Top Banner

of 19

1 Introduction General

Aug 07, 2018

Download

Documents

ngtchung
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/21/2019 1 Introduction General

    1/45

    COURSEFACILITIES LAYOUT TRAINING

    INTRODUCTION & GENERAL

    1

  • 8/21/2019 1 Introduction General

    2/45

    FACILITIES LAYOUT TRAINING COURSE

    INTRODUCTION & GENERAL

    • The layout process FieldLocation

    Field Layout

    Facility

    Layout

    Equipment /

    Piping Layout

    2

  • 8/21/2019 1 Introduction General

    3/45

    INTRODUCTION & GENERAL

    DEVELOPMENT CONCEPT SELECTION

    3

    Field

    Deveopment

    Concept

    Existing Infra

    Structure

    Pipelines

    Processing Facility Nearby

    Heliport

    Onshore Base FacilitiesSupply boats

    Site Contingency /

    emergency response (EER, oil spill)

    Processing

    Requirements

    (BOD)

    Water depth

    Other

    environmenta

    l issues

    Economy

    CAPEX

    OPEX

    Value of production

    Sub seaFloating

    Fixed

    FPSO

    SPAR

    Semisub

     Art if ic ial is land

    MOPUSTOR

    Jacket supported complex

    Integrated platform (GBS or jacket)

    Minimal wellhead (STAR or equal)

  • 8/21/2019 1 Introduction General

    4/45

    INTRODUCTION & GENERAL

    SAFETY ASPECTS / LAYOUT

    4

    Choise of a location

    Impact of environment on facility

    Site Contingency Plan

    SELECTION OF LOCATION (Y / N)

    Operation Philosophy

    Division into fire zones

    Main equipment / unit divisioning

    Main spacing

    PLOT PLAN

    EQUIPMENT LAYOUT

    Special Studies

     Additional Physical Protection

    Risk Assessments

    Development Concept

    Special

    Studies

    Field / platformorientation is also an issuehere

  • 8/21/2019 1 Introduction General

    5/45

    INTRODUCTION & GENERAL

    SAFETY ASPECTS / LAYOUT / ORIENTATION

    5

    Fixed installation

  • 8/21/2019 1 Introduction General

    6/45

    INTRODUCTION & GENERAL

    LAYOUT AT DIFFERENT LEVELS OF DESIGN

    Pre

    Conceptual

    Design

    Conceptual

    Design

    FEED

    Detailed

    Design

    Front End

    Engineering

    Design

    6

    Plot plans

    Equipment

    Layouts

  • 8/21/2019 1 Introduction General

    7/45

    INTRODUCTION & GENERAL

    GENERAL APPOACH

    Basis of

    Design

    Process

    Design /

    Layout

    HYSYS

    Block diagrams

    PFD'sP&ID's

    Line Lists

    Regulations

    & Standards

    Composition,

    Production Data

    Production Target

    Layout

    Philosophy &

    Strategy

    Operation /

    Maintenance

    Philosophy/strategy

    Safety

    Philosophy /

    Strategy

    Other

    philosophies /

    strategies

    Preliminary

    Layout

    DetailedLayout

    Equipment

    List

    EquipmentSizing

    7

  • 8/21/2019 1 Introduction General

    8/45

    INTRODUCTION & GENERAL

    DETAILED CONSIDERATIONS

    8

    PROCESS &

    EQUIPMENT

    WORK &

    OPERATIONS

    LOCATION

    SPACE REQ. /

    SPACING /

     ACCESS REQ

    Equipment to perform

    unit operations /

     Alternatives

    Rooms, Workshops

    Service facilities,

    Non-process equipm.

    LAYOUT

    EQUIPMENT TYPES

    (SPACE / ORIENTATION / LOCATION)

    SPACE REQUIREMENTS,

    NON-PROCESS EQUIPMENT,

    WORKING ENVIRONM / HUMAN FACTORS

  • 8/21/2019 1 Introduction General

    9/45

    INTRODUCTION & GENERAL

    LOCATION OF INSTALLATIONSupporting structure and water depth:

    In shallow waters, artificial islands are options 9

  • 8/21/2019 1 Introduction General

    10/45

    INTRODUCTION & GENERAL

    LOCATION OF INSTALLATIONWind rose for location is important for orientations

    10

    Example North SeaExample Arabian Gulf 

  • 8/21/2019 1 Introduction General

    11/45

    INTRODUCTION & GENERAL

    LOCATION OF INSTALLATIONOne additional factor – ships traffic intensity:

    11

  • 8/21/2019 1 Introduction General

    12/45

    INTRODUCTION & GENERAL

    LOCATION OF INSTALLATIONOil Logistics

    12

    OIL

    LOGISTICS

    Pipeline

    Production

    directly to

    tanker 

    Production to

    tank

    TANK

    Sub sea tank Tank platform FSO

    Concrete

    GBSSteel tank

    Offloading

    from tank

    Submerged

    Loading

    System (SLS)

    SPM

    (Single Point

    Mooring)

    Tandem Hose

    Offloading

    For example SAL

  • 8/21/2019 1 Introduction General

    13/45

    INTRODUCTION & GENERAL

    LOCATION OF INSTALLATIONOffloading systems

    13SPM Calm BuoySPM rigid tower

  • 8/21/2019 1 Introduction General

    14/45

    INTRODUCTION & GENERAL

    ENVIRONMENTAL CONDITIONS• Special – specific sensitive areas

    • Water depth & tides (HAT, LAT)

    • Wind, Waves

    • Current

    • Marine growth

    • Sea ice / ice bergs

    • Snow & ice (ice load on structure)

    • Air / sea temperature

    • Humidity

    • Earthquake / seismic design conditions

    14

  • 8/21/2019 1 Introduction General

    15/45

    INTRODUCTION & GENERAL

    ENVIRONMENTAL CONDITIONS - STANDARDS• ISO 19901-1: Metocean Design & Operationg Considerations

    • ISO 19901-2: Seismic design

    • ISO 19901-3: Geotechnical & foundation design

    15

  • 8/21/2019 1 Introduction General

    16/45

    INTRODUCTION & GENERAL

    PLATFORM TYPES & JACKETS

    • Maersk Oil, Gorm Field, Denmark

    16

  • 8/21/2019 1 Introduction General

    17/45

    INTRODUCTION & GENERAL

    PLATFORM TYPES & JACKETS

    • Riser Platform, Denmark

    17

  • 8/21/2019 1 Introduction General

    18/45

    INTRODUCTION & GENERAL

    PLATFORM TYPES & JACKETS

    • Integrated Deck on GBS

    18

  • 8/21/2019 1 Introduction General

    19/45

    INTRODUCTION & GENERAL

    PLATFORM TYPES & JACKETS

    • Unmanned minimum platform, 4-legged jacket,

    helideck19

  • 8/21/2019 1 Introduction General

    20/45

    INTRODUCTION & GENERAL

    PLATFORM TYPES & JACKETS

    • Unmanned minimum platform, tripod column jacket,

    no helideck20

  • 8/21/2019 1 Introduction General

    21/45

    INTRODUCTION & GENERAL

    PLATFORM TYPES & JACKETS

    • Unmanned minimum platform, tripod column jacket,

    helideck21

  • 8/21/2019 1 Introduction General

    22/45

    INTRODUCTION & GENERAL

    PLATFORM TYPES & JACKETS

    • Qatar, Al Shaheen, E-location

    22

  • 8/21/2019 1 Introduction General

    23/45

    INTRODUCTION & GENERAL

    SOME USUAL JACKET TYPES

    23

  • 8/21/2019 1 Introduction General

    24/45

    INTRODUCTION & GENERAL

    SITE CONTINGENCY PLAN

    Two main issues to consider for the actual site:

    • Operational & Maintenance Support & logistics

    • Emergency Response support & logistics

    24

  • 8/21/2019 1 Introduction General

    25/45

    SITE CONTINGENCY PLAN

    OTHER REQUIRED STRATEGIES / PHILOSOPHIES• Operation / Maintenance philosophy / strategy

    • Safety philosophy / strategy

    • Human factors strategy/plan

    • Emergency shutdown Philosophy (ESD isolation/blowdown)

    • Active/passive fire protection Strategy

    • Expansion strategy

    • Rotating equipment selection philosophy / strategy

    • Major static equipment selection philosophy / strategy

    • Valve and actuator selection philosophy / strategy

    • Mechanical handling philosophy / strategy

    25

  • 8/21/2019 1 Introduction General

    26/45

    OTHER REQUIRED PHILOSOPHIES / STRATEGIES

    SAFETY PHILOSOPHY / STRATEGY• Ref. ISO 13702

    • FES (Fire & Explosion Strategy) incl. design fire loads and blast

    pressures

    • EERS (Escape, Evacuation and rescue strategy)

    26

  • 8/21/2019 1 Introduction General

    27/45

    OTHER REQUIRED PHILOSOPHIES / STRATEGIES

    MECHANICAL HANDLING PHILOSOPHY / STRATEGY• Adress all equipment > 25 kg to be handled

    • Requirements for laydown areas

    • Transport routes

    • Requirements for cranes, permanent lifting appliances and

    portable lifting equipment

    • Etc

    27

  • 8/21/2019 1 Introduction General

    28/45

    CONCEPTUAL PROCESS LAYOUT

    BLOCK DIAGRAM

    Storage

    (tank)

    pump Heating (heatexch)

    Mix / storage

    cold pot. water 

    closed heating

    medium system

    Mixer 

    Filling point

    Product

    28

  • 8/21/2019 1 Introduction General

    29/45

    CONCEPTUAL PROCESS DESCRIPTION

    PROCESS FLOW DIAGRAM (PFD)

    29

  • 8/21/2019 1 Introduction General

    30/45

    CONCEPTUAL PROCESS DESCRIPTION

    MAIN PROCESS SCHEMATIC

    30

    V1

    V2

    V3

    TEG

    NGLREC

    SALE

    JT

    FUEL

    FUEL

    FUEL

    LIFT

    EXPORT GAS

    STABILIZED CRUDE OIL FOR EXPORT

    PRODUCED WATER TOTREATMENT

    MULTIPHASE FLUIDFROM WELL(S)

    IP

    LP2 LP1

    HP

  • 8/21/2019 1 Introduction General

    31/45

    CONCEPTUAL PROCESS DESCRIPTION

    PIPING & INSTRUMENT DIAGRAM (P&ID)• P&ID’s in oil&gas generally follows ISA S5.1

    • ISA S5.1 has 3 levels of detailing

    • Simplified diagram

    • Conceptual diagram

    • Detailed diagram

    31

  • 8/21/2019 1 Introduction General

    32/45

    CONCEPTUAL PROCESS DESCRIPTION

    P&ID SIMPLIFIED LEVEL (ISA S5.1)

    32

  • 8/21/2019 1 Introduction General

    33/45

    CONCEPTUAL PROCESS DESCRIPTION

    P&ID CONCEPTUAL LEVEL (ISA S5.1)

    33

  • 8/21/2019 1 Introduction General

    34/45

    CONCEPTUAL PROCESS DESCRIPTION

    P&ID DETAILED LEVEL (ISA S5.1)

    34

  • 8/21/2019 1 Introduction General

    35/45

    PHYSICAL LAYOUT

    PLOT PLAN

    35

    Plot plansshows theentire level

    in one

    drawing.

    Unit / main

    equipment

    level

  • 8/21/2019 1 Introduction General

    36/45

    PHYSICAL LAYOUT

    EQUIPMENT LAYOUT

    36

    Equipment

    layout is a “unit plot

    plan”, i.e.

    the plotplan is

    dividedinto units /

    modules.

    Other than

    mainequipment

    also shown

  • 8/21/2019 1 Introduction General

    37/45

    PHYSICAL LAYOUT

    HAZARDOUS AREA CLASSIFICATION

    37

    One drwg

    per decklevel +

    overall view

  • 8/21/2019 1 Introduction General

    38/45

    PHYSICAL LAYOUT

    HAZARDOUS AREA CLASSIFICATION

    38

    In addition

    to planviews – side

    views

    (elevations)required

    from more

    than one

    side

  • 8/21/2019 1 Introduction General

    39/45

    PHYSICAL LAYOUT

    F&G DETECTOR LAYOUT

    39

  • 8/21/2019 1 Introduction General

    40/45

    PHYSICAL LAYOUT

    FIRE & SAFETY PLAN

    40

  • 8/21/2019 1 Introduction General

    41/45

    PHYSICAL LAYOUT

    DELUGE AREA PROTECTION DRAWING

    41

  • 8/21/2019 1 Introduction General

    42/45

    PHYSICAL LAYOUT

    FRAMING PLAN

    42

  • 8/21/2019 1 Introduction General

    43/45

    LISTS

    EQUIPMENT LIST

    • All equipment shown in layouts/plot plans are shown in

    equipment list

    • First input to equipment list is from PFD/P&ID

    • Size/Weight is shown in the equipment lists

    • For pre-conceptual and conceptual designs, sizes are based on

    experience and estimates

    • On day 3 we will revert to methods for estimation of

    sizes/weights.

    43

  • 8/21/2019 1 Introduction General

    44/45

    LISTS

    EQUIPMENT LIST

    44

  • 8/21/2019 1 Introduction General

    45/45

    THANK YOU

    45