Fault Response Island Operation V1.2.doc 1 January 14, 2010 Printed 6/16/2011 Distributed Energy Resource Controller Reconfigure Systems in response to Faulted Segment with Islanding Version 1.2 January 13, 2010 1 Descriptions of Function This function describes the sequence of activities required for fault isolation and provides for the creation of islands behind the fault on isolated sections of the distribution feeder fed by local generation. 1.1 Function Name Distributed Energy Resource Controller Reconfigure Systems in Response to Faulted Segment with Islanding 1.2 Function ID IECSA identification number of the function 1.3 Brief Description This function describes the sequence of activities required for handling a fault condition on a distribution feeder. This particular scenario provides not only fault isolation, but provides for the creation of islands behind the fault on isolated sections of the distribution feeder fed by local generation. While this scenario holds many points in common, it differs from the existing EPRI use case “Controlled Islanding” in that it specifically addresses islands created below the substation. 1.4 Narrative The presence of generation and storage units in the distribution grid create the possibility of islands. While most of the effort to date has been in mechanisms to suppress the creation of islands, an ideal solution would encourage viable islands in fault conditions, thus enhancing system availability for the greatest possible number of customers. There are considerable technical hurdles to this however. The smaller the island, the harder it is to maintain a perfect match between generation and load. Further, the weaker the system, the more difficult it is to keep voltage and frequency in an acceptable range. While these problems make the maintenance of an island over a long period of time increasingly difficult , they might be a viable solution for isolating some segment of customers from momentary interruptions and other outages that last between minutes and
25
Embed
1 Descriptions of Function - EPRIsmartgrid.epri.com/UseCases/Fault Response Island Operation V1.2.… · 1 Descriptions of Function ... might be a viable solution for isolating some
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Fault Response Island Operation V1.2.doc 1 January 14, 2010 Printed 6/16/2011
1 Descriptions of Function This function describes the sequence of activities required for fault isolation and provides for the creation of islands behind the fault on isolated sections of the distribution feeder fed by local generation.
1.1 Function Name Distributed Energy Resource Controller Reconfigure Systems in Response to Faulted Segment with Islanding
1.2 Function ID IECSA identification number of the function
1.3 Brief Description This function describes the sequence of activities required for handling a fault condition on a distribution feeder. This particular scenario provides not only fault isolation, but provides for the creation of islands behind the fault on isolated sections of the distribution feeder fed by local generation. While this scenario holds many points in common, it differs from the existing EPRI use case “Controlled Islanding” in that it specifically addresses islands created below the substation.
1.4 Narrative The presence of generation and storage units in the distribution grid create the possibility of islands. While most of the effort to date has been in mechanisms to suppress the creation of islands, an ideal solution would encourage viable islands in fault conditions, thus enhancing system availability for the greatest possible number of customers. There are considerable technical hurdles to this however. The smaller the island, the harder it is to maintain a perfect match between generation and load. Further, the weaker the system, the more difficult it is to keep voltage and frequency in an acceptable range. While these problems make the maintenance of an island over a long period of time increasingly difficult , they might be a viable solution for isolating some segment of customers from momentary interruptions and other outages that last between minutes and
Fault Response Island Operation V1.2.doc 2 January 14, 2010 Printed 6/16/2011
hours. This approach introduces other issues that must be addressed as well. Left to its own devices, it is inevitable that the islanded system will drift out of phase with the primary electrical power system. This will require switching equipment that can detect the out of phase condition and prevent accidentally closing into it. It will also require a mechanism bring the two systems close enough together to reduce the phase angle difference to a point where closing the switch will not create a hazardous situation or provide undue stress to connected equipment.
As detailed by this use case, the first step in creating a viable island is identifying it. This will require an approach similar to the Remedial Action Schemes used by transmission systems. The primary difference is that due to the dynamic nature of the problem coupled with the number of possible combinations, this process must be a continuous one done in real time.
The system will have to evaluate both controlled and uncontrolled segments, as the potential island could result from both controlled and uncontrolled (autonomous) switching operations (i.e. fuse). There are currently systems available that can manage the creation of small islands within a larger distribution networks. Typically deployed on small isolated power systems (like remote refineries), they depend on a combination of direct load control of large motors in conjunction with switching operations to match the load to the available generation. In a modern distribution system a similar approach can be taken. The presence of an Advanced Metering Infrastructure (AMI) system allows additional opportunities. First, the connect/disconnect switch can be used to drop the load on a network segment. This allows finer control that simply dropping an entire segment. Second, the load break device in many AMI meters can act as a programmable circuit breaker. This allows the Distributed Energy Resource Controller (DERC) to send commands limiting the load for each meter. It is expected that the AMI meter would in turn communicate this limit to the in home thermostat, or even home automation controls. This load limiting would help improve the stability of the network by limiting the total load to a level that provided some margin in the system. In addition, the DERC would reconfigure the DES units to support system stability. In the event the outage on the primary electrical system persists, the DERC would continue to evaluate the situation and continue to take necessary action. Generally, this would entail further reducing the island, but could entail activating additional segments in the event that the system was approaching an off peak period.
1.5 Actor (Stakeholder) Roles Describe all the people (their job), systems, databases, organizations, and devices involved in or affected by the Function (e.g. operators, system administrators, technicians, end users, service personnel, executives, SCADA system, real-time database, RTO, RTU, IED, power system). Typically, these actors are logically grouped by organization or functional boundaries or just for collaboration purpose of this use case. We need to identify these groupings and their relevant roles and understand the constituency. The same actor could play different roles in different Functions, but only one role in one Function. If the same actor (e.g. the same person) does play multiple roles in one Function, list these different actor-roles as separate rows.
Fault Response Island Operation V1.2.doc 3 January 14, 2010 Printed 6/16/2011
Grouping (Community) , Group Description
DER Actors Actors used in the DER Use Case
Actor Name Actor Type (person, device, system etc.)
Actor Description
AMI Interface Device Interface between AMI system and other field systems. The assumption is that the AMI interface would not require communications to travel all the way to the AMI Head end system and back to the field. Ideally, the AMI interface allows peer to peer communications to AMI network devices in the field with distribution automation devices and systems also physically located in the field.
Distributed Energy Resource Controller (DERC)
System System located in the substation that coordinates Distributed Energy Resources. Monitors operations schedules, status and controls operation of DER Device equipment.
Distribution Management System
System Provides real-time data to the system demand modeler and control room operator
Electrical Power System (EPS)
System All of the equipment required to deliver quality electrical power to the end user at utilization voltage
Fault Identification, Location, Isolation and Service Restoration Application (FILISR)
System System that uses automation to aid and increase speed of recovery of fault events. Involved during entire fault process from identification to system restoration
Load-shedding Device (AMI Unit)
Device Sheds load to balance the load-generation within an area before islanding , generally a component of the AMI system
OMS System Operations Management System Protection System
System Collection of IEDs and or Bay controllers responsible for the coordination and execution of actuators and other devices primarily dedicated to protection
SCADA System System System that monitors load control as well as providing forecast and real-time distribution information to the system demand modeler and control room operator
Substation Device Electrical Actuators , control systems and protection equipment involved in the bulk
Fault Response Island Operation V1.2.doc 4 January 14, 2010 Printed 6/16/2011
Grouping (Community) , Group Description
DER Actors Actors used in the DER Use Case
Actor Name Actor Type (person, device, system etc.)
Actor Description
transformation of power from transmission voltages to subtransmission or distribution voltages
WOMS System Work Order Management System. Used to schedule work for Operations including scheduled outages.
Bay Controller Device An Intelligent Electronic Device that coordinates or controls one or more subordinate IEDs
DERC Remedial Action Scheme Function (DERC RAS)
System Component of the DERC that is responsible for identifying and validating viable alternative network configurations based on likely contingencies.
DER Device Device Equipment controlled by DERC. Could include generation and load devices. Device can be Storage, Wind, Solar.
IED Device Intelligent Electronic Device. CPU and supporting subsystems that receives sensor data from one or more sensors and uses that data to coordinate and control one or more actuators (i.e. breaker, LTC, capacitor bank etc)
DERC Power Flow Monitoring Component
System Component of the DERC that monitors power flow on the associated line segments.
DERC Availability Monitor
System Component of the DERC that monitors the availability of the Substation Equipment and DER Devices on the associated system.
DERC Network Configuration Component
System Component of the DERC that predicts equipment scenarios that will fulfill the requirements from the scenarios developed from the other DERC Components
AMI Subsystem System Subsystem of the AMI Network
AMI Endpoints Device AMI Meters or endpoints on the distribution system
Fault Response Island Operation V1.2.doc 5 January 14, 2010 Printed 6/16/2011
Grouping (Community) , Group Description
DER Actors Actors used in the DER Use Case
Actor Name Actor Type (person, device, system etc.)
Actor Description
Replicate this table for each logic group.
1.6 Information exchanged Describe any information exchanged in this template.
Information Object Name Information Object Description
Power Flow of Line Segments Power flow of the associated line segments that are being monitored from the DERC
Calculations of Balanced Segment/Segmentation Scenarios
Calculations of Balanced Segment/Segmentation Scenarios
Calculations of Balanced Segments from load shedding/current limiting Scenarios
Calculations of Balanced Segments from load shedding/current limiting scenarios
Scenario Ratings according to SAIDI, SAIFI and critical loads
Scenario Ratings according to SAIDI, SAIFI and critical loads
Emergency Substation Equipment Commands for Scenarios
Emergency Substation Equipment Commands to complete the requirements for the given scenario.
Additional System Components for Balanced Operation for scenario
Additional system components (Substation Equipment, Bay Controllers, IEDs, etc.) for balanced operation for the scenario
Appropriate Profiles Appropriate Profiles for the Bay Controllers and IEDs
Fault Detection Detection of a fault on the electric power system
DERC RAS Islanding Scenario Orders
Altered protection settings appropriate to island operation, as well as adjusted ranges appropriate to island operation
Fault Response Island Operation V1.2.doc 6 January 14, 2010 Printed 6/16/2011
Information Object Name Information Object Description
Transfer Trip Signal for DER Devices Transfer Trip Signal for to open up the DER Devices
Emergency Load Shed/Current Limiting Orders
Emergency Load Shed/Current Limiting Orders for the AMI Endpoints to help relieve some of the stress off the electrical power system
Optimized DER Device Generation Schedule
Generation profiles for a select group of DER Device Generation Units on a section of the EPS.
Optimal Voltage Regulation Profiles Voltage profiles for a section of the EPS.
Optimal System Protection Setting Profiles
Protection Settings for the Protection System on a section of the EPS.
Optimized Charge/Discharge Commands/Schedule for DER Storage Units
Charge/discharge profiles for a select group of DER Device Storage Units on a section of the EPS.
Optimized DER Device Generation Commands/Schedule
Generation profiles for a select group of DER Device Generation Units on a section of the EPS.
Optimal Voltage Regulation Profiles Voltage profiles for the DER Device Storage Units for a section of the EPS.
Optimal System Protection Setting Profiles
Protection Settings for the Protection System on a section of the EPS.
Scheduling of maintenance work order
Scheduling of maintenance work orders
Maintenance Order Affected Segment and timeframe
Maintenance Order Affected Segment and timeframe
DERC RAS Islanding Scenario Orders
DERC RAS Islanding Scenario Orders
Load Shed/Current Limiting Orders Load Shed/Current Limiting Orders for the AMI Endpoints to help relieve some of the stress off the electrical power system
Ready for island operation The system is ready for island operation
Substation Equipment Commands Substation Equipment Commands to operate a device.
Fault Response Island Operation V1.2.doc 7 January 14, 2010 Printed 6/16/2011
Information Object Name Information Object Description
1.7 Activities/Services Describe or list the activities and services involved in this Function (in the context of this Function). An activity or service can be provided by a computer system, a set of applications, or manual procedures. These activities/services should be described at an appropriate level, with the understanding that sub-activities and services should be described if they are important for operational issues, automation needs, and implementation reasons. Other sub-activities/services could be left for later analysis.
Activity/Service Name Activities/Services Provided
1.8 Contracts/Regulations Identify any overall (human-initiated) contracts, regulations, policies, financial considerations, engineering constraints, pollution constraints, and other environmental quality issues that affect the design and requirements of the Function.
Contract/Regulation Impact of Contract/Regulation on Function
Policy
From Actor
May Shall Not
Shall Description (verb) To Actor
Fault Response Island Operation V1.2.doc 8 January 14, 2010 Printed 6/16/2011
Constraint Type Description Applies to
2 Step by Step Analysis of Function Describe steps that implement the function. If there is more than one set of steps that are relevant, make a copy of the following section grouping (Steps to implement function, Preconditions and Assumptions, Steps normal sequence, Post-conditions) and provide each copy with its own sequence name.
2.1 Steps to implement function – Name of Sequence Name of this sequence.
2.1.1 Preconditions and Assumptions Describe conditions that must exist prior to the initiation of the Function, such as prior state of the actors and activities
Identify any assumptions, such as what systems already exist, what contractual relations exist, and what configurations of systems are probably in place
Identify any initial states of information exchanged in the steps in the next section. For example, if a purchase order is exchanged in an activity, its precondition to the activity might be ‘filled in but unapproved’.
Actor/System/Information/Contract Preconditions or Assumptions
2.1.2 Steps – Name of Sequence Describe the normal sequence of events, focusing on steps that identify new types of information or new information exchanges or new interface issues to address. Should the sequence require detailed steps that are also used by other functions, consider creating a new “sub” function, then
Fault Response Island Operation V1.2.doc 9 January 14, 2010 Printed 6/16/2011
referring to that “subroutine” in this function. Remember that the focus should be less on the algorithms of the applications and more on the interactions and information flows between “entities”, e.g. people, systems, applications, data bases, etc. There should be a direct link between the narrative and these steps.
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
# Triggering event? Identify the name of the event.1
What other actors are primarily responsible for the Process/Activity? Actors are defined in section1.5.
Label that would appear in a process diagram. Use action verbs when naming activity.
Describe the actions that take place in active and present tense. The step should be a descriptive noun/verb phrase that portrays an outline summary of the step. “If …Then…Else” scenarios can be captured as multiple Actions or as separate steps.
What other actors are primarily responsible for Producing the information? Actors are defined in section1.5.
What other actors are primarily responsible for Receiving the information? Actors are defined in section1.5.
(Note – May leave blank if same as Primary Actor)
Name of the information object. Information objects are defined in section 1.6
Elaborate architectural issues using attached spreadsheet. Use this column to elaborate details that aren’t captured in the spreadsheet.
Reference the applicable IECSA Environment containing this data exchange. Only one environment per step.
1 Normal Operation
DERC Power Flow Monitoring Component
Monitors Power Flow
DERC Power Flow Monitoring Component monitors power flows of feeders within its scope
DERC Power Flow Monitor
DERC Power Flow Monitor
Power Flow of Line Segments
2.1 DERC RAS Continuous Calculations of Balanced Segment/Segmentation Scenarios
DERC RAS continually calculates a series of instantaneous balanced scenarios based on possible segmentation schemes
DERC RAS DERC RAS Calculations of Balanced Segment/Segmentation Scenarios
Continuous monitoring of system and updating of contingent islanding operations
1 Note – A triggering event is not necessary if the completion of the prior step – leads to the transition of the following step.
Fault Response Island Operation V1.2.doc 10 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
2.2 DERC RAS Continuous Calculations of Balanced Segments from load shedding/current limiting Scenarios
DERC RAS continually calculates a series of achievable balanced scenarios with load shedding/current limiting based on possible segment schemes
DERC RAS DERC RAS Calculations of Balanced Segments from load shedding/current limiting Scenarios
Possible segmentation schemes are limited by the availability of phase angle matching switching gear
3 DERC Availability Monitor
Rates Scenarios according to SAIDI, SAIFI and critical loads
DERC Availability Monitor rates scenarios by SAIDI , SAIFI impacts, with consideration of critical loads
DERC Availability Monitor
DERC Availability Monitor
Scenario Ratings according to SAIDI, SAIFI and critical loads
4.1 DERC Network Configuration Component
Determining breakers
DERC Network Configuration Component determines Substation Equipment which should be tripped in event of emergency to create balanced island areas
DERC Network Configuration Component
DERC Network Configuration Component
Emergency Substation Equipment Commands for Scenarios
4.2 DERC Network Configuration Component
Additional System Components
DERC Network Configuration Component determines additional system operations that will need to be performed to balance island areas
DERC Network Configuration Component
DERC Network Configuration Component
Additional System Components for Balanced Operation for scenario
Fault Response Island Operation V1.2.doc 11 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
5 Substation DERC
Create Profiles
Substation DERC Creates appropriate profiles for Bay Controllers and dependent IEDs as required and pushes them to affected Bay Controllers and dependent IEDs as required
Substation DERC
Bay Controllers and IEDs
Appropriate Profiles
Includes load shedding and AMI Current Limiting
6.1 Protection System
Fault Detected
Fault is detected is detected by the Protection System and Command Signals are sent to the Substation Equipment
Protection System
Substation Equipment
Fault Detection
6.2 FLISR FLISR Fault is detected and communicated to Substation DERC
FLISR Substation DERC
Fault Detection
6.2.1
Substation DERC
DERC RAS Islanding Scenario Accepted
Substation DERC determines the appropriate DERC RAS Islanding Scheme based on maximizing system indices with instantaneous trip (no delay for load shedding and pushes orders out
Substation DERC
Protection System
DERC RAS Islanding Scenario Orders
Altered protection settings appropriate to island operation, as well as adjusted ranges appropriate to island operation
Fault Response Island Operation V1.2.doc 12 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
6.2.2
Protection System
Transfer Trip Protection System initiates transfer trip for DER devices on affected segments and delivers it to Substation DERC
Protection System
Substation DERC
Transfer Trip Signal for DER Devices
6.2.3
Substation DERC
Execute Protection Actions
Protection System effects protection scheme.
Substation DERC
DER Devices Transfer Trip Signal for DER Devices
7.1 DERC RAS Calculate appropriate Scheme
DERC RAS calculates appropriate scheme and generates Load Shed, current limit orders based on the loss of generation on faulted segments and passes them to AMI Subsystem
DERC RAS AMI Subsystem
Emergency Load Shed/Current Limiting Orders
Load shed and current limiting is still enacted to provide a margin for operation and provide for security margin
7.2 AMI Subsystem
Sends AMI Commands
AMI Subsystem sends commands to the AMI Endpoints
AMI Subsystem
AMI Endpoints
Emergency Load Shed/Current Limiting Orders
8.1 Substation DERC
Charge Schedule
Substation DERC generates storage charge/discharge orders based on new generation and loading profile
Substation DERC
Substation DERC
Optimized Charge/Discharge Schedule for DER Storage Units
Fault Response Island Operation V1.2.doc 13 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
8.2 Substation DERC
Generation Schedule
Substation DERC calculates Optimized DER Device Generation Schedule based on new generation and loading profile
Substation DERC
Substation DERC
Optimized DER Device Generation Schedule
8.3 Substation DERC
Voltage regulation Profile
Substation DERC generates voltage regulation profiles based on new generation and loading profile
Substation DERC
Substation DERC
Optimal Voltage Regulation Profiles
8.4 Substation DERC
Protection Setting Profiles
Substation DERC calculates Optimal System Protection Setting Profiles for the day based on new generation and loading profile
Substation DERC
Substation DERC
Optimal System Protection Setting Profiles
8.5 Substation DERC
Charge/Discharge Schedule Push
Substation DERC pushes Optimized Charge/Discharge Schedule for DER Storage Units to DER Device (storage units).
Substation DERC
DER Device Storage Unit
Optimized Charge/Discharge Commands/Schedule for DER Storage Units
Fault Response Island Operation V1.2.doc 14 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
8.5.1
DER Device Storage Units
Storage Responds Accordingly
The DER Units Respond Accordingly
DER Device Storage Unit
DER Device Storage Unit
Optimized Charge/Discharge Commands/Schedule for DER Storage Units
8.6 Substation DERC
Generation Schedule Push
Substation DERC pushes Optimized DER Device Generation Schedule to DER Device (generation units).
Substation DERC
DER Device Generation Unit
Optimized DER Device Generation Commands/Schedule
8.6.1
DER Device Generation Units
Generation Responds Accordingly
The DER Units Respond Accordingly
DER Device Generation Unit
DER Device Generation Unit
Optimized DER Device Generation Commands/Schedule
8.7 Substation DERC
Voltage Regulation Profile Push
Substation DERC pushes Optimal Voltage Regulation Profiles to the Substation Voltage Regulation System as appropriate
Substation DERC
Substation Voltage Regulation System
Optimal Voltage Regulation Profiles
8.7.1
Substation Voltage Regulation System
Substation Voltage Regulation System Responds Accordingly
The Substation Voltage Regulation System Respond Accordingly
Substation Voltage Regulation System
Substation Voltage Regulation System
Optimal Voltage Regulation Profiles
Fault Response Island Operation V1.2.doc 15 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
8.8 Substation DERC
Protection Setting Profile Push
Substation DERC pushes Optimal System Protection Setting Profiles to the Protection System as appropriate
Substation DERC
Protection System
Optimal System Protection Setting Profiles
8.8.1
Protection System
Protection System Responds Accordingly
The Protection System Responds Accordingly
Protection System
Protection System
Optimal System Protection Setting Profiles
9 DERC Power Flow Monitoring
Power Flow Reports
DERC Power Flow Monitoring function reports balance and flows
DERC Power Flow Monitoring
DERC Power Flow Monitoring
Power Flow of Line Segments
10 Substation Operation as an embedded island
Substation continues operation with an embedded island
2.1.3 Post-conditions and Significant Results Describe conditions that must exist at the conclusion of the Function. Identify significant items similar to that in the preconditions section.
Describe any significant results from the Function
Actor/Activity Post-conditions Description and Results
Fault Response Island Operation V1.2.doc 16 January 14, 2010 Printed 6/16/2011
2.2 Steps to implement function – Name of Sequence Name of this sequence.
2.2.1 Preconditions and Assumptions Describe conditions that must exist prior to the initiation of the Function, such as prior state of the actors and activities
Identify any assumptions, such as what systems already exist, what contractual relations exist, and what configurations of systems are probably in place
Identify any initial states of information exchanged in the steps in the next section. For example, if a purchase order is exchanged in an activity, its precondition to the activity might be ‘filled in but unapproved’.
Actor/System/Information/Contract Preconditions or Assumptions
2.2.2 Steps – Name of Sequence Describe the normal sequence of events, focusing on steps that identify new types of information or new information exchanges or new interface issues to address. Should the sequence require detailed steps that are also used by other functions, consider creating a new “sub” function, then referring to that “subroutine” in this function. Remember that the focus should be less on the algorithms of the applications and more on the interactions and information flows between “entities”, e.g. people, systems, applications, data bases, etc. There should be a direct link between the narrative and these steps.
Fault Response Island Operation V1.2.doc 17 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
# Triggering event? Identify the name of the event.2
What other actors are primarily responsible for the Process/Activity? Actors are defined in section1.5.
Label that would appear in a process diagram. Use action verbs when naming activity.
Describe the actions that take place in active and present tense. The step should be a descriptive noun/verb phrase that portrays an outline summary of the step. “If …Then…Else” scenarios can be captured as multiple Actions or as separate steps.
What other actors are primarily responsible for Producing the information? Actors are defined in section1.5.
What other actors are primarily responsible for Receiving the information? Actors are defined in section1.5.
(Note – May leave blank if same as Primary Actor)
Name of the information object. Information objects are defined in section 1.6
Elaborate architectural issues using attached spreadsheet. Use this column to elaborate details that aren’t captured in the spreadsheet.
Reference the applicable IECSA Environment containing this data exchange. Only one environment per step.
1 Normal Operation – A section is taken out of service for maintenance
DERC Power Flow Monitoring Component
Monitors Power Flow
DERC Power Flow Monitoring Component monitors power flows of feeders within its scope
DERC Power Flow Monitor
DERC Power Flow Monitor
Power Flow of Line Segments
2.1 DERC RAS Continuous Calculations of Balanced Segment/Segmentation Scenarios
DERC RAS continually calculates a series of instantaneous balanced scenarios based on possible segmentation schemes
DERC RAS DERC RAS Calculations of Balanced Segment/Segmentation Scenarios
Continuous monitoring of system and updating of contingent islanding operations
2 Note – A triggering event is not necessary if the completion of the prior step – leads to the transition of the following step.
Fault Response Island Operation V1.2.doc 18 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
2.2 DERC RAS Continuous Calculations of Balanced Segments from load shedding/current limiting Scenarios
DERC RAS continually calculates a series of achievable balanced scenarios with load shedding/current limiting based on possible segment schemes
DERC RAS DERC RAS Calculations of Balanced Segments from load shedding/current limiting Scenarios
Possible segmentation schemes are limited by the availability of phase angle matching switching gear
3 DERC Availability Monitor
Rates Scenarios according to SAIDI, SAIFI and critical loads
DERC Availability Monitor rates scenarios by SAIDI , SAIFI impacts, with consideration of critical loads
DERC Availability Monitor
DERC Availability Monitor
Scenario Ratings according to SAIDI, SAIFI and critical loads
4.1 DERC Network Configuration Component
Determining breakers
DERC Network Configuration Component determines Substation Equipment which should be tripped in event of emergency to create balanced island areas
DERC Network Configuration Component
DERC Network Configuration Component
Emergency Substation Equipment Commands for Scenarios
4.2 DERC Network Configuration Component
Additional System Components
DERC Network Configuration Component determines additional system operations that will need to be performed to balance island areas
DERC Network Configuration Component
DERC Network Configuration Component
Additional System Components for Balanced Operation for scenario
Fault Response Island Operation V1.2.doc 19 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
5 Substation DERC
Create Profiles
Substation DERC Creates appropriate profiles for Bay Controllers and dependent IEDs as required and pushes them to affected Bay Controllers and dependent IEDs as required
Substation DERC
Bay Controllers and IEDs
Appropriate Profiles
Includes load shedding and AMI Current Limiting
6.1 WOMS Schedule Maintenance
WOMS system schedules maintenance
WOMS WOMS Scheduling of maintenance work order
6.2 WOMS Sends affected segments
WOMS sends affected segments and time frame (minutes ahead) to DMS/OMS/SCADA
WOMS DMS/OMS/SCADA
Maintenance Order Affected Segment and timeframe
6.3 Substation DERC
DERC RAS Islanding Scenario Accepted
Substation DERC determines the appropriate DERC RAS Islanding Scheme based on maximizing system indices with full load shedding.
Substation DERC
Protection System
DERC RAS Islanding Scenario Orders
Altered protection settings appropriate to island operation, as well as adjusted ranges appropriate to island operation
Substation DERC selects appropriate DERC RAS scheme based on maximizing system indices with full load shedding.
Fault Response Island Operation V1.2.doc 20 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
6.3.1
DERC DERC generates Load Shed, current limit orders and passes them to AMI
DERC AMI Subsystems
Load Shed/Current Limiting Orders
DERC generates Load Shed, current limit orders and passes them to AMI
6.3.2
AMI Subsystem
Sends AMI Commands
AMI Subsystem sends commands to the AMI Endpoints
AMI Subsystem
AMI Endpoints
Load Shed/Current Limiting Orders
7.1 Substation DERC
Charge Schedule
Substation DERC generates storage charge/discharge orders based on new generation and loading profile
Substation DERC
Substation DERC
Optimized Charge/Discharge Schedule for DER Storage Units
7.2 Substation DERC
Generation Schedule
Substation DERC calculates Optimized DER Device Generation Schedule based on new generation and loading profile
Substation DERC
Substation DERC
Optimized DER Device Generation Schedule
7.3 Substation DERC
Voltage regulation Profile
Substation DERC generates voltage regulation profiles based on new generation and loading profile
Substation DERC
Substation DERC
Optimal Voltage Regulation Profiles
Fault Response Island Operation V1.2.doc 21 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
7.4 Substation DERC
Protection Setting Profiles
Substation DERC calculates Optimal System Protection Setting Profiles for the day based on new generation and loading profile
Substation DERC
Substation DERC
Optimal System Protection Setting Profiles
7.5 Substation DERC
Charge/Discharge Schedule Push
Substation DERC pushes Optimized Charge/Discharge Schedule for DER Storage Units to DER Device (storage units).
Substation DERC
DER Device Storage Unit
Optimized Charge/Discharge Commands/Schedule for DER Storage Units
7.5.1
DER Device Storage Units
Storage Responds Accordingly
The DER Units Respond Accordingly
DER Device Storage Unit
DER Device Storage Unit
Optimized Charge/Discharge Commands/Schedule for DER Storage Units
7.6 Substation DERC
Generation Schedule Push
Substation DERC pushes Optimized DER Device Generation Schedule to DER Device (generation units).
Substation DERC
DER Device Generation Unit
Optimized DER Device Generation Commands/Schedule
7.6.1
DER Device Generation Units
Generation Responds Accordingly
The DER Units Respond Accordingly
DER Device Generation Unit
DER Device Generation Unit
Optimized DER Device Generation Commands/Schedule
Fault Response Island Operation V1.2.doc 22 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
7.7 Substation DERC
Voltage Regulation Profile Push
Substation DERC pushes Optimal Voltage Regulation Profiles to the Substation Voltage Regulation System as appropriate
Substation DERC
Substation Voltage Regulation System
Optimal Voltage Regulation Profiles
7.7.1
Substation Voltage Regulation System
Substation Voltage Regulation System Responds Accordingly
The Substation Voltage Regulation System Respond Accordingly
Substation Voltage Regulation System
Substation Voltage Regulation System
Optimal Voltage Regulation Profiles
7.8 Substation DERC
Protection Setting Profile Push
Substation DERC pushes Optimal System Protection Setting Profiles to the Protection System as appropriate
Substation DERC
Protection System
Optimal System Protection Setting Profiles
7.8.1
Protection System
Protection System Responds Accordingly
The Protection System Responds Accordingly
Protection System
Protection System
Optimal System Protection Setting Profiles
8 DERC Power Flow Monitoring
Power Flow Reports
DERC Power Flow Monitoring function reports balance and flows
DERC Power Flow Monitoring
DERC Power Flow Monitoring
Power Flow of Line Segments
9 DERC Ready for island operation
Substation DERC signals OMS ready for island operation
Substation DERC
OMS Ready for island operation
Fault Response Island Operation V1.2.doc 23 January 14, 2010 Printed 6/16/2011
# Event Primary Actor Name of Process/Activity
Description of Process/Activity
Information Producer
Information Receiver
Name of Info Exchanged Additional Notes IECSA
Environment
10 SCADA Trips Substation Equipment
OMS Trips Substation Equipment via SCADA
OMS SCADA Substation Equipment Commands
11 Substation Normal Operation
Substation continues operation with an embedded island
2.2.3 Post-conditions and Significant Results
Actor/Activity Post-conditions Description and Results
Electric Power System Operating within normal ranges with one or more de energized segments, and one or more islanded segments within the distribution grid.
2.3 Architectural Issues in Interactions Elaborate on all architectural issues in each of the steps outlined in each of the sequences above. Reference the Step by number. Double click on the embedded excel file – record the changes and save the excel file (this updates the embedded attachment).
2.4 Diagram For clarification, draw (by hand, by Power Point, by UML diagram) the interactions, identifying the Steps where possible.
Fault Response Island Operation V1.2.doc 24 January 14, 2010 Printed 6/16/2011
CentralizedDERC
SubStation DERC
(Location 1)
AMI
Substation Protection Systems
DER Controller
AMI Units
5
5
5.1.1
5.2.1
5.2.2
Fault Response Island Operation V1.2.doc 25 January 14, 2010 Printed 6/16/2011
3 Auxiliary Issues
3.1 References and contacts Documents and individuals or organizations used as background to the function described; other functions referenced by this function, or acting as “sub” functions; or other documentation that clarifies the requirements or activities described. All prior work (intellectual property of the company or individual) or proprietary (non-publicly available) work must be so noted.
ID Title or contact Reference or contact information
[1]
3.2 Action Item List As the function is developed, identify issues that still need clarification, resolution, or other notice taken of them. This can act as an Action Item list.
ID Description Status
[1]
3.3 Revision History For reference and tracking purposes, indicate who worked on describing this function, and what aspect they undertook.
No Date Author Description
1.1 10/26/2009 Charles Vincent Original Fault Response Use Case
1.2 1/14/2010 Brian D. Green Update Actors, Steps and Diagram