1 Integration of Variable Generation into the Grid: Need for TVLs (Transfer Variability Limits) Gordon Dobson-Mack (Chair) Dynamic Transfer Capability Task Force Wind Integration Forum – Steering Committee November 17 2011 BCCPG BCCPG
Jan 11, 2016
1
Integration of Variable Generation into the Grid:
Need for TVLs (Transfer Variability Limits)
Gordon Dobson-Mack (Chair)Dynamic Transfer Capability Task Force
Wind Integration Forum – Steering CommitteeNovember 17 2011
BCCPGBCCPG
2
• Discuss the need for TVLs and what can be done to increase them
Purpose of Presentation
3
1. Variability & its impacts:– Increased variability is a reality for operations;– Dynamic Transfers contribute to variability;– Transfer Variability impacts the grid;– Need Transfers Variability Limits for some systems.
2. DTC Task Force– Mandate & Membership;– Deliverables;
3. What Next?– Questions & Options;
Outline
4
BPA’s Installed Wind
Source: BPA: http://transmission.bpa.gov/business/operations/Wind/WIND_InstalledCapacity_Plot.pdf
6
NWPP Wind Generation Levels
2010 Coincident Peak Load = 60,200 MW
Dec 2010 Installed Wind Gen = 7,800 MW
Dec 2012 Installed+Committed
Wind Gen = 13,200 MW
2010 Spring Min Load (HE04) = 32,745 MW
Source: NWPP & DTC TF: http://www.columbiagrid.org/documents-search.cfm search “DTCTFPhaseFullReport031611.pdf”
7Source: http://www.westgov.org/EIMcr/meetings/07MAR11/present/panel5/l_beane.pdf see slide #3
• Generation Problem: – Need to maintain Generation Balance;– Want access to least cost & most flexible Ancillary Services
• Transmission Problem…As well:– Transmission system designed historically for routine
predictable changes;– Must be ready to withstand the next worst
contingency;– Voltage control and RAS arming are local measures
that must be factored into the solution.
Generation or Transmission Problem?
9
R L
C
R L R LR L
CCCC
LoadTransmission Line
Transmission Line Physics
10
Maximum TTC,Transmission Tuned
Light Load or line open - High Voltageunless reactive switched off
Low Voltage:Without addedReactive – couldBe a voltage collapse
Reactive “Tuning” And Remedial Action Schemes (RAS)
Power - Voltage Curves andReliability N-1 Limits
N-1 Outage
Acceptable Voltage Range
Vo
ltag
e L
evel
N-1 Outage
Reliability Limits
Operating MW Range no Caps in
MW Power Level
Operating MW Range Caps in
CapacitorSwitched on
NormalN-0
Added Switching
Remedial Action Schemes (RAS) RAS armRAS un-arm
Capacitor In
Capacitor Out
0 10 20 30 40 50 60 Minutes
MW
Flo
w
1850 MW
2050 MW
Path flow with VG
Traditional tie line flow
13
1414
Present Dynamic Schedule Requirements
Montana – NW•50 MW BPA Loads•20 MW Glacier Wind•1318 MW Colstrip Participants•91 MW NWE
Idaho – NW•200 MW PAC•60 MW Boardman
DTC Studies-BPA Report (Feb 2010)
15
DTC Task Force – Part of Wind Integration Study Team (WIST)
DTC Task Force• Convened October 2010• Technical Staff primarily from NW & CA entities• ~55 Meetings to date.
Purpose:1. Develop a technical consensus on how to facilitate
increased Dynamic Transfers without compromising system reliability
2. BAs & TPs to establish DTC Limits on paths3. Determine if & how to expand DTC
16
DTC TF (Phase 3 )Membership
Avista: Rich Hydzik
BPA: Brian Tuck, Ramu Ramanathan
BCH: Steven Pai, Sanjeet Sanghera,
CAISO: Jim Price
Gaelectric: Dan Wheeler
IPCO: Orlando Ciniglio
MSR: Dave Arthur, Ann Fisher
NWE: Rikin Shah, Ray Brush
PAC: Sanman Rokade
PGE: Philip Augustin, Don Johnson
PSE: Alex Berres, Joe Seabrook
TANC: Abbas Abed, Shawn Matchim
SMUD: Richard Buckingham
WAPA (Folsum): Kirk Sornborger
•
Powerex: Gordon Dobson-MackDTC TF ChairTel: [email protected]
Columbia Grid: Marv LandauerNorthern Tier: Rich BaylessNWPP: Don Badley
3
17
DTC TF Work Process
Phase 1 (03/11)
Phase 2 (07/11)
Phase 3 (11/11)
Define Problem &
Identify Assumptions
Develop DTC Limit
Methodology
Calculate DTC Limits, Refine
Methodology & Identify
Enhancements
18
Three Conditions Restricting Transfer Variability Limits
Customer Impacts
Acceptable?
Equipment Impacts
Acceptable?
Operating Points
Reliable?
Condition 1 Condition 2 Condition 3
19
• Does not calculate TVLs for particular Paths;– Recommends a methodology;– Leaves limit calculations to Transmission Providers
• Does not recommend specific projects– Describes generic projects to enhance TVLs
– Leaves specific project recommendations to TPs
Caveats for Phase 3 Report
20
• TVL is a real issue;– Impediment to transfer imbalance energy and
regulation between BAs;– Will limit where & how the region can integrate
wind;– Limits can be raised, but not overnight.
• Need for TVLs will vary by system;
• Should plan for increased transmission flexibility to manage the increasingly variable flows on grid
Bottom Line – so far
21
• How automated is your RAS arming?
• How much automatic voltage control do you have
across your system?
• What are the TVLs for your major flowgates?
• How will your company manage TVLs?
• What capital projects are planned to increase Transmission Flexibility?
Questions for Companies
22
•Modifying some SOL assumptions (e.g. overshedding);
•Automating RAS
•Automating voltage control
•Ensure voltage control equipment is designed for frequent switching
(**Detailed TVL studies needed to identify most effective solutions)
Options for increasing TVLs
Questions?