1 INCOSE HRA Advanced Risk Management Conference 2007 Courtney Lane INCOSE HRA Risk Management Conference November 9, 2007 It’s More Than Just Numbers: How to Implement a Qualitative Risk Analysis Approach This document is confidential and is intended solely for the use and information of the client to whom it is addressed.
20
Embed
1 INCOSE HRA Advanced Risk Management Conference 2007 Courtney Lane INCOSE HRA Risk Management Conference November 9, 2007 Its More Than Just Numbers:
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
1
INCOSE HRA Advanced Risk Management Conference 2007
Courtney LaneINCOSE HRA Risk Management Conference
November 9, 2007
It’s More Than Just Numbers: How to Implement a Qualitative
Risk Analysis Approach
This document is confidential and is intended solely for the use and information of the client to whom it is addressed.
2
INCOSE HRA Advanced Risk Management Conference 2007
Purpose
Describe the difference between qualitative and quantitative risk analysis
Discuss common problems associated with qualitative analysis
Examine best practices for implementing a qualitative risk analysis approach
3
INCOSE HRA Advanced Risk Management Conference 2007
Standard Risk Management Process
Develop Strategy
This presentation will focus on the analysis sub-process. This sub-process should be defined in an organization’s risk management strategy
Analyze
PlanMonitor
and Control
Identify
4
INCOSE HRA Advanced Risk Management Conference 2007
Components of Risk Analysis
Probability of occurrence
Impact to a project’s cost, schedule, and technical objectives
Timeframe
Handling method
By identifying these components, project managers will be able to determine the magnitude of the risk and effectively prioritize handling of the risks
5
INCOSE HRA Advanced Risk Management Conference 2007
Difference Between Qualitative and Quantitative Analysis
Qualitative vs. Quantitative
Use ranges to select probability and impact rankings
Absolute numerical estimates are used for impact and probability
Focuses on overall level of individual risks (e.g. high, medium, low)
Allows project’s to aggregate individual risks to determine the overall level of project risk
Allows programs to quickly prioritize risks based on a number of criteria
Uses complicated analysis such as Monte Carlo simulation to prioritize risks
6
INCOSE HRA Advanced Risk Management Conference 2007
Why use Qualitative Analysis over Quantitative?
Lack of historical data
Lack of the necessary time and resources to conduct complicated analysis
Desire to use criteria for prioritization that is difficult to quantify– Timeframe
– Critical dependencies
– Political considerations
The type of analysis appropriate for an organization is dependent upon the risk management maturity level of the organization
7
INCOSE HRA Advanced Risk Management Conference 2007
3: Proactive Processes standardized across the organizationManagement comfortable with risk managementRisk management data used in decision making processes
4: Predictive Use of quantitative analysis to predict future resultsCost/benefit analysis implemented
5: Optimization Opportunities to exceed project objectives are identified and managed
Source: Modified from SEI’s Capability Maturity Model
Most organizations are not at an appropriate maturity level to implement quantitative risk analysis
8
INCOSE HRA Advanced Risk Management Conference 2007
Top Problems Related to Qualitative Analysis
#1Using inappropriate criteria to determine probability and consequence levels
#2 Trying to “quantify” qualitative data
#3Relying on risk scores generated by risk management tools to determine a list of top risks
9
INCOSE HRA Advanced Risk Management Conference 2007
Problem #1: Inappropriate Criteria
Criteria is often too detailed
Subject matter experts lack the necessary expertise to appropriately select the criteria
Easy to “game” the analysis since justification of criteria selection is extremely subjective
Poor criteria definitions make it difficult for risk analysts to accurately reflect impacts to cost, schedule, and performance
10
INCOSE HRA Advanced Risk Management Conference 2007
Solution: Understand Your Audience
Determine what questions decision makers want the risk management process to answer
Assess the level of expertise of those performing the risk assessments
Select criteria that balances the needs and abilities of both parties
11
INCOSE HRA Advanced Risk Management Conference 2007
Examples of Qualitative Analysis CriteriaNegligible
(A)
Marginal
(B)
Significant
(C)
Critical
(D)
Catastrophic
(E)
Cost Minimal or no impact
$25K-$50K $50K-100K $100K-250K >$250K
Schedule Schedule slip < 7 days
Schedule slip between 7 and 14 days
Schedule slip between 14 and 21 days
Schedule slip between 21 and 30 days
Schedule slip greater than 1 month
Performance Minimal or no impact
No impact to key performance parameter; degraded capability performance
Degraded enterprise capability performance
Degraded capability performance with impacts to one key performance parameter
Degraded capability performance with impacts to more than one key performance parameter
Criteria is too detailed and thus difficult to assess
12
INCOSE HRA Advanced Risk Management Conference 2007
Examples of Qualitative Analysis CriteriaNegligible
(A)
Marginal
(B)
Significant
(C)
Critical
(D)
Catastrophic
(E)
Cost Minimal or no impact
<5% of overall budget
5-7%of overall budget
7-10% of overall budget
>10% of overall budget
Schedule Minimal or no impact
Additional resources required; able to meet need dates
Minor slip in key milestones; not able to meet need dates
Major slip in key milestone or critical path impacted
Can’t achieve key team or major project milestone
Performance Minimal or no impact
Acceptable with some reduction in margin
Acceptable with significant reduction in margin
Acceptable; no remaining margin
Unacceptable
Source: Risk Management Guide for DoD Acquisition
Criteria is extremely subjective and could be easily “gamed”
13
INCOSE HRA Advanced Risk Management Conference 2007
Examples of Qualitative Analysis CriteriaNegligible
(A)
Marginal
(B)
Significant
(C)
Critical
(D)
Catastrophic
(E)
Cost Minimal or no impact
Cost impacts contained within the project
Cost impacts contained within the program
Cost impacts contained within the organization
Cost impacts affect external partners and could jeopardize program
Schedule Minimal or no impact
Impacts to critical path contained within the project
Impacts to critical path contained within the program
Impacts to critical path of more than one program in the organization
Impacts the critical path of external partners and could jeopardize program
Performance Minimal or no impact
Impacts to critical functions of the project
Impacts to critical functions of the program
Impacts to critical functions of the organization
Impacts to critical functions of external partners and could jeopardize the program
Criteria definitions are easy to assess and impact levels are consistent across criteria
14
INCOSE HRA Advanced Risk Management Conference 2007
Problem #2: Quantifying Qualitative Data
Engineers often feel more comfortable using numbers when performing analysis – Assign numbers to levels of impact– Use specific probabilities instead of ranges– Risk scores often determined by multiplying impact by probability
However, most risk analysis uses uncalibrated ordinal scales– Cannot perform math on uncalibrated scales– Gives a false sense of rigor– Decisions made on inaccurate data
Performing math on qualitative data may lead to inaccurate conclusions and a false sense of rigor
15
INCOSE HRA Advanced Risk Management Conference 2007
Solution: Do Not Include Numbers in Analysis
Avoid assigning numbers to levels of impact and probability– Use probability ranges
– Use letters to represent levels of impact and probability
Use the highest level of individual impacts to determine overall impact (don’t average impacts)
Use a risk matrix to determine overall level of risk
16
INCOSE HRA Advanced Risk Management Conference 2007
Example Qualitative Risk Analysis
Overall level of risk
is Red
17
INCOSE HRA Advanced Risk Management Conference 2007
Problem #3: Overemphasizing Risk Scores
If problem #2 is not overcome, this becomes a much larger problem
Even if numerical scores are not used, rankings could be incorrect– Risk tools can generate a list of top risks based on locations on the
risk matrix
– Cannot rely solely on the placement on the risk matrix
– Dependencies, political issues and timeliness factors also play a part
Overemphasis of risk scores to determine top risks results may result in poor decisions made by senior leaders
18
INCOSE HRA Advanced Risk Management Conference 2007
Solution:
Tailor list of top risks based on the audience
Consider all factors, not just likelihood and consequence, when creating the list
Do not use arbitrary thresholds to determine handling strategies
Aim to manage all yellow and red risks
19
INCOSE HRA Advanced Risk Management Conference 2007
Summary and Conclusion
Select the appropriate type of analysis based on the risk management maturity level of the organization
Typical challenges associated with qualitative analysis can be overcome:– Know your audiences
– Avoid using numbers to perform analyses
– Consider other factors when selecting list of top risks
Qualitative analysis can provide leaders with enough information to make sound decisions if implemented properly
20
INCOSE HRA Advanced Risk Management Conference 2007