1 General Services Administration SERBCA Conference September 29, 2011 Public Buildings Service Southeast Sunbelt Region Total Building Commissioning & Recommissioning Timothy Wisner, PE, CEM, PMP
Apr 02, 2015
1
General Services AdministrationSERBCA ConferenceSeptember 29, 2011
Public Buildings ServiceSoutheast Sunbelt Region
Total Building Commissioning& Recommissioning
Timothy Wisner, PE, CEM, PMP
G S A ’ S P U B L I C B U I L D I N G S S E R V I C E (P B S)
Landlord for over 400 federal agencies, bureaus & commissions
Portfolio of 353.9 M rentable square feet Space for over 1,000,000 tenants 8,603 owned and leased assets 30 LEED certified properties (currently, many more soon)
AK
Northwest/ArcticRegion 10
Rocky MountainRegion 8
Great LakesRegion 5
Heartland Region 6
Greater SouthwestRegion 7
Southeast Region 4
Mid-AtlanticRegion 3
NewEnglandRegion 1
Pacific RimRegion 9
Northeast &CaribbeanRegion 2
HI
GU
VI
PR
DC
WA
OR
UT
MTND
WY
SD
CO
ID
CA
NV
AZ NMOK
TX LA
AR
NE IA
KS MO
MI
WI
ILIN
MI
OH
KY
TN
MS ALGA
FL
SC
NC
WVMD
VA
PA
NY
NJ
DE
VT NH
ME
MACT RI
National Capital Region 11
P B S R E G I O N A L O R G A N I Z A T I O N S
4
• Kentucky, Tennessee, North Carolina, South Carolina, Georgia, Alabama, Mississippi and Florida
• 39,000,000 square feet of federally owned or leased office, laboratory, warehouse, and courts space.
SOUTHEAST SUNBELT REGION
• 130 Leased and Owned Buildings in EUAS
• 21.5-million gross square feet (GSF)– Largest - AFC, 2.4-million GSF– Smallest – Warehouse 1000 GSF
• $ 28.9-million FY 09 Utility Cost
• Enough energy to power 10,831 homes annually
Tracked Building Inventory
5
What is GSA Commissioning?
n GSA has adopted the definition of the National Conference on Building Commissioning (NCBC):
“Systematic process of assuring by verification and documentation, from the design phase to a minimum of one year after construction, that all facility systems perform interactively in accordance with the design documentation and intent, and in accordance with the owner’s operational needs, including preparation of operation personnel”
GSA Commissioning & Recommissioning
6
What is GSA’s Policy on Commissioning?
PBS DIRECTIVE FOR ASSISTANT REGIONAL ADMINISTRATORS, PBS DIRECTORS, PROPERTY DEVELOPMENT DIRECTORS, PORTFOLIO MANAGEMENT
FROM: F. JOSEPH MORAVEC, COMMISSIONER SUBJECT: Release of The Building Commissioning Guide
Summary. Each Prospectus level project team -whether on new construction, major repair and alteration, or modernization -shall use “Total Building Commissioning” practices beginning with the project planning phase, and concluding at one year after tenant occupancy.
GSA Commissioning & Recommissioning
7
Our Definitive Source Document
GSA Commissioning & Recommissioning
8
Old School Commissioning:n HVAC Systems and Equipmentn Startup, Testing, and Turnover
Total Building Commissioningn Defines all project performance goals (Programming)n Proactively supports project goals during design (QA)n Validates performance in construction (QC)n Revisits performance goals after tenant occupancy (POE)
GSA Commissioning & Recommissioning
9
HVAC systemsPlumbingBuilding Management SystemPower DistributionEmergency PowerSecurityLighting and Lighting ControlsDomestic Hot WaterFire Alarm/life safety systemsVertical Transportation
COMMISSIONED BUILDING SYSTEMS
• curtain wall assemblies • roofing, • windows doors• construction joints, • etc.
Building Envelope systems
10
Why Does GSA Commission?n Design Excellence buildings are complexn Our tenants include judges, congresspeople, heads of
federal agencies, and others who we would rather not disappoint
n In all buildings, O&M and utility costs are closely linked to FFO
n In all buildings, tenant labor costs far exceed rent, O&M, and utilities, so productivity is crucial for tenant satisfaction
GSA Commissioning & Recommissioning
n Built late 1990’s, $ 85 million, 240,000 sq. ft. 17-story, high rise
n 2001, building was suspect of having “sick building syndrome” as employees complained of dizziness, headaches, and itchy eyes.
n The building suffered from significant water intrusion through multiple facade systems
n Extensive investigation of existing facade systems to document conditions and to identify water infiltration sources
n Design of remedial repairs for multiple types of facade systems including curtainwall, punch windows, metal panels, louvers, sealants, roofing systems , davits and tiebacks for the building
n Cost in for repairs and testing $ 20 million
Why GSA Total Building Commissions - Really
Sam M Gibbons US Courthouse, Tampa, FL
n Started Construction 2002 with 3-year timeline and $ 100 million budget
n Opened 2007 wit $ 69 million increased costs thanks to water leaks, faulty equipment, and subcontractor lawsuits
n Still, after acceptance GSA has had to pay an additional $ 4 million in repairs
Why GSA Total Building Commissions - Really
Willkie D. Ferguson Jr. Courthouse Miami, FL
1. SDV Services Busway repairs and inspections $63,100 2. Siemens Emergency Bus Duct Replacements $52,441.06 3. Universal HVAC Repairs completed (Floors 6-9) $360,100.00 4. Universal HVAC Repairs – planned (Floors 10-14) $457,788.00 5. Teng Commissioning Report of HVAC deficiencies $320,014.16 6. Reprogramming of HVAC systems $257,856.00 7. AHU programming pilot $15,000 8. Carpet Replacements $336,657.17 9. Missing Infrastructure $116,500.00 10. MCS Claim Settlement $210,000.00 11. Water Feature repairs $255,318.00 12. Chiller Piping $200,000.00 13. Waterproofing exterior limestone columns $135,000.00 14. Emergency generator exhaust repairs $200,000.00 15. Roofing repairs $369,062.00 16. Short Circuit Breaker replacements $319,000.00
POST OCCUPANCY CLAIMS
WILKIE D. FERGUSON JR. COURTHOUSE
17. Noise in Courtrooms at Judge’s bench $130,000.00 18. DERM UST SAR Reports & Tests-- $30,000.00 19. RJA Inspections $6,814.13 20. Tower Building Sallyport $102,000.00 21 Chiller cleaning $26,963.52 22 Guards $38,976.00 23 Chiller plant leaks design $7,372.00 24 Control loops Parking area $53,451.87 25. Correct leak at generator exhaust $16,000.00 26. Elevator code deficiencies $21,665.00 27. Sanitary sewer clean-outs $2,504.00 28. Repair Sallyport wall due to bus duct explosion $6,184.00 29. UPS Battery tests and re-certifications $11,100.00 30. UPS Repair $12,451.78 31. Limit switch for gate arm $3,465.00 32. MC cable credit $70,278.00
POST OCCUPANCY CLAIMS (continued)
WILKIE D. FERGUSON JR. COURTHOUSE
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul0
200000
400000
600000
800000
1000000
1200000
1400000
Wilkie Ferguson Courthouse Energy Use Aug 2010 to July 2011
2010
2011
Projected Use
KW
H
GSA Commissioning & Recommissioning
17
What is GSA Recommissioning?
According to the GSA Building Commissioning Guide, Recommissioning shall generally include:
• Establishing that original basis of design and operation is still appropriate for use, occupancy, tenant agencies and GSA goals, and modify the operations/controls sequencing as appropriate for optimum operations
• Reviewing and benchmarking key systems operations/performance against the Basis of Design
• Evaluating envelope tightness/pressurization by infrared or other methods
• Performing energy analysis• Recommending repairs/modifications to optimize building
performance
GSA Commissioning & Recommissioning
18
Why Recommission?
n Buildings are a moving targetn Space usage changesn Equipment changesn Systems changen Original design intent is usually no
longer completely valid
GSA Commissioning & Recommissioning
19
Why Recommission?
n O & M is imperfectn Inadequate budgetsn Training Incomplete or erroneous
understanding of design intent and how to run the systems
n Incomplete documentation on buildingn Retrofits, and no single plan of how to run
the systems as modifiedn Systems are too complex for operators
GSA Commissioning & Recommissioning
20
EISA Sec 432 requires Federal Agencies complete Evaluations to include an energy and water evaluations and commissioning assessment for all of their covered facilities every four years.
Covered Facilities are a subset of an agency’s inventory that makes up 75% of its total energy consumption.
GSA’s covered facilities are comprised of 198 Facilities across the 11 regions.
EISA Sec 432 Evaluation Compliance Plan
GSA Commissioning & Recommissioning
21
AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA)
• $100 Million for “Building Tune-ups”
22
ARRA Recommissioning/Tune-up
• Building Tune-up includes– First, Fix all obvious Controls Problems– Recommission– Add Advanced Metering– Implement Energy Conservation Measures– Improve building O & M
23
ARRA Recommissioning/Tune-up
• Over 180 Buildings for Building Tune-up• Lots in every Region• Selected by highest Energy Intensity• Tune-up has High Return per Dollar Spent• Uniform Building Data Collection/Confirmation
24
ARRA Recommissioning/Tune-up
• Justification for Small Project ECMs– Mostly, highest ROI wins– $300 Million in ARRA Small Projects
funding
25
What are our resources?
n Sample Scopes of Work for Commissioning forn Design-Bid-Buildn CMcn Design-Bridge-Buildn Design-Build
GSA Commissioning & Recommissioning
26
Summary
Get a copy of “The Building Commissioning Guide”
n Log on to www.gsa.gov/commissioning
n Log on to www.wbdg.org/commissioning
GSA Commissioning & Recommissioning
27
SERBCA Conference
Q&A