientation is also an issuehere
8/21/2019 1 Introduction General
5/45
INTRODUCTION & GENERAL
SAFETY ASPECTS / LAYOUT / ORIENTATION
5
Fixed installation
8/21/2019 1 Introduction General
6/45
INTRODUCTION & GENERAL
LAYOUT AT DIFFERENT LEVELS OF DESIGN
Pre
Conceptual
Design
Conceptual
Design
FEED
Detailed
Design
Front End
Engineering
Design
6
Plot plans
Equipment
Layouts
8/21/2019 1 Introduction General
7/45
INTRODUCTION & GENERAL
GENERAL APPOACH
Basis of
Design
Process
Design /
Layout
HYSYS
Block diagrams
PFD'sP&ID's
Line Lists
Regulations
& Standards
Composition,
Production Data
Production Target
Layout
Philosophy &
Strategy
Operation /
Maintenance
Philosophy/strategy
Safety
Philosophy /
Strategy
Other
philosophies /
strategies
Preliminary
Layout
DetailedLayout
Equipment
List
EquipmentSizing
7
8/21/2019 1 Introduction General
8/45
INTRODUCTION & GENERAL
DETAILED CONSIDERATIONS
8
PROCESS &
EQUIPMENT
WORK &
OPERATIONS
LOCATION
SPACE REQ. /
SPACING /
ACCESS REQ
Equipment to perform
unit operations /
Alternatives
Rooms, Workshops
Service facilities,
Non-process equipm.
LAYOUT
EQUIPMENT TYPES
(SPACE / ORIENTATION / LOCATION)
SPACE REQUIREMENTS,
NON-PROCESS EQUIPMENT,
WORKING ENVIRONM / HUMAN FACTORS
8/21/2019 1 Introduction General
9/45
INTRODUCTION & GENERAL
LOCATION OF INSTALLATIONSupporting structure and water depth:
In shallow waters, artificial islands are options 9
8/21/2019 1 Introduction General
10/45
INTRODUCTION & GENERAL
LOCATION OF INSTALLATIONWind rose for location is important for orientations
10
Example North SeaExample Arabian Gulf
8/21/2019 1 Introduction General
11/45
INTRODUCTION & GENERAL
LOCATION OF INSTALLATIONOne additional factor – ships traffic intensity:
11
8/21/2019 1 Introduction General
12/45
INTRODUCTION & GENERAL
LOCATION OF INSTALLATIONOil Logistics
12
OIL
LOGISTICS
Pipeline
Production
directly to
tanker
Production to
tank
TANK
Sub sea tank Tank platform FSO
Concrete
GBSSteel tank
Offloading
from tank
Submerged
Loading
System (SLS)
SPM
(Single Point
Mooring)
Tandem Hose
Offloading
For example SAL
8/21/2019 1 Introduction General
13/45
INTRODUCTION & GENERAL
LOCATION OF INSTALLATIONOffloading systems
13SPM Calm BuoySPM rigid tower
8/21/2019 1 Introduction General
14/45
INTRODUCTION & GENERAL
ENVIRONMENTAL CONDITIONS• Special – specific sensitive areas
• Water depth & tides (HAT, LAT)
• Wind, Waves
• Current
• Marine growth
• Sea ice / ice bergs
• Snow & ice (ice load on structure)
• Air / sea temperature
• Humidity
• Earthquake / seismic design conditions
14
8/21/2019 1 Introduction General
15/45
INTRODUCTION & GENERAL
ENVIRONMENTAL CONDITIONS - STANDARDS• ISO 19901-1: Metocean Design & Operationg Considerations
• ISO 19901-2: Seismic design
• ISO 19901-3: Geotechnical & foundation design
15
8/21/2019 1 Introduction General
16/45
INTRODUCTION & GENERAL
PLATFORM TYPES & JACKETS
• Maersk Oil, Gorm Field, Denmark
16
8/21/2019 1 Introduction General
17/45
INTRODUCTION & GENERAL
PLATFORM TYPES & JACKETS
• Riser Platform, Denmark
17
8/21/2019 1 Introduction General
18/45
INTRODUCTION & GENERAL
PLATFORM TYPES & JACKETS
• Integrated Deck on GBS
18
8/21/2019 1 Introduction General
19/45
INTRODUCTION & GENERAL
PLATFORM TYPES & JACKETS
• Unmanned minimum platform, 4-legged jacket,
helideck19
8/21/2019 1 Introduction General
20/45
INTRODUCTION & GENERAL
PLATFORM TYPES & JACKETS
• Unmanned minimum platform, tripod column jacket,
no helideck20
8/21/2019 1 Introduction General
21/45
INTRODUCTION & GENERAL
PLATFORM TYPES & JACKETS
• Unmanned minimum platform, tripod column jacket,
helideck21
8/21/2019 1 Introduction General
22/45
INTRODUCTION & GENERAL
PLATFORM TYPES & JACKETS
• Qatar, Al Shaheen, E-location
22
8/21/2019 1 Introduction General
23/45
INTRODUCTION & GENERAL
SOME USUAL JACKET TYPES
23
8/21/2019 1 Introduction General
24/45
INTRODUCTION & GENERAL
SITE CONTINGENCY PLAN
Two main issues to consider for the actual site:
• Operational & Maintenance Support & logistics
• Emergency Response support & logistics
24
8/21/2019 1 Introduction General
25/45
SITE CONTINGENCY PLAN
OTHER REQUIRED STRATEGIES / PHILOSOPHIES• Operation / Maintenance philosophy / strategy
• Safety philosophy / strategy
• Human factors strategy/plan
• Emergency shutdown Philosophy (ESD isolation/blowdown)
• Active/passive fire protection Strategy
• Expansion strategy
• Rotating equipment selection philosophy / strategy
• Major static equipment selection philosophy / strategy
• Valve and actuator selection philosophy / strategy
• Mechanical handling philosophy / strategy
25
8/21/2019 1 Introduction General
26/45
OTHER REQUIRED PHILOSOPHIES / STRATEGIES
SAFETY PHILOSOPHY / STRATEGY• Ref. ISO 13702
• FES (Fire & Explosion Strategy) incl. design fire loads and blast
pressures
• EERS (Escape, Evacuation and rescue strategy)
26
8/21/2019 1 Introduction General
27/45
OTHER REQUIRED PHILOSOPHIES / STRATEGIES
MECHANICAL HANDLING PHILOSOPHY / STRATEGY• Adress all equipment > 25 kg to be handled
• Requirements for laydown areas
• Transport routes
• Requirements for cranes, permanent lifting appliances and
portable lifting equipment
• Etc
27
8/21/2019 1 Introduction General
28/45
CONCEPTUAL PROCESS LAYOUT
BLOCK DIAGRAM
Storage
(tank)
pump Heating (heatexch)
Mix / storage
cold pot. water
closed heating
medium system
Mixer
Filling point
Product
28
8/21/2019 1 Introduction General
29/45
CONCEPTUAL PROCESS DESCRIPTION
PROCESS FLOW DIAGRAM (PFD)
29
8/21/2019 1 Introduction General
30/45
CONCEPTUAL PROCESS DESCRIPTION
MAIN PROCESS SCHEMATIC
30
V1
V2
V3
TEG
NGLREC
SALE
JT
FUEL
FUEL
FUEL
LIFT
EXPORT GAS
STABILIZED CRUDE OIL FOR EXPORT
PRODUCED WATER TOTREATMENT
MULTIPHASE FLUIDFROM WELL(S)
IP
LP2 LP1
HP
8/21/2019 1 Introduction General
31/45
CONCEPTUAL PROCESS DESCRIPTION
PIPING & INSTRUMENT DIAGRAM (P&ID)• P&ID’s in oil&gas generally follows ISA S5.1
• ISA S5.1 has 3 levels of detailing
• Simplified diagram
• Conceptual diagram
• Detailed diagram
31
8/21/2019 1 Introduction General
32/45
CONCEPTUAL PROCESS DESCRIPTION
P&ID SIMPLIFIED LEVEL (ISA S5.1)
32
8/21/2019 1 Introduction General
33/45
CONCEPTUAL PROCESS DESCRIPTION
P&ID CONCEPTUAL LEVEL (ISA S5.1)
33
8/21/2019 1 Introduction General
34/45
CONCEPTUAL PROCESS DESCRIPTION
P&ID DETAILED LEVEL (ISA S5.1)
34
8/21/2019 1 Introduction General
35/45
PHYSICAL LAYOUT
PLOT PLAN
35
Plot plansshows theentire level
in one
drawing.
Unit / main
equipment
level
8/21/2019 1 Introduction General
36/45
PHYSICAL LAYOUT
EQUIPMENT LAYOUT
36
Equipment
layout is a “unit plot
plan”, i.e.
the plotplan is
dividedinto units /
modules.
Other than
mainequipment
also shown
8/21/2019 1 Introduction General
37/45
PHYSICAL LAYOUT
HAZARDOUS AREA CLASSIFICATION
37
One drwg
per decklevel +
overall view
8/21/2019 1 Introduction General
38/45
PHYSICAL LAYOUT
HAZARDOUS AREA CLASSIFICATION
38
In addition
to planviews – side
views
(elevations)required
from more
than one
side
8/21/2019 1 Introduction General
39/45
PHYSICAL LAYOUT
F&G DETECTOR LAYOUT
39
8/21/2019 1 Introduction General
40/45
PHYSICAL LAYOUT
FIRE & SAFETY PLAN
40
8/21/2019 1 Introduction General
41/45
PHYSICAL LAYOUT
DELUGE AREA PROTECTION DRAWING
41
8/21/2019 1 Introduction General
42/45
PHYSICAL LAYOUT
FRAMING PLAN
42
8/21/2019 1 Introduction General
43/45
LISTS
EQUIPMENT LIST
• All equipment shown in layouts/plot plans are shown in
equipment list
• First input to equipment list is from PFD/P&ID
• Size/Weight is shown in the equipment lists
• For pre-conceptual and conceptual designs, sizes are based on
experience and estimates
• On day 3 we will revert to methods for estimation of
sizes/weights.
43
8/21/2019 1 Introduction General
44/45
LISTS
EQUIPMENT LIST
44
8/21/2019 1 Introduction General
45/45
THANK YOU
45